Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Tamil Nadu Generation And ... vs P.Meeraza
2022 Latest Caselaw 8770 Mad

Citation : 2022 Latest Caselaw 8770 Mad
Judgement Date : 26 April, 2022

Madras High Court
Tamil Nadu Generation And ... vs P.Meeraza on 26 April, 2022
                                                                W.A.Nos.3038 and 3039 of 2021



                                    IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                DATED : 26.04.2022

                                                     CORAM :

                        THE HON'BLE MR.MUNISHWAR NATH BHANDARI, CHIEF JUSTICE
                                                       AND
                                  THE HON'BLE MR.JUSTICE D.BHARATHA CHAKRAVARTHY


                                           W.A.Nos.3038 and 3039 of 2021


                     1. Tamil Nadu Generation and Distribution Corporation Ltd
                        rep. by its Chief Engineer
                        North Chennai Thermal Power Station – I
                        Chennai – 600 120.

                     2. The Superintending Engineer/Mech-II
                        TANGEDCO
                        North Chennai Thermal Power Station – I
                        Chennai – 600 120.

                     3. The Superintending Engineer/Mech-I
                        TANGEDCO
                        North Chennai Thermal Power Station – I
                        Chennai – 600 120.                                 .. Appellants

                                                        Vs

                     P.Meeraza                                             .. Respondent

Prayer: Appeals under Clause 15 of the Letters Patent against the judgment dated 24.2.2021 passed in W.P.No.13238 of 2020 and 2987 of 2021.

__________

https://www.mhc.tn.gov.in/judis W.A.Nos.3038 and 3039 of 2021

For the Appellants : Mr.J.Ravindran Additional Advocate General for M/s.L.Jaivenkatesh

For the Respondent : Mr.B.Kumar Senior Advocate for Mr.T.Sudhanraj

COMMON JUDGMENT (Delivered by The Hon'ble Chief Justice)

Heard the writ appeals for challenge to the judgment dated

24.2.2021, whereby the writ petition filed by the petitioner/non-

appellant to quash the proceedings of the third appellant

withholding the amount which is due and payable to the

petitioner/non-appellant.

2. It is a case where the petitioner/non-appellant was given

three different works under three different contracts. The work in

respect of the first and second contracts was completed and,

accordingly, the appellants issued completion certificate to show

their satisfaction and made the entire payment due towards the first

and second contracts. While the third contract was still to be

executed by the petitioner/non-appellant, an order was passed to

__________

https://www.mhc.tn.gov.in/judis W.A.Nos.3038 and 3039 of 2021

recover the amount in reference to the first and second contracts

based on an audit objection and orders to this effect were passed on

15.12.2018 and 19.8.2020. Challenge to the aforesaid orders was

sustained for the reason that after issuance of the completion

certificate and payment of due amount, the recovery could not have

been effected in regard to the works executed qua the third contract.

3. Learned Additional Advocate General submits that even

after the issuance of the completion certificate and payment of due

amount pertaining to the first and second contracts, recovery was

permissible under paragraph 22 of the instructions to bidders, which

reads as under:

“22.0 Recoveries of Dues:

Amount due from the supplier to the Corporation for the default in any other previous purchase orders will be adjusted from the pending payments against the purchase order placed on the vendor in this specification, which may plead be noted.”

4. Paragraph 22 permits recovery of the amount due from

__________

https://www.mhc.tn.gov.in/judis W.A.Nos.3038 and 3039 of 2021

supplier to the Corporation for the default in any other previous

purchase orders and can be adjusted from the pending payment

against the purchase order placed on the vendor in this

specification. Paragraph 22 can be invoked in two situations (i)

there should be default in the previous purchase order, while it is

executed; and, (ii) on account of such default, the amount should

due from the supplier to the Corporation.

5. In the instant case, both the conditions are not made out

for the reason that on completion of the first and second contracts,

completion certificates were issued by the writ appellants and the

petitioner/non-appellant was paid the entire amount due. The issue

has been re-opened only in reference to the audit objection, without

showing any provision in the agreement entered into between the

parties to re-open the matter even after issuance of the completion

certificate and making payment.

6. Accordingly, the learned Single Judge found reason to cause

interference with the impugned orders. The audit objection was also

__________

https://www.mhc.tn.gov.in/judis W.A.Nos.3038 and 3039 of 2021

taken into consideration by the learned Single Judge in paragraph

(6) of the judgment. For ready reference, paragraph (6) is quoted

hereunder:

“6. In response to this audit objection, the learned Senior Counsel appearing for the petitioner has drawn the attention of this Court to the following tender conditions.

'3.0 Supply of compressed air: The contractor has to make his own arrangement for the compressed air required for the work at his cost.

4.0 Power Supply: Free power supply will be provided to the Contractor from the nearest available Corporation's power supply point, for the contractor's offices and stores. The contractor should make his own arrangement to extend the power to the area of work and also maintain such extension lines at his cost.'”

7. Learned counsel for the petitioner/non-appellant submits

that as per the conditions of the agreement, the contractor was

entitled to free power supply for their requirement, but the

__________

https://www.mhc.tn.gov.in/judis W.A.Nos.3038 and 3039 of 2021

appellants failed to supply the electricity, because the first available

point was at the distance of 6 km and it was not possible to get

electricity from that place and otherwise it was the obligation of the

appellants to provide free power supply and, obviously, it has to be

at the place of execution of the work and not at a distance of 6 km

and in that circumstances, the petitioner/non-appellant was left with

no option but to use the diesel. It is to cover the default on the part

of the appellants in not supplying free power, the audit has raised

the erroneous objection about the usage of diesel instead of power

supply and mulcted the responsibility on the petitioner/non-

appellant.

8. The appellants have otherwise not shown any action taken

against the officials who had paid excess amount to the contractor.

Therefore, the audit objection remains for the sake of it and,

accordingly, the learned Single Judge has rightly caused interference

in the order passed by the appellants while allowing the writ

petition.

__________

https://www.mhc.tn.gov.in/judis W.A.Nos.3038 and 3039 of 2021

For the foregoing reasons, we do not find any error in the

judgment of the learned Single Judge warranting interference. The

appeals are dismissed. There will be no order as to costs.

Consequently, C.M.P.Nos.20835 and 20836 of 2021 are closed.

                                                               (M.N.B., CJ)      (D.B.C., J.)
                                                                         26.04.2022
                     Index : Yes/No
                     sasi




                     __________



https://www.mhc.tn.gov.in/judis W.A.Nos.3038 and 3039 of 2021

THE HON'BLE CHIEF JUSTICE AND D.BHARATHA CHAKRAVARTHY,J.

(sasi)

W.A.Nos.3038 and 3039 of 2021

26.04.2022

__________

https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter