Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.Ultra Tech Cement Ltd vs The Tamil Nadu Electricity Board
2023 Latest Caselaw 2926 Mad

Citation : 2023 Latest Caselaw 2926 Mad
Judgement Date : 21 March, 2023

Madras High Court
M/S.Ultra Tech Cement Ltd vs The Tamil Nadu Electricity Board on 21 March, 2023
    2023:MHC:1499

                                                                           W.P.No.25917 of 2010

                                    IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                DATED : 21.03.2023

                                                       CORAM

                            THE HONOURABLE MR.JUSTICE S.M.SUBRAMANIAM

                                                W.P.No.25917 of 2010
                                                        and
                                                M.P.Nos.2 & 3of 2010

                     M/s.Ultra Tech Cement Ltd.,
                     Reddipalayam Cement Works
                     (Previously Known as Samruddhi Cement Ltd.,
                     & Prior to that as Grasim Industries Ltd.,)
                     Represented by its Senior Vice President (F&C)
                     Ariyalur Taluk 621 704
                     Perambalur                                        ... Petitioner

                                                           Vs.

                     1.The Tamil Nadu Electricity Board,
                       Rep. by its Chairman,
                       No.800, Anna Salai,
                       Chennai 600 002.

                     2.The Chief Engineer,
                       Civil Designs,
                       Tamil Nadu Electricity Board,
                       3rd Floor, NPKRR Maaligai,
                       No.144 Anna Salai, Chennai 600 002.

                     3.The Chief Engineer,
                       Tamil Nadu Electricity Board,
                       Mettur Thermal Power Station,
                       Mettur Dam – 636 406.                           ... Respondents


                     Page 1 of 19

https://www.mhc.tn.gov.in/judis
                                                                                   W.P.No.25917 of 2010




                     Prayer: Writ Petition filed under Article 226 of the Constitution of India for
                     issuance of a Writ of Certiorarified Mandamus, calling for the entire records
                     of the 3rd respondent in Lr.No.CE/SE/M.II/EE/O&AHS/MTPS-I/F shortcolle
                     / D.No.957/10 dated 20.10.2010 being the consolidated order levying a
                     penalty of Rs.34,77,608/- for the alleged short collection of fly ash for the
                     period between April 2008 and August 2010 as also the prior demand
                     Lr.No.CE/SE/M.II/EE/O&AHS/MTPS/F.Shortcolle/D.No.669/09                    dated
                     05.08.2009 for April 2008 to July 2009, Lr. No. CE/SE/M. II/EE /O&AHS
                     /MTPS /F.Short Colle/D.No. 839/09 dated 29.09.2009 for August 2009, Lr.
                     No. CE/SE/M.II/EE /O&AHS/MTPS /F.ShortColle /D.No.780/10 dated
                     23.08.2010 for July 2010 and Lr. No. CE/SE/M. II/EE/O&AHS /MTPS
                     /F.ShortColle/D.No.874/10 dated 23.09.2010 for August 2010 all of which
                     were confirmed and formed part of the final impugned demand dated
                     20.10.2010 of the 3rd respondent and quash the same as illegal and arbitrary
                     and consequently direct the 1st respondent to issue appropriate instructions to
                     the 3rd respondent to strictly comply with the terms of the agreement between
                     parties and not a levy and penalty for short collection.



                                    For Petitioner          : Mr.Rahul Balaji

                                    For R1 & R2             : No Appearance

                                    For R3                  : Mr.K.Arun Prasad




                     Page 2 of 19

https://www.mhc.tn.gov.in/judis
                                                                                    W.P.No.25917 of 2010


                                                          ORDER

The demand notice issued by the respondent / TANGEDCO invoking

the terms and conditions of Memorandum of Understanding executed at

Headquarters / TNEB with the petitioner company and the TANGEDCO is

under challenge in the present writ petition.

2. The petitioner is a company and the manufacturer of cement. The

petitioner states that they produce cement of high quality and manufacture of

cement involves several raw materials including gypsum and fly ash. In this

regard, admittedly, the contract was signed between the petitioner company

and the respondent TANGEDCO. Based on the Memorandum of

Understanding between the parties, the petitioner has to install, erect and

maintain collection system and storage of fly ash with its cost at MTPS and

thereafter to collect fly ash for a period of nine years from the date of

commissioning of the system.

3. In pursuance of the said MOU, which has a validity period of 9

years from the date of commissioning, the petitioner has been diligently

carrying out its obligations in collecting the fly ash. While so, the 3 rd

https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010

respondent issued impugned communications dated 05.08.2009, 23.08.2010

and 23.09.2010 stating that the alleged percentage of collection of fly ash is

lesser than the stipulated 100% in terms of the MOU and thereby levying a

penalty for the said period.

4. The petitioner submitted representations specifically pointed out that

the reasons for alleged non-collection of the possible quantities was because

of the ESP installed by the respondent / Board were ineffective that some of

them are not functioning and due to such reasons. However, the 3rd

respondent without rectifying their instruments and the representations

submitted by the petitioner issued impugned communications and imposed

penalty, which was subsequently confirmed by the impugned order dated

20.10.2010.

5. The petitioner further states that the method in which the original

quantity that would become available in not known. It appears from the

various communications that the petitioner received from the respondent, that

the respondent board is merely following theoretical formulae for

determining the total ash that ought to be generated and collected.

https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010

6. The learned counsel for the petitioner is of an opinion that the

respondent Board's calculations for short collection are based on the amount

of fly ash collected. But the same has been done without actual weighments

in as much as weigh bridge was installed in the 3rd respondent thermal station

only in April 2010. Therefore, the very basis for determining the penalty and

the calculations are not reliable and the impugned communications was

issued based on the unilateral decision taken by the respondent / Board.

7. In support of the said contention, the learned counsel for the

petitioner relied on the judgment of the Hon'ble Supreme Court of India in

the case of State of Karnataka vs. Shree Rameshwara Rice Mills,

Thiruthahalli reported in (1987) 2 SCC 160, particularly paragraphs 7 and 8,

which reads as under:

''7.On a consideration of the matter we find ourselves

unable to accept the contentions of Mr.Iyenger. The terms of

Clause 12 do not afford scope for a liberal construction being

made regarding the powers of the Deputy Commissioner to

adjudicate upon a disputed question of breach as well as to

https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010

assess the damages arising from the breach. The crucial words

in Clause 12 are ?and for any breach of conditions set forth

hereinbefore, the first party shall be liable to pay damages to

the second party as may be assessed by the second party?. On a

plain reading of the words it is clear that the right of the second

party to assess damages would arise only if the breach of

conditions is admitted or if no issue is made of it. If is was the

intention of the parties that the officer acting on behalf of the

State was also entitled to adjudicate upon a dispute regarding

the breach of conditions the wording of Clause 12 would have

been entirely different. It cannot also be argued that a right to

adjudicate upon an issue relating to a breach of conditions of

the contract would flow from or is inhered in the right conferred

to assess the damages arising from a breach of conditions. The

power to assess damages, as pointed out by the Full Bench, is a

subsidiary and consequential power and not the primary power.

Even assuming for arguments sake that the terms of Clause 12

afford scope for being construed as empowering the officer of

the State to decide upon the question of breach as well as assess

https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010

the quantum of damages, we do not think that adjudication by

the officer regarding the breach of the contract can be sustained

under law because a party to the agreement cannot be an

arbiter in his own cause. Interests of justice and equity require

that where a party to a contract disputes the committing of any

breach of conditions the adjudication should be by an

independent person or body and not by the other party to the

contract. The position will, however, be different where there is

no dispute or there is consensus between the contracting parties

regarding the breach of conditions. In such a case the officer of

the State, even though a party to the contract will be well within

his rights in assessing the damages occasioned by the breach in

view of the specific terms of Clause 12.

8.We are, therefore, in agreement with the view of the

Full Bench that the powers of the State under an agreement

entered into by it with a private person providing for assessment

of damages for breach of conditions and recovery of the

damages will stand confined only to those cases where the

breach of conditions is admitted or it is not disputed.?

https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010

8. In the case of J.G. Engineers Private Limited vs. Union of India

and another reported in (2011) 5 SCC 758 at paragraphs 19 and 20, which

reads as under:

''?........

19.In fact the question whether the other party committed

breach cannot be decided by the party alleging breach. A

contract cannot provide that one party will be the arbiter to

decide whether he committed breach or the other party

committed breach. That question can only be decided by only an

adjudicatory forum, that is, a court or an Arbitral Tribunal.

20.In State of Karnataka v. Shree Rameshwara Rice Mills

this Court held that adjudication upon the issue relating to a

breach of condition of contract and adjudication of assessing

damages arising out of the breach are two different and distinct

concepts and the right to assess damages arising out of a

breach would not include a right to adjudicate upon as to

whether there was any breach at all. This Court held that one of

the parties to an agreement cannot reserve to himself the power

https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010

to adjudicate whether the other party has committed breach.

This Court held: (SCC p. 164, paras 7-8)

?7. ... Even assuming for argument's sake that the terms

of Clause 12 afford scope for being construed as empowering

the officer of the State to decide upon the question of breach as

well as assess the quantum of damages, we do not think that

adjudication by the officer regarding the breach of the contract

can be sustained under law because a party to the agreement

cannot be an arbiter in his own cause. Interests of justice and

equity require that where a party to a contract disputes the

committing of any breach of conditions the adjudication should

be by an independent person or body and not by the other party

to the contract. The position will, however, be different where

there is no dispute or there is consensus between the

contracting parties regarding the breach of conditions. In such

a case the officer of the State, even though a party to the

contract will be well within his rights in assessing the damages

occasioned by the breach in view of the specific terms of Clause

https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010

8.We are, therefore, in agreement with the view of the

Full Bench that the powers of the State under an agreement

entered into by it with a private person providing for assessment

of damages for breach of conditions and recovery of the

damages will stand confined only to those cases where the

breach of conditions is admitted or it is not disputed.?

9. Relying on the above judgments, the learned counsel for the

petitioner reiterated that the petitioner may be driven to the Civil Court only

in the event of permitting him to present their case. The basis on which a

decision is taken for issuing an order of demand itself is not explained to the

petitioner and under those circumstances, the petitioner has chosen to file the

present writ petition. Thus, the order impugned is directly in violation of the

principles of natural justice and the present writ petition is to be considered.

10. The learned counsel appearing on behalf of the respondents relying

on the counter affidavit made a submission that admittedly, the dispute arises

based on the contractual obligation between the parties. The impugned order

is in tune with the contract conditions, specifically condition No.5. Thus, the

https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010

writ petition is not maintainable, as such disputes are to be adjudicated before

the competent civil Court of law and not in a writ proceedings. The

respondents filed counter narrating facts and circumstances to establish that

the petitioner has violated certain terms and conditions and the manner in

which the calculations are made and the impugned demand notices are

issued.

11. However, this Court is of the considered opinion that all such

disputed facts cannot be adjudicated in a writ proceedings, as it requires

examination of documents in original and evidences and even oral evidences.

Prima facie, it is raised that no opportunity was provided to the petitioner,

even to present their case and it is to be considered. In a contractual

obligation between the parties, whether such a show cause notice or

opportunity is required to be given or not is to be considered. No doubt, it

depends on the facts and circumstances and also the terms and conditions

agreed between the parties. However, it cannot be concluded by holding that

in each and every case, a show cause notice and an opportunity of presenting

the case must be provided in contractual obligations. Thus, a writ cannot be

entertained merely on the ground that no opportunity to present the case is

https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010

given in the event of the dispute with reference to the terms and conditions of

the contract between the parties.

12. It is needless to state that the terms and conditions agreed are

known to the parties. Once agreed to the terms and conditions are violated,

the question of further opportunity by any one of the parties would not arise.

A dispute arises in the present case, as the petitioner states that an

opportunity is to be given to present their case. This Court is of an opinion

that such a procedure, which is not agreed between the parties need not be

considered, as providing of an opportunity is also a dispute, which is to be

considered with reference to the agreed terms and conditions of the contract.

13. The concept of principles of natural justice can be applied in a

contract only in certain circumstances and the performance of contractual

obligation between the parties cannot be compared with the statutory

functions of the authorities. Though in the present case, the Tamil Nadu

Electricity Board is a State under Article 12 of the Constitution of India.

Thus, a distinction is to be drawn between the contractual obligation between

the parties and the statutory functions and the powers to be exercised under

https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010

the statute by such officials of the State. These distinct factors are to be

demarcated when the facts are clear and more so relatable to the terms and

conditions of contract.

14. Presuming that a writ Court examines the terms and conditions of

the contract, a doubt arises whether it is possible to form an opinion with

reference to the factual disputes which is to be adjudicated in an elaborate

manner with reference to the original documents and evidences.

Undoubtedly, there is a possibility of error, omission, commission or

otherwise, if any such opinion is formed. That is the reason why the

Constitutional Courts have taken a consistent view that in the matter of

contractual obligations between the parties, they must approach the Civil

Court of law as it involves trial nature adjudication, which would provide an

opportunity to examine and cross examine the witnesses to cull out the truth

and resolve the issues in the manner known to law.

15. Per contra, based on the mere affidavit in a writ petition and

relying on certain xerox copies of the documents, which is enclosed in the

typed set of papers, such factually disputed issues can never be adjudicated in

https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010

a concrete manner so as to give complete justice to the parties, who are all

approaching the writ Court.

16. With reference to the judgment relied upon by the petitioner, the

Hon'ble Apex Court of India in Shree Rameshwara Rice Mills case cited

supra at paragraphs-7 and 8 itself held that “the position will, however, be

different where there is no dispute or there is consensus between the

contracting parties regarding the breach of conditions. In such a case the

officer of the State, even though a party to the contract will be well within his

rights in assessing the damages occasioned by the breach in view of the

specific terms of Clause 12”. Therefore, only in the event of no dispute and

there is a consensus between the contracting parties, the writ Court may be in

a position to take a decision in such nature of issues and not otherwise.

Therefore, the Hon'ble Supreme Court entertained the argument in a

particular case by distinguishing the facts and ruled that the contractual

obligations may be entertained by the writ Court only if there is no dispute

between the contracting parties and there is a consensus. Even in paragraph-

9, the Hon'ble Supreme Court observed that recovery of the damages will

stand confined only to those cases where, the breach of conditions is

https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010

admitted or it is not disputed.

17. In the present case, the demand notice is disputed by the petitioner,

the manner in which the Tamil Nadu Electricity Board assessed the damages

or otherwise is also questioned by the petitioner. In this regard, examination

in detail with reference to the terms and conditions of the contract are

imminent and require adjudication. Even in the other case relied on by the

petitioner, the proposition laid down by the Hon'ble Supreme Court in

J.G.Engineers Private Limited case (cited supra) is referred and in

paragraph-19 the Hon'ble Apex Court observed that “a contract cannot

provide that one party with the arbiter to decide whether he committed

breach or the other party committed breach. That question can only be

decided by only an adjudicatory forum, that is, a Court or an Arbitral

Tribunal”. Admittedly, in the present case, the parties have not agreed for

arbitration, thus, necessarily they have to approach the Competent Court of

law for the purpose of adjudicating issues.

18. Let us look into the reliance placed by the petitioner i.e. Clause:5

of the Memorandum of Understanding. Clause-5 reads as under:

https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010

“5.Performance of the cement company in collecting

100% of Fly Ash will be reviewed for a period of one year and

penalty deemed fit will be imposed for the short collection of Fly

Ash due to the fault of company after one year of the reviewed

period.”

19. The above clause reveals that the collection of fly ash will be

reviewed for a period of one year and penalty deemed fit will be imposed for

the short collection of fly ash due to the fault of the company. For

understanding purposes, this Court is of an opinion that the parties agreed

that the performance of the petitioner company will be reviewed and penalty

deemed fit will be imposed. Thus, the petitioner was very much aware and

agreed regarding imposition of penalty by the TANGEDCO. Question arises

whether an opportunity is to be provided prior to issuance of any such

demand notice. In this regard, it is stated in the Clause that penalty deemed

fit will be imposed for short collection of fly ash due to the fault of the

company. This exactly is the dispute to be adjudicated as the short collection

of fly ash and the quantum of short collection and the fault of the company or

https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010

there is no fault of the company and the quantum of penalty to be imposed

are disputed facts, which cannot be adjudicated in a writ proceedings.

20. These issues require an elaborate examination of the records and

evidences. As far as the opportunity is concerned, no doubt if there is a

consensus between the parties or if any doubt arises with reference to the

performance or otherwise, it is open to the parties to the contract to negotiate

and form an opinion and resolve the issues in an amicable manner. Therefore,

it is for the petitioner to approach the competent authorities, if they agree for

such consensus or for a negotiation and settlement of issues. However, the

impugned order is concerned, it is for the petitioner to initiate appropriate

steps for effective adjudication of the disputes for the purpose of redressing

their grievances in the manner known to law.

21. The petitioner if chosen to approach the competent Court of law for

resolving the issues, the Court shall consider the period in which the writ

petition was pending before the High Court for the purpose of condoning the

delay, if any petition to condone the delay is filed by the petitioner.

https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010

22. With these observations, the Writ Petition stands dismissed. No

costs. Consequently, connected Miscellaneous Petitions are closed

21.03.2023 Jeni Index : Yes Speaking order Neutral Citation : Yes

To

1.The Chairman, The Tamil Nadu Electricity Board, No.800, Anna Salai, Chennai 600 002.

2.The Chief Engineer, Civil Designs, Tamil Nadu Electricity Board, 3rd Floor, NPKRR Maaligai, No.144 Anna Salai, Chennai 600 002.

3.The Chief Engineer, Tamil Nadu Electricity Board, Mettur Thermal Power Station, Mettur Dam – 636 406.

https://www.mhc.tn.gov.in/judis W.P.No.25917 of 2010

S.M.SUBRAMANIAM, J.

Jeni

W.P.No.25917 of 2010

21.03.2023

https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter