Sunday, 10, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

P.Stanley Paulraj vs The State Of Tamilnadu Rep. By Its
2021 Latest Caselaw 22971 Mad

Citation : 2021 Latest Caselaw 22971 Mad
Judgement Date : 24 November, 2021

Madras High Court
P.Stanley Paulraj vs The State Of Tamilnadu Rep. By Its on 24 November, 2021
                                                                         W.P.No.34089, 34090 of 2012

                                  IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                  Dated 24.11.2021

                                                      CORAM:

                             THE HONOURABLE MR.JUSTICE D.KRISHNAKUMAR

                                          W.P.No.34089, 34090 of 2012 and
                                             M.P.No.1 &2 of 2012 and
                                                 M.P.No.1 of 2013

                       P.Stanley Paulraj,
                       Assistant Director (PWD),
                       Hydrology Sub-Division (IHH),
                       Poondi 602 023, Thiruvallur District.             ... Petitioner in both
                                                                                writ petitions

                                                       Vs.

                       1. The State of Tamilnadu rep. by its
                          Secretary to Government,
                          Public Works Department,
                          Secretariat, Chennai 600 009.

                       2. The Engineer-in Chief (Buildings)
                          and Chief Engineer (Buildings),
                          Chennai Region and Chief Engineer (General),
                          Public Works Department, Chepauk,
                          Chennai 600 005.                             ... Respondents in

both writ petitions

Prayer in W.P.No.34089 of 2012: Writ petition filed under Section 226 of the Constitution of India seeking to issue a Writ of Certiorarified Mandmus , to call for the records connected with the charge memo

https://www.mhc.tn.gov.in/judis W.P.No.34089, 34090 of 2012

No.C11(2)/1161/2012-2 dated 24.08.2012 of the second respondent and quash the same and direct the respondents to consider the name of the petitioner for promotion to the post of Executive Engineer on par with junior and consequently promote the petitioner as Superintending Engineer with all benefits and pass orders.

Prayer in W.P.No.34090 of 2012: Writ petition filed under Section 226 of the Constitution of India seeking to issue a Writ of Certiorarified Mandmus , to call for the records connected with the charge memo No.C11(2)/1161/2012-1 dated 24.08.2012 of the second respondent and quash the same and direct the respondents to consider the name of the petitioner for promotion to the post of Executive Engineer on par with junior and consequently promote the petitioner as Superintending Engineer with all benefits and pass orders.


                                                    In both writ petitions


                                  For petitioner          : Mr.G.Elanchezhiyan
                                  For respondents         : Mr.T.Arunkumar, Addl.Govt. Pleader
                                                            for R1 to R2


                                                    COMMON ORDER


Both the writ petitions have been filed to quash the two charge

memos dated 24.08.2012 issued by the second respondent and direct

https://www.mhc.tn.gov.in/judis W.P.No.34089, 34090 of 2012

the respondents to consider the name of the petitioner for promotion to

the post of Executive Engineer on par with the Juniors and

consequently promote the petitioner as Superintending Engineer with

all benefits and pass orders.

2. Since the parties in both the writ petitions are one and the

same; and the reliefs sought for are connected to each other, this court

is inclined to pass common order.

3. The case of the petitioner in brief:

The writ petitioner was initially appointed as Assistant Engineer

on 30.10.1979 and thereafter, he was relieved from service on

15.05.1987. Subsequently, he was given re-posting in the year 1991

and he was promoted as Assistant Director (AEE), Hydrology Sub

Division, Poondi. The writ petitioner made a request before the

respondents to consider for further promotion to the post of Executive

Engineer and Superintending Engineer. Since it was not considered, he

filed a writ petition in W.P.No.10828 of 2012 seeking direction to the

respondents to consider the claims of the petitioner for promotion as

https://www.mhc.tn.gov.in/judis W.P.No.34089, 34090 of 2012

Executive Engineer, on par with his Juniors with effect from the year

2006 and with consequential promotion as Superintending Engineer on

par his Juniors with all benefits. This court by order dated 13.06.2012,

directed the respondents to consider the petitioner's representation.

3.1. But, in order to deny the right of the petitioner, the

respondents issued two charge memos i.e. one is under Rule 17(a) and

another is under Rule 17(b) of Tamil Nadu Civil Service (Disciplinary

and Appeal) Rules 1955, both dated 24.08.2012, with regard to the

shortage of Cement bags and Steel.

3.2. The contention of the petitioner is that after receiving the

charge memos, he submitted an application on 24.09.2012 to extend

the time to submit his explanation and also to furnish all the relevant

documents. Thereafter, he submitted his explanation to the two charge

memos on 04.10.2012 to the respondent. However, there is no

progress on the disciplinary proceedings.

3.3. The primordial contentions of the petitioner is that the above

said occurrence happened during the period from 07.07.1994 to

25.04.1997, but the charges have been framed against the petitioner

only on 24.08.2012, which is time barred. On that score, the above

https://www.mhc.tn.gov.in/judis W.P.No.34089, 34090 of 2012

charge memos are liable to be quashed.

4. The contentions raised in the counter affidavit in brief:

The petitioner was working as Assistant Engineer, Public works

Department, Nagercoil from 7.7.1994 to 25.04.1997 and he was

transferred to Coastal Process Section, Kanyakumari on 25.04.1997.

The writ petitioner had filed O.A.No.5215 of 1997 before the Tamil

Nadu Administrative Tribunal against the order of recovery dated

12.04.1997 with regard to the shortage of cement. Consequent on the

abolition of the above Tribunal, the case was transferred to the file of

High Court in W.P.No.31454 of 2006 and this court vide order dated

23.03.2009, had dismissed the writ petition. Against which, the

petitioner had filed an Appeal in W.A.No.582/2009 before the Division

Bench, and vide order dated 15.07.2010, this court allowed the appeal

and set aside the order of recovery. However, in the order of appeal, it

was observed that, it would be open to the respondent to proceed

against the petitioner, as per rules in accordance with law, if so advised.

https://www.mhc.tn.gov.in/judis W.P.No.34089, 34090 of 2012

4.1. Based on the above order, the order of recovery was

cancelled. Thereafter, the petitioner was directed to appear before the

Executive Engineer on 24.09.2010, with relevant documents to

reconcile the difference in account of materials. After reconciling, the

quantity of 74 bags of cement worth Rs.10,630/- was found to be short.

As far as Steel was concerned, he did not reconcile the materials in

account at all. As such, shortage of steel was worth to Rs.74,382/-.

Hence charges framed under Section 17(a) and 17(b) of Tamil Nadu

Civil Services (Discipline and Appeal) Rules with regard to the

shortage of Cement and Steel respectively.

4.2. The documents required by the petitioner were furnished to

him on 01.10.2012 to enable him to submit his explanation to the

charges. He submitted his representation dated 24.08.2012 to the

respondent. Therefore, the contention of the petitioner that without

furnishing the documents, the respondents are attempting to conduct

enquiry is not correct.

4.3. Earlier, the writ petitioner filed W.P.No.10828 of 2012 and

obtained direction to consider his claim for promotion as Executive

Engineer on par with his juniors from the year 2006. As the persistent

https://www.mhc.tn.gov.in/judis W.P.No.34089, 34090 of 2012

attitude of the petitioner in not heeding to the instructions to remit the

amount of Rs.74,382/- towards the value of shortage of steel continued

to prevail, there was no other option, but to proceed against him under

the Rule 17(b) of the Tamil Nadu Civil Services (Discipline and

Appeal) Rules. Consequently, his claim for promotion to the post of

Executive Engineer and Superintending Engineer could not be

entertained, until finalization of the disciplinary proceedings.

4.4. As regards the limitation period is concerned, it operates

only in the Tamil Nadu Pension Rules 1978. As far as the serving

personnel are concerned, they are liable to be proceeded till the date of

their retirement for the omissions and commissions committed by them

at any point of time, during their service. Therefore, there is nothing

wrong in pursuing action in the charge memo dated 24.08.2012 for the

occurrences that took place from 07.07.1994 to 25.04.1997. Hence, this

writ petition is liable to be dismissed.

5. The learned counsel appearing for the petitioner relied upon

the G.O.Ms.No.2201 dated 9.11.1982 issued by the Government of

Tamil Nadu, wherein, direction has been given, by fixing time limit, for

https://www.mhc.tn.gov.in/judis W.P.No.34089, 34090 of 2012

pointing out the discrepancies, shortages noticed in transfer papers of

Pubic Works Department Section Officers. Therefore, inview of the

above Government Order, the impugned orders are time barred and the

same are liable to be quashed.

6. To support his contentions, he further relied upon the

decisions of this court reported in 2005(4) CTC 403 (Mahadevan P.V.

Vs. M.D.Tamilnadu Housing Board); 2006 SCC (L & S) 919

(M.R.Bijilani Vs. Union of India); 2006(2) CTC 635 (M.Elangovan

Vs. Trichy District Central Co-operative Bank Ltd. rep. by its

General Manager, Trichy) and submitted that if there is an inordinate

delay in issuing the charges and conclude the proceedings on the part

of the respondent, then the impugned charges are liable to be quashed.

Hence, he prayed to dismiss the impugned charges and direct the

respondents to consider the name of the petitioner for further

promotion as Executive Engineer and Superintending Engineer.

7. Per contra, it is contended by the learned counsel appearing

for the respondents that with regard to the shortages of Steel, the

https://www.mhc.tn.gov.in/judis W.P.No.34089, 34090 of 2012

petitioner has not heeded to the instructions to remit the amount of

Rs.74,382/-. Hence, action was proceeded against him by framing

charges under 17(b) of Tamil Nadu Civil Services (Discipline and

Appeal) Rules and inview of the same, his name was not included in

the panel for promotion. He further contended that, the period of

limitation operates only in the Tamil Nadu Pension Rules 1978 and as

far as the serving personnel are concerned, they are liable to be

proceeded till the date of their retirement for the omissions and

commissions committed by them at any point of time during their

service. Hence, the writ petitions are liable to be dismissed.

8. Heard the rival submissions made by the learned counsels to

both side and I have perused the materials on record.

9. The respondents have framed the following charges by issuing

two charge memos dated 24.08.2012 as against the petitioner.

I. Charge framed under Rule 17(a) of Tamil Nadu Civil SErvices (Discipline and Appeal) Rules:

He (P.Stanley Paulraj, Assistant Executive Engineer, PWD) had failed to maintain the stores properly under his direct

https://www.mhc.tn.gov.in/judis W.P.No.34089, 34090 of 2012

control and also failed to properly maintain the accounts of stores with an intention of malpractices in the accounting of cement without any relevance to the Bin Card entires and Day Book entries which resulted in loss to the Government to a tune of Rs.10,630/- (and 10% storage charges and 5% storage charges thereon) being the cost of 74 bages of cement and thus violated the Para 304 of Tamil Nadu Public Works “D” Code and Article 273 of Tamil Nadu Financial Code Vol.I.

II. Charges framed under Rule 17(b) of Tamil Nadu Civil Services (Discipline & Appeal) Rules.

Charge No.1 That Thiru P.Stanley Paulraj, Assistant Executive Engineer, PWD in his former capacity as the Assistant Engineer, PWD Buildings Construction Sub Division, Nagercoil on his relief on transfer, had failed t hand over his section charges to his successor in a complete shape in gross violation of para 304 of Tamil Nadu Public Works "D" code and para 340 of Tamil nadu Public Works "A" code.

Charge No.2 That Thiru P.Stanley Paulraj, in his former capacity as the Assistant Enginer of Section I, Buildings Construction Sub Division, Nagercoil in gross violation of Article 273 of Tamil Nadu Financial Code Vol.I, had failed to safeguard the Government materials i.e. 3750 kg. Steel worth Rs.74,382/- thus causing loss to the Government by not handing over the materials.

Charge No.3 That Thiru P.Stanley Paulraj, Assistant Executive Engineer, by committing the said irregularities had failed to

https://www.mhc.tn.gov.in/judis W.P.No.34089, 34090 of 2012

maintain absolute integrity and devotion to duty as warranted under Rule 20 of Tamil Nadu Government Servants Conduct Rule 1973.

10. The Primordial submission of the counsel for the petitioner is

that, the charge memos are time barred. It is not disputed by the

respondents that the impugned charge memos were issued with regard

to shortage of Cement bags and Steel for a period from 07.07.1994 to

25.04.1997 and the charge memos were issued on 24.08.2012. Further,

it is pertinent to extract the relevant portion of the decision rendered by

the Honourable Supreme Court in P.V.Mahadevan Vs. M.D.Tamil

Nadu Housing Board reported in 2005(4) CTC, which reads thus:

10. The very same ground has been specifically raised in this appeal before this court wherein, it is stated that the delay of more than 10 years in initiating the disciplinary proceedings by issuance of charge memo would render the departmental proceedings vitiated and that in the absence of any explanation for the inordinate delay in initiating such proceedings of issuance of charge memo would justify the prayer for quashing the proceedings as made in the writ petition.

10. ...

11. ...

12. ..

13. ...

https://www.mhc.tn.gov.in/judis W.P.No.34089, 34090 of 2012

14. Under the circumstances, weare of the opinion that allowing the respondent to proceed further with the departmental proceedings at this distance of time will be very prejudicial to the appellant. Keeping a higher Government official under charges of corruption and dispute integrity would cause unbearable mental agony and distress to the officer concerned. The protracted disciplinary enquiry against a government employee should, therefore, be avoided ot only in the interests of the government employee, but in public interest and also in the interest of inspiring confidence in the minds of the government employees. At this stage, it is necessary to draw the curtain and to put an end to the enquiry. The appellant had already suffered enough and more on account of the disciplinary proceedings. As a matter of fact, the mental agony and sufferings of the appellant due to the protracted disciplinary proceedings would be much more than the punishment. For the mistakes committed by the department in the procedure for initiating the disciplinary proceedings, the appellant should not be made to suffer.

15. We, therefore, have no hesitation to quash the charge memo issued against the appellant. The appeal is allowed. The appellant will be entitled to all the retiral benefits in accordance with law. The retrial benefits shall be disbursed within three months from this date. No costs.

11. Further, the Honourable Supreme Court, following the

Judgment in P.V. Mahadevan Vs. Managing Director, Tamil Nadu

Housing Board, reported in 2005(4) CTC, in its decision in Ranjeet

https://www.mhc.tn.gov.in/judis W.P.No.34089, 34090 of 2012

Singh Vs. State of Haryana and others reported in 2008(3) CTC 781,

has held thus.

9. We have extracted the charges against the appellant. These charges did not require any detailed investigation. Inview of the unexplained delay of nine years, the Trial Court was justified in holding that the entire enquiry was vitiated and in declaring that the order of punishment to be null and void. The Appellate Court did ot have any justifiable reason to interfere with the said finding. In the circumstances, we are of the view that the High Court ought to have interfered in the matter as the Appeal involved a substantial question of law, i.e. whether issue of charge sheet after nine years, when there are no special circumstance to explain the delay vitiated the enquiry. As the matter is old and as we have already found that the delay vitiated the enquiry, no purpose will be served by remitting the matter. We propose to dispose of the Appeal on merits.

10. We, therefore, allow this Appeal and set aside the judgment and decree of the High Cout and First Appellate Court and restore the judgment and decree of the Trial Court. Parties are to bear their respective costs.

12. That apart, this court in the decision in S.Rathinavelu Vs.

kChairman, Tamil Nadu Water Supply and Drainage Board,

Chennai and Another reported in 2009(3) MLJ 479, had held thus:

https://www.mhc.tn.gov.in/judis W.P.No.34089, 34090 of 2012

“ Though the learned counsel for the petitioner during the course of arguments has raised the point of delay in initiating the disciplinary proceedings, no satisfactory reasons have been placed by the Board for the inordinate delay of 10 years in initiating the disciplinary proceedings. In this context, it is worthwhile to extract few decisions of the Supreme Court as well as this court on the issue of delay in initiating of the disciplinary proceedings.”

13. It is not disputed by the respondents that, the Charge Memos

were issued on 24.08.2012, for shortage of materials for the period

from 07.07.1994 to 25.04.1997. Further, it is the contentions of the

petitioner that the respondents have not furnished the documents as

required by him, as contemplated under Rules. Therefore, non

furnishing of documents is a violation of principles of natural justice.

In the meantime the respondents have prepared a Panel for the post of

Superintending Engineer and this promotion was stalled by the

respondents, pending charges framed against the writ petitioner.

14. It is contended by the respondents that the Serving Personnel

are liable to be proceeded, till the date of their retirement, for the

https://www.mhc.tn.gov.in/judis W.P.No.34089, 34090 of 2012

omissions and commissions committed by them at any point of time

during their service. But the respondents have not given neither proper

reasons nor satisfied explanations for the inordinate delay in framing

the charges and initiating the disciplinary proceedings against the writ

petitioner. Therefore, the impugned order suffers legal infirmity and

the same is liable to be quashed.

15. Inview of the above discussions, the impugned charge

memos are quashed. Further, the writ petitioner has attained the age of

superannuation. Hence, he is entitled for notional promotion to the

post of Executive Engineer, on par with his junior.

16. Accordingly, it is ordered as follows:

(i) The impugned Charge Memos dated 24.08.2012 are quashed.

(ii) The respondents are directed to consider the claim of the

petitioner for notional promotion to the post of Executive Engineer on

par with his junior with all consequential benefits, if otherwise he is

eligible, in accordance with law, as early as possible, within a period

of 12 weeks from the date of receipt of a copy of this order.

https://www.mhc.tn.gov.in/judis W.P.No.34089, 34090 of 2012

17. With the above directions, both the writ petitions in

W.P.No.34089, 34090 of 2012 are allowed. Consequently, connected

miscellaneous petitions are closed. No costs.

24.11.2021

Index:Yes/No Internet:Yes/No mst To

1. The Secretary to Government, The State of Tamilnadu, Public Works Department, Secretariat, Chennai 600 009.

2. The Engineer-in Chief (Buildings) and Chief Engineer (Buildings), Chennai Region and Chief Engineer (General), Public Works Department, Chepauk, Chennai 600 005.

https://www.mhc.tn.gov.in/judis W.P.No.34089, 34090 of 2012

D. KRISHNAKUMAR, J.

mst

W.P.No.34089, 34090 of 2012 and M.P.No.1 &2 of 2012 and M.P.No.1 of 2013

24.11.2021.

https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter