Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.Sakthi Engineering ... vs Bharat Sanchar Nigam Limited
2023 Latest Caselaw 3708 Mad

Citation : 2023 Latest Caselaw 3708 Mad
Judgement Date : 3 April, 2023

Madras High Court
M/S.Sakthi Engineering ... vs Bharat Sanchar Nigam Limited on 3 April, 2023
                                                                              S.A.No.1174 of 2008




                                  IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                              DATED : 03.04.2023

                                                     CORAM

                         THE HONOURABLE MR. JUSTICE V. LAKSHMINARAYANAN

                                               S.A.No.1174 of 2008


                     M/s.Sakthi Engineering Constructions
                     a registered Partnership Firm rep. by
                     Mr.N.Kirubasankar
                     having its office at
                     No.16, Jai Nagar, Palayapalayam Road
                     Erode - 638 011.                    ...Appellant/1st Respondent
                                                               /Plaintiff
                                                        Vs.

                     1.Bharat Sanchar Nigam Limited
                       represented by its Chief General Manager,
                       Telecom (Tamil Nadu Circle) B.S.N.L.,
                       Anna Salai, Chennai - 600 002. ...1st Defendant/1st Appellant

                     2.The General Manager
                       Telecom, B.S.N.L.,
                       Gandhiji Road,
                       Erode - 638 001.                 ...2nd Defendant/2nd Appellant




                     1/11

https://www.mhc.tn.gov.in/judis
                                                                                       S.A.No.1174 of 2008



                     3.Telecommunications India Ltd.,
                       rep. by its Senior General Manager,
                       24, Chakrapani Street, 1st Floor,
                       West Mambalam,
                       Chennai - 600 033.                ...3rd Defendant/3rd Respondent
                                                                /Respondents

                     PRAYER:              Second Appeal filed under Section 100 of the Code of
                     Civil Procedure against the Judgment and Decree dated 22.04.2008 in
                     A.S.No.42 of 2007 on the file of the learned Additional District Judge
                     (Fast Track Court No.1) Erode, reversing the Judgment and Decree
                     dated 14.11.2006 in O.S.No.402 of 2004 on the file of the learned I
                     Additional District Munsif, Erode.


                                  For Appellant     : Mr.B.Singaravelu
                                  For Respondents : Mr.M.S.Velusamy


                                                          JUDGMENT

The plaintiff is the appellant. The plaintiff is the partnership firm

doing contractual works, such as, laying optic fiber cables, microwave

tower installations, transmission, equipments installations, etc., The

parties are referred to in the same ranking as before the Trial Court.

https://www.mhc.tn.gov.in/judis S.A.No.1174 of 2008

2.The first defendant decided to install and maintain

Telecommunication Networks in Tamil Nadu Circle. The 2nd defendant

is his subordinate with respect to Erode Telecom District. The 3rd

defendant is the Government of India Enterprise which had been

floated for the purpose of undertaking Telecommunication

Development and Maintenance works at pre-approved rates on turn key

basis, etc., The rates are approved by the first defendant and the works

to be executed were awarded by the 2nd defendant. The plaintiff

claimed that it is a registered contractor with the Government of India

and several other private agencies for laying Optic Fiber Cables. It is

the case of the plaintiff that the offer was made by the plaintiff and it

was accepted by the 3rd respondent for laying HDPE pipe lines and

pulling the cables to Padiyur Telephone Exchange. The second work

was trench laying activity for the HDPE pipe lines and pulling up the

cables from Kangeyam Telecom Exchange. The extent of work was

about 7050 meters running along with Kangeyam – Dharapuram Road.

https://www.mhc.tn.gov.in/judis S.A.No.1174 of 2008

3.According to the plaintiff, it had carried out the works, i.e., the

trenching and laying of pipes on Padiyur Telecom Exchange as well as

from Kangeyam Telecom Exchange. The said work was inspected by

both the 3rd defendant as well as the defendants 1 and 2 and found to

be correct. The rates on which the work was being executed was

approved by the first defendant and the beneficiary of the work was the

2nd defendant. As already pointed out, the 3rd defendant is only a

consultant for the purpose of identifying the contractor. On completion

of the work, the defendants produced the bills under the following

categories:

1.Kankeyam - Padiyur OFC work under project No:ED/W.O/F-1 AND F-2/97. The balance is :Rs. 65,753.00

Interest at the rate of 18% for Rs.65,753.00 From 30.08.2002 to 15.09.2004 :Rs. 24,164.15

------------------

                     Total                                                   :Rs. 89,917.15
                                                                             ------------------






https://www.mhc.tn.gov.in/judis
                                                                                    S.A.No.1174 of 2008




2.Velliravelli work under Project No:ED/F-4/97 The balance is :Rs. 77,020.00

Interest from 30.10.1999 to 15.09.2004 :Rs. 67,585.05

-------------------

                     Total                                              :Rs.1,44,605.05
                                                                        -------------------

                     Total Amount payable by the defendants
                     (89,917.15 + 1,44,605)                             :Rs.2,34,522.20

The claim of the plaintiff was that he is entitled to a sum of

Rs.2,34,522/-. This consists of two components namely Rs.65,753/-

@18% from 30.08.2002 to 16.09.2004 and Rs.77,020/- from

30.10.1999 till 16.09.2004.

4.This suit was resisted by the defendants 1 and 2 and the 3rd

defendant separately. The stand that was taken by the defendants 1 and

2 in Para 11 was that there was no direct connection between the

plaintiff and the defendants and that the work was executed only at the

instance of the 3rd defendant and as the 3rd defendant is the person

who issued the contract he is liable to pay the same.

https://www.mhc.tn.gov.in/judis S.A.No.1174 of 2008

5.The 3rd defendant had taken a stand that that he had offered the

tenders on behalf of the defendants 1 and 2 and as the area of work was

limited instead of calling tenders it adopted the procedure of finalising

the sealed quotations. The main plea of the plaintiff that the cables

were laid and work had been completed, had been accepted. It was the

case of the 3rd defendant that the work was completed on 12.11.1998

instead of 31.07.1998.

6.Insofar as the second project is concerned, according to them,

the work was awarded on 24.07.1998 and the work was to be

completed on 23.10.1998, but the work was completed on 28.11.1999.

The plea was not that the work was not done but it was done with some

delay.

7.The trial Court found that the case of the plaintiff is proved and

genuine and decreed the suit as prayed for with costs.

https://www.mhc.tn.gov.in/judis S.A.No.1174 of 2008

8.On appeal, the learned First Appellate Judge held that there is

no privity of contract between the defendants 1 and 2 and the plaintiff

and allowed the appeal. As against the reversal finding, this Second

Appeal has been filed.

9.The Second Appeal has been admitted and the following

Substantial Questions of law were framed:

"a) Is the Lower Appellate Courts below correct

and justified in reversing the well-considered Judgement

of the trial Court?

b)Is the Lower Appellate Court correct and

justified in holding that there was no agreement between

plaintiff and defendants 1 and 2 and that consequently

they are not liable for the suit claim?

c) Are not the defendants 1 and 2 estopped from

denying their liability to the suit claim?"

https://www.mhc.tn.gov.in/judis S.A.No.1174 of 2008

10.I am saved the trouble of going into the details as against the

other contract granted for the same period because the plaintiff had

presented O.S.No.189 of 2005 which was decreed on 06.09.2007.

Against the said Judgment and Decree, the respondents herein had filed

A.S.No.1116 of 2007. The learned Single Judge of this Court went

through the evidence and found as in this case that the day to day

progress of the work had been followed by the respondents herein and

returned the finding that the bills that was submitted by the

plaintiff/appellant to the respondents/defendants 1 and 2 were being

returned on one reason or the other. The Court held that there is a

privity of contract between the appellants and the respondents and

decreed the suit. The said finding had been confirmed by this Court as

pointed out above. Therefore, the ground on privity of contract does

not exist any more. Hence, I am constrained to reverse the finding.

https://www.mhc.tn.gov.in/judis S.A.No.1174 of 2008

11.Mr.M.S.Velusamy, learned counsel for the respondent fairly

submitted that as against the order of this Court in A.S.No.1116 of

2007, a Special Leave Petition was preferred to the Supreme Court and

such Special Leave Petition was also dismissed. This Court having

already concluded for the contract between the appellant and the

respondents in A.S.No.1116 of 2007, I am afraid I cannot go into the

said issue all over again. The contractors are the same and the parties

are the same and only the work to be executed at a different place. The

manner of execution of the work is similar and the contract was also

similar in nature. The defence taken in both the suits are also identical

and one having reached the finality, I cannot take a different view in

this appeal. Therefore, this Court holds that there is a privity of

contract between the appellant/plaintiff and the defendants 1 and 2.

12.This Second Appeal is allowed. The suit in O.S.No.402 of

2004 on the file of the learned I Additional District Munsif, Erode, is

decreed. I am not inclined to grant 18% interest from the date of Plaint

https://www.mhc.tn.gov.in/judis S.A.No.1174 of 2008

till the date of decree granted by the trial Court. This Court modifies

the interest @18% from the date of demand till the date of presentation

and 12% thereafter. There will be no costs in this appeal.


                                                                                      03.04.2023

                     Index      : Yes/No
                     Internet         : Yes/No
                     Speaking order : Yes/No
                     mps

                     To

                     1.The Additional District Judge,
                     (Fast Track Court No.1),
                     Erode.

                     2.The I Additional District Munsif,
                     Erode.






https://www.mhc.tn.gov.in/judis
                                               S.A.No.1174 of 2008



                                  V. LAKSHMINARAYANAN, J.



                                                            mps




                                         S.A.No.1174 of 2008




                                                   03.04.2023






https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter