Sunday, 10, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

G.A.Projects Pvt. Ltd vs Kamarajar Port Ltd
2021 Latest Caselaw 22355 Mad

Citation : 2021 Latest Caselaw 22355 Mad
Judgement Date : 15 November, 2021

Madras High Court
G.A.Projects Pvt. Ltd vs Kamarajar Port Ltd on 15 November, 2021
                                                                               OSA (CAD) No.107 of 2021

                                      IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                      DATED:     15.11.2021

                                                              CORAM :

                                     THE HON'BLE MR.SANJIB BANERJEE, CHIEF JUSTICE
                                                               AND
                                        THE HON'BLE MR.JUSTICE P.D.AUDIKESAVALU
                                                  OSA (CAD) No.107 of 2021

                     G.A.Projects Pvt. Ltd
                     No.3, K.H. Road
                     Ennore
                     Chennai 600 057.                                         ..    Appellant

                                                                Vs.

                     Kamarajar Port Ltd
                     3rd Floor, Jawahar Building, 1
                     7, Rajaji Salai
                     Chennai 600 001.                                         ..    Respondent

                           Appeal filed under Section 13(1) of Commercial Courts Act
                     against the order dated 14.09.2021 in Arb. Appln. (Comm.Div) No.167
                     of 2021.

                                  For the Appellant       :      Mr.Om Prakash
                                                                 Senior Counsel
                                                                 for Ms.Tanya Kapoor

                                                      JUDGMENT

(Delivered by the Hon'ble Chief Justice)

The appeal is directed against an order dated September 14,

2021 passed on an application under Section 9 of the Arbitration and

__________

https://www.mhc.tn.gov.in/judis OSA (CAD) No.107 of 2021

Conciliation Act, 1996.

2. The grievance of the appellant contractor is that some five

years after a road was constructed and made over by the appellant to

the respondent employee, the Arbitration Court has appointed experts

to look into the condition of the road. The appellant asserts that no

inspection conducted now will reveal the nature or character of the

road that was constructed and made over by the appellant to the

respondent in the year 2016.

3. The contract between the parties envisaged the construction

of some internal roads by the contractor. The contract was time-bound

and it is the appellant's contention that following the delay on the part

of the employer in releasing the land and in taking other measures,

the contractor was constrained to terminate the contract and make a

demand for the payment due to the contractor.

4. In terms of the arbitration agreement between the parties, a

reference was instituted, in which the employer also carried a counter-

claim. The Arbitrator allowed a substantial part of the appellant's claim

__________

https://www.mhc.tn.gov.in/judis OSA (CAD) No.107 of 2021

which came to be challenged in proceedings under Section 34 of the

Arbitration and Conciliation Act, 1996 and succeeded, primarily on the

ground that two documents may not have been appropriately

considered or due opportunity given to the employer to deal with the

same. The Arbitration Court also referred to Clause 22 of the

agreement that pertained to a default period during which the

contractor would be liable to repair the road. The appellant's endeavor

to have the order setting aside the award annulled failed in the appeal.

Admittedly, the parties have carried the disputes to a de novo

reference.

5. The appellant submits that it is utterly futile to make any

attempt to inspect the present condition of the road. According to the

appellant, no expert would be able to assess what the condition of the

road may have been in the year 2016 by looking at it or inspecting the

same in the year 2021. The appellant also refers to the contract

requiring an engineer to be appointed and for the engineer to oversee

the work done by the contractor. According to the appellant, the

engineer had required several tests to be undertaken and over 2200

tests had been undertaken in course of the work done by the

__________

https://www.mhc.tn.gov.in/judis OSA (CAD) No.107 of 2021

appellant. In certain cases, these tests reflected perceived anomalies

or defects on the part of the contractor and this, according to the

appellant, formed the basis of the counter-claim which was taken by

the employer before the Arbitrator. The appellant also says that if the

results of any tests were disputed by the contractor, the contract

envisaged a joint inspection to be conducted. It is, in such

circumstances, that the appellant says that the order impugned

appointing independent experts from the IIT and from the Civil

Engineering Department may not be appropriate.

6. At the end of the day, what is to be assessed in course of the

fresh reference is the extent of the work which has been done by the

appellant and the liability of the employer in such regard. In addition, if

there are any counter-claims, the same have to be looked into. It is

necessary, for such purpose, that the condition in which the roads

were handed over by the appellant to the employer must be looked

into. While it is difficult to imagine for a lay person as to what an

expert would look into a road five years after its installation, but that is

why the expert is considered to be the expert in the field. There does

not appear to be any perverse exercise of the discretion clearly

__________

https://www.mhc.tn.gov.in/judis OSA (CAD) No.107 of 2021

available with the Arbitration Court. However, whatever objections the

appellant may have against the report or reports filed by the experts

may be canvassed before the Arbitral Tribunal in accordance with law.

It must not be forgotten that the final assessment will be made by the

Arbitrator and if any piece of the experts' opinion is not based on

objective criteria in terms of the contract, including IS 456 or like

parameters which are recognised in the field of road construction, it

will be open to the appellant to point out the same.

7. The judgment and order impugned do not call for any

interference, though the views expressed by the experts may be

challenged in accordance with law by the appellant herein.

8. OSA (CAD) No.107 of 2021 is dismissed. CMP No.18256 of

2021 is closed. There will be no order as to costs.

                                                                 (S.B., CJ.)      (P.D.A., J.)
                                                                           15.11.2021

                     Index : Yes/No

                     kpl


                     __________



https://www.mhc.tn.gov.in/judis
                                        OSA (CAD) No.107 of 2021



                                   THE HON'BLE CHIEF JUSTICE
                                                AND
                                        P.D.AUDIKESAVALU, J.

                                                           (kpl)




                                    OSA (CAD) No.107 of 2021




                                                   15.11.2021




                     __________



https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter