Sunday, 10, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sugunammal vs The Principal Secretary To ...
2021 Latest Caselaw 22837 Mad

Citation : 2021 Latest Caselaw 22837 Mad
Judgement Date : 23 November, 2021

Madras High Court
Sugunammal vs The Principal Secretary To ... on 23 November, 2021
                                                                          W.P.No.14644 of 2012 etc. batch

                                  IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                  DATED : 23.11.2021

                                                         CORAM

                             THE HONOURABLE MR. JUSTICE G.K.ILANTHIRAIYAN

                                  W.P.Nos.14644, 14645, 15011 to 15016, 15032 to 15041
                                              and 15043 to 15045 of 2012
                                        M.P.Nos.1 & 2 (20 Nos) 4 & 4 of 2012 and
                                           W.M.P.Nos. 23002 to 23018 of 2016

                     W.P.No.14644 of 2012:

                     Sugunammal                                                   ... Petitioner

                                                           Vs


                     1.The Principal Secretary to Government,
                       Government of Tamilnadu,
                       Energy C-1, Department,
                       Fort St. George,
                       Chennai - 9.

                     2.The District Collector,
                       Vellore District,
                       Vellore.

                     3.The Revenue Divisional Officer,
                       Vellore.
                     4.The Tahsildar,
                       Katpadi,
                       Vellore District.


                     Page 1 of 26
https://www.mhc.tn.gov.in/judis
                                                                             W.P.No.14644 of 2012 etc. batch

                     5.Power Gird Corporation of India Ltd.,
                       Rep. by its Deputy General Manager,
                       A.Surendiran,
                       No.2 (Old No.160) I Lane
                       Bharathi Nagar, North Usman Road,
                       T.Nagar, Chennai - 600017.                                                  ...
                     Respondents

                        (R5 impleaded as per order dated 14.06.2012
                        in M.P.No.3 of 2012 in W.P.No.14644 of 2012)

                     Prayer: Writ Petition is filed under Article 226 of the Constitution of India
                     praying to issue a Writ of Certiorari, calling for the records relating to the
                     proceedings of the first respondent in G.O.Ms.No. 77, Energy (C-1)
                     Department dated 22.09.2011, No.11(2)/EGY/404(c)/2011, quash the same
                     in respect of the petitioner land measuring an extent of 0.19.0 hectares in
                     S.No.84/1A2 and a land an extent of 0.08.0 hectares in S.No.84/1B1,
                     Elayanallur Village, Katpadi Taluk, Vellore District.

                                  For Petitioner    : Mr.M.Devaraj
                                                      (in all WPs)

                                  For R1 to R4      : Mr.A.Selvendran
                                                      Special Government Pleader
                                                      (in all WPs)

                                  For R5            : Mr.T.Thyagarajan (Senior Counsel)
                                                      for V.Kalyanaraman
                                                      (in all WPs)




                     Page 2 of 26
https://www.mhc.tn.gov.in/judis
                                                                               W.P.No.14644 of 2012 etc. batch

                                                    COMMON ORDER

                                  The writ petition is filed to issue a Writ of Certiorari, calling for

                     the records relating to the proceedings of the first respondent in

                     G.O.Ms.No.77,         Energy     (C-1)      Department      dated       22.09.2011,

                     No.11(2)/EGY/404(c)/2011 and to quash the same in respect of the

                     petitioner's land measuring to an extent of 0.19.0 hectares in S.No.84/1A2

                     and a land measuring to an extent of 0.08.0 hectares in S.No.84/1B1,

                     Elayanallur Village, Katpadi Taluk, Vellore District.



                                  2. It is submitted that the Government of India by the

                     communication        dated     20.10.2009    accorded     prior      approval        for

                     supplementary transmission system associated with Vallur Termal Power

                     Station for establishment of Tiruvalam 765/400 KV Sub-Station to facilitate

                     import of power to Southern Region especially to Tamil Nadu. In pursuance

                     thereto, the Tamil Nadu Electricity Board identified lands measuring to an

                     extent of 150 acres at Elayanallur Village for establishment of 765/400 KV

                     Sub-Station by the fifth respondent and 400/230 KV by the Tamil Nadu

                     Electricity Board. In this regard, on 27.03.2010 the Tamil Nadu Electricity


                     Page 3 of 26
https://www.mhc.tn.gov.in/judis
                                                                             W.P.No.14644 of 2012 etc. batch

                     Board addressed a letter to the second respondent herein requesting to

                     acquire the land either by private negotiation or through acquisition.

                     Accordingly, the fifth respondent vide letter dated 19.05.2010 requested the

                     second respondent to initiate acquisition proceedings invoking Section 17 of

                     the Land Acquisition Act, 1894 (hereinafter referred to as 'the Act' for short).



                                  3. It is further submitted that on 28.08.2010, the fourth

                     respondent conducted a public meeting and taking into consideration the

                     urgency of the significant project in question, opted to initiate land

                     acquisition process individually without informing to the Tamil Nadu

                     Electricity Board. The Commissioner, Land Administration called upon the

                     second respondent to send proposals for draft notification under Section 4(1)

                     and draft declaration under Section 6 of the Act.



                                  4. It is further submitted that on 30.08.2011, the first respondent

                     accorded administrative sanction under Section 17(1) of the Act by issuing

                     G.O.Ms.No.70, Energy (C-1) Department for acquiring lands measuring to

                     an extent of 105.92 acres for establishment of 765/400 KV Power Grid



                     Page 4 of 26
https://www.mhc.tn.gov.in/judis
                                                                           W.P.No.14644 of 2012 etc. batch

                     Station. The first respondent had issued notification under Section 4(1) of

                     the Act intending to acquire the land belong to the petitioners and other land

                     invoking urgency provision of Section 17(1) of the Act and dispensing with

                     the 5-A enquiry under the said Act. The said notification was published in

                     Tamil Nadu Gazette Extraordinary in G.O.Ms.No.72, Energy (C-1)

                     Department, dated 07.09.2011. The declaration under Section 6 of the Act

                     was issued under G.O.(Ms). No.77 Energy (C-1) Department dated

                     22.09.2011. The declaration under Section 6 of the Act was followed by an

                     errata issued by the first respondent on 22.02.2012 altering the extent of

                     land and including the trees, well, pumpset etc., which has been left over in

                     the earlier notification.



                                  5. It is further submitted that the third respondent had issued

                     certain notices for determining the compensation. According to the

                     petitioners, no proper enquiry was conducted in determining the proper

                     value. However, the third respondent passed an award dated 29.03.2012

                     thereby determined the compensation. On receipt of the said proceedings of

                     the third respondent, the petitioners came to understand about the


                     Page 5 of 26
https://www.mhc.tn.gov.in/judis
                                                                           W.P.No.14644 of 2012 etc. batch

                     acquisition process.



                                  6. Learned counsel for the petitioners submitted that all the

                     petitioners challenged G.O. Ms. No.77, Energy (C-1) Department, dated

                     22.09.2011 and declaration under Section 6 of the Act on the ground that as

                     per Section 17 of the Act, the enquiry under Section 5-A of the Act can be

                     dispensed in the cases as provided under the said section and Section 17(2)

                     enumerates the cases in which the urgency provisions can be invoked and

                     the possession of the land taken immediately and as per sub-section (b)

                     immediate possession is necessary for library or any educational institution,

                     for construction of any building for common use of the inhabitants of such

                     village, or godown for any society or any dwelling house for the poor, or any

                     irrigation tank drainage channel or well, or any road. The present acquisition

                     is not for the above enumerated purpose. Therefore, the invocation of

                     Section 17(4) in the present case is without jurisdiction of the first

                     respondent. He further submitted that the first respondent failed to publish

                     the notice under Sections 4(1) and 6 of the Act which are mandatory by law

                     and the same would prejudice to the petitioners.


                     Page 6 of 26
https://www.mhc.tn.gov.in/judis
                                                                          W.P.No.14644 of 2012 etc. batch




                                  7. Learned Senior Counsel appearing for the fifth respondent

                     submitted that the entire procedure are duly followed and he has produced

                     the records to prove the same. In fact, the entire project has been completed

                     and now 765/400 KV Power Grid Station is functioning in the lands which

                     are acquired. The notification under Section 4(1) of the Act was published in

                     the Government Gazette No.309 dated 07.09.2011 and the same was

                     published in local dailies viz., Malai Murasu and Namadhu MGR on

                     09.09.2011 and 10.09.2011. Thereafter, the declaration under Section 6 of

                     the Act was published in the Tamil Nadu Government Gazette No.358 dated

                     22.09.2011 and the same was published in two vernacular dailies viz., Dhina

                     Thanthi and Malai Murasu dated 30.10.2011. Thereafter, on 03.11.2011

                     Form A notice under Section 4(1) of the Act was displayed in the offices of

                     the National Highways and Revenue offices.




                                  8. He further submitted that the land acquisition proposals

                     approved by the Principal Secretary and Commissioner of Land


                     Page 7 of 26
https://www.mhc.tn.gov.in/judis
                                                                            W.P.No.14644 of 2012 etc. batch

                     Administration on 02.02.2012. On 06.03.2012, direction under Section 7 of

                     the Act was issued to the Land Acquisition Officer and Revenue Divisional

                     Officer, Vellore. On 08.03.2012, the Public Notice under Section 9(1) of the

                     Act was issued by the Land Acquisition Officer. Therefore, the Land

                     Acquisition Officer called upon the land owners including all the petitioners

                     for enquiry to be held on 26.03.2012 as contemplated Section 9(2) of the

                     Act. On 12.03.2012, the values of the tree and structure were duly approved

                     by the Commissioner of Land Administration. On 26.03.2012, all the

                     petitioners and other land owners appeared for enquiry before the Land

                     Acquisition Officer. On 29.03.2012, all the petitioners including other land

                     owners were duly issued letter to collect 80% of the compensation. On

                     30.03.2012, the compensation award amount has been disbursed to the

                     respective land owners. Thereafter, the subject property had been taken over

                     on 25.05.2012 and the Land Acquisition Officer handed over the possession

                     of lands measuring to an extent of 105.92 acres to the fifth

                     respondent/corporation. Thereafter,     the   fifth   respondent      has     taken

                     possession of the entire extent of the land of the petitioners and now, the

                     entire project has been completed and it is functioning.


                     Page 8 of 26
https://www.mhc.tn.gov.in/judis
                                                                             W.P.No.14644 of 2012 etc. batch




                                  9. Therefore, all the writ petitions fail and devoid of merits and

                     they are liable to be dismissed. Accordingly, the Writ Petitions are dismissed.

                     Consequently, the connected Miscellaneous Petitions are closed. No costs.

                                                                                            23.11.2021

                     Index:Yes/No
                     dm

                     G.K.ILANTHIRAIYAN, J.

These Writ Petitions have been listed before this Court under the

caption “For being mentioned”, at the instance of the learned counsel

appearing for the petitioners.

2. The learned Counsel appearing for the petitioners in all

the Writ Petitions wants to submit some citations and requested that his

submission may be incorporated in the order dated 24.11.2021, passed in

W.P.No.14644 of 2012 etc.

3. In view of the request made by the learned counsel for

the petitioners, the entire order in W.P.No.14644 of 2012 dated 23.11.2021,

https://www.mhc.tn.gov.in/judis W.P.No.14644 of 2012 etc. batch

shall read as follows:

“The Writ Petition is filed to issue a Writ of Certiorari, calling for

the records relating to the proceedings of the first respondent in

G.O.Ms.No.77, Energy (C-1) Department dated 22.09.2011,

No.11(2)/EGY/404(c)/2011 and to quash the same in respect of the

petitioners' land measuring to an extent of 0.19.0 hectares in S.No.84/1A2

and a land measuring to an extent of 0.08.0 hectares in S.No.84/1B1,

Elayanallur Village, Katpadi Taluk, Vellore District.

2. The Government of India by the communication dated

20.10.2009 accorded prior approval for supplementary transmission system

associated with Vallur Termal Power Station for establishment of Tiruvalam

765/400 KV Sub-Station to facilitate import of power to Southern Region

especially to Tamil Nadu. In pursuance thereto, the Tamil Nadu Electricity

Board identified lands measuring to an extent of 150 acres at Elayanallur

Village for establishment of 765/400 KV Sub-Station by the fifth respondent

and 400/230 KV by the Tamil Nadu Electricity Board. In this regard, on

27.03.2010 the Tamil Nadu Electricity Board addressed a letter to the

https://www.mhc.tn.gov.in/judis W.P.No.14644 of 2012 etc. batch

second respondent herein requesting to acquire the land either by private

negotiation or through acquisition. Accordingly, the fifth respondent vide

letter dated 19.05.2010 requested the second respondent to initiate

acquisition proceedings invoking Section 17 of the Land Acquisition Act,

1894 (hereinafter referred to as 'the Act' for short).

https://www.mhc.tn.gov.in/judis W.P.No.14644 of 2012 etc. batch

3. On 28.08.2010, the fourth respondent conducted a

public meeting and taking into consideration the urgency of the significant

project in question, opted to initiate land acquisition process individually

without informing to the Tamil Nadu Electricity Board. The Commissioner,

Land Administration called upon the second respondent to send proposals

for draft notification under Section 4(1) and draft declaration under Section

6 of the Act. On 30.08.2011, the first respondent accorded administrative

sanction under Section 17(1) of the Act by issuing G.O.Ms.No.70, Energy

(C-1) Department for acquiring lands measuring to an extent of 105.92 acres

for establishment of 765/400 KV Power Grid Station. The first respondent

had issued notification under Section 4(1) of the Act intending to acquire the

land belong to the petitioners and other land invoking urgency provision of

Section 17(1) of the Act and dispensing with the 5-A enquiry under the said

Act. The said notification was published in Tamil Nadu Gazette

Extraordinary in G.O.Ms.No.72, Energy (C-1) Department, dated

07.09.2011. The declaration under Section 6 of the Act was issued under

G.O.(Ms). No.77 Energy (C-1) Department dated 22.09.2011. The

declaration under Section 6 of the Act was followed by an errata issued by

https://www.mhc.tn.gov.in/judis W.P.No.14644 of 2012 etc. batch

the first respondent on 22.02.2012 altering the extent of land and including

the trees, well, pumpset etc., which has been left over in the earlier

notification.

4. The third respondent had issued certain notices for

determining the compensation. According to the petitioners, no proper

enquiry was conducted in determining the proper value. However, the third

respondent passed an award dated 29.03.2012 thereby determined the

compensation. On receipt of the said proceedings of the third respondent,

the petitioners came to understand about the acquisition proceedings.

5. The learned counsel for the petitioners submitted that all the

petitioners challenged G.O. Ms. No.77, Energy (C-1) Department, dated

22.09.2011 and declaration under Section 6 of the Act on the ground that as

per Section 17 of the Act, the enquiry under Section 5-A of the Act can be

dispensed in the cases as provided under the said section and Section 17(2)

enumerates the cases in which the urgency provisions can be invoked and

the possession of the land taken immediately and as per sub-section (b)

https://www.mhc.tn.gov.in/judis W.P.No.14644 of 2012 etc. batch

immediate possession is necessary for library or any educational institution,

for construction of any building for common use of the inhabitants of such

village, or godown for any society or any dwelling house for the poor, or any

irrigation tank drainage channel or well, or any road. The present acquisition

is not for the above enumerated purpose. Therefore, the invocation of

Section 17(4) in the present case is without jurisdiction of the first

respondent. He further submitted that the first respondent failed to publish

the notice under Sections 4(1) and 6 of the Act which are mandatory by law

and the same would prejudice to the petitioners.

5.1. The learned counsel appearing for the petitioners further

submitted that when the provision under Section 17(2) of the Act invoked,

the first respondent must be satisfied that the acquisition of land is very

urgent to invoke the emergency provision. There must be material before the

first respondent to invoke the emergency provision. The requisition has been

made on 19.05.2010 and the administrative sanction accorded on

30.08.2011. Only after one year, the emergency provision was invoked,

followed by the declaration under Section 22.09.2011. Further the

https://www.mhc.tn.gov.in/judis W.P.No.14644 of 2012 etc. batch

compensation was determined unilaterally on 23.09.2012. It would clearly

show that the right of the petitioners under Section 5(A) of the Act is

arbitratively deprived and the entire acquisition proceeding is liable to be set

aside.

5.2. He vehemently contended that though emergency

provision was invoked by the first respondent, there was no real and

substantive urgency warranting invocation of urgency clause, much less

urgency warranting dispensing with enquiry under Section 5(A) of the Act.

The dispensing with the enquiry as contemplated under Section 5(A) of the

Act is only directory in nature and the owners of the land may dispense with

enquiry under Section 5(A) of the Act, even as per the provisions.

5.3. In support of his contention, he relied upon the

judgement reported in 2011 (5) SCC 553 in the case of Radhyshyam & ors

Vs. State of Uttar Pradesh & ors., in which the Hon'ble Supreme Court of

India held that the property of a citizen cannot be acquired by the State or its

agencies without complying with the mandate provisions under Sections 4,

https://www.mhc.tn.gov.in/judis W.P.No.14644 of 2012 etc. batch

5A and 6 of the Act. A public purpose, however, laudable it because the

same have the effect of depriving the owner of his right to property without

being heard. Only in a case or real urgency, the State can invoke the urgency

provisions and dispense with the requirement of hearing the land owners or

other interested person. The urgency clause can be invoked only for the

purpose of acquisition cannot brook the delay of even a few weeks or

months. Therefore, before excluding the application of Section 5(A) of the

Act, the authority concerned must be fully satisfied that time of few weeks

or months likely to be taken in conducting inquiry under Section 5(A) of the

Act will in all probability, frustrate the public purpose for which the land is

proposed to be acquired. Further held that if planned industrial development

of the district is treated as public purpose within the meaning of Section 4 of

the Act, there was no urgency which could justify the exercise of power by

the State Government under Sections 17(1) and 17(4) of the Act. Therefore,

time required for ensuring compliance with the provisions contained in

Section 5(A) of the Act, cannot by any stretch of imagination, be portrayed

as delay which will frustrate the purpose of acquisition.

https://www.mhc.tn.gov.in/judis W.P.No.14644 of 2012 etc. batch

5.4. He also relied upon the judgement reported in 2011 (4)

MLJ 78 in the case of S.Muthuvenkataseshan Vs. State of Tamil Nadu &

ors., in which this Court held that the emergency provision contained in

Section 17 of the Act can be invoked if only the emergency is one of grave.

In the said case, the project was originally proposed in the year 1999,

whereas the notification was issued only in the year 2001 i.e., after two

years. Thus, the Government itself allowed the proposal to be kept pending

for two years. The right to own property, though not a fundamental right, is

now a constitutional right under Article 300A of the Constitution of India

and the same cannot be deprived without following due process of law.

5.5. The learned counsel appearing for the petitioners also

relied upon another judgment reported in 2011 (4) SCC 769 in the case of

Dev Sharan & ors Vs. State of Uttar Pradesh & ors., in which the Hon'ble

Supreme Court of India held that the concept of public purpose on this

broad horizon must also be read into the provisions of emergency power

under Section 17 of the Act, with the consequential dispensation of right of

https://www.mhc.tn.gov.in/judis W.P.No.14644 of 2012 etc. batch

hearing under Section 5(A) of the Act. The Courts must examine these

questions very carefully when little Indians lose their small property in the

name of mindless acquisition at the instance of the State.

5.6. He also relied upon the judgment reported in 2012 (12)

SCC 675 in the case of Bharat Sewak Samaj Vs. Lieutenant Governor and

ors., in which the Hon'ble Supreme Court of India held that the authority

must have subjective satisfaction of the need for invoking urgency clause

under Section 17 of the Act keeping in mind the nature of the public

purpose, real urgency that the situated demands and the time facts., i.e.,

whether taking possession of the property can wait for a minimum period

within which the objections could be received from the landowners and the

inquiry under Section 5(A) of the Act could be completed. Therefore, the

learned counsel appearing for the petitioners in all the Writ Petition

submitted that though entire project has been completed and the sub-station

is functioning there on, the entire land acquisition proceedings lapsed and

the respondent ought to have initiated the proceedings afresh and liable to

pay compensation under the new Act.

https://www.mhc.tn.gov.in/judis W.P.No.14644 of 2012 etc. batch

6. Per contra, the learned Senior Counsel appearing for the

fifth respondent submitted that the entire procedure are duly followed and he

has also produced the records to prove the same. In fact, the entire project

has been completed and now 765/400 KV Power Grid Station is functioning

in the lands which were acquired. The notification under Section 4(1) of the

Act was published in the Government Gazette No.309 dated 07.09.2011 and

the same was published in local dailies viz., Malai Murasu and Namadhu

MGR on 09.09.2011 and 10.09.2011. Thereafter, the declaration under

Section 6 of the Act was published in the Tamil Nadu Government Gazette

No.358 dated 22.09.2011 and the same was published in two vernacular

dailies viz., Dhina Thanthi and Malai Murasu dated 30.10.2011. Thereafter,

on 03.11.2011 Form A notice under Section 4(1) of the Act was displayed in

the offices of the National Highways and Revenue offices.

6.1. He further submitted that the land acquisition proposals

approved by the Principal Secretary and Commissioner of Land

Administration on 02.02.2012. On 06.03.2012, direction under Section 7 of

https://www.mhc.tn.gov.in/judis W.P.No.14644 of 2012 etc. batch

the Act was issued to the Land Acquisition Officer and Revenue Divisional

Officer, Vellore. On 08.03.2012, the Public Notice under Section 9(1) of the

Act was issued by the Land Acquisition Officer. Therefore, the Land

Acquisition Officer called upon the land owners including all the petitioners

for enquiry to be held on 26.03.2012 as contemplated Section 9(2) of the

Act. On 12.03.2012, the values of the tree and structure were duly approved

by the Commissioner of Land Administration. On 26.03.2012, all the

petitioners and other land owners appeared for enquiry before the Land

Acquisition Officer. On 29.03.2012, all the petitioners including other land

owners were duly issued letter to collect 80% of the compensation. On

30.03.2012, the compensation award amount has been disbursed to the

respective land owners. Thereafter, the subject property had been taken over

on 25.05.2012 and the Land Acquisition Officer handed over the possession

of lands measuring to an extent of 105.92 acres to the fifth

respondent/corporation. Thereafter, the fifth respondent has taken

possession of the entire extent of the land of the petitioners and now, the

entire project has been completed and it is functioning.

https://www.mhc.tn.gov.in/judis W.P.No.14644 of 2012 etc. batch

7. Heard Mr.Devaraj, learned counsel appearing for the

petitioners, Mr.A.Selvendran, learned Government Pleader appearing for the

respondents 1 to 4 and Mr.T.Thyagarajan, learned Senior Counsel appearing

for the fifth respondent in all the Writ petitions.

8. In order to facilitate import of power to southern region,

especially to Tamil Nadu, the Ministry of Power, Government of India by the

communication dated 20.10.2009 accorded prior approval for

supplementary transmission system associated with Vallur Thermal Power

Station for establishment of Tiruvalam 765/400 kv sub-station. In pursuant

thereto, the Tamil Nadu Electricity Board identified lands to an extent of 150

acres at Elayanallur Village for the establishment of 765/400 KV sub-station

by the fifth respondent and 400/230 KV by the Tamil Nadu Electricity

Board. The Tamil Nadu Electricity Board addressed a letter to the second

respondent herein on 27.03.2010, requesting to acquire the land either by

private negotiation or through acquisition. On 19.05.2010, the fifth

respondent addressed a letter to the second respondent to initiate acquisition

proceedings by invoking Section 17 of the Act.

https://www.mhc.tn.gov.in/judis W.P.No.14644 of 2012 etc. batch

9. On 28.08.2010, the fourth respondent convened a

public meeting at Elayanallur Village to appraise the public the importance

of the project. Taking into consideration of the urgency of the project, the

fifth respondent has initiated land acquisition process individually without

reference to the Tamil Nadu Electricity Board. In that regard, on

07.09.2010, the fifth respondent addressed a letter to the second respondent

to invoke urgency clause under Section 17 of the Act, for the land to be

acquired. On 06.12.2010, the Assistant Commissioner of Land Reforms,

Villupuram issued “no objection certificate” on the basis of Form 36

submitted under Section 37 of the Tamil Nadu Reforms (Fixation of Ceiling

on Land) Act, 1961. On 31.12.2010, the proposal has been forwarded by

the second respondent to the first respondent through the Commissioner,

Land Administration. The Revenue Secretary vide his letter dated

10.03.2011, called the Energy Secretary, Commissioner of Land

Administration, Commissioner of Land Reforms and the fifth respondent for

a joint metting with the Chief Secretary, Government of Tamil Nadu

regarding land acquisition for the proposed sub-station. On 17.03.2011, the

https://www.mhc.tn.gov.in/judis W.P.No.14644 of 2012 etc. batch

said meeding was convened and thereby called upon the second respondent

to send proposal for draft notification under Section 4(1) of the Act and draft

declaration under Section 6 of the Act.

10. Thereafter, on 30.08.2011, the first respondent accorded

administrative sanction under Section 17(1) of the Act, by G.O.Ms.No.70

Energy (C-1) Department, for acquiring land ad measuring 105.92 acres for

establishment of 765/200 KV Power Grid station to fulfillment of conditions

mentioned therein. The first respondent issue notification under Section 4(1)

of the Act under the urgency provision of Section 17(1) of the Act in

G.O.Ms.No.72 Energy (C-1) Department dated 07.09.2011 and declaration

under 6 of the Act was issued in G.O.Ms.No.77 Energy (C-1) Department,

dated 22.09.2011.

11. Now the entire project has been completed and from

31.03.2014 onwards, 765/400 KV power station is functioning. After

completion of all requirements as contemplated under the Act, on

31.07.2012 the award was passed and the entire compensation award

https://www.mhc.tn.gov.in/judis W.P.No.14644 of 2012 etc. batch

amount has been deposited on 23.06.2014 and the land acquisition

proceedings are pending before the Sub Court, Vellore. He further

submitted that the establishment of the sub station to facilitate the power

demand of southern States particularly Tamil Nadu and as such, the

respondents rightly invoked the emergency clause for the establishment of

765/400 KV sub-station, by the fifth respondent and 400/230 KV by the

Tamil Nadu Electricity Board.

12. As stated supra, on 19.05.2010, the first respondent

initiated acquisition proceedings by invoking Section 17 of the Act. On

30.08.2011, the first respondent accorded sanction to acquire the land under

Section 17(1) of the Act. Immediately on 07.09.2011, notification under

Section4(1) of the Act was issued and the same was published in the public

gazette. Therefore, there is absolutely no delay for invoking the provisions

under Section 17(1) of the Act.

13. That apart, the similar project established by invoking

Section 17 of the Act, was challenged before this Court in W.P.No.35069 of

https://www.mhc.tn.gov.in/judis W.P.No.14644 of 2012 etc. batch

2012 and this Court by an order dated 02.08.2013, after considering all the

points raised by the learned counsel appearing for the petitioners dismissed

that Writ Petition, and the same was also confirmed by the Hon'ble Division

Bench of this Court in W.A.No.1737 of 2013 dated 07.11.2013. The Hon'ble

Division Bench of this Court held in that case that neither pre-acquisition

delay not post-acquisition delay and invocation of urgency clause requires

decision at various levels by various authorities and considering the said

fact, the period of one year taken to arrive at such a decision cannot be said

to be a delay at all. In the case on hand, the original records produced by the

respondents has substantiate the stand taken by the first respondent. Hence,

the above judgements cited by the learned counsel appearing for the

petitioners do not help the case of the petitioners. Therefore, all the Writ

Petitions fail and devoid of merits and they are liable to be dismissed.

14. Accordingly, all the Writ Petitions are dismissed.

Consequently, the connected Miscellaneous Petitions are closed. There shall

be no order as to costs.

03.12.2021 rts/dm

https://www.mhc.tn.gov.in/judis W.P.No.14644 of 2012 etc. batch

G.K.ILANTHIRAIYAN, J.

dm

To

1.The Principal Secretary to Government, Government of Tamilnadu, Energy C-1, Department, Fort St. George, Chennai - 9.

2.The District Collector, Vellore District, Vellore.

3.The Revenue Divisional Officer, Vellore.

4.The Tahsildar, Katpadi, Vellore District.

5.Power Gird Corporation of India Ltd., Rep. by its Deputy General Manager, A.Surendiran, No.2 (Old No.160) I Lane Bharathi Nagar, North Usman Road, T.Nagar, Chennai - 600017.

W.P.No.14644 of 2012 etc. batch

23.11.2021

https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter