Citation : 2023 Latest Caselaw 2926 Mad
Judgement Date : 21 March, 2023
2023:MHC:1499
W.P.No.25917 of 2010
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 21.03.2023
CORAM
THE HONOURABLE MR.JUSTICE S.M.SUBRAMANIAM
W.P.No.25917 of 2010
and
M.P.Nos.2 & 3of 2010
M/s.Ultra Tech Cement Ltd.,
Reddipalayam Cement Works
(Previously Known as Samruddhi Cement Ltd.,
& Prior to that as Grasim Industries Ltd.,)
Represented by its Senior Vice President (F&C)
Ariyalur Taluk 621 704
Perambalur ... Petitioner
Vs.
1.The Tamil Nadu Electricity Board,
Rep. by its Chairman,
No.800, Anna Salai,
Chennai 600 002.
2.The Chief Engineer,
Civil Designs,
Tamil Nadu Electricity Board,
3rd Floor, NPKRR Maaligai,
No.144 Anna Salai, Chennai 600 002.
3.The Chief Engineer,
Tamil Nadu Electricity Board,
Mettur Thermal Power Station,
Mettur Dam – 636 406. ... Respondents
Page 1 of 19
https://www.mhc.tn.gov.in/judis
W.P.No.25917 of 2010
Prayer: Writ Petition filed under Article 226 of the Constitution of India for
issuance of a Writ of Certiorarified Mandamus, calling for the entire records
of the 3rd respondent in Lr.No.CE/SE/M.II/EE/O&AHS/MTPS-I/F shortcolle
/ D.No.957/10 dated 20.10.2010 being the consolidated order levying a
penalty of Rs.34,77,608/- for the alleged short collection of fly ash for the
period between April 2008 and August 2010 as also the prior demand
Lr.No.CE/SE/M.II/EE/O&AHS/MTPS/F.Shortcolle/D.No.669/09 dated
05.08.2009 for April 2008 to July 2009, Lr. No. CE/SE/M. II/EE /O&AHS
/MTPS /F.Short Colle/D.No. 839/09 dated 29.09.2009 for August 2009, Lr.
No. CE/SE/M.II/EE /O&AHS/MTPS /F.ShortColle /D.No.780/10 dated
23.08.2010 for July 2010 and Lr. No. CE/SE/M. II/EE/O&AHS /MTPS
/F.ShortColle/D.No.874/10 dated 23.09.2010 for August 2010 all of which
were confirmed and formed part of the final impugned demand dated
20.10.2010 of the 3rd respondent and quash the same as illegal and arbitrary
and consequently direct the 1st respondent to issue appropriate instructions to
the 3rd respondent to strictly comply with the terms of the agreement between
parties and not a levy and penalty for short collection.
For Petitioner : Mr.Rahul Balaji
For R1 & R2 : No Appearance
For R3 : Mr.K.Arun Prasad
Page 2 of 19
https://www.mhc.tn.gov.in/judis
W.P.No.25917 of 2010
ORDER
The demand notice issued by the respondent / TANGEDCO invoking
the terms and conditions of Memorandum of Understanding executed at
Headquarters / TNEB with the petitioner company and the TANGEDCO is
under challenge in the present writ petition.
2. The petitioner is a company and the manufacturer of cement. The
petitioner states that they produce cement of high quality and manufacture of
cement involves several raw materials including gypsum and fly ash. In this
regard, admittedly, the contract was signed between the petitioner company
and the respondent TANGEDCO. Based on the Memorandum of
Understanding between the parties, the petitioner has to install, erect and
maintain collection system and storage of fly ash with its cost at MTPS and
thereafter to collect fly ash for a period of nine years from the date of
commissioning of the system.
3. In pursuance of the said MOU, which has a validity period of 9
years from the date of commissioning, the petitioner has been diligently
carrying out its obligations in collecting the fly ash. While so, the 3 rd
https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010
respondent issued impugned communications dated 05.08.2009, 23.08.2010
and 23.09.2010 stating that the alleged percentage of collection of fly ash is
lesser than the stipulated 100% in terms of the MOU and thereby levying a
penalty for the said period.
4. The petitioner submitted representations specifically pointed out that
the reasons for alleged non-collection of the possible quantities was because
of the ESP installed by the respondent / Board were ineffective that some of
them are not functioning and due to such reasons. However, the 3rd
respondent without rectifying their instruments and the representations
submitted by the petitioner issued impugned communications and imposed
penalty, which was subsequently confirmed by the impugned order dated
20.10.2010.
5. The petitioner further states that the method in which the original
quantity that would become available in not known. It appears from the
various communications that the petitioner received from the respondent, that
the respondent board is merely following theoretical formulae for
determining the total ash that ought to be generated and collected.
https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010
6. The learned counsel for the petitioner is of an opinion that the
respondent Board's calculations for short collection are based on the amount
of fly ash collected. But the same has been done without actual weighments
in as much as weigh bridge was installed in the 3rd respondent thermal station
only in April 2010. Therefore, the very basis for determining the penalty and
the calculations are not reliable and the impugned communications was
issued based on the unilateral decision taken by the respondent / Board.
7. In support of the said contention, the learned counsel for the
petitioner relied on the judgment of the Hon'ble Supreme Court of India in
the case of State of Karnataka vs. Shree Rameshwara Rice Mills,
Thiruthahalli reported in (1987) 2 SCC 160, particularly paragraphs 7 and 8,
which reads as under:
''7.On a consideration of the matter we find ourselves
unable to accept the contentions of Mr.Iyenger. The terms of
Clause 12 do not afford scope for a liberal construction being
made regarding the powers of the Deputy Commissioner to
adjudicate upon a disputed question of breach as well as to
https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010
assess the damages arising from the breach. The crucial words
in Clause 12 are ?and for any breach of conditions set forth
hereinbefore, the first party shall be liable to pay damages to
the second party as may be assessed by the second party?. On a
plain reading of the words it is clear that the right of the second
party to assess damages would arise only if the breach of
conditions is admitted or if no issue is made of it. If is was the
intention of the parties that the officer acting on behalf of the
State was also entitled to adjudicate upon a dispute regarding
the breach of conditions the wording of Clause 12 would have
been entirely different. It cannot also be argued that a right to
adjudicate upon an issue relating to a breach of conditions of
the contract would flow from or is inhered in the right conferred
to assess the damages arising from a breach of conditions. The
power to assess damages, as pointed out by the Full Bench, is a
subsidiary and consequential power and not the primary power.
Even assuming for arguments sake that the terms of Clause 12
afford scope for being construed as empowering the officer of
the State to decide upon the question of breach as well as assess
https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010
the quantum of damages, we do not think that adjudication by
the officer regarding the breach of the contract can be sustained
under law because a party to the agreement cannot be an
arbiter in his own cause. Interests of justice and equity require
that where a party to a contract disputes the committing of any
breach of conditions the adjudication should be by an
independent person or body and not by the other party to the
contract. The position will, however, be different where there is
no dispute or there is consensus between the contracting parties
regarding the breach of conditions. In such a case the officer of
the State, even though a party to the contract will be well within
his rights in assessing the damages occasioned by the breach in
view of the specific terms of Clause 12.
8.We are, therefore, in agreement with the view of the
Full Bench that the powers of the State under an agreement
entered into by it with a private person providing for assessment
of damages for breach of conditions and recovery of the
damages will stand confined only to those cases where the
breach of conditions is admitted or it is not disputed.?
https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010
8. In the case of J.G. Engineers Private Limited vs. Union of India
and another reported in (2011) 5 SCC 758 at paragraphs 19 and 20, which
reads as under:
''?........
19.In fact the question whether the other party committed
breach cannot be decided by the party alleging breach. A
contract cannot provide that one party will be the arbiter to
decide whether he committed breach or the other party
committed breach. That question can only be decided by only an
adjudicatory forum, that is, a court or an Arbitral Tribunal.
20.In State of Karnataka v. Shree Rameshwara Rice Mills
this Court held that adjudication upon the issue relating to a
breach of condition of contract and adjudication of assessing
damages arising out of the breach are two different and distinct
concepts and the right to assess damages arising out of a
breach would not include a right to adjudicate upon as to
whether there was any breach at all. This Court held that one of
the parties to an agreement cannot reserve to himself the power
https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010
to adjudicate whether the other party has committed breach.
This Court held: (SCC p. 164, paras 7-8)
?7. ... Even assuming for argument's sake that the terms
of Clause 12 afford scope for being construed as empowering
the officer of the State to decide upon the question of breach as
well as assess the quantum of damages, we do not think that
adjudication by the officer regarding the breach of the contract
can be sustained under law because a party to the agreement
cannot be an arbiter in his own cause. Interests of justice and
equity require that where a party to a contract disputes the
committing of any breach of conditions the adjudication should
be by an independent person or body and not by the other party
to the contract. The position will, however, be different where
there is no dispute or there is consensus between the
contracting parties regarding the breach of conditions. In such
a case the officer of the State, even though a party to the
contract will be well within his rights in assessing the damages
occasioned by the breach in view of the specific terms of Clause
https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010
8.We are, therefore, in agreement with the view of the
Full Bench that the powers of the State under an agreement
entered into by it with a private person providing for assessment
of damages for breach of conditions and recovery of the
damages will stand confined only to those cases where the
breach of conditions is admitted or it is not disputed.?
9. Relying on the above judgments, the learned counsel for the
petitioner reiterated that the petitioner may be driven to the Civil Court only
in the event of permitting him to present their case. The basis on which a
decision is taken for issuing an order of demand itself is not explained to the
petitioner and under those circumstances, the petitioner has chosen to file the
present writ petition. Thus, the order impugned is directly in violation of the
principles of natural justice and the present writ petition is to be considered.
10. The learned counsel appearing on behalf of the respondents relying
on the counter affidavit made a submission that admittedly, the dispute arises
based on the contractual obligation between the parties. The impugned order
is in tune with the contract conditions, specifically condition No.5. Thus, the
https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010
writ petition is not maintainable, as such disputes are to be adjudicated before
the competent civil Court of law and not in a writ proceedings. The
respondents filed counter narrating facts and circumstances to establish that
the petitioner has violated certain terms and conditions and the manner in
which the calculations are made and the impugned demand notices are
issued.
11. However, this Court is of the considered opinion that all such
disputed facts cannot be adjudicated in a writ proceedings, as it requires
examination of documents in original and evidences and even oral evidences.
Prima facie, it is raised that no opportunity was provided to the petitioner,
even to present their case and it is to be considered. In a contractual
obligation between the parties, whether such a show cause notice or
opportunity is required to be given or not is to be considered. No doubt, it
depends on the facts and circumstances and also the terms and conditions
agreed between the parties. However, it cannot be concluded by holding that
in each and every case, a show cause notice and an opportunity of presenting
the case must be provided in contractual obligations. Thus, a writ cannot be
entertained merely on the ground that no opportunity to present the case is
https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010
given in the event of the dispute with reference to the terms and conditions of
the contract between the parties.
12. It is needless to state that the terms and conditions agreed are
known to the parties. Once agreed to the terms and conditions are violated,
the question of further opportunity by any one of the parties would not arise.
A dispute arises in the present case, as the petitioner states that an
opportunity is to be given to present their case. This Court is of an opinion
that such a procedure, which is not agreed between the parties need not be
considered, as providing of an opportunity is also a dispute, which is to be
considered with reference to the agreed terms and conditions of the contract.
13. The concept of principles of natural justice can be applied in a
contract only in certain circumstances and the performance of contractual
obligation between the parties cannot be compared with the statutory
functions of the authorities. Though in the present case, the Tamil Nadu
Electricity Board is a State under Article 12 of the Constitution of India.
Thus, a distinction is to be drawn between the contractual obligation between
the parties and the statutory functions and the powers to be exercised under
https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010
the statute by such officials of the State. These distinct factors are to be
demarcated when the facts are clear and more so relatable to the terms and
conditions of contract.
14. Presuming that a writ Court examines the terms and conditions of
the contract, a doubt arises whether it is possible to form an opinion with
reference to the factual disputes which is to be adjudicated in an elaborate
manner with reference to the original documents and evidences.
Undoubtedly, there is a possibility of error, omission, commission or
otherwise, if any such opinion is formed. That is the reason why the
Constitutional Courts have taken a consistent view that in the matter of
contractual obligations between the parties, they must approach the Civil
Court of law as it involves trial nature adjudication, which would provide an
opportunity to examine and cross examine the witnesses to cull out the truth
and resolve the issues in the manner known to law.
15. Per contra, based on the mere affidavit in a writ petition and
relying on certain xerox copies of the documents, which is enclosed in the
typed set of papers, such factually disputed issues can never be adjudicated in
https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010
a concrete manner so as to give complete justice to the parties, who are all
approaching the writ Court.
16. With reference to the judgment relied upon by the petitioner, the
Hon'ble Apex Court of India in Shree Rameshwara Rice Mills case cited
supra at paragraphs-7 and 8 itself held that “the position will, however, be
different where there is no dispute or there is consensus between the
contracting parties regarding the breach of conditions. In such a case the
officer of the State, even though a party to the contract will be well within his
rights in assessing the damages occasioned by the breach in view of the
specific terms of Clause 12”. Therefore, only in the event of no dispute and
there is a consensus between the contracting parties, the writ Court may be in
a position to take a decision in such nature of issues and not otherwise.
Therefore, the Hon'ble Supreme Court entertained the argument in a
particular case by distinguishing the facts and ruled that the contractual
obligations may be entertained by the writ Court only if there is no dispute
between the contracting parties and there is a consensus. Even in paragraph-
9, the Hon'ble Supreme Court observed that recovery of the damages will
stand confined only to those cases where, the breach of conditions is
https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010
admitted or it is not disputed.
17. In the present case, the demand notice is disputed by the petitioner,
the manner in which the Tamil Nadu Electricity Board assessed the damages
or otherwise is also questioned by the petitioner. In this regard, examination
in detail with reference to the terms and conditions of the contract are
imminent and require adjudication. Even in the other case relied on by the
petitioner, the proposition laid down by the Hon'ble Supreme Court in
J.G.Engineers Private Limited case (cited supra) is referred and in
paragraph-19 the Hon'ble Apex Court observed that “a contract cannot
provide that one party with the arbiter to decide whether he committed
breach or the other party committed breach. That question can only be
decided by only an adjudicatory forum, that is, a Court or an Arbitral
Tribunal”. Admittedly, in the present case, the parties have not agreed for
arbitration, thus, necessarily they have to approach the Competent Court of
law for the purpose of adjudicating issues.
18. Let us look into the reliance placed by the petitioner i.e. Clause:5
of the Memorandum of Understanding. Clause-5 reads as under:
https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010
“5.Performance of the cement company in collecting
100% of Fly Ash will be reviewed for a period of one year and
penalty deemed fit will be imposed for the short collection of Fly
Ash due to the fault of company after one year of the reviewed
period.”
19. The above clause reveals that the collection of fly ash will be
reviewed for a period of one year and penalty deemed fit will be imposed for
the short collection of fly ash due to the fault of the company. For
understanding purposes, this Court is of an opinion that the parties agreed
that the performance of the petitioner company will be reviewed and penalty
deemed fit will be imposed. Thus, the petitioner was very much aware and
agreed regarding imposition of penalty by the TANGEDCO. Question arises
whether an opportunity is to be provided prior to issuance of any such
demand notice. In this regard, it is stated in the Clause that penalty deemed
fit will be imposed for short collection of fly ash due to the fault of the
company. This exactly is the dispute to be adjudicated as the short collection
of fly ash and the quantum of short collection and the fault of the company or
https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010
there is no fault of the company and the quantum of penalty to be imposed
are disputed facts, which cannot be adjudicated in a writ proceedings.
20. These issues require an elaborate examination of the records and
evidences. As far as the opportunity is concerned, no doubt if there is a
consensus between the parties or if any doubt arises with reference to the
performance or otherwise, it is open to the parties to the contract to negotiate
and form an opinion and resolve the issues in an amicable manner. Therefore,
it is for the petitioner to approach the competent authorities, if they agree for
such consensus or for a negotiation and settlement of issues. However, the
impugned order is concerned, it is for the petitioner to initiate appropriate
steps for effective adjudication of the disputes for the purpose of redressing
their grievances in the manner known to law.
21. The petitioner if chosen to approach the competent Court of law for
resolving the issues, the Court shall consider the period in which the writ
petition was pending before the High Court for the purpose of condoning the
delay, if any petition to condone the delay is filed by the petitioner.
https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010
22. With these observations, the Writ Petition stands dismissed. No
costs. Consequently, connected Miscellaneous Petitions are closed
21.03.2023 Jeni Index : Yes Speaking order Neutral Citation : Yes
To
1.The Chairman, The Tamil Nadu Electricity Board, No.800, Anna Salai, Chennai 600 002.
2.The Chief Engineer, Civil Designs, Tamil Nadu Electricity Board, 3rd Floor, NPKRR Maaligai, No.144 Anna Salai, Chennai 600 002.
3.The Chief Engineer, Tamil Nadu Electricity Board, Mettur Thermal Power Station, Mettur Dam – 636 406.
https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010
S.M.SUBRAMANIAM, J.
Jeni
W.P.No.25917 of 2010
21.03.2023
https://www.mhc.tn.gov.in/judis
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!