Saturday, 09, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.Napc Limited vs The Superintending Engineer
2021 Latest Caselaw 20036 Mad

Citation : 2021 Latest Caselaw 20036 Mad
Judgement Date : 30 September, 2021

Madras High Court
M/S.Napc Limited vs The Superintending Engineer on 30 September, 2021
                                                                     OSA Nos.188 and 189 of 2019

                                     IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                DATED:      30.09.2021

                                                         CORAM :

                                THE HON'BLE MR.SANJIB BANERJEE, CHIEF JUSTICE
                                                          AND
                                      THE HON'BLE MR.JUSTICE P.D.AUDIKESAVALU
                                             OSA Nos.188 and 189 of 2019

                      M/s.NAPC Limited
                      184/214, Royapettah High Road
                      MMPDA Tower, 2nd Floor, Royapettah,
                      Chennai 600 014.                                   ...   Appellant in
                                                                               both OSAs.

                                                           Vs.

                      1. The Superintending Engineer,
                         National Highways, TNSCC Complex,
                         Jai Nagar, 206/N, Jawaharlal Nehru Salai,
                         Opp. Mofussil Bus Stand, Chennai 600 106.

                      2. K.Srinivasan
                         Sole Arbitrator
                         C2, Block 1, Mayfair Apts, 2A, LIC Colony Road,
                         Velachery, Chennai 600 042.                 ...       Respondents in

both OSAs.

Appeals filed against the common order dated 10.07.2019 in OP Nos.881 and 899 of 2018 on the file of original side of this court by upholding the arbitration award published for implementation.

                            For the Appellant        :      Mr.Satish Parasaran,
                                                            Senior Counsel,
                                                            for Mr.Arun C.Mohan

                            For the 1st Respondent :        Mr.Edwin Prabhakar,
                                                            Special Government Pleader
                                                            (Civil Side)

http://www.judis.nic.in

                      ____________

                                                                    OSA Nos.188 and 189 of 2019

                                               COMMON JUDGMENT

                                      (Delivered by the Hon'ble Chief Justice)



The contractor is the appellant questioning an order passed

under Section 34 of the Arbitration and Conciliation Act, 1996 setting

aside an award on the ground of lack of authority and limitation. The

appellant had partially succeeded before the arbitrator and the award

provided for a sum of slightly over Rs.4.21 crore, inclusive of interest

till the date of the award.

2. The contract was for the construction of a two-lane by-pass

around Kanchipuram in the Villupuram Division connecting NH4 and

the Kancheepuram – Vandavasi Road. It included the construction of a

major bridge. The contract was, as accepted by the parties, for a

period of 24 months from April 18, 2010. A first lot of claim was made

by the contractor on January 9, 2012 for the period up to October,

2011, which was rejected by the respondent employer on March 9,

2012. The tenure under the contract was extended on or about April

17, 2012 for a period of seven months. On July 27, 2012, a second lot

of claim came to be made by the contractor for the period November,

2011 to May, 2012. Again, the employer rejected the claim on

September 7, 2012. On or about October 16, 2012, the tenure was

extended for a further six months. On January 30, 2014, the third lot http://www.judis.nic.in

____________

OSA Nos.188 and 189 of 2019

of claim was made by the contractor. There is no dispute that the

demand for arbitration was made by the contractor on August 14,

2015. Under Section 21 of the Act of 1996, the commencement of

arbitration happens upon a demand for an arbitral reference made by

one party being received by the other party. Despite the demand for

an arbitral reference in accordance with the arbitration clause found at

clause 50 of the agreement between the parties which is dated April

19, 2010, the contractor was constrained to request the Chief Justice’s

Designate under Section 11(6) of the Act of 1996 to constitute an

arbitral tribunal. A sole arbitrator was appointed.

3. Unfortunately, the arbitrator has been quite unnecessarily

impleaded as a party to the appeal since the arbitrator was also

impleaded before the arbitration court. It is completely unnecessary

for arbitrators to be arrayed as party unless personal allegations are

made and the arbitrator is required to answer such allegations. Despite

several orders in such regard, the unsavory practice continues in this

court, of needlessly impleading arbitrators.

4. There is no dispute that the request under Section 11(6) of

the Act of 1996 was prosecuted upon notice to the employer. At such

point of time, the employer did not step up to suggest that there was

no arbitration agreement between the parties or that the disputes http://www.judis.nic.in

____________

OSA Nos.188 and 189 of 2019

raised by the contractor were not covered by any arbitration

agreement. It was only upon the arbitrator appointed by the Chief

Justice’s Designate taking up the reference that an application was

moved under Section 16 of the Act of 1996 questioning the authority

of the arbitrator to proceed with the reference on the ground that a

particular government order of 1990 vintage issued by the Public

Works Department precluded arbitral references where the value of

the claim was in excess of Rs.5 lakh. Though the employer asserted

the application of G.O.Ms.No.1545 dated July 26, 1990 before the

arbitrator and seeks to rely on such notification to sustain the

judgment and order impugned herein dated July 10, 2010, it does not

appear that the relevant notification was referred to, even indirectly, in

the agreement of April 19, 2020.

5. According to the respondent employer, the agreement

between the parties makes a reference to "PS to SSRB" at clause

4.2(c). Clause 4.2 covers the governing law and the heading of such

clause is "Laws governing contract, observance of laws". Sub-clause

(c) and the reference to "PS to SSRB" implies the set of guidelines

contained in the Preliminary Specifications to Standard Specifications

to Roads and Bridges.

6. Though the submission in such regard makes little meaning, http://www.judis.nic.in

____________

OSA Nos.188 and 189 of 2019

so that the entirety of the argument made on behalf of the employer is

at least referred to, the whole of Clause 4.2 may be seen:

“4.2 LAWS GOVERNING CONTRACT OBSERVANCE OF LAWS:

Local regulations and attachments

a) The law to which the contract is to be subject and according to which the contract is to be constructed shall be the law for the time being in force in the Union of India and State of Tamil Nadu.

b) The contractor shall conform to all laws of the land, and the regulations and bylaws of any local authority, and of any after or lighting companies with whose systems the structure is proposed to be connected. He shall, before making any variations from the drawings or specification that may be necessitated for so conforming give to the Engineer written notice, specifying the variations proposed to be made and the reasons for making them, and apply for instructions thereon. In case the contractor shall not receive such instructions within seven days, he shall proceed with the work conforming to the provisions, regulations or by-laws in question and any variations in the drawings or specifications so necessitated shall be dealt with under Clause 27. The contractor shall give all notice required by the said Acts, regulations or by-laws and pay all fees in connection therewith. He shall also ensure that no attachments are made against all claims or liabilities arising from or based on the violation of such laws ordinances, regulations, by-laws, decrees or attachments by him or by his employees.

http://www.judis.nic.in

____________

OSA Nos.188 and 189 of 2019

c) P.S.to S.S.R.B. is inseparable part of this contract.”

7. Such clause has also, incidentally, been quoted in the

impugned judgment. Nothing in sub-clauses (a) or (b) of Clause 4.2 of

the said agreement makes any government notification or order

applicable to the contract between the parties herein by the remotest

reference thereto. It is now to be seen whether the obscure reference

to "PS to SSRB" would incorporate the reference to the government

order of 1990. Extracts from the Preliminary Specifications to Standard

Specifications to Roads and Bridges have been relied upon on behalf of

the employer at pages 12 to 24 of the typed set filed on its behalf on

September 29, 2021. It is submitted that paragraph 108.02 in the said

Preliminary Specifications would cover the present situation. There is

absolutely no connection between paragraph 108.02 of the Preliminary

Specifications and G.O.Ms.No.1545 dated July 26, 1990. However, to

do justice to the submission made on behalf of the employer, the

entirety of the paragraph is noticed:

"108.02 Laws to the (sic ‘be’) observed -

The Contractor shall at all times observe and comply with all Union and state laws, local laws, ordinances and regulations which in any manner affect the conduct of the works and all such orders as exist at the present and which may be enacted in the future by legislative bodies or tribunals having legal jurisdiction http://www.judis.nic.in

____________

OSA Nos.188 and 189 of 2019

or authority over the work, and no place of misunderstanding or ignorance thereof will be considered. He shall indemnify and save harmless the Government and all its officers, agents employees and servants against any claim or liability arising from or based on the violation of any such law, ordinance, Regulation, order or decree whether by himself or by his employees.

He shall also ensure that no attachments are made against materials or work forming part of or for the use of the contract.

All scaffolding runways hoists and other temporary construction shall comply with all pertinent requirements of Union and state laws, local laws, ordinances and regulations."

8. The relevant clause quoted above refers to Union and State

laws, local laws, ordinances and regulations but does not refer to any

instructions or orders issued by any government. Though the word

"order" appears in the initial part of the clause, such word must be

seen in the context in which it has been used and pertains to the

conduct of the works and all such orders as existing at the time of the

Preliminary Specifications being published as long as they were made

by “legislative bodies or tribunals having legal jurisdiction or authority

over the work.” At any rate, if the government order of 1990 were to

apply to the agreement of April 19, 2010 between the parties, a

http://www.judis.nic.in

____________

OSA Nos.188 and 189 of 2019

solitary line could have been incorporated either in the arbitration

clause or elsewhere, particularly when the agreement was so detailed

and specific.

9. The objection under Section 16 of the Act failed before the

arbitrator. The arbitrator, thereafter, proceeded to render a speaking

award on merits. The respondent herein was obliged to wait to revive

the challenge to the authority of the arbitrator in course of the

proceedings under Section 34 of the Act. The objection was accepted

by the arbitration court.

10. In the judgment and order impugned herein, the work

undertaken and the other preliminary details are noticed over the first

16 pages or so of the judgment before clause 4.2 of the general

conditions governing the agreement dated April 19, 2010 is quoted in

its entirety. The judgment, thereafter, notices G.O.Ms.No.1545, dated

July 26, 1990 and quotes the same. In the discussion at paragraphs

13 to 25 where two issues are referred in tandem – limitation and the

authority to go to arbitration – the impugned judgment refers to

several precedents, including one cited by the respondent in course of

this appeal, before concluding that the claim carried to the reference

was barred by limitation and the value of the claim was such that it

could not have been carried to an arbitral reference. The judgment and http://www.judis.nic.in

____________

OSA Nos.188 and 189 of 2019

order impugned does not refer in any great detail to the relevant dates

as to why the claim of the contractor was perceived to be barred by

limitation. In any event, when the arbitration court was minded to hold

that the arbitration was without jurisdiction, the point of limitation may

not have been addressed.

11. The respondent has referred to a judgment reported at

(2001) 10 SCC 30 (State of A.P. vs. Obulu Reddy) where, in

connection with a reference under the 1940 Act, a similar circular

issued by the State of Andhra Pradesh was referred to. The objection

was taken at the earliest stage when a petition for appointment of an

arbitrator was filed before a Civil Judge (Senior Division). Though the

objection was overruled by the Civil Judge (Senior Division), the

objection was accepted before the High Court and the Supreme Court

endorsed the view taken by the High Court.

12. The judgment has no manner of application in the present

case, particularly when no objection as to the invocation of arbitration

was raised at the Section 11(6) stage by the respondent herein. At any

rate, since the matrix contract of April 19, 2010, which contains the

arbitration agreement was a stand-alone document and did not refer

to the government order of 1990 or any other material from which the

incorporation of the relevant government order would be necessary to http://www.judis.nic.in

____________

OSA Nos.188 and 189 of 2019

be implied, the arbitrator cannot be faulted for having repelled, the

rather unnecessary objection raised by the respondent herein.

13. The second judgment which has been cited by the

respondent is reported at (2009) 7 SCC 696 (M.R.Engineers and

Contractors Private Limited vs. Som Datt Builders Limited). Section

7(5) of the Act of 1996 was considered by the court and it was held,

inter alia, that where the contract between the parties stipulated that a

condition of contract of one of the parties to the contract would form a

part of their contract, (for example, the general conditions of contract

of the Government where the Government is a party), the arbitration

clause forming a part of the general conditions of contract would apply

to the contract between the parties.

14. There are two aspects to the dictum in the said judgment.

The first is the factual aspect as to whether there is any other

document or the like which is referred to in the contract between the

parties for such other document or the like to be looked into and an

arbitration agreement culled out therefrom. For the moment, it may be

assumed that even the negative is read into the Supreme Court

dictum, implying thereby that if a specific arbitration clause is included

in the agreement and a document is referred to in the agreement

which negates the operation of the arbitration clause in certain cases, http://www.judis.nic.in

____________

OSA Nos.188 and 189 of 2019

the same has to be recognised. In the present case, the factual matrix

is not satisfied since no document or material is produced or cited by

the respondent from which it may be reasonably gleaned or inferred

that G.O.Ms.No.1545 would be applicable and would eclipse the

specific arbitration agreement between the parties if the value of the

claim was in excess of Rs.5 lakh. It is only upon the factual

requirement being met that the legal aspect of the dictum would be

required to be gone into: as to the impact of something in another

document or record, which would detract from the specific clause in

the agreement between the parties. In the absence of there being

anything to detract from the arbitration clause, as in the present case,

the second part of the exercise is completely unnecessary.

15. The arbitrator was perfectly justified in completely

disregarding the needless objection carried by the employer,

particularly in the light of the employer not taking such ground at the

Section 11(6) stage. It probably is a matter that needs to be

addressed at some level by the Government. Objections are needlessly

carried and challenges are made and pursued mindlessly – and the

State exchequer burdened – by the whims of officers who do not take

any responsibility and seek to waste time and money on litigation since

the money does not come out of their pockets.

http://www.judis.nic.in

____________

OSA Nos.188 and 189 of 2019

16. As to the issue of limitation, since it is the admitted position

that the commencement of the arbitral proceedings was on August 14,

2015, any claim that may have been lodged or the cause of action

pertaining to which may have arisen within three years prior to August

14, 2015 could not be said to be barred by limitation. It has been

noticed earlier in this judgment that three lots of claims had been

made by the appellant herein: the first on January 9, 2012 which was

rejected on March 9, 2012; the second on July 27, 2012 which was

rejected on September 7, 2012; and the third on January 30, 2014,

irrespective of when it may have been rejected. Since the claims in

respect of the second and the third lots were made at a point of time

within three years prior to August 14, 2015 when the arbitration

proceedings would be deemed to have commenced, the arbitrator

quite appropriately considered such claims on merits and passed

adequate reasons to allow parts thereof. By the same yardstick, the

arbitrator was justified in rejecting the claim initially made by the

contractor on January 9, 2012, since the cause of action in respect

thereof arose at a point of time more than three years prior to August

14, 2015 when the arbitral proceedings are deemed to have

commenced.

17. For the reasons aforesaid, the judgment and order impugned

dated July 10, 2019 cannot be accepted and the same are hereby set http://www.judis.nic.in

____________

OSA Nos.188 and 189 of 2019

aside. The arbitral award dated May 23, 2018 is restored. It is

recorded that the challenge to the award made by the contractor, to

the extent the further claim made therein was rejected, has been

expressly abandoned at this appellate stage. There is no merit in the

respondent’s challenge to the arbitral award, whether on the ground of

lack of authority or limitation or on merits. Accordingly, OSA Nos.188

and 189 of 2019 stand allowed to the extent indicated.

18. The appellant will also be entitled to costs of the proceedings

in this court assessed at Rs.50,000/- (Rupees Fifty Thousand only). It

would be ideal if such costs came out of the relevant officer of the

respondent who engineered the challenge to the arbitral award in this

court.

                                                                    (S.B., CJ.)      (P.D.A., J.)
                                                                              30.09.2021

                      Index : yes
                      tar




http://www.judis.nic.in

                      ____________

                                          OSA Nos.188 and 189 of 2019



                                      THE HON'BLE CHIEF JUSTICE
                                                   AND
                                           P.D.AUDIKESAVALU, J.

                                                                (tar)




                                      OSA Nos.188 and 189 of 2019




                                                        30.09.2021




http://www.judis.nic.in

                      ____________

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter