Citation : 2022 Latest Caselaw 17937 Mad
Judgement Date : 1 December, 2022
A.S.Nos.32 & 33 of 2017
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 01.12.2022
CORAM:
THE HONOURABLE Mr. JUSTICE S.SOUNTHAR
A.S.Nos.32 & 33 of 2017
and C.M.P.No.21099 of 2017
S.B.Buvaneswari ...Appellant in both A.S's
Versus
Sri Foundation, a partnership firm,
duly registered vide No.1209/08 at
SRO Saidapet and represented by its
Managing Partner Mr.Nandakumar
having office at No.1/360,
Thirumurugan Nagar, Mugalivakkam,
Chennai - 600 116. ... Respondent in both A.S's
PRAYER in A.S.No.32 of 2017: Appeal Suit filed under Section 96 r/w Order
XLI Rule 1 CPC, pleased to set aside the judgment and decree dated 20.08.2016
made in O.S.No.210 of 2010 by the learned Principal District Judge of
Kancheepuram District at Chengalpattu, dismissing the counter claim filed by the
appellant with costs.
PRAYER in A.S.No.33 of 2017: Appeal Suit filed under Section 96 r/w Order
XLI Rule 1 CPC, pleased to set aside the judgment and decree dated 20.08.2016
made in O.S.No.210 of 2010 by the learned Principal District Judge of
Kancheepuram District at Chengalpattu, directing the appellant to pay to the
________
Page 1 of 18
https://www.mhc.tn.gov.in/judis
A.S.Nos.32 & 33 of 2017
respondent a sum of Rs.2,07,000/- with proportionate costs with interest at 18%
p.a. from the date of the plaint till the date of realization. Direct the respondent to
pay costs of this appeal and allow this appeal.
For Appellant : Mr.B.S.Jhothiraman
( in both A.S's)
For Respondent : Mr.R.Amizhdhu
( in both A.S's)
O R D E R
The defendant in the suit is the appellant. The respondent filed a suit for
recovery of money seeking a direction to appellant to pay a sum of
Rs.12,28,351/- being the arrears of payment due to the respondent for the
building construction work done by it for the appellant together with interest at
the rate of 12%. The respondent also sought for an injunction restraining the
appellant from dis-possessing respondent from the suit site by removing men and
material. The appellant on her part laid a counter claim seeking a direction to
respondent to pay a sum of Rs.5,11,116/- towards escalation in cost of labour
and materials due to failure of the respondent to keep the time schedule in
completing construction, loss of rental income, mental agony etc., The Trial
Court decreed the suit in part by directing the appellant to pay a sum of
Rs.2,07,000/- to respondent together with interest at the rate of 18% per annum
________
https://www.mhc.tn.gov.in/judis A.S.Nos.32 & 33 of 2017
from the date of plaint to date of realization. The counter claim filed by the
appellant was dismissed in toto. Aggrieved by the decree granting plaint prayer
in part the defendant has come up with A.S.No.32 of 2017. He also filed a
separate appeal in A.S.No.33 of 2017, challenging dismissal of counter claim.
2. Plaint averments:
According to the respondent there was a construction contract between
respondent and appellant entered into on 06.07.2009. The respondent agreed to
construct a residential building in the site belonged to appellant. As per the terms
of agreement respondent agreed to construct a building with an extent of 2,102
sq. ft. at the cost of Rs.1,240/- per sq. ft. When the construction was nearing
completion during March 2010 dispute arose between respondent and the
appellant with regard to the release of further payment by the appellant. As
construction of the building progressed some changes were brought in by the
appellant and her husband and construction was done as per the requirements and
modifications suggested by the appellant. Hence total build up area increased.
According to the respondent as per the revised estimate for the revised built up
area, the total cost of construction came to Rs.45,05,521/-. When the dispute
arose between parties, the cost of the completed construction was worth about
________
https://www.mhc.tn.gov.in/judis A.S.Nos.32 & 33 of 2017
Rs.38,28,351/-. But at that stage, total amount released and paid by the appellant
was only Rs.26.00 lakhs. Therefore, huge amount of Rs.12,28,351/- remained
payable by the appellant to respondent towards the cost of the completed works.
The respondent further averred that majority of the works were completed and as
the appellant failed to release further payment as per the revised estimate, the
respondent was not in position to proceed further with the completion of the
construction. It was also averred that appellant engaged the services of Engineer
called Pandurangan to assess the work done by the respondent and the amount
required for the completion of the building, but the said Engineer demanded bribe
from the respondent for giving favourable report, but he refused. Hence
according to the respondent the said Engineer Pandurangan had given a faulty
report against the respondent. As the appellant tried to get rid of the respondent
from the construction site and attempted to complete the construction through a
third party, the present suit was laid by the respondent for the aforesaid reliefs.
3. Averments found in the written statement:
The appellant filed a detailed written statement denying various averments
found in the plaint filed by the respondent. It was specifically pleaded by the
appellant that as per the time schedule agreed for release of payment she has to
________
https://www.mhc.tn.gov.in/judis A.S.Nos.32 & 33 of 2017
pay 25% as the initial amount, 10% when the building reaches the base ground
level, 20% when the building reaches the roof level and 15% at the stage of
plastering. According to the appellant, the cost of the total project was
Rs.44,05,583/- and she had paid Rs.26.00 lakhs when construction was
unilaterally stopped by respondent. It was also pleaded that both agreed to
appoint an Engineer called Pandurangan to assess the value of the semi finished
building and the amount required for completing the building. According to the
appellant both parties agreed to settle the dispute on the basis of the value fixed
by said Engineer. The appellant also averred that as per the estimate given by the
said Pandurangan the cost of the semi finished building was assessed at
Rs.25,52,000/- and the cost required for completing the building was fixed at
Rs.10,90,796/-. It was also specifically averred by the appellant she already paid
Rs.26.00 lakhs and therefore as per the report furnished by the common Engineer
Ex.B.20 the respondent has to return the sum of Rs.48,000/-. The appellant also
averred that due to failure of respondent in finishing the construction work the
cost of materials has gone up, when she finished construction work by employing
a third source she incurred extra amount for completion of the construction.
Therefore, appellant by way of counter claim claimed Rs.5,11,116/- from the
respondent. On these pleadings both the parties went to trial and the partner of
________
https://www.mhc.tn.gov.in/judis A.S.Nos.32 & 33 of 2017
the respondent firm was examined as P.W.1, the husband of the appellant was
examined as D.W.1 and Mason employed by the appellant to finish construction
work was examined as D.W.2.
4. The Trial Court on appreciation of oral and documentary evidence came
to the conclusion that the contract between the parties got frustrated due to
failure of the appellant to release funds as agreed. The Trial Court accepting the
Engineer's report of said Pandurangan which was marked as Ex.B.20, has come
to a conclusion that the semi finished construction put up by the respondent cost
about Rs.25,52,000/- adding 10% of the same towards profit to the builder, the
cost of the construction was fixed by the Trial Court at Rs.28,07,000/-. As the
appellant paid only Rs.26.00 lakhs, the Trial Court directed the appellant to pay a
sum of Rs.2,07,000/- with proportionate cost and interest. In view of the said
finding, the Trial Court came to the conclusion that respondent is not liable to
pay any amount to appellant as per her counter claim. Aggrieved by the said
judgment and decree the appellant has come up by way of this appeal.
5. The learned counsel for the appellant submitted that as per the
Engineer's report Ex.B.20, the cost of the semi finished building arrived by him at
Rs.25,52,000/- includes profits of the construction company. The learned counsel
________
https://www.mhc.tn.gov.in/judis A.S.Nos.32 & 33 of 2017
by taking me to the remarks made by the Engineer in his foot of the report to the
effect that the above cost includes reasonable materials + labour cost and
contractor's profit for his construction work. Therefore, the learned counsel for
the appellant submitted that the Trial Court erred in adding Rs.2.00 lakhs to the
valuation arrived at by the Engineer under Ex.B.20 towards profit to the builder.
The learned counsel also vehemently argued that the loss suffered by the
appellant due to sudden stoppage of the work by the respondent and
consequential escalation in the cost of construction material was spoken to by
Mason engaged by appellant who was examined as D.W.2. The learned counsel
submitted that the evidence of appellant's husband as D.W.1 was very well
corroborated and supplemented by the evidence of D.W.2. Therefore, it is the
contention of the learned counsel for the appellant that the Trial Court ought not
to have dismissed the counter claim made by the appellant.
6. Per contra the learned counsel for the respondent submitted that even as
per the admission of the appellant in her written statement, the cost of revised
estimate was Rs.44,05,583/- and not as claimed by the respondent at
Rs.45,05,521/-. The learned counsel submitted that when appellant herself
admitted that the cost of the revised estimate was Rs.44,05,583/- the Trial Court
________
https://www.mhc.tn.gov.in/judis A.S.Nos.32 & 33 of 2017
ought to have directed the appellant to pay more amount, but it directed the
appellant to pay only a sum of Rs.2,07,000/-, and hence, decree was passed by
the Court below need not to be interfered with. The learned counsel further
contended in view of the admission made by the appellant in her written
statement that revised estimate is Rs.44,05,583/-, the failure of appellant to
release further sum as agreed was the reason for failure of contract and
consequently the appellant is not entitled to any sum as demanded by her in the
counter claim.
7. On the basis of the pleadings, evidence available on record contentions
of the respective counsel following points are arising out for consideration
1. Whether the construction work was stopped due to default on the part
of the appellant or on the part of the respondent
2. Whether the decree passed by the Trial Court directing the appellant to
pay sum of Rs.2,07,000/- towards balance of costs of semi finished building is
correct or not.
3. Whether the counter claim preferred by the appellant is deserved to be
allowed or not.
________
https://www.mhc.tn.gov.in/judis A.S.Nos.32 & 33 of 2017
8. Points 1 to 3:
Since all the points arising for consideration in the appeal are interlinked.
All the points are taken up for consideration jointly. The first question to be
determined is whether the construction work was stopped due to the fault of the
appellant or due to the fault of the respondent.
9. As per the agreement between the parties the extent of the agreed
construction was 2,102 Sq.ft. It is not in dispute that the respondent had started
construction in the suit property. The appellant herein in his written statement
specifically admitted the revised cost of construction was Rs.44,05,583/-. The
plaintiff in the plaint averment had mentioned that in view of the increased area
of construction, the total estimate for construction of the building had risen to
Rs.45,05,521/-. As per the agreement the respondent agreed to construct 2,102
sq. ft. of building at the rate of Rs.1,240/- Therefore, as per the agreement, the
cost of the construction was Rs.26,06,480/-. But it is not in dispute at the time of
taking up the construction, the respondent put up construction in the increased
area. Though the respondent/plaintiff had averred in his plaint that in view of the
increased area of construction the revised cost for the building had risen to
________
https://www.mhc.tn.gov.in/judis A.S.Nos.32 & 33 of 2017
Rs.45,05,521/-, the same was denied by the appellant in her written statement.
But in paragraph 13 of written statement, the appellant had averred as follows:
“ The defendant denies the allegations in para 4 that the estimate was revised to Rs.45,05,521/-. As stated above, it was revised to Rs.44,05,583/- and not as claimed.”
10. The above averment of the appellant in her written statement explicitly
proves that the total extent of the construction as well as the cost of the
construction was revised later by mutual agreement of the parties. In her written
statement she had specifically admitted that the revised cost was Rs.44,05,583/-.
Had the appellant not agreed for extra construction, absolutely, there was no
necessity for her to agree for revised estimate of Rs.44,05,583/- as against the
original estimate of Rs.26,06,480/-. In view of the specific admission by the
appellant/defendant in her pleadings that revised estimate was Rs.44,05,583/-,
this Court comes to a definite conclusion that though parties agreed to put up
construction for 2,102 sq. ft. of building, subsequently, on mutual agreement they
decided to increase the extent of construction and consequently they revised the
cost of construction.
________
https://www.mhc.tn.gov.in/judis A.S.Nos.32 & 33 of 2017
11. Even as per the admitted case of the appellant/defendant, she had paid
only Rs.26.00 lakhs when the construction was stopped by the respondent.
Therefore, as per the revised estimate cost, appellant has to release more than
Rs.18.00 lakhs when the construction was stopped. Since appellant refused to
release the remaining amount as per the revised estimate, the respondent was
compelled to stop the work. Therefore, I agree with the finding rendered by the
Trial Court that the stoppage of the construction work was only due to the failure
of the appellant to release the remaining sum as per the revised estimate.
12. Once we come to the conclusion that the stoppage of the construction
work had happened only due to the failure of the appellant/defendant to release
balance of cost of construction, the appellant is not entitled to make claim against
the respondent towards escalation of the prices due to the stoppage of work by
the respondent. It is settled law, no person can take advantage of his own default.
Therefore, the appellant is not entitled to make any claim against the respondent
for the extra cost incurred by her for completing the construction work by
engaging a third party. The learned counsel for the appellant by taking this Court
to the evidence of D.W.1 and D.W.2 namely the Mason who helped the
appellant to finish the construction work, contended that there are ample
________
https://www.mhc.tn.gov.in/judis A.S.Nos.32 & 33 of 2017
evidence available on records to show that appellant incurred extra cost in
completing the construction work due to the default committed by the
respondent. Though the appellant's husband who was examined as D.W.1
deposed that he never requested the respondent to increase the extent of
construction. The said version of the D.W.1 is not acceptable for a reason that
the appellant herself in her pleadings admitted that the revised cost of
construction was Rs.44,05,583/-. If the extra construction put up by the
respondent is an unilateral act of his own, certainly there is no need for the
appellant to revise the cost of construction. The very fact that appellant agreed
for increase of cost of construction from Rs.26,06,480/- to Rs.44,05,583/- amply
proves that increase in the area of construction was mutually agreed by the
parties. In view of the discussions made above, this Court come to a conclusion
that the appellant/defendant is not entitled to make a claim against the
respondent/plaintiff towards escalation of cost of construction. Consequently, the
counter claim made by the respondent deserved to be dismissed.
13. The Trial Court taking into consideration Ex.B.20 report of the
Engineer came to the conclusion that the cost of the construction of the semi
finished building was Rs.25,52,000/-. Though the respondent seriously disputed
________
https://www.mhc.tn.gov.in/judis A.S.Nos.32 & 33 of 2017
the valuation adopted by the Engineer by making allegations against the Engineer
has not chosen to challenge the decree passed by the Trial Court. The learned
Trial Judge, in addition to the cost of the construction mentioned by the Engineer
in Ex.B.20 added 10% of the said amount towards minimum profit for the
contractor. In other words, the Trial Court assumed the cost of construction
arrived at by Engineer in Ex.B.20 is the actual cost of the construction excluding
the profit margin of the respondent/plaintiff. The said approach of the Trial Court
is not acceptable to this Court. A reading of the Ex.B.20, Engineer's report would
suggest that the cost of the construction arrived at by the Engineer at
Rs.25,52,000/- includes profit of the contractor. The Engineer who prepared
Ex.B.20 in the foot of the calculation sheet specifically mentioned that the above
cost includes reasonable material and labour cost and contractor profit for
construction. Therefore, a sum of Rs.25,52,000/- arrived at by Engineer under
Ex.B.20 includes profit margin for the contractor. In that case Trial Court is not
justified in adding 10% of the above said sum towards cost of construction.
Admittedly, the appellant already paid a sum of Rs.26.00 lakhs to respondent. As
per the Ex.B.20, Engineer's report the cost of construction of the semi finished
building which includes the profit of the Contractor is only Rs.25,52,000/-
Therefore, the Trial Court is not justified in adding 10% on the said amount and
________
https://www.mhc.tn.gov.in/judis A.S.Nos.32 & 33 of 2017
directing the appellant to pay a further sum of Rs.2,07,000/-. The amount already
paid by the appellant to respondent represents almost equal to the cost of the
construction arrived at by Engineer under Ex.B.20. In these circumstances,
appellant is not liable to pay any further sum to the respondent. Hence, the
decree passed by the Court below directing the appellant to pay a sum of
Rs.2,07,000/- to the respondent is liable to be set aside.
14. In Nut shell:
1. Appeal in A.S.No.32 of 2017 stands allowed by setting aside the judgment
and decree passed by the Trial Court directing the appellant/defendant to
pay a sum of Rs.2,07,000/- with interest at 18% to the respondent.
2. The appeal in A.S.No.33 of 2017 filed by the appellant/defendant
challenging the dismissal of the counter claim stands dismissed.
3. The suit in O.S.No.201 of 2010 is dismissed.
4. There shall be no order as to costs. Consequently, connected
miscellaneous petition is closed.
________
https://www.mhc.tn.gov.in/judis A.S.Nos.32 & 33 of 2017
01.12.2022
Index: Yes/ No Speaking Order / Non-Speaking Order jai
To The Principal District Court, Kancheepuram District, Chengalpattu.
S.SOUNTHAR, J.
jai
________
https://www.mhc.tn.gov.in/judis A.S.Nos.32 & 33 of 2017
A.S.Nos.32 & 33 of 2017 and C.M.P.No.21099 of 2017
01.12.2022
A.S.No.32 and 33 of 2017 and C.M.P.No.21099 of 2017
S.SOUNTHAR, J.
After pronouncement of the judgment, the learned counsel for the appellant
brought to the notice of this Court that in pursuance of the interim order passed by this
Court, the appellant had deposited a sum of Rs.2,07,000/- (Two Lakhs and Seven
Thousand Rupees only) on 13.09.2017 before this Court by way of Demand Draft in
the name of the Registrar General, High Court, Madras.
________
https://www.mhc.tn.gov.in/judis A.S.Nos.32 & 33 of 2017
2. In view of allowing A.S.No.32 of 2017, the appellant is permitted to
withdraw the said amount deposited by him with accrued interest, if any.
01.12.2022
jai
S.SOUNTHAR, J.
jai
________
https://www.mhc.tn.gov.in/judis A.S.Nos.32 & 33 of 2017
A.S.Nos.32 & 33 of 2017 and C.M.P.No.21099 of 2017
01.12.2022
________
https://www.mhc.tn.gov.in/judis
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!