Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.Karismaa Foundations Pvt. ... vs M/S.Olympia Tech Park (Chennai) ...
2021 Latest Caselaw 19522 Mad

Citation : 2021 Latest Caselaw 19522 Mad
Judgement Date : 23 September, 2021

Madras High Court
M/S.Karismaa Foundations Pvt. ... vs M/S.Olympia Tech Park (Chennai) ... on 23 September, 2021
                                                                  OSA Nos.102, 2 and 3 of 2021

                                    IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                               DATED:    23.09.2021

                                                     CORAM :

                                   THE HON'BLE MR.SANJIB BANERJEE, CHIEF JUSTICE
                                                        AND
                                     THE HON'BLE MR.JUSTICE P.D.AUDIKESAVALU
                                            OSA Nos.102, 2 and 3 of 2021
                                        and CMP Nos.4837, 81 and 75 of 2021


                     M/s.Karismaa Foundations Pvt. Ltd.,
                     Rep. by its Director, Mr.C.Rajesh,
                     No.340, 1st South Main Road, Kapaleswarar
                     Nagar, Neelankarai, Chennai 115.                 ...   Appellant in
                                                                            OSA.102/21 &
                                                                            Respondent in
                                                                            OSAs 2 & 3/21

                                                        -vs-

                     M/s.Olympia Tech Park (Chennai) Pvt. Ltd,
                     Plot No.1, SIDCO Industrial Estate,
                     Guindy, Chennai-32
                     (Respondent is substituted in place of
                      M/s.Olympia Infratech Pvt. Ltd.
                       M/s.Opaline Hotels Pvt. Ltd. based on
                        the memo filed)                               ...   Respondent in
                                                                            OSA.102/21 &
                                                                            Appellant in
                                                                            OSAs 2 & 3/21



                               Appeals filed Order XXXVI Rule 11 of O.S. Rules read with
                     Section 37 of the Arbitration and Conciliation Act, 1996, against the


                     ____________
                     Page 1 of 13


https://www.mhc.tn.gov.in/judis/
                                                                       OSA Nos.102, 2 and 3 of 2021

                     common order of this Court dated 08.05.2020 passed in O.P.Nos.435
                     and 633 of 2019 on the file of original side of this court.


                               For the Appellant in
                               OSAs 102/21 &
                               Respondent in
                               OSAs 2 & 3/21           :     Mr.Nithyaesh Natraj

                               For the Respondent in
                               OSAs 102/21 &
                               Appellant in
                               OSAs 2 & 3/21         :       Mr.AR.L.Sundaresan
                                                             Senior Counsel
                                                             for Mr.C.T.Murugappan.

                                                           *****

COMMON JUDGMENT

(Delivered by the Hon'ble Chief Justice)

The dispute falls within a very limited ambit. Both parties to the

arbitral reference have carried appeals from the rejection or partial

rejection of their petitions under Section 34 of the Arbitration and

Conciliation Act, 1996.

2. There were several agreements between the parties, seven

work orders in all, for the construction of several lots of villas. The

appellant in OSA Nos.2 and 3 of 2021 is the owner and the appellant in

____________

https://www.mhc.tn.gov.in/judis/ OSA Nos.102, 2 and 3 of 2021

OSA No.102 of 2021 is the contractor. Under a common order passed

in respect of the arbitration clauses contained in the seven work

orders, a sole Arbitrator was appointed by the Chief Justice's Designate

on April 29, 2018. Despite such order and it being apparent that there

would be a single reference in respect of the entirety of the work, the

owner continued to initially contend before the Arbitrator that the

several work orders had to be treated distinctly. An objection on such

count has been carried even up to this stage. Indeed, the owner filed a

limited counter-claim at the initial stage before filing the further

counter-claim in 2018, which has prompted a minor point to be taken

by the contractor on the ground of limitation. But there is no merit in

the owner's suggestion that the claims under the seven perceived

independent work orders had to be dealt with distinctly nor in the

contractor's objection on the ground of limitation.

3. The Arbitrator, in course of rendering the award of April 8,

2019, held that the reference had always been taken up pertaining to

the entirety of the work, notwithstanding the initial murmurs to the

contrary on the part of the owner. The Arbitrator also noticed that a

combined counter-claim was fashioned by the owner towards the end

____________

https://www.mhc.tn.gov.in/judis/ OSA Nos.102, 2 and 3 of 2021

of the reference where all the heads of counter-claim were clubbed. As

to the ground of limitation taken by the contractor, there does not

appear to be any discussion in the award. However, it is evident that

the owner called upon the contractor to agree to refer the balance

claims of the owner pertaining to some of the work orders by a writing

which the contractor received in or about March, 2018. Upon the

contractor’s failure to act in terms of the request, the owner applied

under Section 11(6) of the said Act and obtained an ex parte order,

which was subsequently recalled and the owner was permitted to carry

a counter-claim to the continuing arbitral reference. It was in such

circumstances that the counter-claim came to be filed late in 2018.

4. Thus, for the purpose of assessing whether the additional

counter-claim which was carried by the owner to the reference in 2018

was barred by limitation, it is necessary to see whether there was a

live claim possible as on the date of the receipt of request for the

reference in or about March, 2018 since such is the date which is

relevant under Section 21 of the Act and the clock of limitation stops

upon the request being received. It is evident from the correspondence

exchanged between the parties that at least in respect of one head of

____________

https://www.mhc.tn.gov.in/judis/ OSA Nos.102, 2 and 3 of 2021

claim, pertaining to defects being rectified, there were

acknowledgments in writing on behalf of the contractor executed on or

about June 13, 2015. Since the request for the reminder of the

disputes to be carried to arbitration was received by the contractor

within three years of such date of June 13, 2015, it is evident that no

part of the counter-claim carried by the owner to the reference was

barred by limitation.

5. As to the merits of the matter, it is evident that the

contractor, as the claimant in the reference, made a total claim of

Rs.2,39,97,236/- comprising a claim in excess of Rs.95 lakh on

account of retention money; another Rs.7.40 lakh on account of non-

conformity report; a third head of Rs.1.40 lakh on account of penalty;

a further amount in excess of Rs.55 lakh for cement coefficient and an

ex-gratia amount in excess of Rs.45 lakh apart from the two amounts

on account of final bills for sums in excess of Rs.25 lakh and Rs.7.65

lakh. The counter-claim was in respect of two heads: penalty at the

rate of 2.5 per cent of the value of the work for the period of delay

amounting to Rs.79,20,738/-; and, defective work which required to

be attended to by a third party for rectification for a sum of

____________

https://www.mhc.tn.gov.in/judis/ OSA Nos.102, 2 and 3 of 2021

Rs.63,72,000/-.

6. The Arbitrator awarded a net amount of Rs.1,18,56,028/- in

favour of the contractor after allowing both heads for which counter-

claim had been filed by the owner, albeit a reduced amount on account

of penalty for the delayed completion of the work. The award also

provided for interest at 12 per cent per annum on the principal sum

awarded with pendente lite interest and interest at the same rate on

the total amount with effect from April 1, 2019.

7. Both parties were aggrieved by the award. The contractor was

dissatisfied that the counter-claim had been allowed. The principal

complaints of the employer were in respect of the amounts awarded

under the heads of non-conformity, ex-gratia and cement coefficient.

By the common judgment and order dated May 8, 2020, the

arbitration court set aside the award of the sum claimed by the owner

on account of defect rectification on the ground that there was no

proof of the amount and no evidence on the basis of which the sum

was claimed or awarded.

____________

https://www.mhc.tn.gov.in/judis/ OSA Nos.102, 2 and 3 of 2021

8. In course of the hearing at this appellate stage, the owner

refers to the arbitral award and the recognition therein that the claim

on account of defective work had been admitted by the contractor

through an employee by the name of Jaganathan. It is evident from

the award that though the contractor had claimed that the documents

in support of the claim on account of defective work were forged and

fabricated, such documents carried the signature of Jaganathan.

Despite Jaganathan being the contractor's employee, he was not called

upon to disown his apparent signature or discredit the three

documents. Thus, there was sufficient basis indicated in such regard to

award the amount on account of defect rectification. The court of the

first instance was clearly mistaken in perceiving Jaganathan to be the

owner's employee.

9. As for the sums awarded in favour of the contractor, the

owner limits the challenge to the three heads of the non-conformity

report, the ex-gratia amount and the cement coefficient.

10. In the award, the Arbitrator alludes to a document marked

as Ex.C9 in the reference to indicate that the ex-gratia amount had

____________

https://www.mhc.tn.gov.in/judis/ OSA Nos.102, 2 and 3 of 2021

been agreed to be paid. The documents pertaining to the claim on

account of ex-gratia reveal a promise made by the owner to the

contractor to release the additional amount and, to such extent, the

claim can be seen to have been admitted. However, the owner

suggests that the amount was payable subject to the project being

completed within time and since the Arbitrator ultimately held that

there was a delay in the completion of the project for which the

Arbitrator awarded a sum in excess of Rs.53 lakh in favour of the

owner and such part of the award has not been interfered with by the

arbitration court, there was no question of the contractor being

entitled to the ex-gratia payment. However, it is apparent that the

overall rate was enhanced and that was referred to as “ex-gratia” in

the relevant correspondence between the parties.

11. As for the non-conformity report, the Arbitrator indicated

some reasons in support of the rather meagre amount of Rs.7.40 lakh.

12. As to the payment claimed on account of cement coefficient,

there is a document exhibited and described as Ex.C24 in the award

which, according to the Arbitrator, amounted to an admission of the

____________

https://www.mhc.tn.gov.in/judis/ OSA Nos.102, 2 and 3 of 2021

relevant head of claim. At the highest, the document can be seen to

be an admission that a claim could be made by the contractor against

the owner on account of cement coefficient, but the relevant document

does not indicate any figure for the Arbitrator to arrive at the

conclusion that the contractor was entitled to a sum of Rs.55,29,397/-

on such account.

13. It is elementary that in respect of claims in engineering

contracts or works contracts, the head of claim has first to be justified

before the quantum is assessed and a figure arrived at. Merely

because the head of claim is admitted, it would not justify the making

of the award without ascertaining the quantum that the claimant is

entitled to in respect of such head of claim. Though such aspect of the

matter did not fall for scrutiny before the arbitration court, it is evident

that the Arbitrator erred in treating the admission in principle to an

admission on quantum and making the award for a sum in excess of

Rs.55 lakh without any shred of evidence in such regard or any reason

indicated in support thereof.

14. The arbitration court, of course, committed an error in

____________

https://www.mhc.tn.gov.in/judis/ OSA Nos.102, 2 and 3 of 2021

regarding Jaganathan to be an employee of the owner rather than of

the contractor. Upon perceiving Jaganathan to be an employee of the

owner, the arbitration court concluded that the claim on account of the

defect rectification had not been proved. However, the owner has

referred to the relevant documents, marked as Ex.B2, Ex.B7 and

Ex.B10 in the reference and all three documents carry the signature

alleged to be of Jaganathan on behalf of the vendor as indicated in the

documents. It is the admitted position that Jaganathan was an

employee of the contractor at the relevant point of time.

15. In view of the above, the interference by the arbitration

court with the amount awarded by the Arbitrator on account of defect

rectification in favour of the owner cannot be sustained. At the same

time, the award, to the extent of Rs.55,29,397/- in principal on

account of cement coefficient can also not be accepted as there does

not appear to have been any evidence in support thereof nor any

reason indicated in support of the quantum in the award itself.

16. As regards the claim on account of cement coefficient, the

court enquired of the parties that if the dispute in respect of the head

____________

https://www.mhc.tn.gov.in/judis/ OSA Nos.102, 2 and 3 of 2021

of claim pertaining to cement coefficient could be resolved, whereupon

counsel appearing for the parties have accepted the court's suggestion

that a principal sum of Rs.25 lakh be paid and received on such

account without the matter being carried any further and given a

closure at this stage. Counsel have agreed to such suggestion upon

instructions for which time was afforded by the court in course of

hearing.

17. Accordingly, the judgment and order dated May 8, 2020 is

set aside insofar as it interdicted the award on the head of defect

rectification in favour of the owner to the extent of Rs.63,72,000/-.

Further, the award is modified by reducing the amount awarded on

account of cement coefficient from Rs.55,29,397/- to Rs.25,00,000/-,

by consent of the parties.

18. Since sufficient reasons have been indicated in the award in

respect of the other heads of claim and the quantum of interest has

been awarded at a reasonable rate of 12 per cent per annum, the

award does not call for any further interference.

____________

https://www.mhc.tn.gov.in/judis/ OSA Nos.102, 2 and 3 of 2021

OSA Nos.102, 2 and 3 of 2021 are disposed of. CMP Nos.4837,

81 and 75 of 2021 are closed. In view of the fair stand taken by the

parties at this stage, no costs are awarded.

                                                                (S.B., CJ.)      (P.D.A., J.)
                                                                          23.09.2021

                     Index : yes

                     sra/kst

                     To:

                     The Sub Assistant Registrar
                     Original Side
                     High Court, Madras.




                     ____________



https://www.mhc.tn.gov.in/judis/
                                           OSA Nos.102, 2 and 3 of 2021



                                       THE HON'BLE CHIEF JUSTICE
                                                    AND
                                            P.D.AUDIKESAVALU, J.

                                                                 (sra)




                                     O.S.A.Nos.102, 2 and 3 of 2021




                                                          23.09.2021




                     ____________



https://www.mhc.tn.gov.in/judis/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter