Friday, 15, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

P.Janakiraman vs The Commissioner
2023 Latest Caselaw 9852 Mad

Citation : 2023 Latest Caselaw 9852 Mad
Judgement Date : 8 August, 2023

Madras High Court
P.Janakiraman vs The Commissioner on 8 August, 2023
                                                                                      C.S.No. 642 of 2018



                             IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                  Dated : 08.08.2023

                                                        CORAM

                                    THE HONOURABLE Ms. JUSTICE P.T. ASHA


                                                   C.S.No. 642 of 2018


                     P.Janakiraman                                             ... plaintiff

                                                           Vs.


                     1.The Commissioner,
                     Corporation of Chennai,
                     Ripon Buildings, Chennai – 600 003.

                     2.The Superintending Engineer,
                     Bus Route Road Department,
                     Corporation of Chennai, Ripon Buildings,
                     Chennai – 600 003.                                        ... defendants


                     Prayer: Plaint filed under Order IV Rule (1) of OS Rules High Court
                     Madras, 1956 read with Order VII Rule (1) of CPC, 1908, for
                                  (a)Directing the defendants to pay a sum of Rs.6,18,00,341/-
                     and pay interest @ 12% from the date of plaint till the date of
                     realisation on Rs.2,60,76,222/-.
                     1/26



https://www.mhc.tn.gov.in/judis
                                                                                          C.S.No. 642 of 2018




                                  (b)Grant such other relief or reliefs as the Hon'ble Court may
                     deem fit and proper in the circumstances of the case.



                                        For Plaintiff     :     Mr. V.Srikanth

                                        For Defendants    :     Mr. Bharath Gowtham
                                                                for Ms.Aswini Devi



                                                        JUDGEMENT

The above suit is filed for recovery of a sum of Rs.6,18,00,341/-

together with interest at 12% per annum from the date of the plaint till

the date of realisation of sum of Rs.2,60,76,222/-.

Plaintiff's case:

2. It is the case of the plaintiff that the defendants had floated

tender for laying of cement concrete road for the stretch from

(i)Ennore Road to Joint Canal Bridge, (ii)Tiruvottiyur High road to

Vaidhyanathan Bridge and (iii)Muthamizh Nagar, 5th Main Road

https://www.mhc.tn.gov.in/judis C.S.No. 642 of 2018

(from north Avenue to South Avenue).

3. The plaintiff had participated in the tender on 23.07.2004.

However, it was only on 27.04.2005 that the 2nd defendant had issued

a letter of acceptance and the site was handed over to the plaintiff on

04.07.2005. The period of contract was fixed at 6 months. The

defendants had taken a year for entrusting the work from the date of

tender, as a result the prices of raw material had increased

substantially.

4. By letter dated 04.10.2005, the plaintiff informed the 2nd

defendant that sufficient site was available only at Muthamizh Nagar,

5th main road and not at Vaidyanathan road and Manali road and

stated that this was only on account of the delay on the part of the

corporation of Chennai. The plaintiff therefore requested the 2nd

defendant to arrange for the sufficient site so that the work in the

other two roads also be completed within the time frame of the

https://www.mhc.tn.gov.in/judis C.S.No. 642 of 2018

contract. The 2nd defendant had responded by calling upon the

plaintiff to submit PERT/CPM chart by letter dated 25.11.2005. By

letter dated 17.12.2005, the plaintiff had submitted PERT chart for the

said three roads individually.

5. The plaintiff would further submit that in May 2006, on

account of assembly election, the plaintiff was not in a position to

continue the work and therefore by letter dated 17.05.2006, the

plaintiff had requested the 2nd defendant to grant an extension of time

by further period of 4 months from 04.04.2006. By letter dated

25.07.2006, the 1st defendant had granted the extension for a period of

6 months on condition that from 04.04.2006 a fine of Rs.5,000/- per

day would be levied and action would be initiated to debar the

plaintiff, in case the work is not completed before 31.08.2006.

6. The plaintiff would submit that on account of efflux of time,

the prices of the raw materials also increased and therefore, the

https://www.mhc.tn.gov.in/judis C.S.No. 642 of 2018

plaintiff once again vide letter dated 06.09.2006 had sought for

extension upto 30.11.2006. The 2nd defendant by letter dated

28.09.2006 granted the extension, after imposing the penalty of

Rs.5,000/- per day upto 30.11.2006. Although the plaintiff by letter

dated 04.10.2006 had requested the 2nd defendant to obtain orders

from the competent authority for escalation of prices since prices of

raw materials and labour had gone up, the 1st defendant by letter dated

14.11.2006 had turned down the request and levied the penalty of

Rs.5,000/- per day upto 30.11.2006.

7. The 2nd defendant had declined the request for escalation of

prices vide their letter dated 24.01.2007, however, granted extension

upto 28.02.2007 to complete all the minor works. The plaintiff

thereafter vide letters dated 31.01.2007 and 01.02.2007 had requested

the defendants to waive fine of Rs.5,000/- per day and once again

requested them to re-consider the plaintiff's request for price

escalation. This request was once again reiterated vide letter dated

https://www.mhc.tn.gov.in/judis C.S.No. 642 of 2018

12.02.2007 and 30.08.2007, none of which was responded to.

8. By letter dated 23.05.2008, the plaintiff had set out the

reasons for the delay and reasons for requesting an escalation of price.

It was their contention that they were unable to take up work in

Manali road from Ennore road to Joint Canal Bridge, since there were

several underground cables running on this road and it was not

possible to shift / remove the cables and proceed with the laying of

the road. In the light of these hurdles, hindrances and difficulties, the

defendants themselves had pre-closed contract with reference to this

stretch of the road and the final bill was disbursed to the plaintiff on

13.03.2007.

9. This would clearly go to prove that the defendants had not

made available the road for which the plaintiff had tendered. The

plaintiff therefore submitted a claim as detailed herein below:

https://www.mhc.tn.gov.in/judis C.S.No. 642 of 2018

Claim No.1 Request payment for the difference in cost between the agreement rate and the escalated rate during the extended period of contract Rs.22,63,751/-

                                  Claim No.2           Request to refund the fine imposed
                                                       and recovered against the terms and
                                                       conditions       of         contract
                                                       Rs.4,15,271/-
                                  Claim No.3           Request payment for the prevention
                                                       of profit earning due to foreclosure
                                                       of contract at Rs.32,43,323/-
                                  Claim No.4           Request payment for the loss of
                                                       profit and over heads due to
                                                       prolongation      of    contract
                                                       Rs.2,01,54,377/-.


10. By letter dated 30.11.2010, the plaintiff had called upon the

2nd defendant to give his decision with reference to each of these

claims, for which there was no response. The plaintiff had addressed

several letters in this regard, to which the defendants had not sent any

reply and ultimately by letter dated 04.05.2011 the request was

rejected as one without basis since the delay according to the

https://www.mhc.tn.gov.in/judis C.S.No. 642 of 2018

defendants was only on account of the plaintiff's lethargic and casual

attitude.

11. Therefore, the plaintiff had preferred an appeal vide their

communication dated 28.05.2011 and requested the defendants to give

decision and stating that in case the authorities are not re-considering

their decision, the plaintiff would be initiating arbitration proceedings

as contemplated under Clause 7.8. Since there was no reply from the

2nd defendant, the plaintiff by letter dated 21.06.2011 had requested

the dispute to be referred to an arbitrator. The 2nd defendant had

replied that there was no provision to consider escalation of price and

therefore the request for appointing arbitrator would not arise. The

plaintiff therefore was constrained to file O.P.No.700 of 2012 under

Section 11 of the Arbitration and Conciliation Act, 1996, seeking

appointment of an arbitrator.

https://www.mhc.tn.gov.in/judis C.S.No. 642 of 2018

12. The defendants had contested the same to the effect that the

resolution through arbitration was available only in cases of claims

below Rs.50,000/- and in all other cases, it was only the Civil Court

that had jurisdiction to deal with the matter. This statement was

recorded by order dated 30.10.2017 and the plaintiff was given liberty

to move the Civil Court. Therefore, the present suit.

13. The 1st defendant had filed a written statement inter alia

denying the very claim of the plaintiff. The defendants had submitted

that the suit was barred by limitation. It is the case of the defendants

that the plaintiff alone was a bidder and the plaintiff had quoted cost

which was 40.12% higher than the office estimate. After negotiation,

the plaintiff had reduced the quote to a sum of Rs.4,22,59,177.40/-

which is 8.11 % higher than the office estimate. Since there were no

bidder and considering the extensive damage to the roads, the

defendants were compelled to award tender to the plaintiff taking into

account the public welfare.

https://www.mhc.tn.gov.in/judis C.S.No. 642 of 2018

14. The defendants would submit that the site was handed over

to the plaintiff on 04.07.2005. As per tender condition no.1-16, the

tender period for competing the work on the three roads was 6 months

from the date of handing over of the site and therefore the work

should have been completed on or before 04.02.2006. However, on

the request of the plaintiff, the contract was extended for a further

period of 6 months from 04.01.2006 for completing the works at the

three sites. Despite the extension, the plaintiff had not taken steps to

expedite the work and the defendants were constrained to send letters

dated 20.04.2006, 28.04.2006 and 17.05.2006, requesting the plaintiff

to expedite the work at Muthamizh Nagar and Vaidyanathan Salai and

to commence the work at Manali road. The defendants had also

intimated the plaintiff that if no action was taken by the plaintiff then

they would have to invoke the tender condition.

https://www.mhc.tn.gov.in/judis C.S.No. 642 of 2018

15. On 17.05.2006, the plaintiff had requested the extension of

time for a further period of 4 months from 04.06.2006. However,

during this extended period the work at Vaidyanathan salai remained

only at the sand and gravel mix level and at Muthamizh Nagar had

progressed to the laying of about 30% of the total length and beyond

this the plaintiff had not shown any progress. The plaintiff appeared

to be working at his convenience and had not given importance to the

public need. Therefore, the defendant had decided to impose penalty

for the delay and non-completion of work by way of penalty of

Rs.5,000/- per day.

16. Though the plaintiff had been entrusted with the work at

three sites, he had only completed the work at 2 sites and the work at

Manali road was dropped since the plaintiff had not even commenced

the work and thereafter the work was finished by another contractor.

The defendant had set out the amounts that had been paid to the

plaintiff with reference to both Muthamizh Nagar and Vaidyanathan

https://www.mhc.tn.gov.in/judis C.S.No. 642 of 2018

salai and had also stated that a sum of Rs.34,81,037/- had been

retained. The defendants had submitted that the claim was highly

exorbitant and without jurisdiction. Therefore, they sought to have

the suit dismissed.

17. This Court by order dated 13.07.2021 had framed the

following issues:

“(i) Whether the suit is within the limitation in view

of the order passed in O.P.No.700 of 2012 dated

30.10.2017?

(ii) Whether the plaintiff is entitled for the suit claim

of Rs.6,18,00,341/- with interest as prayed?

(iii) Whether the request of the plaintiff seeking

extension of time to execute the contract and waiver of

fine imposed will dis-entitled the plaintiff seeking

payment of differences in cost between the agreed rate

and accelerate rate, refund the fine imposed and recover,

https://www.mhc.tn.gov.in/judis C.S.No. 642 of 2018

payment for the prevention of profit arising due to

foreclosure and payment of loss of profit and over its due

to prolongation of contract and

(iv) what other relief, the plaintiff is entitled?

18. The plaintiff had examined P.W.1 and marked Ex.P.1 to

Ex.P.29. On the side of the defendants D.W.1 was examined and

Ex.D.1 to Ex.D.11 were marked on their side.

19. The defendants had raised the preliminary issue of

limitation. Therefore, this Court proceeded to hear the arguments

with reference to limitation on account of the fact that if the issue is

answered in favour of the defendants it would bring the suit to an end.

20. Mr. V.Srikanth, learned counsel for the plaintiff would

submit that though the final bill was settled on 17.08.2007, however,

the rejection of the claim by the defendants was only on 04.05.2011

https://www.mhc.tn.gov.in/judis C.S.No. 642 of 2018

and therefore the time for filing the suit would commence from

14.08.2011 and therefore there is no limitation. The learned counsel

would further submit that as soon as the claim was rejected, the

plaintiff had taken steps to request the defendants to appoint an

arbitrator as per the terms of the contract and ultimately the petition

under Section 11 of the Arbitration and Conciliation Act was ordered

only on 30.10.2017 and therefore the suit is well within time.

21. The learned counsel would rely upon the Judgement of this

Court reported in 2022 SCC Online Mad 3618 – P.P.Thomas Vs.

State of Tamil Nadu, wherein, the learned Judge on examining the

rival contention in the said suit had held that it was only Article 113

that would be applicable for a consolidated suit claim and limitation

period would run from the date when the right to sue first accrues.

22. Per contra, Mr. Bharath Gowtham appearing on behalf of

the defendants would submit that the plaintiff had received the final

https://www.mhc.tn.gov.in/judis C.S.No. 642 of 2018

bill on 17.08.2007 without demur and in fact the same was not even

received under protest. He would rely upon the legal notice issued by

the plaintiff on 23.05.2008, Ex.P.17, where the plaintiff had only

sought for recovery of a sum of Rs.2,01,54,377/- towards loss of

profits and overheads. Therefore, he would submit that the suit which

is filed in the year 2018 in respect of the claim which has been settled

finally in the year 2007 is clearly barred by limitation.

23. The learned counsel would rely upon the Judgement of the

Hon'ble Supreme Court reported in 2016 (14) SCC 761 – State of

Gujarat Vs. Kothari and Associates.

Discussion:

24. As already observed, if the issue of limitation goes in favour

of the defendants then the suit has to be dismissed. However, if the

Court comes to a decision that the suit is not barred by limitation, it is

only then the other issues have to be considered.

https://www.mhc.tn.gov.in/judis C.S.No. 642 of 2018

25. Admittedly, the plaintiff has received the final payment on

17.08.2007 and when he had received the payment, he has not

objected to the same or contended that he is receiving the same

without prejudice to his claim. On the contrary, the plaintiff has

received the amount towards full and final settlement of his dues

under the contract. The subsequent communication of the plaintiff

calling upon the defendants to appoint an arbitrator appears to be an

after thought particularly on considering the notice, Ex.P.17, which

was issued within 10 months of the plaintiff receiving full and final

settlement, in the said notice for the first time the plaintiff has made a

claim with reference to the delay, escalation of prices etc., and had

called upon the defendants to pay a sum of Rs.32,43,323/- towards

compensation for loss of profit for work not done and

Rs.2,01,54,377/- towards loss of profit due to prolongation of

contract, though the full payment was received by the plaintiff on

17.08.2007 there was no response. Further, the plaintiff has not taken

https://www.mhc.tn.gov.in/judis C.S.No. 642 of 2018

any steps whatsoever to institute the suit.

26. The Hon'ble Supreme Court in the Judgement reported in

2016 (14) SCC 761 – State of Gujarat Vs. Kothari and Associates,

was considering the similar case, where the respondent who had

participated in the tender floated by the State of Gujarat in that case,

for every extension that was granted to the contractor had sought for

compensation for the monetary loss due to the extended time limit and

on every occasion the State had denied the compensation. The

contractor had also received the full payment under protest on

01.01.1982 and the security deposit was also refunded. On

07.08.1983, the contractor had issued a statutory notice under Section

80 CPC to the State claiming damages. Ultimately, the suit was filed

on 25.01.1985. The Trial Court held in favour of the contractor

against which the State had preferred an appeal before the High Court

and the contractor had also filed a counter claim. The High Court had

dismissed the appeal and the said dismissal order was taken up to the

https://www.mhc.tn.gov.in/judis C.S.No. 642 of 2018

Hon'ble Supreme Court.

27. While dismissing the appeal filed by the State, the High

Court had opined that limitation need not mandatorily be computed on

the basis of each cause of action. It held that date of return of security

deposit could be taken for calculating the period of limitation.

28. The Hon'ble Supreme Court after considering the arguments

and the facts in the said case has held as follows:

“11.....The High Court’s conclusion that the last

date of breach and last date of payment were relevant,

not each cause of action, was thus patently erroneous.

For each breach, a corresponding amount of damages

for additional costs could have been sought. The suit,

however, was filed on 25.1.1985, well after the limitation

period of three years for even the final breach, as the

various causes of action became time barred on

https://www.mhc.tn.gov.in/judis C.S.No. 642 of 2018

15.11.1979, 15.11.1980, 15.11.1981 and 15.11.1982

respectively.”

“13.In a works contract, more often than not,

delays occur, and that is why it is assumed that time is

not of the essence. Where extensions are asked for and

granted, there must be a clear and discernable stand on

behalf of either of the parties that the extension is

granted and/or accepted without prejudice to the claim of

damages. It has become commonplace that neither party

lodges a claim for damages, but waits for the end of the

contract to raise these disputes, taking advantage of the

nebulous and equivocal nature of the transactions

between them. This, however, is not the position that

obtains before us since the Appellant State had

categorically posited that the claim for damages for the

alleged delay on its part would not be entertained.”

https://www.mhc.tn.gov.in/judis C.S.No. 642 of 2018

29. Ultimately, the Hon'ble Supreme Court held as follows:

“It is thus clear that the Respondent failed to file

the suit for damages within the period prescribed in

the Limitation Act. The suit is required to be dismissed on

this ground alone. The impugned Order is, therefore, set

aside, and the Appeal is allowed, but with no order as to

costs.”

This Judgement will apply on all fours to the case on hand.

30. Therefore, the primary issue of limitation is held against the

plaintiff and the suit is dismissed however without costs.



                                                                                        08.08.2023
                     Internet   : Yes/No
                     Index            :Yes/No
                     Speaking / Non-Speaking
                     kan








https://www.mhc.tn.gov.in/judis
                                                                                 C.S.No. 642 of 2018




List of witness on the side of the Plaintiff:

P.W.1 - Mr. P.Janakiraman

List of Exhibits marked on the plaintiff's side:

Ex.P.1 - is the photocopy of letter of acceptance from Defendant to plaintiff dated 27.04.2005.

E.P.2 - is the photocopy of Agreement executed between the Plaintiff and Defendants dated July,2005.

Ex.P.3 - is the photocopy of Plaintiffs letter to 2nd Defendant requesting free site for execution dated 04.10.2005.

Ex.P.4 - is the photocopy of 2nd Defendant instructed the Plaintiff to submit PERT/CPM Chart dated 25.11.2005.

Ex.P.5 - Ex.P5 is the photocopy of Plaintiff submitted the PERT CHART to the 2nd Defendant dated 17.12.2005.

Ex.P.6 - is the photocopy of a letter from Plaintiff to the 2nd Defendant seeking extension of time for 4 months from 04.06.2006 dated 17.05.2006.

Ex.P.7 - is the photocopy of a notice from the 1st Defendant to the Plaintiff duly imposing fine of Rs.5000/- per day from 04.07.2006 and granted EOT up to 31.08.2006 dated 25.07.2006.

Ex.P.8 - is the photocopy of a letter from Plaintiff to st the 1 Defendant seeking EOT upto 30.11.2006 narrating the price hike of materials dated 06.09.2006.

https://www.mhc.tn.gov.in/judis C.S.No. 642 of 2018

Ex.P9 - is the a letter from Plaintiff to the 2nd Defendant granting EOT upto 30.11.2006 and imposed penalty at Rs.5000/- per day upto 30.11.2006 dated 28.09.2006.

Ex.P.10 - is the photocopy of a letter to the Plaintiff to nd the 2 Defendant to obtain orders for price escalation citing Andhra Pradesh G.O dated 04.10.2006.

Ex.P.11 - is the photocopy of a letter from 1st Defendant to the Plaintiff rejecting the plea of the Plaintiff for price escalation and return of fine amount dated 14.11.2006.

Ex.P.12 - is the photocopy of a letter from Plaintiff to nd the 2 Defendant duly enclosing a judgment and sought for price escalation and EOT upto dated 28.02.2007 dated 24.12.2006.

Ex.P.13 - is photocopy of a letter from Plaintiff to the nd 2 Defendant requesting to waive the fine imposed dated 31.01.2007.

Ex.P.14 - is the photocopy of a letter from Plaintiff to nd the 2 Defendant requesting to waive the fine imposed dated 01.02.2007.

Ex.P.15 - is the photocopy of a letter from Plaintiff to nd the 2 Defendant requesting to Reconsider price escalation dated 12.02.2007.

Ex.P.16 - is the photocopy of a letter from the Plaintiff nd to the 2 Defendant requesting to withdraw the fine imposed and pay price escalation dated 30.08.2007.

Ex.P.17 - is the photocopy of a letter from the Plaintiff to the 2nd Defendant duly submitting claims for redressal dated

https://www.mhc.tn.gov.in/judis C.S.No. 642 of 2018

23.05.2008.

Ex.P.18 - is the photocopy of a letter from the Plaintiff nd to the 2 Defendant requesting to give decision on each claims dated 30.11.2010.

Ex.P.19 - is the photocopy of a letter from the Plaintiff nd to the 2 Defendant once again requesting to give decision on each claims dated 18.04.2011.

Ex.P.20 - is the photocopy of the letter from the 2nd Defendant to the Plaintiff duly rejecting the claims of the Plaintiff dated 04.05.2011.

Ex.P.21 - is the photocopy of a letter from the Plaintiff nd to the 2 Defendant duly prefer an appeal to consider his claims, otherwise Arbitration will arise dated 28.05.2011.

Ex.P.22 - is the photocopy of a letter from 2nd Defendant to the Plaintiff duly rejecting the claims of the Plaintiff and rejected the Arbitration as time barred dated 09.06.2011.

Ex.P.23 - is the photocopy of a letter from the Plaintiff nd to the 2 Defendant requested to appoint an Arbitrator as per clause 7.8 of Agreement dated 21.06.2011.

Ex.P.24 - is the photocopy of a letter from 2nd Defendant to the Plaintiff stating that the appointment of Arbitrator dose not arise dated 20.07.2011.

Ex.P.25 - is the photocopy of a letter from the Plaintiff nd to the 2 Defendant duly enclosing a copy judgment stating that the claims are within the stipulated period for consideration by Arbitration dated 26.08.2011.

https://www.mhc.tn.gov.in/judis C.S.No. 642 of 2018

Ex.P.26 - is the photocopy of a letter from 2nd Defendant to the plaintiff denying appointing an Arbitrator as it is time barred dated 23.11.2011.

Ex.P.27 - is the photocopy of Resolution passed by corporation of Chennai foreclosing the major portion of work allotted to Plaintiff dated 11.05.2012.

Ex.P.28 - is the office copy of the petition in O.P No.700/2012 High Court, Madras dated August, 2012.

Ex.P.29 - is the certified copy of order in O.P.No.700/2012 dated 30.10.2017

List of witness on the side of the Defendants:

D.W.1 - Mr. P.Arivazhagan

List of Exhibits marked on the defendants' side:

Ex.D.1 - Letter from Superintending Engineer to plaintiff dated 16.05.2005

Ex.D.2 - Site Handing over letter dated 04.07.2005.

                     Ex.D.3            -     Bill dated 06.07.2005.

                     Ex.D.4             -    Letter from Superintending Engineer to
                     plaintiff dated 20.04.2006.

                     Ex.D.5             -    Letter from Superintending Engineer to
                     plaintiff dated 28.04.2006






https://www.mhc.tn.gov.in/judis
                                                                              C.S.No. 642 of 2018



                     Ex.D.6             -    Letter from Superintending Engineer to
                     plaintiff dated 17.05.2006.

                     Ex.D.7             -    Letter from Superintending Engineer to
                     plaintiff dated 27.03.2006

                     Ex.D.8         -     Bill dated 08.03.2007.

                     Ex.D.9         -     Bill dated 13.08.2007.

                     Ex.D.10        -     Bill dated 13.08.2007.

                     Ex.D.11        -     Authorisation letter dated 09.12.2021.








https://www.mhc.tn.gov.in/judis
                                            C.S.No. 642 of 2018




                                       P.T. ASHA. J,

                                                       kan




                                  C.S.No. 642 of 2018




                                          08.08.2023








https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter