Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Jayalakshmi Spinning Mills Ltd vs The Chairman
2022 Latest Caselaw 5881 Mad

Citation : 2022 Latest Caselaw 5881 Mad
Judgement Date : 23 March, 2022

Madras High Court
Jayalakshmi Spinning Mills Ltd vs The Chairman on 23 March, 2022
                                                                              W.P. No.24413 of 2014

                                  IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                  DATED: 23.03.2022

                                                      CORAM :

                          THE HONOURABLE MR.JUSTICE K.KALYANASUNDARAM

                                     W.P. No.24413 of 2014 & M.P.Nos.2 & 3 of 2014

                     Jayalakshmi Spinning Mills Ltd.,
                     HTSC No.299, Chikkanampatty,
                     Omalur Taluk, Salem District.
                     Repd. By its Director
                     R.Ravichandran                                         ... Petitioner

                                                          Vs.

                     1. The Chairman
                        Tamil Nadu General and Distribution Corporation Limited,
                        [TANGEDCO],
                        144, Anna Salai, Chennai – 600 002.


                     2. The Chief Financial Controller/Revenue,
                        TANGEDCO,
                        144, Anna Salai, Chennai – 600 002.

                     3. Tamil Nadu Electricity Regulatory Commission,
                        Through its Secretary,
                        No.19A, Rukmini Lakshmipathy Salai,
                        Egmore, Chennai – 600 008.


                     1/25



https://www.mhc.tn.gov.in/judis
                                                                                    W.P. No.24413 of 2014

                     4. The Superintending Engineer,
                        TANGEDCO,
                        Tiruppur Electricity Distribution Circle,
                        Tiruppur.                                                 ... Respondents

                     PRAYER: Writ Petition filed under Article 226 of the Constitution of India
                     praying for issuance of a Writ of Certtiorari to call for the records of the
                     second        respondent        contained        in       impugned           letter
                     CFC/FC/DFC/AAO,HT/AS.3/REV/D.N.115/13 dated 29.07.2013 and quash
                     the same as arbitrary, illegal and violative of the provisions of the Electricity
                     Act, 2003 and the orders of the TNERC.


                                  For Petitioner             : Mr.R.S.Pandiaraj

                                  For Respondents            : Mr.M.Abulkalam
                                                              Standing Counsel for the respondents
                                                                                      1, 2 & 4

                                                       ORDER

The order of cancellation of the benefit of Deemed Demand

Charges issued by the second respondent in proceedings dated 29.07.2013

is sought to be quashed in this writ petition.

https://www.mhc.tn.gov.in/judis W.P. No.24413 of 2014

2. The writ petitioner is the High Tension Electricity Consumers

and they are purchasing the electricity power from the third parties for

generating power and adjusting the same for the benefit of petitioner's

establishments.

3. In this regard certain terms and agreements were agreed

upon between the parties by way of adjudicative process before the Tamil

Nadu Electricity Regulatory Commission.

4. The learned counsel appearing on behalf of the writ

petitioner contented that the unilateral withdrawal of concession granted to

the writ petitioner are arbitrary and unsustainable in view of the order dated

15.05.2006 in petition No.TP 1/05 by the Tamil Nadu Electricity Regulatory

Commission. It is contended that the adjudicative process had been

conducted statements, objections and suggestions were received from all

stakeholders and thereafter a decision was taken by the Tamil Nadu

Electricity Regulatory Commission, Chennai in petition No.T.P.1/2005 and

https://www.mhc.tn.gov.in/judis W.P. No.24413 of 2014

an order was passed in order No.2 dated 15.05.2006. The preamble of the

order stipulates as follows:-

Sub-section (2) of Section 42 of the Electricity Act, 2003, stipulates that the State Commission shall introduce open access in such phases and subject to such conditions as may be specified, within one year of the appointed date. Accordingly, the Commission has notified the Tamil Nadu Electricity Regulatory Commission – Intra State Open Access Regulations 2005 in the Tamil Nadu Government Gazette dated the 3rd August, 2005 so as to introduce open access in Tamil Nadu. As per Regulation 9 of the aforesaid Regulations, various charges payable to State Transmission Utility / Transmission Licensee and Distribution Licensee by an open access customer have to be determined by the Commission. As directed by the Commission, the TNEB filed a petition for determination of the above charges on 26.09.2005 and the Petition was registered and numbered as T.P. 1 of 2005.

In exercise of the powers conferred by section 42 of the Electricity Act, 2003 (Act 36 of 2003) and all other powers enabling it in this behalf, the Tamil

https://www.mhc.tn.gov.in/judis W.P. No.24413 of 2014

Nadu Electricity Regulatory Commission (TNERC) after having considered the written objections, consulted the members of the State Advisory Committee, heard the issues raised by the stakeholders in a public hearing, the reply of the Tamil Nadu Electricity Board, the applicant herein, and having considered the relevant documents available on record, passes this order, fixing the transmission charges, wheeling charges and other charges specified under the aforesaid Open Access Regulations and payable by an open access customer.

                                        Sd.......                    Sd.....                  Sd.....
                              B.Jeyaraman                 S.Thangarathnam                  A.Balraj
                               Member                        Member                   Chairman



5. The learned senior counsel relied on the preamble of the said

order, which states that the Regulatory Commission considered the written

objections, consulted the members of the State Advisory Committee, heard

the issues raised by the stakeholders by way of public hearing and the reply

from the Tamil Nadu Electricity Board and considered all the issues.

Pursuant to the said order dated 15.05.2006 the applicability of Deemed

https://www.mhc.tn.gov.in/judis W.P. No.24413 of 2014

Demand Charges has been stipulated and in respect of Deemed Demand

Charges it is stated that the transmission losses in each voltage play a vital

role in deciding the deemed demand. The loss levels at each voltage are

given above. The loss factor depends on the voltage at which the power is

injected and the voltage at which the open access user draws. Since various

combinations are possible, a simple methodology is adopted to approximate

the loss factor under various scenarios. Even though the power, in an

interconnected grid, flows by displacement and does not actually traverse the

whole distance from point of injection to the point of travel, the accepted

principle, in general is, that the loss estimation shall be based on the

theoretical route of flow. For example, even though the generated power is

injected by a generator at 11 K V and is also drawn at the same voltage of

11 KV at a distant place, the power is supposed to have been transformed

through the higher voltages of 33, 110,230 KV etc., again transformed into

the lower levels and reach the point of drawal. To emulate such scenarios it

is assumed that the said power, flows in an upward and downward direction

as indicated below, through various transformation levels and undergoes

https://www.mhc.tn.gov.in/judis W.P. No.24413 of 2014

50% of the loss, in each direction, in that level. The percentage of deemed

demand supplied by the licensee for typical cases of injection and drawal

and based on the loss factors and also considered by the Regulatory

Commission. Considering the technical aspects the Regulatory Commission

passed an order in respect of billing of monthly consumption which is

segregated into two parts as under.

(i) Quantum of energy supplied by the generator at open access user end and;

(ii) Quantum of energy supplied by Distribution licensee to open access user.

The demand charges in a billing month are to be arrived at as detailed below;

(a) The maximum demand recorded in a month shall be segregated into demand supplied by the generator and the demand supplied by the licensee taking into account the actual energy consumed ini units, the actual energy in units supplied by the generator and average power factor maintained at the consumption poin tin the billing month.

(b) The demand charges payable by the open access customer will be calculated as below:

https://www.mhc.tn.gov.in/judis W.P. No.24413 of 2014

Case 1:

                     Injection Voltage              110 kV
                     Drawal Voltage                 33 kV

Percentage of deemed demand as per the table = 41.28 Sanction Demand 1000 Kva Recorded Demand 855 Kva Units consumed 650000 units Power factor 0.95 Units supplied by generator (at consumption point) : 500000 units Demand supplied by generator =500000/720*0.95=659.72 Kva Demand supplied by the licensee =855-659.72=195.28 Kva Billable demand-supplied by licensee =900-659.72=240.28 (at 90% of the sanctioned demand) Demand charges payable =(659.72*0.4128*300)+(240.28*300) =81699.72+72084=153783.72

Case 2:

                     Injection Voltage              230kV
                     Drawal Voltage                 22/11 kV

Percentage of deemed demand as per the table above = 40.04 Sanction Demand 1000 Kva Recorded Demand 950 Kva Units consumed 700000 units Power factor 0.92 Units supplied by generator (at consumption point) : 700000 units Demand supplied by generator =700000/720*0.92=894.44 Kva Demand supplied by the licensee =950-894.44=55.56 Kva

https://www.mhc.tn.gov.in/judis W.P. No.24413 of 2014

Billable demand-supplied by licensee = 950-894.44=55.56 Kva Demand charges payable = (894.44*0.4004*300)+(55.56*300) = 107440.13+16668=124108.13

6. Importantly in paragraph No.5.24.2 the order passed by the

Regulatory Commission itself categorically states that all the orders will take

effect from the date of this order and till such time the charges are revised.

Further revision shall normally be along with the regular tariff petition by

the licensee. The licensee may also approach the Commission for revision of

these charges by filing a distinct revision petition without linkage to the

regular tariff revision. Further the commission reserves the right to initiate

suo-motu procedure for revision of the charges. Thus it is made clear that the

licensee has got right to approach the Commission for revision of these

charges by filing a distinct revision petition. The commission also shall

initiate suo-motu procedure for revision of the charges. Thus both the

licensee as well as the Commission are empowered to re-open the concession

granted in respect of Deemed Demand charges. It is further made clear that

re-opening of the concession of Deemed Demand Charges is payable either

https://www.mhc.tn.gov.in/judis W.P. No.24413 of 2014

by way of revision petition by the licensee or by way of suo-motu revision by

the Regulatory Commission. Thus the authorities of the board has no

authority to cancel the concession granted unilaterally without reference to

the order passed by the Regulatory Commission by invoking clause 5.24.2

of the order dated 15.05.2006 in petition No.T.P.1 of 2005.

7. The learned senior counsel is of the opinion that the

Regulatory Commission has not passed any such order withdrawing the

concession granted in respect of Deemed Demand Charges to the open

access consumers/fosil fuel based generators. In the absence of any such

order by the Regulatory Commission, it is not open to the authorities of the

electricity board to cancel the concession unilaterally by passing the

impugned order.

8. The learned Additional Advocate General appearing on

behalf of the respondents 1, 2 & 4 opposed the contentions of the learned

counsels appearing for the writ petitioner by stating that grant of Deemed

https://www.mhc.tn.gov.in/judis W.P. No.24413 of 2014

Demand Charges is a concession extended by the Commission at the

instance of the board. Such a concession was agreed to be granted by the

board on certain terms and conditions. The concession was extended

undoubtedly for many years, however on account of certain financial

implications the board has decided to withdraw the concession of the

Deemed Demand Charges and the competent authorities are empowered to

do so. In view of the fact that in the subsequent order passed by the

Regulatory Commission, the concession of Deemed Demand Charges were

omitted. The omission of extending the concession of Deemed Demand

Charges will provide an implied power to the authorities competent of the

Electricity board to cancel the concession of the Deemed Demand Charges

granted to open access consumer/fosil fuel based generators. Thus there is

no irregularity or infirmity in respect of the impugned circular passed in this

regard. It is further contended that the benefit extended is being a concession

can never be claimed as a right by the writ petitioner. The concession is

granted considering various other factors by the commission in the year

2012. On account of the changed circumstances the board by way of an

https://www.mhc.tn.gov.in/judis W.P. No.24413 of 2014

order dated 30.03.2012 in order No.2/2012 the concept of grant of Deemed

Demand Charges were dispensed with. However the learned Additional

Advocate General admitted the fact that there is no specific clause

withdrawing the concession or to dispense with the concession granted

earlier. However such an order for withdrawal of concession was passed

with reference to the wind mill energy case. However in respect of the open

access customers/fosil fuel based generators no such order was passed by

the Tamil Nadu Electricity Regulatory Commission. This being the factum of

the case there is no irregularity or illegality in respect of the cancellation of

concession of Deemed Demand Charges granted earlier to this writ

petitioner. The learned Additional Advocate General further contended that

in respect of Wind Mill Generators and bio-gas power generators the said

concession has been withdrawn and the Regulatory Commission had passed

orders to that effect. When such being the factum of the case the mere

omission shall not be construed as an extension of the concession granted in

all other cases. The concession has been withdrawn and the same cannot be

continued in respect of the writ petitioner alone, who is coming under the

https://www.mhc.tn.gov.in/judis W.P. No.24413 of 2014

category of open access customers/fosil fuel based generators. Thus the writ

petition is liable to be rejected.

9. Considering the arguments advanced on both sides, this

Court is of the opinion that admittedly the concession of Deemed Demand

Charges were granted to all the writ petitioners by way of an order by the

Tamil Nadu Electricity Regulatory Commission in T.P.1 of 2005 dated

15.05.2006. The preamble of the order categorically enumerates that an

adjudicative process had been conducted and written objections,

suggestions, consulted the members of the State Advisory Committee, heard

the issues raised by the stakeholders by way of public hearing and were

obtained before passing an order. This Court is of the opinion that such a

process ought to have been conducted before withdrawing the concession

granted to these writ petitioners. Concept of implied withdrawal can never

be accepted. In view of the fact that through an agreement the concession

was granted and it is contractual in nature. The petitioner is generating

electricity power and keeping the same for their own usage. The service of

https://www.mhc.tn.gov.in/judis W.P. No.24413 of 2014

the electricity board is also utilised by the petitioner for transmitting the

electricity power. Thus the services ought to be compensated by the writ

petitioner undoubtedly all these conditions were considered by providing

opportunity to all the parties and a decision was taken by the Tamil Nadu

Electricity Regulatory Commission. Such being the factum, while

withdrawing the concession it is necessary on the part of the electricity

board to approach the Electricity Regulatory Commission by filing a proper

application or with a request to initiate suo-motu revision under clause

5.24.2 of the said order dated 15.05.2006 in respect of the open access

customers/fosil fuel based generators. In respect of all other categories the

Regulatory Commission had already passed orders withdrawing the

concession of Deemed Demand Charges. Thus it is made clear that the

electricity board has to approach the Tamil Nadu Electricity Regulatory

Commission for the purpose of revision of all such concessions granted to

this category.

https://www.mhc.tn.gov.in/judis W.P. No.24413 of 2014

10. This Court is of the considered opinion that when certain

concession are granted for a clause/group of people by way of adjudicative

process, the said concession can be withdrawn only by following the

procedure. In the event of unilateral cancellation of such concession,

certainly rights of the persons, who enjoyed the concession will be

prejudiced. Even such a consultation process has been stipulated in the order

passed by the Electricity Regulatory Commission dated 15.05.2006 in clause

5.24.2 which contemplates that the licensee may also approach the

Commission for revision of these charges by filing a distinct revision petition

without linkage to the regular tariff revision. Further the commission

reserves the right to initiate suo-motu procedure for revision of the charges.

When such a power has been provided under the very order, there is no

impediment to the Regulatory Commission to initiate suo-motu revision to

re-open the case of open access consumers/fosil fuel based generators.

Electricity board is also competent to submit an application for revision of

the charges before the Regulatory Commission.

https://www.mhc.tn.gov.in/judis W.P. No.24413 of 2014

11. On a perusal of the entire records it is made clear that no

adjudicative process had been conducted before issuing the impugned order

by the Tamil Nadu Regulatory Commission in respect of the category of

open access consumers/fosil fuel based generators. When the concession is

extended to this category withdrawal of the same must be done by providing

an opportunity to the persons who are benefited from and out of the

concession. Admittedly no such opportunity was provided to the writ

petitioner before issuing impugned circular by the respondents. An

opportunity to be provided is for the purpose of submitting the objections in

respect of cancellation of such concession. Thus it is made clear that as per

clause 5.24.2 the Electricity Board is at liberty to approach the Regulatory

Commission if so advised.

12. The learned Additional Advocate General on behalf of the

third respondent Tamil Nadu Electricity Regulatory Commission further

contended that the concept of Deemed Demand benefit was introduced in

Order No.3 of 2006 by the Commission. Though there was no regulation

https://www.mhc.tn.gov.in/judis W.P. No.24413 of 2014

governing the said subject, it was introduced solely with a view to extend a

concession to generators as the introduction of open access was in the initial

stage. The deemed demand is a fiction, which was evolved to promote open

access in the formative stages and rightly Commission has reviewed its own

decision in the subsequent statutory order to dispense with the same. The

concept of demand charges has found statutory sanction in the Electricity

Act, 2003 which provides for recovery of fixed charges but the same is not

the case in respect of deemed Demand charges which does not have

statutory sanction. At best, the facility so far enjoyed can be termed to be a

concessional one to promote open access in the initial stages and any move

to make such concessions to the generators a permanent affair would

amount to unfair enrichment at the cost of the licensee/other consumers.

Further, the demand charges being a component of tariff, the Commission

has the power to revisit the same and revise subsequently as circumstances

warrant.

https://www.mhc.tn.gov.in/judis W.P. No.24413 of 2014

13. With reference to the submissions made by the respective

learned counsels appearing on behalf of the parties to the lis on hand, this

Court is of the opinion that the power to revisit the entire concession of

Deemed Demand Charges is granted to the Tamil Nadu Electricity

Regulatory Commission. The Commission is empowered to revise the order

even by initiating suo-motu revision. The power of suo-motu revision has

been contemplated in the order dated 15.05.2006 itself. Thus there is no

impediment for the commission to initiate suo-motu revision for the purpose

of revisiting the entire concession and to revise the same if necessary. The

grievance of the writ petitioner is that such a suo-motu power had not been

exercised by the Regulatory Commission nor the Commission had

undertaken the process of adjudication by providing an opportunity to the

stakeholders. Without undertaking any such process the unilateral decision

has been taken by the respondent Electricity Board for the withdrawal of the

concession granted earlier. In the absence of a specific order by the

Regulatory Commission in this regard, the power of the Commission to

https://www.mhc.tn.gov.in/judis W.P. No.24413 of 2014

revise the concession of Deemed Charges cannot be usurped by the

authorities of the Electricity Board. Thus the impugned order is one where

the respondents are not following the procedures contemplated nor the

Commission exercised the suo-motu power of revision.

14. It is contended by the learned Additional Advocate General

that the petitioner is attempting to take undue advantage of the omission

made by the authorities in the impugned order. However, this Court cannot

consider the same in view of the fact that the powers conferred on the

Regulatory Commission had not been exercised admittedly by the

respondents. Procedures to be followed also had not been adhered. Thus the

very submission made that the omission on the part of the respondent is

taken as an advantage by the writ petitioner deserves no merit. This apart

this Court cannot draw an inference from and out of such omission made by

the Electricity Board or by the Regulatory Commission. There cannot be any

implied withdrawal of concession, which is permissible. The concession

already granted and in force for long years can be withdrawn or taken away

https://www.mhc.tn.gov.in/judis W.P. No.24413 of 2014

only by following the procedures contemplated and therefore the unilateral

decision of the respondent Board can never be appreciated by this Court.

15. It is further contended by the learned counsel appearing for

respondents that the Regulatory Commission had withdrawn the Deemed

Demand Charges concept in respect of the Wind Energy Generators,

Biomass generators, Bagasse Based Co-generators in Orders No.6, 7 & 8

dated 31.07.2012. However, the open category of the writ petitioner namely

open access consumer/fosil fuel based generators has not been stated in the

counter affidavit. Thus the reason for non-inclusion is not known to this

Court. This Court cannot draw any factual inference in respect of the

withdrawal of the concession granted to all other categories but it should be

applied to the writ petitioner also who belongs to a different category. Such

an inference is not only improbable, which cannot be made, in view of the

fact that specific clause is available in the order of the Regulatory

Commission dated 15.05.2006 for initiation of revision procedures even suo-

motu. Thus it is made clear that the respondents in the event of passing an

https://www.mhc.tn.gov.in/judis W.P. No.24413 of 2014

appropriate orders by following the procedures contemplated cannot

withdraw or cancel the benefit of Deemed Demand Charges already

extended to the writ petitioner. The said concession can be cancelled by

invoking the power by Electricity Regulatory Commission. Accordingly this

writ petition is to be considered.

16. The learned counsel appearing for the writ petitioner has

stated that such an adjudicative process in compliance with the principles of

natural justice has been contemplated in the Tamil Nadu Electricity

Regulatory Commission conduct of business regulations 2004 clause 16 1

& 2 reads as under :-

16 (1) The Commission may initiate any proceedings suo motu or on a petition filed by any affected or interested person.

(2) When the Commission initiates the proceedings, it shall be by a due notice issued by the Commission. The Commission may give such orders and directions as may be deemed necessary, for serving of notices to the affected parties; for the filing of replies and

https://www.mhc.tn.gov.in/judis W.P. No.24413 of 2014

rejoinders against or in support of the petition in such form as the Commission may direct. The Commission may, if it considers appropriate, issue orders for publication of the petition inviting comments from the public or any class of persons on the issue involved in the proceedings in such form as the Commission may direct.

17. In view of the discussions made in the afore mentioned

paragraphs, this Court is of the opinion that the Regulatory Commission has

to under take the process of revision either suo-motu or through an

application if any filed before the commission and conduct the adjudicative

process by issuing notice to all the stakeholders and after hearing the parties

aggrieved, decision shall be taken on merits and in accordance with law. The

compliance of principles of natural justice has been contemplated in the

business regulations, as stated supra. Thus Electricity Regulatory

Commission is bound by that and they have to follow the procedures and

thereafter take a decision and pass orders on merits and in accordance with

law in respect of the withdrawal of the concession of the Deemed Demand

Charges in respect of the writ petitioner. However, it is made clear that the

https://www.mhc.tn.gov.in/judis W.P. No.24413 of 2014

observations made in this judgment will not affect the independent

adjudication if any undertaken by the Electricity Regulatory Commission in

accordance with the procedures contemplated. The Electricity Regulatory

Commission is at liberty to decide the merits and de-merits independently

and pass orders without causing undue delay in view of the fact that the

concession has been already cancelled in respect of other categories.

Accordingly the impugned order passed by the second respondent in letter

No.CFC/FC/DFC/AAO.HT/AS.3/REV/D.N.115/13 dated 29.07.2013 is

quashed and the writ petition is allowed. No costs. Consequently connected

miscellaneous petitions are also closed.

23.03.2022

vrc

Speaking/Non speaking Order

Index : Yes/No

To

https://www.mhc.tn.gov.in/judis W.P. No.24413 of 2014

1. Tamil Nadu General and Distribution Corporation Limited, [TANGEDCO], 144, Anna Salai, Chennai – 600 002.

2. Chief Financial Controller/Revenue, TANGEDCO, 144, Anna Salai, Chennai – 600 002.

3. The Superintending Engineer, TANGEDCO, Tiruppur Electricity Distribution Circle, Tiruppur.

4. Tamil Nadu Electricity Regulatory Commission, Through its Secretary, No.19A, Rukmini Lakshmipathy Salai, Egmore, Chennai – 600 008.

https://www.mhc.tn.gov.in/judis W.P. No.24413 of 2014

K.KALYANASUNDARAM, J.

vrc

W.P. No.24413 of 2014

23.03.2022

https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter