Monday, 11, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Assistant Executive Engineer (O & M) vs P.Sandanamary
2024 Latest Caselaw 19422 Mad

Citation : 2024 Latest Caselaw 19422 Mad
Judgement Date : 17 October, 2024

Madras High Court

The Assistant Executive Engineer (O & M) vs P.Sandanamary on 17 October, 2024

Author: D.Krishnakumar

Bench: D.Krishnakumar

                                                                CMP No.15941 of 2024 in WA SR No.95341 of 2024


                                  IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                DATED: 17.10.2024

                                                      CORAM:

                                  THE HON'BLE MR.JUSTICE D.KRISHNAKUMAR
                                                   AND
                                     THE HON'BLE MR.JUSTICE P.B.BALAJI

                                             C.M.P.No.15941 of 2024
                                                       in
                                             W.A.SR.No. 95341 of 2024

                     The Assistant Executive Engineer (O & M),
                     Maduravoyal, Chennai Electricity Distribution Circle/West,
                     Tamil Nadu Electricity Generation & Distribution Board,
                     Chennai-95.                                          ... Petitioner/Appellant

                                                         -vs-
                     1. P.Sandanamary
                     2. P.Dhanamary
                     3. P.Elizebeth Rani
                     4. P.Josepin Rosay
                     5. P.Roselin
                     6. Lourduammal @ Arulmary
                     7. Rosali
                     8. J.Pushpanathan                                 ... Respondents/Respondents




                     Page 1 of 12


https://www.mhc.tn.gov.in/judis
                                                                    CMP No.15941 of 2024 in WA SR No.95341 of 2024


                     Prayer: C.M.P.No.15941 of 2024 is filed to condone the delay of 637 days
                     in filing the above appeal against the order dated 11.07.2022 made in
                     W.P.No.16262 of 2013.


                     Prayer: W.A.SR.No.95341 of 2024 is filed under Clause 15 of Letters
                     Patent, seeking to allow the Writ Appeal and set aside the order dated
                     11.07.2022 made in W.P.No.16262 of 2013.



                                      For the Petitioner/        : Mr.P.Kumaresan,
                                      appellant                    Additional Advocate General
                                                                   Assisted by
                                                                   Mr.L.Jaivenkatesh
                                      For the Respondents/       : Mr.A.Ashwin Kumar
                                      Respondents



                                                             ORDER

(By D.Krishnakumar, J.)

This Civil Miscellaneous Petition has been filed to condone the delay

of 637 days in filing the above appeal against the order dated 11.07.2022

made in W.P.No.16262 of 2013.

https://www.mhc.tn.gov.in/judis CMP No.15941 of 2024 in WA SR No.95341 of 2024

3. The petitioner/appellant has come forward with a prayer to condone

the delay of 637 days, by giving the reasons in Paragraph No.4 and 5 of the

affidavit, which is extracted below:-

"4. I humbly submit that, the order was received on 07.09.2022 and the legal opinion to file the appeal was forwarded to the legal cell of the department on 23.09.2022. The opinion to file the appeal was forwarded as mail to may office by the legal cell on 17.10.2022, but due to the administrative set backs, we failed to note the same.

5. I humbly submit that, the opinion to prefer appeal came to our knowledge when I visited the Legal Cell department.”

4. In the affidavit, the petitioner has not disclosed any satisfactory or

justified reasons to condone such enormous delay. When the petitioner is

intended to file an appeal and got the legal opinion on 07.09.2022 itself, he

should be vigilant in prosecuting the case, within the reasonable time. In

such circumstances, we are not inclined to show any leniency on the

petitioner department to consider their case.

5. At this juncture, it is worthwhile to refer that, the Apex Court,

while dealing with the issue of delay in extenso in the case of

N.Balakrishnan V. M.Krishnamurthy reported in (1998) 7 SCC observed

https://www.mhc.tn.gov.in/judis CMP No.15941 of 2024 in WA SR No.95341 of 2024

as under:

“9. It is axiomatic that condonation of delay is a matter of discretion of the court Section 5 of the Limitation Act does not say that such discretion can be exercised only if the delay is within a certain limit. Length of delay is no matter, acceptability of the explanation is the only criterion. Sometimes delay of the shortest range may be uncondonable due to want of acceptable explanation whereas in certain other cases delay of very long range can be condoned as the explanation thereof is satisfactory. Once the court accepts the explanation as sufficient it is the result of positive exercise of discretion and normally the superior court should not disturb such finding, much less in reversional jurisdiction, unless the exercise of discretion was on whole untenable grounds or arbitrary or perverse. But it is a different matter when the first cut refuses to condone the delay. In such cases, the superior cut would be free to consider the cause shown for the delay afresh and it is open to such superior court to come to its own finding even untrammeled by the conclusion of the lower court.

10.The reason for such a different stance is thus:

The primary function of a court is to adjudicate the dispute between the parties and to advance substantial justice. Time limit fixed for approaching the court in different situations in not because on the expiry of such time a bad cause would transform into a good cause.

11.Rules of limitation are not meant to destroy the right of parties. They are meant to see that parties do not resort to dilatory tactics, but seek their remedy promptly. the object of providing a legal remedy is to repair the damage caused by reason of legal injury. Law of limitation fixes a life-span for such legal remedy for the redress of the legal injury so suffered.

Time is precious and the wasted time would never revisit. During efflux of time newer causes would sprout up

https://www.mhc.tn.gov.in/judis CMP No.15941 of 2024 in WA SR No.95341 of 2024

necessitating newer persons to seek legal remedy by approaching the courts. So a life span must be fixed for each remedy. Unending period for launching the remedy may lead to unending uncertainty and consequential anarchy. Law of limitation is thus founded on public policy. It is enshrined in the maxim Interest reipublicae up sit finis litium (it is for the general welfare that a period be putt to litigation). Rules of limitation are not meant to destroy the right of the parties. They are meant to see that parties do not resort to dilatory tactics but seek their remedy promptly. The idea is that every legal remedy must be kept alive for a legislatively fixed period of time.

12. A court knows that refusal to condone delay would result foreclosing a suitor from putting forth his cause. There is no presumption that delay in approaching the court is always deliberate. This Court has held that the words "sufficient cause"

under Section 5 of the Limitation Act should receive a liberal construction so as to advance substantial justice vide Shakuntala Devi Jain Vs. Kuntal Kumari [AIR 1969 SC 575] and State of West Bengal Vs. The Administrator, Howrah Municipality [AIR 1972 SC 749].

13. It must be remembered that in every case of delay there can be some lapse on the part of the litigant concerned. That alone is not enough to turn down his plea and to shut the door against him. If the explanation does not smack of mala fides or it is not put forth as part of a dilatory strategy the court must show utmost consideration to the suitor. But when there is reasonable ground to think that the delay was occasioned by the party deliberately to gain time then the court should lean against acceptance of the explanation. While condoning delay the Could should not forget the opposite party altogether. It must be borne in mind that he is a looser and he too would have incurred quiet a large litigation expenses. It would be a salutary guideline that when courts condone the delay due to laches on the part of the applicant the court shall compensate the opposite party for his loss.”

https://www.mhc.tn.gov.in/judis CMP No.15941 of 2024 in WA SR No.95341 of 2024

6. The Apex Court in Esha Bhattacharjee v. Raghunathpur Nafar

Academy, (2013) 12 SCC 649, after considering a series of earlier decisions,

summarised the principles to be followed while considering an application

for condonation of delay. The relevant portion of the said decision is

extracted hereunder:

“21.8. (viii) There is a distinction between inordinate delay and a delay of short duration or few days, for to the former doctrine of prejudice is attracted whereas to the latter it may not be attracted. That apart, the first one warrants strict approach whereas the second calls for a liberal delineation.

21.9. (ix) The conduct, behaviour and attitude of a party relating to its inaction or negligence are relevant factors to be taken into consideration. It is so as the fundamental principle is that the courts are required to weigh the scale of balance of justice in respect of both parties and the said principle cannot be given a total go by in the name of liberal approach.

22.1.(a) An application for condonation of delay should be drafted with careful concern and not in a haphazard manner harbouring the notion that the courts are required to condone delay on the bedrock of the principle that adjudication of a lis on merits is seminal to justice dispensation system.

22.2. (b) An application for condonation of delay should not be dealt with in a routine manner on the base of individual philosophy which is basically subjective.” [emphasis supplied]”

https://www.mhc.tn.gov.in/judis CMP No.15941 of 2024 in WA SR No.95341 of 2024

7. Reiterating the aforesaid principles, the Supreme Court in yet

another case in H.Dohil Constructions Company Private Limited vs Nahar

Exports Limited and another reported in (2015) 1 Supreme Court Cases

680, has categorically held as follows:

“23. When we apply those principles to the case on hand, it has to be stated that the failure of the Respondents in not showing due diligence in filing of the appeals and the enormous time taken in the refiling can only be construed, in the absence of any valid explanation, as gross negligence and lacks in bonafides as displayed on the part of the Respondents. Further, when the Respondents have not come forward with proper details as regards the date when the papers were returned for refiling, the non-furnishing of satisfactory reasons for not refiling of papers in time and the failure to pay the Court fee at the time of the filing of appeal papers on 06.09.2007, the reasons which prevented the Respondents from not paying the Court fee along with the appeal papers and the failure to furnish the details as to who was their counsel who was previously entrusted with the filing of the appeals cumulatively considered, disclose that there was total lack of bonafides in its approach. It also requires to be stated that in the case on hand, not refiling the appeal papers within the time CIVIL APPEAL NOS. OF 2014 22 of 25 (@ SLP (C) Nos.10811-10812 of 2014 & Connected matters prescribed and by allowing the delay to the extent of nearly 1727 days, definitely calls for a stringent scrutiny and cannot be accepted as having been explained without proper reasons. As has been laid down by this Court, Courts are required to weigh the scale of balance of justice in respect of both parties and the same principle cannot be given a go-by under the guise of liberal approach even if it pertains to refiling. The filing of an application for condoning the delay of 1727 days in the matter of refiling without disclosing reasons, much less satisfactory

https://www.mhc.tn.gov.in/judis CMP No.15941 of 2024 in WA SR No.95341 of 2024

reasons only results in the Respondents not deserving any indulgence by the Court in the matter of condonation of delay. The Respondents had filed the suit for specific performance and when the trial Court found that the claim for specific performance based on the agreement was correct but exercised its discretion not to grant the relief for specific performance but grant only a payment of damages and the Respondents were really keen to get the decree for specific performance by filing the appeals, they should have shown utmost diligence and come forward with justifiable reasons when an enormous delay of five years was involved in getting its appeals registered”.

8. A Division Bench of this Court in the case of M/s.Ruskim sea

Foods Limited, Stafford Park 15, Teleford Shropshire TF33BB United

Kingdom rep. By their Power of Attorney Agent Mr.Abdur Rahman

No.42, Sindur Plaza Montieth Lane, Egmore, Chennai 600 008 vs. M/s

Evergreeen Sea Foods Pvt.,Ltd., rep. By its Managing Director,

Mr.T.Loganathan, No.29, Kummalammankoil Street, Tondiarpet,

Chennai 600 081 and others [C.M.P.Nos.21784 and 21785 of 2017 in

OSA No.SR79476 of 2017] decided on 15.02.2018, elaborately dealt with

the issue of condonation of delay in terms of various judgments of the

Supreme Court, was pleased to hold as follows:

“36. The Petitioner has come with unclean hands and the Hon'ble

https://www.mhc.tn.gov.in/judis CMP No.15941 of 2024 in WA SR No.95341 of 2024

Supreme Court in the decisions, which were cited by the Petitioner, had categorically held that the 'length of delay is not a matter, but the acceptance of explanation is only criteria and length of delay may be long, but if there is justification, long delay can also condoned'. If there is a short delay and the explanation is not satisfactory and if it is on account of smack or malafide or on account of dilatory strategy, this Court cannot help the persons, who come before this Court to condone the delay and protract the proceedings.”

9. If the present case on hand is analyzed in line with the judgments of

the Supreme Court as well as this Court, it is obvious that even if the delay is

long, the delay can be condoned, provided it is supported by sufficient

reasons and justifications to exercise the discretion of the Court. It is well-

settled proposition of law that condonation of delay is a matter of discretion

of the court. What the court has to consider is not the length of delay, but

the acceptability of the explanation.

10. In the case on hand, the asseveration as contained in the affidavit

is only a self-serving statement and does not impel us to consider the same

as a sufficient cause for condoning such inordinate delay. No reasons, much

less valid and cogent reasons, are assigned to condone the delay. Hence, we

see no valid ground to condone the huge delay of 637 days in filing the writ

appeal.

https://www.mhc.tn.gov.in/judis CMP No.15941 of 2024 in WA SR No.95341 of 2024

11. For the foregoing reasons, C.M.P.No.21969 of 2024 is dismissed.

Consequently, W.A.SR.No.119846 of 2024 is rejected. No costs.

12. This order shall be communicated to the Chairman cum

Managing Director,of the Tamil Nadu Electricity Generation and

Distribution Board, 144, Anna Salai, Chennai-2 to give necessary

instructions to the officers concerned to file the appeal in an appropriate

case, in which the Board has decided to prefer an appeal, either before the

appellate forum or before this Court or before the District Court, within a

reasonable time. Further, in case any revenue loss is caused to the Board,

inview of the act of officers concerned in filing the appeals belatedly,

necessary legal action also shall be taken against them for recovering that

revenue loss.

                                                                      [D.K.K., J.,]     [P.B.B.,J.,]
                                                                               17.10.2024
                     Index: Yes / No
                     Internet: Yes / No
                     mst



                     Note to Registry to communicate this order





https://www.mhc.tn.gov.in/judis
                                                             CMP No.15941 of 2024 in WA SR No.95341 of 2024


                     To

                     The Chairman cum Managing Director,
                     Tamil Nadu Electricity Generation and
                       Distribution Board,
                     No.144, Anna Salai, Chennai-2







https://www.mhc.tn.gov.in/judis
                                                        CMP No.15941 of 2024 in WA SR No.95341 of 2024


                                                                   D.KRISHNAKUMAR,J.
                                                                                  AND
                                                                          P.B.BALAJI,J.

                                                                                                 mst




C.M.P.No.15941 of 2024 in W.A.SR.No.95341 of 2024

17.10.2024

https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter