Saturday, 09, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.Enexio Power Cooling ... vs Gita Power And Infrastructure ...
2021 Latest Caselaw 17854 Mad

Citation : 2021 Latest Caselaw 17854 Mad
Judgement Date : 1 September, 2021

Madras High Court
M/S.Enexio Power Cooling ... vs Gita Power And Infrastructure ... on 1 September, 2021
                                                              O.S.A.(CAD)Nos.174 and 175 of 2021

                                 IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                               DATED:    01.09.2021

                                                     CORAM :

                                THE HON'BLE MR.SANJIB BANERJEE, CHIEF JUSTICE
                                                        AND
                                     THE HON'BLE MR.JUSTICE P.D.AUDIKESAVALU

                                        O.S.A.(CAD) Nos.174 and 175 of 2021


                      M/S.ENEXIO Power Cooling Solutions
                       India Pvt. Ltd., No.443, Anna Salai,
                      Teynampet, Chennai 600 018,
                      Rep. by President and CEO T.Parasuram.                 ...   Appellant
                                                                             in both OSAs.

                                                        Vs

                      1. Gita Power and Infrastructure Pvt. Ltd
                         Rep. by its Authorised Signatory,
                         Kaushik Ganguly,
                         No.6, Sardar Patel Road, Guindy,
                         Chennai 600 032.                             ...    1st respondent

in OSA.174/2021 and 2nd respondent in OSA.175/2021

2. OPG Power Generation Private Limited, Rep. by its Authorised Signatory, P.Venkatasubramanian, No.6, Sardar Patel Road, Guindy, Chennai 600 032. ... 2nd respondent in OSA 174/2021 and st 1 respondent in OSA.175/2021

____________

http://www.judis.nic.in O.S.A.(CAD)Nos.174 and 175 of 2021

Appeals filed against the common Judgment and Decree dated 23.12.2020 passed in O.P.No.562 of 2020 and O.P.No.533 of 2020 on the file of original side of this court.

                            For the Appellant         :      Mr.R.Parthasarathy
                            in both the appeals              for Mr.P.Giridharan, and
                                                             Mr.H.Siddarth

                            For the 1st Respondent           :     Mr.AR.L.Sundaresan,
                            in both the appeals              Senior Advocate
                                                             for M/s.Krishna Prasad

                            For the 2nd Respondent :         No appearance
                            in both the appeals

                                                COMMON JUDGMENT
                                       (Delivered by the Hon'ble Chief Justice)



The flourishing export of litigation by this country may continue

unabated till the penchant for wanton tinkering with arbitral awards is

reined in. Despite instructive pronouncements in recent years

beginning the Associate Builders case [(2015) 3 SCC 49], the narrow

ambit of authority available in this jurisdiction, sometimes, appears

to be beyond the comprehension of courts in receipt of challenges to

arbitral awards.

2. In the present case, an award rendered by the arbitral

tribunal constituted by the International Chamber of Commerce (ICC)

____________

http://www.judis.nic.in O.S.A.(CAD)Nos.174 and 175 of 2021

has been rendered to naught on the perception of the arbitration

court that the period of limitation applicable to the claim and the

counter-claim may not have been appropriately reckoned and that

the arbitral tribunal failed to take into account evidence that was

before it and ignored the same. In effect, the arbitral award of July

13, 2020 has been set aside on the ground that it was opposed to

public policy as being contrary to the law of the land. The arbitration

court has also proceeded to render independent findings on certain

aspects despite the award dealing with such matters in great detail.

3. It may do well to recount the rules of assessment in this

jurisdiction at the outset. The court exercising authority under

Section 34 of the Arbitration and Conciliation Act, 1996 does not

assume appellate authority. Indeed, it has been the refrain in this

jurisdiction over a century and more of jurisprudence that has

developed that the court is loathe to correct any error since the

parties had abandoned the sovereign forum of the court and had

agreed to carry their disputes to a consensual forum. There is no

doubt that the court exercises a degree of superintendence; but,

ordinarily, errors of jurisdiction are corrected, rather than errors

within jurisdiction. It is also accepted, as in the case of exercise of

____________

http://www.judis.nic.in O.S.A.(CAD)Nos.174 and 175 of 2021

discretion, that if two views are possible on an issue or an aspect,

that the other view appears more plausible to the court may not

empower the court to supplant its view over the arbitral tribunal's

while assessing the propriety of an award.

4. The contract here provided for the setting up of a cooling

tower in Gummudipoondi. The claim of the appellant contractor was

on account of the work and supplies for which it remained unpaid.

The counter-claim by the respondent employer was on account of

liquidated damages for the delay in the erection and commissioning

of the plant, the customs duty component which it ought to have

been reimbursed and sundry other claims on account of damaged

gear box or faulty ducts or the like.

5. The contentions put forth on behalf of the respondent while

challenging the award have been recorded at paragraph 16 of the

judgment and order impugned dated December 23, 2020. Five

principal grounds appear to have been canvassed. The respondent

claimed that the principal claim of the contractor was barred by

limitation; that the tribunal adopted varying yardsticks for examining

the claim and the counter-claim; that the tribunal ignored vital

____________

http://www.judis.nic.in O.S.A.(CAD)Nos.174 and 175 of 2021

evidence particularly as apparent from the minutes of a meeting held

between the parties on April 19, 2018; that the arbitral tribunal

virtually extended the time qua liquidated damages and rejected the

claim on such account by finding that the contractor was entitled to

more time to complete the work than what the contract indicated;

and, that material evidence pertaining to the debit note qua customs

duty was ignored.

6. Certain facts are not in dispute and the relevant dates in

such regard must be taken from the submission made on behalf of

the respondent herein. According to the respondent, the last bill that

was raised by the appellant in connection with the work was on

December 31, 2014. The two debit notes that the respondent raised

on the contractor were issued on August 24, 2015 and January 12,

2016. The respondent complains that the arbitral tribunal erred in

holding that the deemed date of completion of the work was

September 21, 2015 despite the contract providing otherwise. The

respondent lays great stress on a meeting of the parties held on April

19, 2018, the minutes whereof would receive greater attention here

than may have been given thereto in the arbitral award. An offer for

settling the accounts between the parties, not only in respect of the

____________

http://www.judis.nic.in O.S.A.(CAD)Nos.174 and 175 of 2021

Gummidipoondi work but also in respect of a similar contract between

the parties in Gujarat was made by the respondent via an email of

May 26, 2018. Finally, the respondent refers to the claim being

lodged before the ICC secretariat on or about May 2, 2019.

7. In addition to the grounds urged to challenge the award as

noticed in the judgment impugned, the respondent also contends that

the arbitral tribunal erred in rejecting the entirety of the counter-

claim on limitation without considering the merits thereof. The

respondent suggests that the starting point for limitation should have

been the same for both parties. Finally, the respondent seeks to rely

on a recent Supreme Court judgment placed by the appellant to

suggest that if the time taken to conduct the negotiations had to be

excluded, such time would be excluded for both sides and not only for

the claimant.

8. The award dated July 13, 2020 refers extensively to the

scope of the work, the nature of the work, the rival claims, the

evidence and, finally, from paragraph 9 thereof, the findings of the

tribunal have been indicated over roughly 30 or so pages of the

appeal papers. The arbitral tribunal, comprising three members,

____________

http://www.judis.nic.in O.S.A.(CAD)Nos.174 and 175 of 2021

referred to “Delays and liquidated damages” at paragraph 13 of the

award. In course of the discussion on such aspect, the arbitral

tribunal alluded to the counter-claim on account of liquidated

damages exclusively at paragraph 13.15. Prior to that, in the general

discussion as to the rights of the parties and how the contract was

executed, the arbitral tribunal came to a finding that because of

delays that were beyond the control of the contractor, the time to

complete the work stood extended till September 21, 2015. Upon

rendering such finding, the arbitral tribunal recorded thus in respect

of the respondent's counter-claim of liquidated damages for delay:

"As the tribunal has granted an extension of time for completion of the ACC Unit to 21 September 2015 and has also found that the requirements for completion of the ACC Units were achieved on that date, the Tribunal finds that the Claimant has no liability for liquidated damages. ..."

9. The other major head of counter-claim that had been carried

by the respondent to the reference pertained to customs duty. In

such regard, the respondent relied on a letter dated January 24, 2014

issued by an employee or representative of the contractor to the

employer which clearly stated that the customs duty was payable by

the contractor, but made an appeal to the employer to immediately

____________

http://www.judis.nic.in O.S.A.(CAD)Nos.174 and 175 of 2021

pay the customs duty and adjust the amount out of the Gujarat

contract which was being simultaneously executed. There is no

dispute that the admission in the relevant letter is apparent.

However, the arbitral tribunal, upon noticing the letter and the

wording of the agreement between the parties that provided for

various kinds of taxes and duties to be to the account of the

employer, observed that in the light of the imminent arrival of the fin

tube bundles in Chennai, at the time that the letter of January 24,

2014 was issued, it was necessary to have the goods cleared to avoid

demurrage charges. The tribunal considered the apparent admission

contained in the relevant letter to have been made under pressure or

in the extreme situation where a dispute between the parties as to

the liability to pay customs duty would have left the goods rotting in

the docks and unnecessary demurrage charges adding up. In such

circumstances, the tribunal found that the debit note dated August

28, 2015 on account of liquidated damages was unjustified.

10. At paragraph 14.04 of the award, the arbitral tribunal

referred to the relevant clause in the agreement between the parties

to consider whether it was the employer’s liability to pay the customs

duty component despite “customs duty not being specifically included

____________

http://www.judis.nic.in O.S.A.(CAD)Nos.174 and 175 of 2021

in the relevant term”. The tribunal held that the customs duty

component in excess of Rs.5.94 crore “is not reimbursable by the

claimant”. In such circumstances, the tribunal held that the debit

note issued for customs duty on January 12, 2016 was without any

basis. Thus, it is evident that the two major heads of the counter-

claim carried by the employee to the arbitral reference were rejected

on merits.

11. Much is made out by the respondent here as to the issue of

limitation. It is necessary to see the two principal documents which

may be relevant in such regard. The first of such documents is the

recording of the discussion held between the parties at a meeting of

April 19, 2018. The relevant minutes incorporate a chart at the

beginning, which clearly spells out certain heads; including the total

amount billed by the contractor and the total amount paid to the

contractor, the balance amount due to the contractor that had been

retained, the two claims on account of liquidated damages for supply

and erection, the claim on account of customs duty, and the

employer’s claim on account of dismantling modification and duct

fabrication. There is no dispute that at the bottom of the chart, it was

recorded that an amount of Rs.2,78,04,090 was “Final Payable by

____________

http://www.judis.nic.in O.S.A.(CAD)Nos.174 and 175 of 2021

Enexio”. Enexio is the contractor.

12. However, what is of consequence is the remainder of

minutes:

“However, we request that the CD, CVD, and LD’s be looked at leniently and mutually settled. The Contract calls for all taxes such as ED, ST to be reimbursed and CVD is equivalent to Excise duty.

LD is not only due to our ENEXIO’s fault. In any case, this did not cause for any delay in Plant commissioning. We have had huge losses due to US dollar increase during Project stage to the tune of Rs.1.82 crores.

ENEXIO requested that the above amount of Rs.2,78,04,090/- payable by them to M/s.OPG Power Generation Pvt Ltd be adjusted against the amount to be received by M/s.ENEXIO Power Cooling Solutions (I) Pvt Ltd from M/s.OPGS Power Gujarat Pvt Ltd.”

13. Despite the chart at the top of the minutes of the meeting

April 19, 2018 recording the claims of both parties and with the final

line that a certain amount was payable by the contractor to the

employer, it is evident that the contractor insisted, though in

somewhat more polite language, that the customs duty was not

payable by it, nor was any liquidated damages payable since there

____________

http://www.judis.nic.in O.S.A.(CAD)Nos.174 and 175 of 2021

was no delay on its part. Much emphasis is placed by the respondent

on the final paragraph of the minutes which, according to the

respondent, amounts to a virtual admission of the debt due from the

contractor to the employer; but, on a reading of the entirety of the

document and the nature of the relationship between the parties, it

may not have been an unconditional admission that would have left

an open and shut game for the employer in the course of the arbitral

reference. Indeed, the respondent’s assertion that the last paragraph

of the minutes of April 19, 2018 was an admission, is belied by the

immediate subsequent correspondence exchanged between the

parties. On May 25, 2018, an email was issued by the contractor to

the employer, maintaining that a sum in excess of Rs.23 crore

remained due and owing to it for over two years from the employer.

The contractor wanted an immediate release of Rs.3 crore to enable

the contractor to meet its salary commitments. In response to such

email, the employer replied on the same date. The following line from

the employer’s mail of May 26, 2018 stands out:

“Perusing (sic, pursuant to) our discussion, it was my request to close the accounts with Rs.300 Lacs as full and final settlement”.

14. For a start, the admitted mail of May 26, 2018 issued by the

____________

http://www.judis.nic.in O.S.A.(CAD)Nos.174 and 175 of 2021

employer, at the very least, amounts to an unabashed

acknowledgment of the jural relationship between the parties and the

employer being the net debtor to the contractor. Though the

respondent insists that the relevant email combines both the

Gummudipoondi and the Gujarat accounts, the fact that even if the

two accounts were combined for the employer to acknowledge in

writing the jural relationship that it was an overall debtor qua the

contractor, the ingredients in Section 18 of the Limitation Act, 1963

were fulfilled for a fresh period of limitation to run from such date.

15. The arbitral tribunal noticed the minutes of such meeting of

April 19, 2018 at paragraph 16.03(d) of the award while discussing

the issue of limitation and held that the subsequent correspondence

of May 26, 2018 extended the period of limitation qua the claimant in

the reference.

16. Thankfully, the respondent has not propounded as an

absolute proposition that the period of limitation has to be the same

for both parties. It is possible that the period of limitation may be

extended by reason of an act of the other side while the period of

limitation for the original party may not have been extended.

____________

http://www.judis.nic.in O.S.A.(CAD)Nos.174 and 175 of 2021

However, the point that the respondent seeks to make is that if there

were negotiations between the parties and if the document of April

19, 2018 acknowledged a debt due from the contractor to the

employer, the arbitral tribunal’s finding that the entirety of the

counter-claim was barred by limitation may have been out of place.

To some extent, the respondent may be justified, though the

correspondence exchanged on May 26, 2018 can, by no means, be

the starting point of limitation as far as the employer was concerned

albeit such correspondence giving the contractor such benefit.

17. The arbitral tribunal dealt with the several heads of the

counter-claim exclusively at paragraph 16 of the award, apart from

having dealt with the same on merits earlier and on the ground of

limitation at paragraph 16 thereof. At paragraph 17, the discussion is

rather terse in view of the earlier findings and discussion on the

several heads of the counter-claim. Paragraph 17.02 indicates the

five heads of the counter-claim pertaining to liquidated damages for

delay, customs duty, cost of erection of horizontal and vertical

exhaust duct, cost of repair of gear box and cost of repair of fan

modules. Though the reasons given in paragraphs 13, 14 and 15,

respectively, in respect of the first three heads are indicated in

____________

http://www.judis.nic.in O.S.A.(CAD)Nos.174 and 175 of 2021

parenthesis at paragraph 17 of the award, two other heads appear,

clearly to have been rejected only on the ground of limitation and not

otherwise.

18. It is at this stage that the minutes of the meeting held on

April 19, 2018 require to be noticed in greater detail. For a start,

since the arbitral award refers to the relevant document, it cannot be

said, as the respondent asserts, that the minutes were ignored or the

contents thereof were not considered. When the arbitrators

specifically refer to the document and read it in the context of the

subsequent email exchanged between the parties on May 26, 2018, it

cannot be said with any degree of certainty that the contents of the

minutes may not have been noticed or the purports of the discussion

reflected therein may not have been considered while the award was

rendered.

19. Indeed, while rejecting the counter-claims also on the

ground of limitation, including the last two heads of counter-claim,

the arbitral tribunal is deemed to have specifically noticed what was

recorded below the chart in the minutes of the meeting held on April

19, 2018. After all, the last line in the chart indicated an amount due

____________

http://www.judis.nic.in O.S.A.(CAD)Nos.174 and 175 of 2021

from the contractor to the employer and even the final paragraph of

the minutes can be loosely be said to be a somewhat halting

admission of the contractor’s indebtedness to the employer. However,

a commercial document has to be read in context and it must not be

lost sight of the fact that the contractor could not have asserted its

claim in more aggressive terms since it was the employer from which

it had to extract the balance payment. It cannot be missed that even

though the chart indicated that the contractor owed money to the

employer, immediately below the chart, the contractor indicated that

it was not at all responsible for the delay. Thus, the contractor clearly

disputed its liability on account of liquidated damages on both heads.

The contractor also indicated that customs duty was payable by the

employer. Again, the second major head of claim of the employer was

dealt with. It is in such light that the subsequent admission in the

last paragraph of the minutes should be seen and the admission, at

the highest, was conditional and hedged with the contractor’s appeal

that it should not be found liable for the delay or on account of

customs duty.

20. In contrast and notwithstanding the respondent’s assertion

that both the Gummudipoondi and Gujarat contracts were dealt with

____________

http://www.judis.nic.in O.S.A.(CAD)Nos.174 and 175 of 2021

in the contractor’s email of May 26, 2018, the employer did not assert

its claims on any of the heads specifically and merely offered to close

the transaction by seeking to pay a further amount of Rs.3 crore in

full and final settlement. In a sense, it is evident that notwithstanding

the apparent admission in the minutes of April 19, 2018, the

contractor, at least, kept the contractor’s defense pertaining to

liquidated damages and customs duty open though the employer did

not specifically assert any of its claims. Thus, the negotiations that

were held between the parties may have been confined to the areas

of disagreement rather than the areas of acceptance which included

the claims on account of the duct repair, fan repair and the like. It is

thus the arbitral tribunal concluded that the email of May 26, 2018

would hold good for a fresh period of limitation to be counted

therefrom for the contractor, but it would not hold good in respect of

the specific heads of claim of the employer.

21. On the facts as they panned out before the arbitral tribunal,

it was a possible view. Once it is acknowledged that a possible view

on the set of facts had been taken by the arbitral tribunal, that the

other view appeals more to the court is of no relevance as the court

cannot substitute the tribunal's view by supplanting its own.

____________

http://www.judis.nic.in O.S.A.(CAD)Nos.174 and 175 of 2021

22. As to whether the enforcement of a claim is barred by the

prescription of limitation, it depends on the nature of the claim and

the period prescribed therefor in the Schedule to the Limitation Act,

1963. For the purpose of ascertaining which of the Articles in the

Schedule would be attracted to a particular claim, the surrounding

circumstances need to be noticed to find the appropriate provision. It

is possible for a claim to either fall under Article 18 of the Schedule

for the price of work or such a claim may also be seen to be under

residuary Article 113 of the Schedule. Again, upon ascertaining the

nature of the claim and assessing the appropriate Article which would

be applicable, it would lead, in some cases, for it to be determined as

to whether the period of limitation for enforcement of the claim would

be reckoned from when the right to sue accrues or when the right to

sue first accrues.

23. In paragraph 16 of the award, the arbitral tribunal

specifically referred to the Act of 1963 and considered the

applicability “of a time bar” to each of the heads of claim and to the

counter-claim. In respect of the counter-claim, the tribunal noted

that there was no evidence that the heads of counter-claim “were

____________

http://www.judis.nic.in O.S.A.(CAD)Nos.174 and 175 of 2021

included in the ongoing negotiations.” The tribunal reckoned that the

contractor “is deemed to have completed its obligations” on

September 21, 2015 “and thus, that is the latest date from which the

limitation period of three years must run” in respect of the counter-

claim. On such reasoning, the arbitral tribunal held that the counter-

claim delivered by the employer on July 15, 2019 was barred by

limitation.

24. What is apparent from the award is that the arbitral tribunal

was aware of the applicable law and made an assessment in

accordance therewith. In such circumstances, that there could be a

different view taken on the set of facts may not be an appropriate

ground under Section 34 of the Act of 1996 to obliterate the finding

on such count rendered by the arbitral tribunal and substitute it by

the other view which appeals more to the court. After all, the

assessment in the jurisdiction under Section 34 of the Act of 1996

has more to do with the decision-making process, rather than the

decision itself, unless the decision appears to be palpably erroneous

or manifestly arbitrary and causes grave miscarriage of justice.

25. A challenge to an arbitral award requires high tests to be

____________

http://www.judis.nic.in O.S.A.(CAD)Nos.174 and 175 of 2021

met by the challenger. An apparently erroneous view may not

necessarily be corrected, nor will a flawed finding or a perceived

mistaken interpretation excite the court unless there is something

more to the matter. The high tests were not met by the respondent

herein and it appears that the arbitration court embarked on an

independent exercise to assess the several of the heads of claim and

counter-claim, including on the aspect of limitation, without reference

to the award or attempting to ascertain whether the arbitral tribunal

had applied its mind to the matters in issue.

26. Since both the parties have referred to a judgment reported

at (2020) 14 SCC 643 (Geo Miller and Company Pvt. Ltd vs.

Chairman, Rajasthan Vidyut Utpadan Nigam Ltd) and paragraph 28

thereof, such judgment needs to be noticed. The discussion

pertaining to the judgment must begin with a caveat that it was in

the context of a request under Section 11 of the Act of 1996 and, as

they say, a judgment must be seen to have decided exactly what it

did and not the larger conspectus which it may deemed to have.

Paragraph 28 of the report in Geo Miller instructs as follows:

“28. Having perused through the relevant precedents, we agree that on a certain set of facts and circumstances, the period during which the parties were

____________

http://www.judis.nic.in O.S.A.(CAD)Nos.174 and 175 of 2021

bona fide negotiating towards an amicable settlement may be excluded for the purpose of computing the period of limitation for reference to arbitration under the 1996 Act. However, in such cases the entire negotiation history between the parties must be specifically pleaded and placed on the record. The Court upon careful consideration of such history must find out what was the ‘breaking point’ at which any reasonable party would have abandoned efforts at arriving at a settlement and contemplated referral of the dispute for arbitration. This "breaking point" would then be treated as the date on which the cause of action arises, for the purpose of limitation. The threshold for determining when such a point arises will be lower in the case of commercial disputes, where the party’s primary interest is in securing the payment due to them, than in family disputes where it may be said that the parties have a greater stake in settling the dispute amicably, and therefore delaying formal adjudication of the claim.”

27. On any liberal reading of the dictum as evident from the

above passage, it cannot be said that a special period of limitation

has been carved out by the Supreme Court in addition to the

provisions of the Act of 1963. The passage instructs that when parties

are in the process of negotiation and an issue as to limitation comes

up and the party seeking to explain away the time seriously pleads

____________

http://www.judis.nic.in O.S.A.(CAD)Nos.174 and 175 of 2021

the time taken for negotiations and brings cogent evidence in such

regard, the block of time may have to be excluded. The entire

discussion in the above passage has to be seen in the light of Section

18 of the Act of 1963 and how the acknowledgement of a jural

relationship between the parties gives a fresh lease of time under the

Limitation Act to the claimant. If “A” and “B” are found to have been

in negotiation and there is some written evidence of the negotiation,

where “A” asserts as a creditor, the very fact that there is evidence of

the negotiation is a virtual acknowledgment of jural relationship

between the parties. The judgment cannot be read to have provided

any more than what is already permissible in law.

28. The judgment and order impugned cover territories which a

court in exercise of its limited authority under Section 34 of the Act

should restrain itself from venturing into. The judgment reveals a

completely different basis for reckoning what the period of limitation

ought to have been without expressly referring to the findings in the

arbitral award or the discussion relevant in such regard. Indeed, the

impugned judgment embarks on an independent exercise to assess

the claim or the validity thereof, which is scarcely possible within the

restricted ambit of authority available under the relevant statutory

____________

http://www.judis.nic.in O.S.A.(CAD)Nos.174 and 175 of 2021

provision.

29. For the reasons aforesaid, O.S.A.Nos.174 and 175 of 2021

are allowed and the judgment and order impugned dated December

23, 2020 are set aside. The arbitral award of July 13, 2020 is

restored.

30. Since it was possible for the employer in this case to urge

some of the grounds, including limitation, there will be no order as to

costs as far as the present appeals are concerned.

C.M.P.No.7963 of 2021 is closed.

                                                                 (S.B., CJ.)       (P.D.A., J.)
                                                                            01.09.2021

                      Index : yes
                      tar/sasi

                      To:

                      The Sub Assistant Registrar
                      Original Side
                      High Court
                      Madras.




                      ____________

http://www.judis.nic.in
                                           O.S.A.(CAD)Nos.174 and 175 of 2021

                                             THE HON'BLE CHIEF JUSTICE
                                                          AND
                                                  P.D.AUDIKESAVALU, J.

                                                                       (sasi)




                                      O.S.A.(CAD)Nos.174 and 175 of 2021




                                                                01.09.2021




                      ____________

http://www.judis.nic.in

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter