Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sree Ganesh & Co vs The State Of Tamil Nadu
2023 Latest Caselaw 15211 Mad

Citation : 2023 Latest Caselaw 15211 Mad
Judgement Date : 29 November, 2023

Madras High Court

Sree Ganesh & Co vs The State Of Tamil Nadu on 29 November, 2023

Author: R. Subramanian

Bench: R. Subramanian

                                                                                  A.S.No. 438 of 2014


                                  IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                      Judgment Reserved on      :   07.11.2023

                                      Judgment Pronounced on :      29.11.2023

                                                      CORAM:
                              THE HONOURABLE MR. JUSTICE R. SUBRAMANIAN
                                                        And
                            THE HONOURABLE MR. JUSTICE N. SENTHILKUMAR


                                                A.S.No. 438 of 2014


                    Sree Ganesh & Co.,
                    a Registered Partnership Firm
                    represented by its Managing Partner
                    N. Ganesan.                               .. Appellant


                                                       Versus


                    1.     The State of Tamil Nadu,
                           Represented by the Superintending Engineer (H),
                           Nabard and Rural Circle,
                           Maravaneri Extension,
                           Salem-636 007.

                    2.     The Divisional Engineer,
                           (High Ways),
                           Nabard and Rural Roads,
                           Coimbatore.                               .. Respondents



https://www.mhc.tn.gov.in/judis
                    1/19
                                                                                      A.S.No. 438 of 2014




                              Appeal Suit filed under Section 96 and Order 40, Rule 1 of the Code

                    of Civil Procedure against the Judgment and Decree in O.S.No. 95 of

                    2010, dated 20.12.2013, on the file of the II Additional District Judge,

                    Salem.


                              For Appellant       : Mr.T.R. Rajagopalan
                                              Senior Counsel
                                              For Mr.T.R.Rajaraman

                              For Respondents : Mr.T.Chandrasekaran
                                          Special Government Pleader (Civil Side)
                                                        ----


                                                       JUDGMENT

N. SENTHILKUMAR, J.

This First Appeal has been preferred against the Judgment and

Decree in O.S.No.95 of 2010, dated 20.12.2013 passed by the learned II

Additional District Judge, Salem.

2. The appellant/plaintiff has filed the suit in O.S.No. 95 of 2010

under Section 26 and Order 7, Rules 1 to 14 of the Code of Civil Procedure

https://www.mhc.tn.gov.in/judis

against the defendants 1 and 2 for directing the respondents/defendants to

pay the suit amount with future interest amounting to Rs.44,60,919/-.

3. The case of the plaintiff is that the first defendant invited

Tenders for construction of a High Level Bridge across Aliyar river near

Atthupollachi including formation and improvement of approach road

from Km 85/4 of Avinasi-Thiruppur-Palladam-Pollachi-Cochin Road, Via

Meenakarai to Aathupollachi Km 0/0-3/2 and the plaintiff's tender was

accepted by the first defendant. An agreement was entered between the

plaintiff and the first defendant on 21.02.2007 in CR481A/06-07 for a

value of Rs.3,65,59,759/-. The time for completing the work was 15

months and based on the agreement dated 21.02.2007, the plaintiff

commenced the work as per schedule and the work was completed on

23.12.2008. After completion of work, the first defendant has issued the

completion certificate to the plaintiff on 31.12.2008.

4. According to the plaintiff, a prohibitory order was passed by

this Court in respect of sand quarrying from Paramiyam Depot in

Akkaraipalayam Village. The Superintending Engineer, Public Works

Department, has notified the same by way of Letter No.

https://www.mhc.tn.gov.in/judis

JDO/71B/662M/06, dated 12.12.2006. The designated quarry, which is

situated at 82/8 Km in SH-19, from where gravel and Carted Earth were to

be quarried was partly used as a road and hence gravel and carted earth

could not be quarried to complete the construction. The same was also

informed to the second defendant by the plaintiff through Ex.A8 and

Ex.A11 dated 13.06.2008 and 07.08.2008. The plaintiff further submitted

that according to the terms of the contract, the rates were fixed for (i) Sand

Rs.256.00, (ii) Gravel and Carted Earth Rs.24.00 and (iii) Blue Metal and

Rough Stone Rs.89.10, and such materials were not available from the

designated quarries. As regards the prohibition order imposed by this

Court regarding quarring of sand from Parambiyam Depot and the same

was notified by the Superintending Engineer, Public Works Department by

way of letter in JDO/71B/662M/06, dated 12.12.2006. The plaintiff had

collected the sand from Cauvery River bed in Kulithalai and Musri sand

quarries, which is situated 140 kilo-metres away, with an extra additional

distance of 54 kilo-metres from the original designated quarry, that is,

Paramiyam Depot in Akkaraipalayam Village in Amaravathi River Bed.

5. It is the further case of the plaintiff that the gravel and Carted

https://www.mhc.tn.gov.in/judis

Earth were also collected from Palaiyur Village, which is situated at 20

kilo metres away, with an extra lead of 15 kilo-metres and Blue Metal and

Rough Stones were purchased from Five Star quarry, with a lead of 30

kilo-metres and additional lead of 9 kilo-metres. Therefore, the plaintiff

has furnished the excess expenditure incurred by him, which are as

follows:-

Sl. Description of Qnty / Difference in Total Cost No. Material Cost of Conveyance of Conveyance

1 Metal 10605.82 cum @ Rs.57.90 Rs.614,077.00 2 Sand 4905.85 cum @ 237.50 Rs.1,165,139.00 3 Gravel 3040.28 cum @ 81.50 Rs.247,783.00 4 Carted Earth 29864.05 cum @ 81.50 Rs.2,433,920.00 Total Rs.4,460,919.00

6. The defendants 1 and 2 have submitted that, based on the

contract agreement entered into between the plaintiff and the first

defendant on 21.02.2007, the time to complete the said work was fixed as

15 months. One of the conditions specified in the tender itself is that the

plaintiff should have to inform about the sources from Paramiyam Depot,

where the plaintiff/Firm is intended to quarry the materials, and out of

which, the plaintiff has not incurred any additional expenditure. The

https://www.mhc.tn.gov.in/judis

defendants have specifically denied that the plaintiff has actually incurred

any loss, as set out in Paragraph No.8 of the plaint which is follows:-

“8. The plaintiff submits that according to the contract the transport charges for collection of sand was Rs.256.00 but the actual cost involved was Rs.494.50p and there was an excess expenditure of Rs.237.50. Similarly as per contract, the transport charges for gravel was Rs.24.00 whereas the plaintiff incurred the expenditure of Rs.150.50 and there was an excess expenditure of Rs.81.50. Similarly according to the contract the rate for transportation of blue metal and rough stone was Rs.89.10 whereas by the collection of the materials from other sources the plaintiff was to pay Rs.147.00 and there was an excess expenditure of Rs.57.90. The plaintiff is herewith furnishing the particulars of the quantities of the materials collected and the excess expenditure incurred by the plaintiff.”

7. Further, the defendants have denied the receipt of notice dated

13.06.2008 and March 2009 issued by the plaintiff and the defendants had

not received any notice in the month of March 2009. However, the

defendants have received the notice dated 07.04.2009 and the 2nd defendant

had sent a reply notice to the plaintiff stating that as per the agreement

dated 21.02.2007, the plaintiff is not entitled any additional claim.

https://www.mhc.tn.gov.in/judis

8. Based on the above pleadings, the following issues were

framed by the trial Court:-

(i) Whether the plaintiff is entitled to the extra

cost incurred due to increase in the length of haul for

collecting materials for the construction of high level

bridge across Aliyar River ?

(ii) Whether the plaintiff is entilted to recover

the suit claim ? and

(iii) To what relief, if any, the plaintiff is entitled to ?

9. Before the trial Court, PW1 and PW2 were examined and

Exs.A1 to A21 were marked on the side of the plaintiff. DW1 was

examined and Ex.B1 to Ex.B7 were marked on the side of the defendants.

10. Upon consideration of the above documents and the evidence

on record, the learned trial Judge dismissed the suit. Aggrieved by the

same, the plaintiff has preferred the present appeal.

https://www.mhc.tn.gov.in/judis

11. We have heard Mr.T.R. Rajagopalan, learned Senior Counsel

assisted by Mr.T.R.Rajaraman, learned counsel appearing for the

appellant/plaintiff and Mr.T.Chandrasekaran, learned Special Government

Pleader (Civil Side) appearing for the respondents/defendants.

12. The learned Senior Counsel appearing for the

appellant/plaintiff contended that the appellant/plaintiff issued a notice to

the defendants on 13.06.2008 as per Ex.A8, narrating the additional

expenditure incurred by the appellant/plaintiff for transportation from the

subject place to complete the project. He further contended that, when this

Court has prohibited, quarrying operations from the Paramiyam Depot in

Akkaraipalayam Village, and the Superintendenting Engineer, Public

Works Department, vide letter in JDO/71B/662M/06, dated 12.12.2006,

prohibited the quarrying, the appellant/plaintiff had to complete the

construction work and has procured the sand from different places. The

defendants had not disputed the transportation of sand from the different

quarries and this fact goes unchallenged by the defendants as per Ex.A18

https://www.mhc.tn.gov.in/judis

13. The learned Senior Counsel further drew our attention that, to

complete the construction work as contemplated under the Tender, the

plaintiff has transported the sand from different places and other

designated places, namely, Kulithalai and Musri which is evident from

Ex.P8. He further pointed out that, due to perennial flow of water at the

time of construction, there was some delay in completing the project as per

the scheduled time and the construction work was completed on all aspects

on 23.12.2008.

14. The learned Senior Counsel further pointed out that the Tender

was originally given to one M/s.P.S.Construction Limited and the said

contractor was not able to execute the work, and therefore, the previous

contract was terminated and fresh tender was invited, whereby the

appellant/Firm submitted their Tender, which was accepted and the work

entrusted to them with a revised estimated cost 27.31%, above the

estimated rate, because the cost of sand, Carted Earth, gravel and blue

metals have been escalated and time was taken for preparation of tender

schedule and awarding the contract.

https://www.mhc.tn.gov.in/judis

15. The learned Senior Counsel further contended that, based

upon Ex.A18 receipt of purchase of sand from Kulithalai and Musri sand

quarry in Cauvery River Bed, emphasis was laid as per Ex.P19

specification report, which would go to show that the plaintiff had

collected and transported the sand from Kulithalai and Musri to the

construction site and the same was also duly intimated by the plaintiff to

the defendants by way of their letter dated JDO/71B/662M/06, dated

12.12.2006. Exs.A14 and A15 would clearly go to show that the plaintiff

had informed the respondents about the additional/extra cost of

Rs.44,60,919/-.

16. The learned Senior Counsel would point out that the

appellant/plaintiff had submitted the details of materials which were

procured from Five Star quarry, as per Ex.A6, which will go to show that

the blue metal and other materials were procured from far off places. That

by itself would demonstrate that the plaintiff is entitled for additional

claim.

https://www.mhc.tn.gov.in/judis

17. Per contra, Mr.T.Chandrasekaran, learned Special Government

Pleader (Civil Side) appearing for the respondents/defendants categorically

denied receipt of the letter dated 13.06.2008. According to him, as per

Ex.A10 postal receipts are dated 26.06.2008 and 27.06.2008, but the seal

of the first respondent herein (Superintending Engineer, Nabard), is dated

25.06.2008 and it is hard to believe as to how they could send the letter

with Postal Department Seal, showing the dates as 26.06.2008 and

27.06.2008 and the postal receipts show the date as on 25.06.2008 and this

demonstrates that the plaintiff had not sent any notice as per Ex.A8, dated

13.06.2008. The respondents/defendants have also vehemently contended

that the relevant portion of the contract which reads as follows:-

“107-2. Source of materials.- All materails shall be obtained from the sources designated in the contract. The excavation of materials from sources designated in the contract shall be under the direction of the Engineer at all times insofar as selection of material or exact location of excavation as involved.

If sources previously approved are found to be unacceptable at any time and fail to produce the materials satisfactory to the Engineer, the Contractor shall furnish materials from other approved sources. The Contractor https://www.mhc.tn.gov.in/judis

will not be reimbursed for any extense in developing the new source, but allowance or deduction will be made as the case may be, for the increase or decrease in cost due to an increase or decrease in the length of haul.” (emphasis supplied) clearly mandates that the plaintiff is bound to take (i) Aggregates and

rough stone, (ii) Sand, (iii) Gravel and (iv) Carted Earth, all of which

have to be collected from the designated places.

18. The learned Special Government Pleader would submit that

the Ex.A6 statement issued by the Five Star Metals Private Limited,

Moochamkundu, Govindapuram, Palakkad, to Sri Ganesh & Co., Ledger

Account for the period from 01.10.2007 to 28.01.2008 totally a sum of

Rs.1,70,500/-, from 01.02.2008 to 29.02.2008 totally a sum of

Rs.1,18,900/- and another one commencing from 01.02.2008 to

29.03.2008 toally a sum of Rs.2,15,900/- regarding the purchase of gravel

and carted earth and rough stone and therefore, the total amount which has

aggregated to the tune of Rs.5,05,300/- cannot be taken into consideration.

19. We have considered the rival submissions of the parties.

https://www.mhc.tn.gov.in/judis

20. The Tender was awarded to the plaintiff and according to the

tender conditions, (i) Aggregates (ii) Sand (iii) Gravel (iv) Carted Earth

and rough stone, had to be collected from the Parambium Depot and other

designated places. However, this Court was pleased impose ban on

quarrying sand from the Parambium Depot and the Superintending

Engineer, Public Works Department, had notified the same, by his letter

No.JDO/71B/662M/06, dated 12.12.2006. While that being the situation,

Ex.A18 will demonstrate that the appellant/plaintiff was left with no other

option, but to draw the sand from Kulithalai and Musri to complete the

process and to justify the same, he has produced the bills vide Ex.A21

series which were not disputed by the defendants herein.

21. The next contention of the appellant is that, the blue metal

was procured from the Five Star Quarry at Palakkad as per Ex.A6. But

there is no evidence to show that Ex.A6 is the bill to establish that they

have purchased or procured the same for the purpose of construction under

the above tender.

22. As rightly pointed out by the learned Senior Counsel

appearing for the appellant/plaintiff the letters dated 07.04.2009 and

https://www.mhc.tn.gov.in/judis

March 2009 i.e., Exs.A14 and A15 would go to show that the appellant

herein have explained the escalation cost and additional cost that were

incurred to complete the construction. Similarly, making a demand to pay

the additional income as per Ex.A8 also strengthens the case of the

appellant. As discussed earlier, there are bills which would establish that

Ex.A18 is for transportation of sand from Kulithalai and Musri to the

construction site. Though it is the claim of the appellant that Ex.A21,

would establish the case of the appellant on the details for the procurement

of blue metal for the purpose of construction, we are unable to rely upon

the Ex.A21 as there is no reference that the material was procured for the

purpose of this construction. Though the respondents have denied the

receipt of notice issued by the plaintiff dated 07.08.2008, it is evident from

Ex.A16 viz., a letter from the second respondent to the plaintiff's counsel

pointing out that the appellant has not followed the Tender conditions and

also the appellant had not raised such claim for the additional cost and the

appellant/plaintiff had incurred and the same cannot be taken into account.

The appellant, as per Exs.A14 and A16, had narrated all these

circumstances which warranted procurement of materials from far off

places. Though the letter issued by the second respondent as per Ex.A16

https://www.mhc.tn.gov.in/judis

by way of Letter No. 707/2009/DO/dated 01.06.2009. It is only a denial

without any basis. Clause 107-2 of the contract provides for allowance for

increase or decrease in cost due to increase or decrease in the length of the

haul.

23. Therefore, we are not inclined to accept the contention as well

as the objections raised by the respondents for the simple reason that,

Ex.A18 would demonstrate that sand was quarried from different

locations, namely, Kulithalai and Musri. At the same time, we are of the

opinion that there are no ample materials to establish that (i) Aggregates

and rough stone, (ii) Gravel and (iii) Carted Earth, were transported from

other places apart from the designated sites.

24. It is clear that the respondents have miserably failed to make

note of the order passed by this Court imposing a ban on any quarrying

activities at Parambiyam Depot, which is also evident from the letter of the

Superintending Engineer, Public Works Department through his letter No.

JDO/71B/662M/06, dated 12.12.2006. Having accepted the Tender

conditions which has a time frame, the appellant/plaintiff has produced

https://www.mhc.tn.gov.in/judis

sufficient materials by way of Ex.A18, dated 31.06.2012 which would go

to show that sand was transported from Kulithalai and Musri Depots.

DW1 in his cross-examination has admitted that there was a ban imposed

by this Court as evidenced by the Letter in JDO/71B/662M/06, dated

12.12.2006 issued by the Superintending Engineer, Public Works

Department regarding quarrying in the Parambiyam Depot.

25. Therefore, we are inclined to allow this appeal partly to the

extent the claim of transportation of sand, to the tune of Rs.11,65,139/-.

26. Though it was pointed out by the learned Senior Counsel

appearing for the appellant that the appellant had procured blue metal from

Five Star Quarry by way of Ex.A6, that by itself will not indicate the blue

metal was procured for the purpose of construction under the tender in

question. We are unable to rely upon Ex.A6 and the claim cannot be

accepted.

27. Accordingly, this Appeal Suit is partly allowed. The judgment

and decree in O.S.No. 95 of 2010, dated 20.12.2013 on the file of the II

https://www.mhc.tn.gov.in/judis

Additional District Judge, Salem, are set aside. There will be a decree for

payment of a sum of Rs.11,65,139/- [Rupees Elevan Lakh Sixty Five

Thousand and One Hundred Thirty Nine Only] in favour of the

appellant/plaintiff-Firm together with interest at the rate of 9% per annum

from the date of institution of the suit till the date of decree and thereafter,

@6% per annum from the date of decree till the date of realization of the

entire amount. There shall be no order as to costs in this appeal suit.

                                                                    [R.S.M., J]     [N.S., J]
                                                                          29.11.2023
                    Index:Yes/No
                    Speaking order: Yes/No
                    Neutral Citation: Yes/No
                    MSM
                    To
                    1. The II Additional District Judge,
                       Salem.
                    2. The Section Officer,
                       V.R. Section, High Court, Madras.




https://www.mhc.tn.gov.in/judis






                                   R. SUBRAMANIAN, J
                                                and
                                  N. SENTHILKUMAR, J



                                                       MSM




                                  Pre-Delivery Judgment in





                                              Delivered on
                                               29.11.2023




https://www.mhc.tn.gov.in/judis






https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter