M/S.Pioneer Hydrothermal ... vs M/S.Techsharp Engineers Pvt. Ltd
2022 Latest Caselaw 1150 Mad

Citation : 2022 Latest Caselaw 1150 Mad
Judgement Date : 25 January, 2022

Madras High Court
M/S.Pioneer Hydrothermal ... vs M/S.Techsharp Engineers Pvt. Ltd on 25 January, 2022
                                                                                  Arb.Appln.No.180 of 2021

                                  IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                   Dated: 25.01.2022

                                                        Coram:

                   THE HONOURABLE MR. JUSTICE SENTHILKUMAR RAMAMOORTHY

                                         Arbitration Application No.180 of 2021

                M/s.Pioneer Hydrothermal Services Pvt. Ltd.
                Pioneer House, 3-10-4/B/2,
                Near St.Joseph's High School,
                Ramanthapur, Hyderabad – 500 013
                Represented by its Director and Authorised Signatory,
                Konghot Krishna Prasad, Aged 34 years, S/o.Methil Gangadharan,
                Residing at Flat No.E-304, 3rd Floor, Aparna Sarovar Granda, Kanchi
                Gachibowli Nallagandla, Lingampally, K.V.Rangareedy,
                Hyderabad – 500 013.                                    ... Applicant

                                                        /versus/

                1. M/s.Techsharp Engineers Pvt. Ltd.,
                   Represented by its Authorised Officer,
                   C-39, 2nd Avenue,
                   Anna Nagar, Chennai – 600 040,
                   presently having office at
                   No.10/17, 8th Street,
                   M-Block, Anna Nagar East,
                   Chennai – 600 102.

                2. M/s.Bharath Petroleum Corporation Limited (BPCL),
                   Kochi Refinery,
                   Karimughal Road, Thrippunithura,
                   Ambalamugal, Kochi,
                   Kerala – 682 302                                  ... Respondents



                Page 1 of 12
https://www.mhc.tn.gov.in/judis
                                                                                     Arb.Appln.No.180 of 2021

                Prayer: This Arbitration Application is filed under order XIV Rules 8 of Original
                Side Rules read with Section 9 of Arbitration and Conciliation Act, 1996 praying
                this Court, pending the hearing and final adjudication of the dispute by an arbitral
                tribunal, should not be pleased to pass an order of Interim Directions shall be
                granted against the respondent and not to direct a prohibitory order against the 2 nd
                respondent prohibiting them for praying any amount to the tune of
                Rs.10,22,85,244/- (Rupees Ten Crores Twenty Two lakhs Eighty Five Thousand
                and two forty four only) thereon to the 1st respondent and consequently direct the
                2nd respondent to deposit the said amount with this Hon'ble Court.


                                        For Applicant      : Mr.Vipin Warrier

                                        For R1             : Mr.R.V.Prabhat, for
                                                             Mr.Jayesh B.Dolia

                                        For R2             : Mr.M.Vijayan, for
                                                             M/s.King & Partridge


                                                        ORDER

The applicant seeks a prohibitory order restraining the 2nd respondent

from making payments to the 1st respondent to the extent of Rs.10,22,85,244/- and

to direct the 2nd respondent to deposit the said amount before this Court.

https://www.mhc.tn.gov.in/judis Arb.Appln.No.180 of 2021

2. A work order dated 30.04.2016 was issued to the applicant by the

1st respondent herein in relation to the supply and application of insulation of

piping system on back to back basis for the offsite of IREP project of BPCL, Kochi

Refinery (the 2nd respondent herein). Pursuant thereto, the applicant undertook

work. The terms and conditions annexed to the work order, include the terms of

payment as clause 10. As per the terms of payment, the applicant was entitled to

submit running account (RA) bills for payment on account or as advances. The

payment breakup, including the 10% retention amount, is specified in the said

clause 10. Upon execution of work, the applicant raised several RA bills. On

receipt of such bills, it appears that some payments were made by the 1st

respondent. According to the applicant, full payment was not made against these

RA bills; and a statement indicating the details of bills issued and payments

received in respect thereof is relied upon in this regard by the applicant. On such

basis, the applicant claims that the aggregate outstanding is a sum of about

Rs.10,22,85,243/-. On the contrary, the 1st respondent states that RA bills 1 to 11

were paid. As regards RA bill 11-A, it is stated that the said RA bill is the 2 nd RA

bill raised in the same month. Since the terms of payment do not provide for

raising more than one RA bill in the same month, RA bill 11-A was rejected. As

regards the bills raised subsequent thereto, it is stated that the said bills were not

https://www.mhc.tn.gov.in/judis Arb.Appln.No.180 of 2021

processed because joint measurements were not taken in spite of the 1 st respondent

calling upon the applicant to come forward for measurements and reconciliation.

The 1st respondent relies upon the reply notice dated 01.03.2018 in this regard.

3. As indicated earlier, the 2nd respondent is the employer, which

awarded the main contract to the 1st respondent. The 2nd respondent states, on

instructions, that all the RA bills raised by the 1st respondent on the 2nd respondent

were settled. The 1st respondent produced a copy of the final bill dated 21.03.2019

in compliance with directions issued by me earlier. The said final bill of the 1 st

respondent is for a sum of Rs.5,15,37,000/-. As regards the final bill, the 2nd

respondent states that such final bill was not received. The 2nd respondent further

submits, on instructions, that a sum of Rs.4,00,37,000/- may be payable by the 2nd

respondent to the 1st respondent. If a final bill of current date is raised by the 1 st

respondent in this regard, the 2nd respondent states that the said bill would be

processed, and, subject to the aforesaid, if directed by this Court, the 2nd

respondent is ready and willing to create a fixed deposit account in respect of the

above mentioned sum of Rs.4,00,37,000/- subject to the outcome of arbitration

proceedings.

https://www.mhc.tn.gov.in/judis Arb.Appln.No.180 of 2021

4. A preliminary issue was raised by the 1st respondent that the

arbitral proceedings initiated by the applicant earlier were rejected by the Arbitral

Tribunal on the ground that such proceedings were premature. In view thereof, it is

contended that the present Section 9 application is not maintainable. On merits, the

1st respondent relies upon several judgments in support of the contention that the

present application is liable to be rejected. The said judgments are set out below:

(i). M/s.A-1 Biz Solutions Chennai v. M/s.Cascade Billing Center Inc,

judgment dated 27.07.2011, Madras High Court (DB).

(ii). Raman Tech and Process Engineering v. Solanki Traders, judgment

dated 20.11.2007 (SC)

(iii). Shinago Holdings v. M. Ethiraj, judgment dated 11.08.2017, Madras

High Court (DB).

(iii). BMW India v. Libra Automotives, order dated 09.07.2019, Delhi

High Court.

5. On the basis of the above judgments, the 1 st respondent contends

that an application under Section 9 of the Arbitration and Conciliation Act, 1996

(the Arbitration Act) seeking a prohibitory order should be tested against the

https://www.mhc.tn.gov.in/judis Arb.Appln.No.180 of 2021

requirements of Order 38 Rule 5 of C.P.C. Consequently, the applicant is under an

obligation to establish a prima facie case that the amount claimed is due and

owing to the applicant from the 1st respondent. However, the establishment of a

prima facie case is insufficient. In addition, the applicant is under an obligation to

establish that the 1st respondent intends to defeat the fruits of a potential arbitral

award by alienating or moving its assets outside the jurisdiction of the Court.

According to the 1st respondent, in the case at hand, the applicant has failed to

establish even a prima facie case in as much as measurements have admittedly not

been taken and the bills have not been certified. As regards the 2nd requirement

under Order 38 Rule 5, the 1st respondent contends that the applicant has

completely failed to establish that the 1st respondent would refuse to make payment

if an arbitral award is pronounced in favour of the applicant.

6. At the outset, the preliminary objection of the 1st respondent

should be dealt with. As indicated above, such preliminary objection is that the

arbitral proceedings initiated by the applicant earlier were rejected on the ground

that such proceedings are premature and would have to await the final bill payment

by the 2nd respondent to the 1st respondent since it is a back-to-back contract. An

application may be filed under Section 9 of the Arbitration Act either prior to the

https://www.mhc.tn.gov.in/judis Arb.Appln.No.180 of 2021

constitution of the arbitral tribunal or, subject to establishing that the remedy under

Section 17 is not efficacious, in course of arbitral proceedings, or after the award is

pronounced but before such award is enforceable. In the case at hand, the

applicant approached the Arbitral Tribunal, but an application under Section 16 of

the Arbitration Act was allowed. It is stated by learned counsel for the applicant

that the said order has been assailed before this Court. Therefore, the facts on

record disclose that the applicant has demonstrated the manifest intent to resolve

the dispute through arbitration. Accordingly, the preliminary objection is overruled.

7.Turning to the merits of the application, the principal objection of

the 1st respondent is that the requirements of Order 38 Rule 5 of C.P.C were not

satisfied by the applicant. Therefore, this objection should be subjected to close

scrutiny. In the affidavit in support of this application, the applicant has stated

that a principal sum of Rs.6,62,17,343/- is due and payable to the applicant by the

1st respondent towards work done pursuant to the work order. The applicant has

averred as follows in paragraph 11 of the affidavit in support of the application:

“The 1st Respondent had been evading and avoiding making payments to this Applicant from December, 2017 and will not release payments to this

https://www.mhc.tn.gov.in/judis Arb.Appln.No.180 of 2021

Applicant once the payments are received by the 1st Respondent from the 2nd Respondent. The Applicant owing to the conduct of the 1st Respondent reasonably apprehends that the 1st Respondent will not make payments to this Applicant once the payments are received by 1st Respondent from 2nd Respondent”.

8. In support of the application, the applicant has filed all the bills

raised by the applicant on the 1st respondent. In addition, a statement setting out

the details of bills, amounts received in respect thereof and amounts outstanding

has been filed.

9. The contention of the 1st respondent that a prima facie case should

be made out is unexceptionable. The work order provides for the processing of RA

bills subject to retention. All the RA bills are on record. There is no

communication on record from the 1st respondent setting out reasons for rejecting

these bills. The main objection is that the outstanding bills were not certified and

that measurements were not taken. Nevertheless, in the absence of an express

communication stating that the work was not done or that the amounts claimed in

these bills are not payable, the applicant has made out a prima facie case. This

leads to the next issue whether the requirement under Order 38 Rule 5 that the 1 st

respondent would remove the assets from the jurisdiction of the Court and thereby

https://www.mhc.tn.gov.in/judis Arb.Appln.No.180 of 2021

defeat the fruits of the potential arbitral award has been satisfied by the applicant.

On this issue, it should be noticed that the applicant is not seeking to attach a

movable or immovable property of the 1st respondent. Instead, the asset is in the

form of a receivable from the 2nd respondent to the 1st respondent. The said

receivable is money. Given the nature of the asset, the test of removal of assets

from the jurisdiction of the Court cannot be applied without tweaking such test to

suit the nature of the asset. In response to the submission of the 2nd respondent that

it is ready and willing to place Rs.4,00,00,037 in a fixed deposit account, the

contention of the 1st respondent is that this money would be put to use by the 1 st

respondent. Moreover, as stated above, in the affidavit in support of the

application, the applicant has stated that the 1st respondent has evaded and avoided

payments from December 2017. The admitted position, as on date, is that no

payments were made pursuant to any bills subsequent to RA bill 11. About 4 years

have elapsed in the meantime. In these facts and circumstances, in my view, the

requirements of Order 38 Rule 5 of C.P.C., as applicable to a garnishee application

in respect of a receivable, stand satisfied.

10.Although the applicant makes a principal claim for a sum of

Rs.6,62,17,343/- and has submitted a statement which seems to indicate that the

principal receivable is about Rs.7,62,00,000/-, the contract envisages retention

https://www.mhc.tn.gov.in/judis Arb.Appln.No.180 of 2021

until measurements are taken and the completion certificate is issued. Therefore, a

prohibitory order for the full amount claimed is not appropriate. In any event,

learned counsel for the 2nd respondent indicated that a sum of about

Rs.4,00,37,000/- may be payable by the 2nd respondent to the 1st respondent.

Therefore, the prohibitory order should be limited to that extent. Accordingly,

Arbitration Application No.180 of 2021 is disposed of with the following

directions:

(i). The applicant is permitted to raise an invoice of current date

towards the final bill. Such invoice may be issued without prejudice to the 1 st

respondent's contention in respect of the previously issued invoice, whether for

purposes of limitation or otherwise.

(ii). Upon receipt of such invoice, the 2nd respondent is directed to

create a fixed deposit account for a sum of Rs.4,00,37,000/- to the credit of

Arbitration Application No.180 of 2021 in an interest bearing account in any

nationalised bank. Such fixed deposit shall be for an initial period of one year.

Upon establishing such fixed deposit account, the 2nd respondent is directed to

hand over a copy of the fixed deposit receipt to the applicant and the 1st respondent

herein.

(iii). The applicant may approach the arbitral tribunal if extensions of

https://www.mhc.tn.gov.in/judis Arb.Appln.No.180 of 2021

the fixed deposit are required after the initial period of one year. The fixed deposit

shall abide by the outcome of arbitral proceedings between the applicant and the 1st

respondent.

(iv) The 2nd respondent is restrained from making the final bill

payment to the 1st respondent except by way of creating the fixed deposit as

directed above.

(v) It is needless to say that the observations contained in this order

are tentative and for interlocutory purposes only, and that the arbitral tribunal may

examine these issues without being influenced by such observations, be it in the

dispute between the applicant and the 1st respondent or the dispute between the 1st

respondent and the 2nd respondent.



                                                                                         25.01.2022

                Index             : Yes/No.
                Internet          : Yes/No.
                Bsm


                                                              SENTHILKUMAR RAMAMOORTHY J,


                                                                                                       bsm





https://www.mhc.tn.gov.in/judis
                                         Arb.Appln.No.180 of 2021




                                  Arb.Appln.No.180 of 2021




                                                  25.01.2022





https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter