Citation : 2021 Latest Caselaw 11351 Mad
Judgement Date : 1 June, 2021
Original Petition Nos.96 & 97 of 2021
THE HIGH COURT OF JUDICATURE AT MADRAS
Reserved on Delivered on
20~10~2021 28 ~10~2021
CORAM:
THE HONOURABLE MR.JUSTICE N. SATHISH KUMAR
ARBITRATION ORIGINAL PETITION Nos.96 & 97 of 2021 &
A.Nos.2868 & 2870 of 2021
M/s.Chennai Metro Rail Limited,
Administration Building,
Chennai Metro Rail Depot,
Poonamallee High Road,
Koyambedu, Chennai – 600 107. ... Petitioner in both O.Ps.
.Vs.
The Joint Venture M.s,Transtonnelstroy – Afcons JV
Comprising of,
1] Transtonnelstroy Limited,
4/1. Luganskaya Str,
Moscow, 115516, Russia.
AND
2] Afcons Infrastructure Limited,
Afcons House, 16, Shah Industrial Estate,
Veera Desai Road, Azad Nagar [P.O.],
Post Box No.11978, Andheri [W],
Mumbai – 400 053. ... Respondents in both O.Ps.
Page 1 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
Prayer: Petitions filed under section 34 [2] [a] [iv], 34 [2] [b] [ii], 34 [2A] read with sections 18 and 28 of the Arbitration and Conciliation Act, 1996 [As Amended] to set aside the impugned Award dated 01.06.2021 passed by the Arbitral Tribunal and allow these petitions with costs.
For Petitioner : Mr.R.Yashod Vardhan, SC
for Mr.S.Arjun Suresh
For respondents : Mr.G.Masilamani, SC
for Mr.D.Balaraman
COMMON ORDER
Aggrieved over granting extension of time in both the petitions O.P.No.96
of 2021 and 97 of 2021 have been filed challenging the awards.
2. The subject matter of O.P.No.96 of 2021 is the scope of work relating to
design and construction of underground stations at Shenoy Nagar, Anna Nagar
East, Anna Nagar Tower, Thirumanalam and Associated Tunnels in respect of the
Contract No.UAA-05 The date of commencement of the contract was on
07.02.2011 and scheduled date of completion was on 07.01.2015. The total
Contract value is Rs.1030.99 crores. However, the revised completion date was
Page 2 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
agreed upon between the parties by an addendum dated 29.08.2013 and the
completion dated was extended upto 05.07.2015.
3. In respect of subject matter of O.P.No.97 of 2021, the scope of work
relate to design and construction of underground stations at Washermanpet,
Mannadi, High Court, Chennai Central and Egmore and Associated Tunnels in
respect of Contract No.UAA-01. The contract commencement date was on
07.02.2011 and scheduled completion date was on 07.04.2015. The value of the
contract was Rs.1556.81 crores. The revised completion date as per the addendum
was extended upto 30.03.2016.
4. As the dispute arose between the parties in respect of the contracts,
particularly, with regard to the extension of time, the matter has been referred to
arbitral tribunal. The claimant herein after called as TTA-JV made the claim in
respect of the contract in U.A.A.No.05 [O.P.No.96 of 2021] before the arbitral
tribunal. In Claim No.1 extension of time is sought up to 28.12.2017 for the
events between 07.02.2011 and 31.12.2012. In Claim No.2, extension was sought
upto 26.01.2019 for the events between 16.04.2013 and 31.05.2014. However, the
Page 3 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
Arbitral Tribunal had passed the following award :
1] The Claimant is entitled to an Extension of Time for 179
days for overall completion of the works [i.e., KD-17: Achieve
issuance of taking Over Certificate] with the revised Key dates as
per Annexure – 1 of Addendum No.1, on account of Respondent's
delay upto 15.04.2013.
2] The Claimant is entitled to further Extension of Time for
302 days for overall completion of the works with revised date as
02.05.2016 [i.e., KD-17: Achieve issuance of Taming Over
Certificate] and with revised key dates for completion of individual
Key dates as tabulated in Annexure -9 of this award, on account of
respondent's delay upto 31.05.2014.
3] The Claimant is not liable to pay any Liquidated damages
till the revised date for achievement of each Key Dates as detailed
in Annexue – 9 of this Award and the refund of LD amount under
Claim Nos.1 & 2 of this Award shall be made only upon
considering the further revision of Kds if any in the final
adjudication of all extension of time claims under the Contract.
Page 4 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
4] The Parties are directed to equally share the Arbitrators
fees and Arbitral proceedings expenses. However, th expenses
incurred by each party in connection with the preparations,
presentations etc., of its case prior to, during and after the
proceedings shall be borne by each party itself.
5. O.P.No.97 of 2021 is in respect of the contract in U.A.A. No.01, wherein
the claimant, before the arbitral tribunal in Claim No.1 claimed extension of time
is sought up to 28.12.2020 for the events between 07.02.2011 and 28.02.2013. In
Claim No.2, extension was sought upto 15.05.2021 for the events between
16.04.2013 and 31.05.2014. However, the Arbitral Tribunal had passed the
following award :
1] The Claimant is entitled to an Extension of Time for 357
days for overall completion of the works [i.e., KD-19: Achieve
issuance of taking Over Certificate] with the revised Key dates as
per Annexure – 1 of Addendum No.1, on account of Respondent's
delay upto 15.04.2013.
Page 5 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
2] The Claimant is entitled to further Extension of Time for
851 days for overall completion of the works with revised date as
29.07.2018 [i.e., KD-19: Achieve issuance of Taming Over
Certificate] and with revised key dates for completion of individual
Key dates as tabulated in Annexure -9 of this award, on account of
respondent's delay upto 31.05.2014.
3] The Claimant is not liable to pay any Liquidated damages
till the revised date for achievement of each Key Dates as detailed
in Annexue – 9 of this Award and the refund of LD amount under
Claim Nos.1 & 2 of this Award shall be made only upon
considering the further revision of KDs if any in the final
adjudication of all extension of time claims under the Contract.
4] The Parties are directed to equally share the Arbitrators
fees and Arbitral proceedings expenses. However, th expenses
incurred by each party in connection with the preparations,
presentations etc., of its case prior to, during and after the
proceedings shall be borne by each party itself.
Page 6 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
6. Since both the Original petitions relate to extension of time and the
challenge was made on the same grounds, this Court is inclined to dispose both the
Original Petitions in a Common Order.
7. Though several grounds have been raised, the main challenge against the
award is that no opportunity has been given to the petitioner herein. Besides,
unmarked documents have been relied upon by the arbitral tribunal after
concluding the arguments of both sides and without giving any opportunity to the
petitioner to disprove the data said to have been produced by the respondent
herein. The learned Senior Counsel appearing for the petitioner has pressed his
arguments mainly on the ground that the very data or particulars relied upon by the
respondent were disputed by the petitioner. Such being the position, when the
correctness of the entries in the so called software were disputed and without
giving an opportunity to produce evidence to show that such particulars were
entered by the respondent on their own, the same goes to the root of the matter.
Hence, it is his contention that the learned arbitral tribunal have relied upon the
unmarked documents without giving an opportunity to the petitioner. Therefore, it
Page 7 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
is his contention that such procedure adopted by the trbunal in passing the award
in extending the time limit [EOT] cannot be sustained in the eye of law.
8. Whereas, the learned Senior Counsel appearing for the respondent
mainly contended that the data and the particulars were maintained from the very
inception of the contract and copies have been furnished to the petitioner. The
software relied upon by the arbitral award were sought to be maintained as per the
contract. In the contract itself, it is specifically agreed that only the software
which was produced has been maintained by the parties and various details and
data have been entered then and there and copies have been furnished to the other
side. Only such data have been relied upon by the learned arbitral tribunal being
the technical persons. In such view of the matter, it is his contention that merely
because further opportunity has not been provided to the petitioner, it cannot be
said that no opportunity has been provided. It is his contention that what was
relied upon by the arbitral tribunal is the admitted documents. Therefore, the
question of granting further opportunity will not arise. It is his further contention
that as per Clause [4.14] CPA [15], Appendix [4] Employer's Requirement
– programmes relating to submission of Baseline Programme [BLP]
Page 8 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
and updated Baseline Programmes on the monthly basis to the ER with a copy to
CMRL in Primavara P6 Software as per the requirement of Contract Clause 3 of
Appendix 4 Programme Requirements. It is his further contention that the primary
object of the above said programme was to monitor the progress works, through
the special computer software [Primavara P6] especially when the monthly
updated dated programme running more than 100 printed pages containing 1000s
of datas / numbers relating to achievements of Key Datas [KDs] for this complex
project with various interface and system wide contractors operating in
overlapping works of several kinds.
9. It is the further contention of the learned Senior Counsel that pursuant to
the contract clauses TTA-JV submitted the Baseline Programme [BLP] [detailed
chart with dates for commencement and completion of each work by the
Contractor] to ER and the same was approved on 27.07.2011. It is his contention
that the said BLP was submitted before the Tribunal along with SOC. Further,
TTA-IV had submitted contemporaneously regular monthly Updated Rolling
Programmes to the ER with a copy to CMRL. Moreover, the said programmes
were uploaded in the DMS [Document Management System], which were
Page 9 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
accessible to the ER / CMRL. Such updated monthly Programmes upto
28.02.2013 and 31.05.2014 were submitted to the respondent /CMRL [Hard &
Soft Copy] on 08.03.2013 and 16.06.2014 respectively. The same were received
and acknowledged by the ER / CMRL. As per Clause 5.5 of Appendix 4,
Programme Requirements of the Contract, the ER shall review and comment on
the Programme and information submitted by TTA-JV, within 4 weeks and
otherwise issue notices, if any. Having received the programme and information
on 08.03.2013 and 16.06.2014, ER did not issue any notice or otherwise on the
submission made by TTA-JV. Whereas, for the first time in their memo dated
30.09.2020, the petitioner has denied the contents of the programmes before the
tribunal. Before the Tribunal, the petitioner also admitted that the Rolling
programme dated 16.06.214 submitted by the claimant is significant to the
adjudication of the present issue and the rolling and updated programmes forms
integral part of the contemporaneous records to determine the instant dispute.
10. It is his further contention that since the Monthly uptated programme
was submitted by TTA-JV, the said Rolling programme updated in
contemporaneous records. It is his further contention that the petitioner has
Page 10 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
neither objected to the direction of the Tribunal to produce the updated
programmes which was the same programme submitted in the year 2013, 2014 of
TTA-JV to ER and CMRL. Hence, it is his contention that the programmes
submitted before the tribunal is not a new one and therefore, it cannot be said that
the tribunal has no power to look into the document which is not in dispute.
Hence, it is his contention that merely because the number was not given for the
documents, it cannot be said that the tribunal has no power to look into the
documents. Therefore, the strict procedure of the Evidence Act cannot be
expected before the tribunal both in respect of rolling and updated programme.
The software was in possession of both the parties since 2013 and 2014.
Therefore, the alleged objection is nothing but an empty and useless formality and
the same is not maintainable. There is no allegation of misconduct or bias against
Arbitral Tribunal. The petitioner is aware of all the above details and it is already
spelt out in the affidavit filed in the application filed under section 23 of the
Arbitration and Conciliation Act. Therefore, they cannot contend that they have
no knowledge about the document. In support of his contentions, he relied on the
following judgments :
Page 11 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
MCDermott International Inc. Vs. Burn Standard Co.
Ltd. and others reported in [2006] 11 SCC 181
K.P.Poulose Vs. State of Kerala and another reported in
[1975] 2 SCC 236
Ssangayong Engineering Vs. NHAI reported in [2019] 15
SCC 131
Delhi Airport Metro Express Pvt. Ltd. Delhi Metro Rail
Corporation Ltd. reported in 2021 SCC OnLine 695
Delta Distilleries Ltd. Vs. United Spirit Ltd. reported in
2014 [1] SCC 113
11. It is not in dispute that the claim and cost related claims are pending
before the same tribunal in both the original petitions. The subject matter of the
awards is only for extension of time. It is relevant to note that the claimant
adopted the Key Dates as per the Addendum No.1 and sequences between Key
Dates as per the appendix 2B of the contract to arrive at the time of completion.
The learned arbitral tribunal infact has observed in Volume 2 of the impugned
award in page No.156 para [o] that apart from the reasons stated by the claimant,
Page 12 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
the erroneous logic adopted by the claimant in the Appendix – C might have
resulted to discrepancy in days of extension sought under EOT-1 & Claim No.1.
12. In para [q] of the award, the arbitral tribunal has held as follows :
In view of the above, the tribunal arrives at a conclusion that
after analyzing/arriving at a decision on individual delay events,
the same will be impacted in the respective contemporaneous
detailed work programme [CPM network Primavera programme],
to assess the effect on times for completion of individual Kds &
also on overall complete of works. The impact analysis shall be
performed by this Tribunal using the CPM programming software
[Primavera software] installed by he Claimant as per our
directions. It is relevant to note that the Tribunal themselves
analysed using CPM programma primavera installed by the
claimant as per the tribunal directions. Such primavera software
produced before the tribunal has not been accepted as documents.
It is not in dispue that these documents came on record after
completion of the arguments by both sides.
Page 13 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
13. Further, the tribunal in para 7.2.4 has held as follows :
“... During the cross examination, the C.W.3 confirmed some
of his statements. However, he is unable to reconcile some of the
calculatiosn and the quantification of the claims as pointed by the
respondent during the arguments. Further, C.W.3 has made some
incorrect statements as evident from the deposition that is relied
upon the respondent during the course of arguments. The Tribunal
observed various arithmetic and computational errors admitted by
C.W.3. The Tribunal also observed that there is a flaw in the
methodology and logic in quanitifcation of claims. Hence, the
quantification part of the claim explained by C.W.3 is not acceptable
by the Tribunal. Further, the Tribunal during the internal
deliberations decided to adopt Critical Path Method using Primavera
Software [P6], used in the project, which was furnished by the
parties. In view of the above, the evidence of C.W.3 with reference
to quantum analysis for determination of extension of time and
quantification of claims and the statements of C.W.3 wherein he
Page 14 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
himself admitted errors were not relied on by this Tribunal in the
subsequent analysis.”
and finally, the tribunal not relied upon the evidence of C.W.3, has analysed the
revised data work programme to arrive at a conclusion on EOT. Such documents
were unmarked before the tribunal during the course of trial or arguments and the
documents came on record only after the arguments and finally, the tribunal
passed the award granting extension of time. The entire extension of time is based
on the updated programme as on 31.05.2014.
14. The documents available on record placed before this Court indicate
that the claimant was taking steps to instal primavera software in the Presiding
Arbitrator computer tribunal only on 21.04.2021 and the communication also
indicate that the claimant is taking necessary steps for instalment of requisite
software. The rolling and the updated programme as on May 2014 have been
submitted to the ER on 07.06.2014 and the same was not marked before the
learned arbitrator.
15. The petitioner has filed an application under Section 23 of the
Page 15 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
Arbitration and Conciliation Act before the arbitral tribunal, wherein, a specific
stand has been taken stating that the purported impact analysis based on CPM
which took into account all events upto 31.05.2014 and the respondent infact
specifically disputed the contents of the rolling programme. The entries found
were disputed by the respondent namely the petitioner herein. It is their specific
case that the claimant has failed to consider any delays that are attributable to it
while preparing the aforesaid rolling programme and consequently, the petitioner
strongly denied the data and contents of the aforesaid document as well as the
alleged analysis of the claimant in preparing the same, in the entirety. In the same
application, the petitioner herein has submitted that the rolling programme dated
16.06.2014 to be taken on record to prove their case, besides the affidavit dated
07.07.2020 filed by the claimant. Objections have been filed by the claimant for
the above application. In para 6 of the objections, the claimant themselves
admitted that they are not relying on the rolling programme which sought to be
relied upon by the respondent. The learned arbitral tribunal has passed an Order in
the above application on 22.10.2020, wherein it has been held as follows :
“Further, when the respondent is denied the data and contents
of the said documents in its entirety and the Claimant is also not
Page 16 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
relying the said document, the Tribunal is unable to understand, why
such document is to be marked before this Arbitral proceedings and
more particularly at the concluding stage of arbitration proceedings.
5. However, the Arbitral Tribunal considered the said
application, since the reconstituted Arbitral Tribunal hearing the
matters afresh and the Affidavit of the Claimant dated 07.07.2020
being a recent document, the Arbitral Tribunal following the
principles of natural justice, decided to provide another and full
opportunity to the Respondent. Accordingly, the Rolling Progamme
dated 16.06.2014 is taken on record as Exhibit R-301 and the
Affidavit dated 07.07.2020 is taken on record as Exhibit R-302. The
above said two docuemnts are taken on record subject to relevancy
and materiality to the dispute before the Arbitral Tribunal. The
Claimant is also given liberty to raise the objections and to make
submissions with reference to the above said documents.”
16. It is to be noted that the tribunal had considered the communication by
way of an email in both cases on 16.04.2021 and 15.03.2021 directing the
Page 17 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
respondents herein to submit primavera software. The rolling programme of the
year 2013 was never marked before the arbitral proceedings. The above email
indicate that the primavera software was installed in one of the computer of the
tribunal which has not been communicated to the petitioner herein. Ultimately,
the tribunal extended time only based on the above unmarked rolling programme
as on 28.02.2013 and 16.04.2013 and 31.05.2014 respectively. When the parties
have raised certain dispute with regard to the data and entries which was stored in
the computer and software, merely because the particular software is sought to be
followed as per the contract, the contents or data cannot be taken as gospel truth
on its face value, particularly, when both sides have raised certain reservations as
to the rolling program. The tribunal being a technical member having decided in
their internal deliberations to analyse the data stored in the primavera software
ought to have given an opportunity to the parties, particularly after embarking
such an exercise. Only on such opportunity being given, the parties would have
been in a better position to show each of the entries are binding and reliable and
which of the entries are not relied and not proved. Only on the proof of such
entries or by way of an admission, the documents can be relied upon by the
tribunal. No doubt, strict rule of Evidence Act is not required to be followed by
Page 18 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
the Tribunal. However, fundamental principles governing the fields of
adjudication to prove any document cannot be ignored altogether. In this case, the
tribunal has relied upon the software and rolling programmes which was produced
after the arguments was over and the tribunal themselves had undertaken such an
exercise to analyse the entires and concluded its finding by extending EOT.
17. In McDemott International Inc. Vs. Burn Standard Co. Ltd. and others
reported in [[2006] 11 SCC 181], the Apex Court has held that the quantification
of claim computed by taking recourse to one other formula, having regard to the
facts and circumstances of the case, would eminently fall within the domain of the
arbitrator and if the arbitrator, applied a particular formula in assessing the amount
of damages, he cannot be set to have committed an error warranting interference
by the Court. Absolutely, there is no dispute with regard to the above judgment.
Though adopting the well known formula fall within the domain of the tribunal,
such a principle cannot be imported in relying any documents, which is, in fact,
not admitted by the other side.
18. In K.P.Poulose Vs. State of Kerala and another reported in [[1975] 2
Page 19 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
SCC 236, the Honourable Apex Court has held that if the materials required to
arrive at just and fair decision to resolve the controversy between the parties, even
if one party did not produce the documents before the arbitrator, it was incumbent
pon him to get hold of relevant documents for the purpose of just decision.
19. In Ssangayong Engineering Vs. NHAI reported in [[2019] 15 SCC 131,
the Hounourable Apex Court has held that the power of the Courts under Section
34 of the Arbitration and Conciliation Act to interfere with the arbitral award is
further restricted after 2015 Amendment of Arbitration and Conciliation Act. It is
not a case of drawing adverse inference. Whereas, the tribunal has relied upon the
documents which were unmarked, particularly, when both sides have not relied
upon the same during the adjudication process, without providing an opportunity
to the parties.
20. It is relevant to note that in the judgment of the Honourable Apex Court
in Ssangayong Engineering Vs. NHAI, it has been held as follows :
50. Section 24(3) is a verbatim reproduction of Article 24(3) of
the UNCITRAL Model Law on International Commercial Arbitration
Page 20 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
[“UNCITRAL Model Law”]. Similarly, Section 26(1) and (2) is a
verbatim reproduction of Article 26 of the UNCITRAL Model Law.
Sub-section (3) of Section 26 has been added by the Indian
Parliament in enacting the 1996 Act.
54. In Fouchard, Gaillard, Goldman on International
Commercial Arbitration (Kluwer Law International, 1999)
[“Fouchard”] it is stated:
“In some rare cases, recognition or enforcement of an award
has been refused on the grounds of a breach of due process. One
example is the award made in a quality arbitration where the
defendant was never informed of the identity of the arbitrators
hearing the dispute [Danish buyer v German (F.R.) seller, IV Y.B.
Comm. Arb. 258 (1979) (Oberlandesgericht Cologne)]. It also
occurred in a case where various documents were submitted by one
party to the arbitral tribunal but not to the other party [G.W.I. Kersten
& Co. B.V. v. Société Commerciale Raoul Duval et Co., XIX Y.B.
Comm. Arb.708 (Amsterdam Court of Appeals) (1992)], in another
case where the defendant was not given the opportunity to comment
Page 21 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
on the report produced by the expert appointed by the tribunal
[Paklito Inv. Ltd. v. Klockner East Asia Ltd., XIX Y.B. Comm. Arb.
664, 671 (Supreme Court of Hong Kong) (1994)], and again where
the arbitral tribunal criticized a party for having employed a method
of presenting evidence which the tribunal itself had suggested [Iran
Aircraft Indus. v Avco Corp., 980 F.2d 141 (2nd Cir. 1992)].” (at p.
987) 55. Gary Born (supra) states:
“German courts have adopted similar reasoning, holding that
the right to be heard entails two related sets of rights: (a) a party is
entitled to present its position on disputed issues of fact and law, to
be informed about the position of the other parties and to a decision
based on evidence or materials known to the parties [See, e.g.,
Judgment of 5 July 2011, 34 SCH 09/11, II(5)(c)(bb)
(Oberlandesgericht Munchen)]; and (b) a party is entitled to a
decision by the arbitral tribunal that takes its position into account
insofar as relevant [See, e.g., Judgment of 5 October 2009, 34 Sch
12/09 (Oberlandesgericht Munchen)]. Other authorities provide
comparable formulations of the content of the right to be heard [See,
Page 22 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
e.g., Slaney v. Int’l Amateur Athletic Foundation, 244 F.3d 580, 592
(7th Cir. 2001)].” (at p. 3225)
56. Similarly, in Redfern and Hunter (supra):
“11.73. The national court at the place of enforcement thus has a
limited role. Its function is not to decide whether or not the award is
correct, as a matter of fact and law. Its function is simply to decide
whether there has been a fair hearing. One mistake in the course of
the proceedings may be sufficient to lead the court to conclude that
there was a denial of justice. For example, in a case to which
reference has already been made, a US corporation, which had been
told that there was no need to submit detailed invoices, had its claim
rejected by the Iran-US Claims Tribunal, for failure to submit
detailed invoices! The US court, rightly it is suggested, refused to
enforce the award against the US company [Iran Aircraft Ind v Avco
Corp. 980 F.2d. 141 (2nd Cir. 1992)]. In different circumstances, a
German court held that an award that was motivated by arguments
that had not been raised by the parties or the tribunal during the
arbitral proceedings, and thus on which the parties had not had an
Page 23 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
opportunity to comment, violated due process and the right to be
heard [See the decision of the Stuttgart Court of Appeal dated 6
October 2001 referred to in Liebscher, The Healthy Award,
Challenge in International Commercial Arbitration (Kluwer law
International, 2003), 406]. Similarly, in Kanoria v Guinness, [2006]
EWCA Civ. 222, the English Court of Appeal decided that the
respondent had not been afforded the chance to present its case when
critical legal arguments were made by the claimant at the hearing,
which the respondent could not attend due to a serious illness. In the
circumstances, the court decided that ‘this is an extreme case of
potential injustice’ and resolved not to enforce the arbitral award.
11.74. Examples of unsuccessful ‘due process’ defences to
enforcement are, however, more numerous. In Minmetals Germany v
Ferco Steel, [1999] CLC 647, the losing respondent in an arbitration
in China opposed enforcement in England on the grounds that the
award was founded on evidence that the arbitral tribunal had obtained
through its own investigation. An English court rejected this defence
on the basis that the respondent was eventually given an opportunity
Page 24 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
to ask for the disclosure of evidence at issue and comment on it, but
declined to do so. The court held that the due process defence to
enforcement was not intended to accommodate circumstances in
which a party had failed to take advantage of an opportunity duly
accorded to it.
57. In Minmetals Germany GmbH v. Ferco Steel Ltd., [1999]
CLC 647, the Queen’s Bench Division referred to this ground under
the New York Convention, and held as follows:
“The inability to present a case issue Although many of those states
who are parties to the New York Convention are civil law
jurisdictions or are those which like China derive the whole or part of
their procedural rules from the civil law and therefore have
essentially an inquisitorial system, art. V of the Convention protects
the requirements of natural justice reflected in the audi alteram
partem rule. Therefore, where the tribunal is procedurally entitled to
conduct its own investigations into the facts, the effect of this
provision will be to avoid enforcement of an award based on findings
of fact derived from such investigations if the enforcee has not been
Page 25 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
given any reasonable opportunity to present its case in relation to the
results of such investigations. Article 26 of the CIETAC rules by
reference to which the parties had agreed to arbitrate provided:
‘Article 26 – The parties shall give evidence for the facts on which
their claim or defence is based. The arbitration tribunal may, if it
deems it necessary, make investigations and collect evidence on its
own initiative.’ That, however, was not treated by the Beijing court as
permitting the tribunal to reach its conclusions and make an award
without first disclosing to both parties the materials which it had
derived from its own investigations. That quite distinctly appears
from the grounds of the court’s decision – that Ferco was, for reasons
for which it was not responsible, unable ‘to state its view’. Those
reasons could only have been its lack of prior access to the sub-sale
award and the evidence which underlay it. I conclude that it was to
give Ferco’s lawyer an opportunity to refute this material that the
Beijing court ordered a ‘resumed’ arbitration.” (at pp. 656-657)
Page 26 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
21. The tribunal has relied upon the documents which has been disputed by
the other side without giving an opportunity to substantiate or disprove certain
entries made in the software and the conclusion of the tribunal is merely on the
basis of such documents, without an opportunity being granted and the same
certainly violates the procedure contemplated under section 34[2] [a] of the
Arbitration and Conciliation Act. Since the petitioner was not given an
opportunity to present their case, besides, the statements and documents not being
communicated to the petitioner and the same has been relied upon by the tribunal
and no opportunity has been given to disprove the contents of the documents,
particularly when the data and the entries have been denied by the petitioner
herein, this Court is of the view that the award of the arbitral tribunal extending
time without proper opportunity is liable to be interfered.
22. It is relevant to note that the dispute with regard to the other claims,
cost related claims are still pending before the arbitral tribunal. Though these
awards have been passed separately in respect of extension of time, since, the main
dispute in respect of various monetary claims are pending before the arbitral
Page 27 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
tribunal, the learned Arbitral Tribunal ought to have decided all the disputes in the
same proceedings instead of passing separate award for extension of time alone.
Since, the main dispute is still pending before the Arbitral Tribunal, it is well open
to the claimant to prove the documents and claim extension of time in the existing
proceedings. The learned arbitral tribunal can very well give an opportunity to the
parties in respect of extension of time sought by the claimant. After affording
proper opportunity to both sides, extension of time can be decided in the existing
claim itself which are pending before the arbitral tribunal in both the contracts
viz., UAA 05 and UAA 01. In such view of the matter, this Court is of the view
that the claimant instead of going for mere extension of time before the tribunal,
they ought to have referred the entire dispute including extension of time. As this
Court has found that no opportunity has been given and unmarked documents
have been relied upon by the tribunal, the award passed by the tribunal in both the
matters are liable to be set aside.
23. Accordingly, these Original Petitions are allowed and the award passed
by the arbitral tribunal in both the matters are set aside. The parties are at liberty
Page 28 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
to claim extension of time in the existing proceedings pending before the arbitral
tribunal. Consequently, connected applications are closed.
28.10.2021
vrc
Page 29 / 30
https://www.mhc.tn.gov.in/judis Original Petition Nos.96 & 97 of 2021
N. SATHISH KUMAR, J.
vrc
Common Order in:
ARBITRATION ORIGINAL PETITION Nos.96 & 97 of 2021
28.10.2021
Page 30 / 30
https://www.mhc.tn.gov.in/judis
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!