Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Ringfeder Power Transmission ... vs Rajesh Mootha
2023 Latest Caselaw 8001 Mad

Citation : 2023 Latest Caselaw 8001 Mad
Judgement Date : 11 July, 2023

Madras High Court
Ringfeder Power Transmission ... vs Rajesh Mootha on 11 July, 2023
                                                                         ARB. O.P.(Com. Div) No.298 of 2023

                                  IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                    DATED : 11.07.2023

                                                         CORAM

                                  THE HON'BLE MR.JUSTICE ABDUL QUDDHOSE

                                         ARB. O.P.(Com. Div) No.298 of 2023
                                                         and
                                           Arb. Application No.184 of 2023,
                                      O.A. No.293 of 2023 and A. No.2851 of 2023

                Ringfeder Power Transmission India Private Ltd.,
                Represented by its Managing Director
                Mr.Dheepan Ramalingam
                No.4, Mount Poonamallee Road,
                Kattupakkam,
                Chennai – 600 056.                        ...                Petitioner
                                             vs.
                Rajesh Mootha
                No.555, MKN Road,
                Alandur,
                Chennai – 600 016.                        ...                Respondent

                Prayer : Arbitration Original Petition (Commercial Division) filed under
                Section 11(6) of the Arbitration and Conciliation Act, 1996 to appoint an
                Arbitrator to adjudicate the dispute between the petitioner and the respondent in
                terms of the Agreement dated 29.04.2021and to direct the respondents to pay
                costs.

                                   For Petitioner       : Mr.C. Suraj
                                   For Respondent       : Mr.Anish Gopi
                                                          for M/s.P.B. Ramanujam Associates




https://www.mhc.tn.gov.in/judis
                1/18
                                                                                    ARB. O.P.(Com. Div) No.298 of 2023

                                                ORDER

Arbitration O.P. (Comm. Div.) No.298 of 2023 has been filed by the

petitioner seeking for appointment of an Arbitrator under Section 11 of the

Arbitration and Conciliation Act, 1996.

2. There seems to be a dispute between the petitioner and the respondent

under a Built Suit Facility Agreement dated 29.04.2021. Under the aforesaid

agreement, the respondent has agreed to construct a building and thereafter on

completion hand over possession of the same and grant sub lease in favour of

the petitioner for a specified period. Advance payments have been made by the

petitioner to the respondent under the Built Suit Facility Agreement dated

29.04.2021.

3. According to the petitioner, the respondent has committed breach of

contract by not adhering to the terms and conditions of the Built Suit Facility

Agreement dated 29.04.2021. There is an arbitration agreement in the Built

Suit Facility Agreement dated 29.04.2021 which is extracted hereunder :

12. GOVERNING LAW AND ARBITRATION :

12.1 Governing Law : This Agreement is governed by and shall be construed in accordance with the laws of the Republic of India.

12.2 Dispute Resolution : The non-defaulting party may give written notice of the Dispute to the defaulting party on the occurrence of the Event of Default as provided under Clause 7(a), (b), (e), (f), (g), (h), (i), (j) & (k) of this Agreement which gives rise to such dispute or on the day such event comes to the notice of the applicable Party. If any dispute arising between the Parties

https://www.mhc.tn.gov.in/judis

ARB. O.P.(Com. Div) No.298 of 2023

are not amicably settled within (7) seven days of commencement of attempts to settle the dispute, the Dispute shall be referred to and be finally adjudicated by Arbitration. For sake of clarity, the parties agree that the seven days period herein provided runs simultaneously along with the seven days exercise their right under Clause 8(a) & Clause 8(c) of this Agreement.

12.3 Arbitration : The Parties agree that the Seat of Arbitration proceedings will be Chennai in the English language in accordance with the provisions of the Arbitration and Conciliation Act, 1996 as it then would be prevalent by a Sole arbitrator mutually appointed by the Parties. The decision of the sole arbitrator shall be final and binding on the Parties.

4. The petitioner seeks for refund of the advance amount together with

interest and damages from the respondent for the alleged breach of contract

committed by the respondent under the Built Suit Facility Agreement dated

29.04.2021. The petitioner had sent a termination notice on 24.02.2023 to the

respondent terminating the contract i.e., Built Suit Facility Agreement dated

29.04.2021. The petitioner has also appointed an Arbitrator and has initiated

arbitration by invoking the Arbitration Clause available in the Built Suit

Facility Agreement dated 29.04.2021 by sending a notice of invocation to the

respondent on 29.03.2023. A reply dated 19.04.2023 has also been sent by the

respondent to the petitioner denying the contentions of the petitioner.

Thereafter, the petitioner had filed two applications under Section 9 of the

https://www.mhc.tn.gov.in/judis

ARB. O.P.(Com. Div) No.298 of 2023

Arbitration and Conciliation Act, 1996 viz., Arbitration Application No.184 of

2023 and O.A. No.293 of 2023.

5. Arbitration Application No.184 of 2023 was filed seeking for a

direction to the respondent to furnish security by way of a Bank Guarantee to

the extent of the advance amounts paid by the applicant and O.A. No.293 of

2023 was filed for an injunction to restrain the respondent from not putting up

any further construction and from handing over possession of the property to a

third party. The respondent had entered appearance in the said applications and

they have filed an application in Application No.2851 of 2023 seeking for

dismissal of Arbitration Application No.184 of 2023 filed by the applicant on

the ground that the Arbitration Agreement, which the applicant relies upon is

contained in an insufficiently stamped document. All the three applications are

still pending consideration and is listed before this Court today. Subsequent to

the filing of the aforesaid applications, Arbitration O.P. (Comm. Div.) No.298

of 2023 has been filed under Section 11 of the Arbitration and Conciliation Act,

1996 by the applicant based on the Arbitration Agreement seeking for

appointment of an Arbitrator by this Court.

https://www.mhc.tn.gov.in/judis

ARB. O.P.(Com. Div) No.298 of 2023

6. The learned counsel for the respondent in Arbitration O.P. (Comm.

Div.) No.298 of 2023 would submit that the contentions of the respondent,

which have been stated in Application No.2851 of 2023, wherein the

respondent had filed an application to dismiss the application namely

Arbitration Application No.184 of 2023 filed by the applicant under Section 9

of the Arbitration and Conciliation Act, 1996 can be treated as counter to the

application filed by the applicant under Section 11 of the Arbitration and

Conciliation Act, 1996 seeks for appointment of an Arbitrator by this Court.

7. The sum and substance of the dispute between the parties in this

Section 11 application viz., Arbitration O.P. (Comm. Div.) No.298 of 2023 is

whether the Built Suit Facility Agreement dated 29.04.2021 is an agreement

which comes under the purview of Article 5(i) of Indian Stamp Act, 1899,

which deals with an agreement relating to construction, or will it fall under the

purview of Article 5(j) which deals with an agreement not specifically provided

for under Article 5. The contention of the petitioner in this Section 11

application is that the agreement which the petitioner has entered into with the

respondent is in the nature of an agreement to enter into a lease and therefore,

Article 5(j) gets attracted and the stamp duty payable for the said Agreement is

only Rs.20/-. According to the applicant, the Built Suit Facility Agreement https://www.mhc.tn.gov.in/judis

ARB. O.P.(Com. Div) No.298 of 2023

dated 29.04.2021, has been sufficiently stamped in accordance with Article 5(j)

of the Indian Stamp Act, 1899 by affixing a stamp duty of Rs.20/-. However,

according to the respondent, the Built Suit Facility Agreement dated

29.04.2021 is insufficiently stamped. According to the learned counsel for the

respondent being an agreement relating to construction of a building, the stamp

duty payable by the petitioner for the said agreement will fall within the

purview of Article 5(i) of the Indian Stamp Act, 1899, which relates to

construction of building. According to him, as per the said Article, the Stamp

duty payable is Rupee one for every Rs.100/- or part thereof of the cost of the

proposed construction or the value of the construction or the consideration

specified in the agreement, whichever is higher.

8. The learned counsel for the petitioner relied upon relevant Clauses in

the Built Suit Facility Agreement dated 29.04.2021, wherein an arbitration

agreement is found. After relying upon the said Clauses, he would submit that

the Built Suit Facility Agreement dated 29.04.2021 is only an agreement to

enter into a future lease as the petitioner has not been put in possession of the

property. The learned counsel for the petitioner also relied upon Section

17(2)(v) of the Registration Act, 1908 and would submit that since the Built

Suit Facility Agreement dated 29.04.2021 merely creates a right for the https://www.mhc.tn.gov.in/judis

ARB. O.P.(Com. Div) No.298 of 2023

petitioner to obtain another document in the nature of a sublease agreement

from the respondent, the question of payment of Stamp duty as per Section

(5)(i) will not arise. He would also submit that as on date, the petitioner does

not have any vested right over the super structure constructed by the respondent

and therefore, the stamp duty payable by the petitioner under the Built Suit

Facility Agreement dated 29.04.2021 is only under Article 5(j) of the Indian

Stamp Act i.e., Rupees twenty only.

9. The learned counsel for the petitioner would also submit that the

decision of the Hon'ble Supreme Court in the case of N.N.Global Mercantile

Private Ltd., vs. Indo Unique Flame Ltd. And others reported in 2023 SCC

Online SC 495 has no applicability to the facts of the instant case. He would

submit that in the aforesaid decision of the Hon'ble Supreme Court, it has been

made clear that the said decision was pronounced by the Hon'ble Supreme

Court not with reference to an application under Section 9 of the Arbitration

and Conciliation Act, 1996. He would also submit that the facts of the case in

the decision of the Hon'ble Supreme Court referred to supra are totally different

from the facts of the instant case. According to the learned counsel for the

petitioner, since the petitioner was not put in possession and does not have any

vested right as on date over the constructed portion of the building nor over the https://www.mhc.tn.gov.in/judis

ARB. O.P.(Com. Div) No.298 of 2023

land, the decision of the Hon'ble Supreme Court referred to supra has no

applicability to the facts of the instant case. In support of his stand that only in

cases where it is evident that possession, right or title is passed on to the

applicant under the agreement, the question of payment of Stamp duty under

Article 5(i) may arise. He relied upon a judgment of the Hon'ble Supreme

Court in the case of Food Corporation of India and others vs. Babulal

Agrawal reported in 2004 2 SCC 712. He would submit that in the said

judgment, it has been made clear that only in cases, where under an agreement

a person has been put in possession and a right or title has been created in his

favour at the time of the agreement, the document requires to be stamped as per

Article 5(i) of the Stamp Act and is admissible in evidence.

10. Learned counsel for the petitioner would submit that in the case on

hand, under the Built Suit Facility Agreement dated 29.04.2021, it has been

made clear that it is in the nature of an agreement to enter into a lease as the

sublease agreement will be entered into between the parties only after the due

performance of the Built Suit Facility Agreement dated 29.04.2021 by the

respondent. He would submit that being in the nature of an agreement to enter

into a lease, it is only an executory agreement and not an agreement creating

rights in the immovable property in favour of the petitioner and therefore, the

requirement to pay Stamp Duty as per Article 5(i) will not arise. https://www.mhc.tn.gov.in/judis

ARB. O.P.(Com. Div) No.298 of 2023

11. Per contra, learned counsel appearing for the respondent would

reiterate the contents of the application filed by the respondent seeking for

dismissal of Section 9 applications filed by the applicant by stating that the

Built Suit Facility Agreement dated 29.04.2021 is in the nature of an agreement

for construction and therefore, the stamp duty payable will fall under the

purview of Article 5(i) of the Indian Stamp Act, 1899 and not under Article

5(j). He also drew the attention of this Court to the decision of the Hon'ble

Supreme Court in the case of case of N.N.Global Mercantile Private Ltd., vs.

Indo Unique Flame Ltd. And others reported in 2023 SCC Online SC 495

referred to supra. In particular, he referred to paragraphs 117, 118, 120 of the

said judgment. He would submit that as seen from the aforesaid decision of the

Hon'ble Supreme Court, an instrument, which is exigible to stamp duty, which

contains an Arbitration Clause and which is insufficiently stamped, cannot be

said to be a contract within the meaning of Section 2(h) of the Contract Act

and enforceable as per Section 2(g) of the Contract Act. He would further

submit that as seen from the aforesaid decision of the Hon'ble Supreme Court

an arbitration agreement in an unstamped instrument, when it is mandatorily

required to be stamped is not an enforceable arbitration agreement.

12. Relying upon the aforesaid decision of the Hon'ble Supreme Court,

the learned counsel for the respondent would submit that the Built Suit https://www.mhc.tn.gov.in/judis

ARB. O.P.(Com. Div) No.298 of 2023

Facility Agreement dated 29.04.2021 which contains the Arbitration Clause has

been insufficiently stamped and therefore, not admissible in evidence and

therefore, the Arbitration agreement contained therein cannot be acted upon by

the applicant for the purpose of seeking appointment of an Arbitrator by this

Court under Section 11 of the Arbitration and Conciliation Act, 1996.

Discussion :

13. As seen from the terms and conditions of the Built Suit Facility

Agreement dated 29.04.2021 entered into between the petitioner and the

respondent it is in the nature of an agreement to enter into a lease. The

petitioner has agreed to enter upon the property which has been allotted to the

respondent by SIPCOT on completion of the construction by the respondent as

per the Built Suit Facility Agreement dated 29.04.2021. The same is also not

disputed by the respondent as seen from his application filed to dismiss the

Section 9 application filed by the petitioner. The relevant Clauses in the Built

Suit Facility Agreement dated 29.04.2021 also confirms that the petitioner will

be put in possession of the property only after the completion of the

construction by the respondent as per the Built Suit Facility Agreement dated

29.04.2021. Admittedly, the Built Suit Facility Agreement dated 29.04.2021

contains an Arbitration agreement which is stated supra.

https://www.mhc.tn.gov.in/judis

ARB. O.P.(Com. Div) No.298 of 2023

14. The only issue that arises for consideration in this Section 11

application is whether the agreement viz., the Built Suit Facility Agreement

dated 29.04.2021 has been properly stamped or not. According to the petitioner

it is properly stamped, whereas the respondent contends that it is insufficiently

stamped. According to the respondent, the agreement viz., Built Suit Facility

Agreement dated 29.04.2021 is in the nature of an agreement for construction

and therefore Article 5(i) of the Indian Stamp Act, 1899 applies, whereas the

petitioner contends that the Built Suit Facility Agreement, dated 29.04.2021

will fall under Article 5(j) of the Stamp Act and hence the stamp duty paid at

Rs.20/- is correct.

15. Article 5(i) and 5(j) of the Indian Stamp Act, 1899 reads as follows :-


                 5(i)                           If relating to construction of One rupee for every hundred
                                                building                       rupees or part thereof of the
                                                                               cost    of   the    proposed
                                                                               construction or the value of
                                                                               construction      or      the
                                                                               consideration specified in
                                                                               the agreement, whichever is
                                                                               higher.

Explanation – For the purpose of this clause, “building” includes any unit, residential, commercial, institutional, industrial or otherwise proposed to be constructed on an undivided share of land 5(j) If not otherwise provided [Twenty rupees] Exemptions :-

Agreement or memorandum of agreement : (a) for or relating to the purchase or sale of goods or merchandise exclusively not being an agreement or memorandum of agreement chargeable under clause (d), clause (e), clause (f), clause (g), or clause (h) of this article or a note or memorandum chargeable under No.43; (b) made in the form of tenders to the Central Government for, or relating to any loan

https://www.mhc.tn.gov.in/judis

ARB. O.P.(Com. Div) No.298 of 2023

16. When it is not in dispute that the petitioner has not been put in

possession of the property and no rights over the property has been created in

its favour under the Built Suit Facility Agreement dated 29.04.2021, the

question of payment of Stamp Duty as per Article 5(i) of the Indian Stamp Act,

1989 will not arise for the following reasons :-

a) The Built Suit Facility Agreement dated 29.04.2021 does not

confer any vested right over the property in favour of the petitioner.

b) The petitioner has paid only the advance amounts to the

respondent under the Built Suit Facility Agreement dated 29.04.2021

and according to the petitioner, the respondent has committed breach of

contract. It is also seen from the Clauses contained in the agreement

that only after completion of the construction by the respondent and on

payment of the consideration by the petitioner, the respondent will put

the petitioner in possession of the property, whereas that stage has not

arisen as of now.

c) The Built Suit Facility Agreement dated 29.04.2021 also

stipulates that in future, the parties will have to enter into a sub lease

agreement on completion of the construction by the respondent under

which, the petitioner will be put in possession of the property.

https://www.mhc.tn.gov.in/judis

ARB. O.P.(Com. Div) No.298 of 2023

d) Article 5(j) of the Indian Stamp Act, 1899 which deals with

agreements which are not otherwise provided will get attracted in view

of the fact that the nature of the Built Suit Facility Agreement dated

29.04.2021 is only in the nature of an agreement to enter into a lease

and is not the final agreement which the parties have agreed to enter

into in the near future on completion of the construction by the

respondent.

17. It is clear from the Hon'ble Supreme Court's decision relied upon by

the learned counsel for the petitioner in the case of Food Corporation of India

and others vs. Babulal Agrawal reported in 2004 2 SCC 712, that when no

possession, right or title has passed on to the petitioner in praesenti at the time

of the execution of the agreement, such an agreement is only an executory

agreement and not an agreement creating rights in the immovable property.

The Built Suit Facility Agreement dated 29.04.2021 which contains an

Arbitration Clause is one such agreement which has not created any rights as on

date of the agreement for the petitioner over the property in question. Hence,

the petitioner has properly valued the said agreement by paying the proper

stamp duty of Rs.20/- as per Article 5(j) of the Indian Stamp Act, 1899.

18. The petitioner has also terminated the contract by its termination

notice dated 24.02.2023 on account of the alleged breach of contract committed https://www.mhc.tn.gov.in/judis

ARB. O.P.(Com. Div) No.298 of 2023

by the respondent. The petitioner is also not seeking any rights over the

property in question and therefore, the Stamp Duty of Rs.20/- affixed in the

Built Suit Facility Agreement dated 29.04.2021 which contains an Arbitration

Clause is correct and only in accordance with the residuary Clause viz., Article

5(j) of the Indian Stamp Act, 1899, the stamp duty has been paid at Rs.20/-

19. The Constitution Bench judgment of the Hon'ble Supreme Court

relied upon by the learned counsel for the respondent in the case of

N.N.Global Mercantile Private Ltd., vs. Indo Unique Flame Ltd. And others

reported in 2023 SCC Online SC 495 has no applicability to the facts of the

instant case as in that decision, possession was delivered to the respondent.

Since the petitioner has satisfied that the document, viz., Built Suit Facility

Agreement dated 29.04.2021 has been properly stamped in accordance with

law, the Constitution Bench judgment of the Hon'ble Supreme Court relied

upon by the learned counsel for the respondent in the case of N.N.Global

Mercantile Private Ltd., vs. Indo Unique Flame Ltd. And others reported in

2023 SCC Online SC 495 has no bearing for the instant case as that was a

decision, where the subject document was insufficiently stamped and the

Hon'ble Supreme Court has held that an Arbitration agreement contained in the

insufficiently stamped document cannot be acted upon. Whereas in the instant

case since the agreement viz., Built Suit Facility Agreement dated 29.04.2021 https://www.mhc.tn.gov.in/judis

ARB. O.P.(Com. Div) No.298 of 2023

which contains an Arbitration Clause has been sufficiently stamped in

accordance with Article 5(j) of the Indian Stamp Act 1899, the arbitration

agreement contained therein is a valid arbitration agreement and is an

enforceable one.

20. For the foregoing reasons, the petition filed by the petitioner in

Arbitration O.P. (Comm. Div.) No.298 of 2023 under Section 11 of the

Arbitration and Conciliation Act, 1996 seeking for appointment of an

Arbitrator by this Court is maintainable as the arbitration agreement in the Built

Suit Facility Agreement dated 29.04.2021 is a valid arbitration agreement. The

petitioner has invoked the arbitration prior to the filing of this petition by

sending a notice to the respondent on 29.03.2023, which has been duly

acknowledged by the respondent, who has also sent a reply on 19.04.2023.

Since there was no consensus between the parties with regard to the name of

the Arbitrator, the petitioner was constrained to file this application under

Section 11 of the Arbitration and Conciliation Act seeking for appointment of

an Arbitrator.

21. For the foregoing reasons, necessarily, this Court will have to appoint

an Arbitrator since there is a valid arbitration agreement and there has been no

consensus between the parties for appointment of an Arbitrator. Accordingly,

this petition is allowed as prayed for in Arbitration O.P. (Comm. Div.) No.298 https://www.mhc.tn.gov.in/judis

ARB. O.P.(Com. Div) No.298 of 2023

of 2023 by appointing Mr.P.V. Balasubramaniam, learned Senior Advocate as

Arbitrator to decide the disputes / differences between the parties arising out of

the Built Suit Facility Agreement dated 29.04.2021 on merits and in

accordance with law and pass an Arbitral Award accordingly by issuing the

following directions :

(a) This Court appoints Mr.P.V. Balasubramaniam, learned

Senior Advocate, who is having office at No.47/2, Rams Surabhi

Apartments, 1st Main Road, R.A.Puram, Chennai - 600 028, (Mobile

No.9841041888) as a sole Arbitrator to decide the disputes between

the petitioner and the respondent arising out of the Built Suit Facility

Agreement, dated 29.04.2021.

(b) The Arbitrator shall be paid his remuneration / fees in

accordance with the 4th schedule of the Arbitration and Conciliation

Act, 1996.

(c) Both the parties shall equally share the arbitrator's fees.

(d) The Arbitrator shall conduct the arbitration in accordance

with the provisions of the Arbitration and Conciliation Act, 1996 and

shall complete the arbitration within the specified time as prescribed

under the said Act.

https://www.mhc.tn.gov.in/judis

ARB. O.P.(Com. Div) No.298 of 2023

22. The Section 9 applications viz., Arbitration Application No.184 of

2023 and O.A. No.293 of 2023 are disposed of by directing the applicant to

approach the Arbitrator for seeking the said reliefs by filing applications under

Section 17 of the Arbitration and Conciliation Act, 1996. It is for the

Arbitrator to decide the merits of those interim applications as and when they

are filed and decide the same in accordance with law. Consequently

application Nos.2851 of 2023 filed by the respondent is closed. No costs.

11.07.2023

vsi2

https://www.mhc.tn.gov.in/judis

ARB. O.P.(Com. Div) No.298 of 2023

ABDUL QUDDHOSE, J.

vsi2

ARB. O.P.(Com. Div) No.298 of 2023

11.07.2023

https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter