Monday, 11, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.Zillion Infraprojects Pvt ... vs Bharat Heavy Electricals Limited
2021 Latest Caselaw 15200 Mad

Citation : 2021 Latest Caselaw 15200 Mad
Judgement Date : 29 July, 2021

Madras High Court
M/S.Zillion Infraprojects Pvt ... vs Bharat Heavy Electricals Limited on 29 July, 2021
                                                                                      O.P.No.161 of 2017

                                     IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                       DATED: 29/7/2021

                                                           CORAM

                                   THE HONOURABLE Mr.JUSTICE N.SATHISH KUMAR

                                                     Arb.O.P.No.426 of 2021

                     M/s.Zillion Infraprojects Pvt Ltd
                     (formerly known as Durha Constructions Private Limited)
                     rep. by its Authorised Representative
                     5th Floor, Anushka Shopping Mall
                     Plot No.2 Garg Trade Centre
                     Sector 11, Rohini
                     New Delhi 110 085.                    ...       Petitioner

                                                               Vs

                     Bharat Heavy Electricals Limited
                     Power Sector Southern Region
                     Tek-Towers, No.11, Old Mahabalipuram Road
                     Okkiyam
                     Thoraipakkam
                     Chennai 600 097.                  ...                    Respondent



                                   Original Petition has been filed under Section 11 (4) & (6) of the

                     Arbitration and Conciliation Act, 1996, to appoint an Arbitrator to hear and

                     decide the disputes between the parties arising out of LOI through Fax

                     bearing No.BHEL:PSSR:SCT:1319, dated 11/16.3.2009.

                     1/8


https://www.mhc.tn.gov.in/judis/
                                                                                       O.P.No.161 of 2017




                                   For petitioner          ...         Mr.S.Vijay Kumar

                               For respondent              ...         Mr.Chethan Sagar

                                                             ------
                                                            ORDER

This Arbitration Original Petition has been filed to appoint an

Arbitrator to hear and decide the disputes between the parties arising out of

LOI through Fax bearing No.BHEL:PSSR:SCT:1319, dated 7/7/2009.

2. Heard Mr.S.Vijayakumar, learned counsel for the petitioner and

Mr.Chethan Sagar, learned counsel for the respondent.

3. The respondent had issued a notice inviting Tender, for handling

of site stores/storage yard, transportation to site of work, erecting, testing &

commissioning of complete Boiler structures, pressure parts, etc. The date

of contract is 6/11/2007. The period of completion is originally eight

months. The work was completed only on 30/9/2010. The petitioner

claimed extra expenses of Rs.7,27,066 and again laid a claim on 14/11/2013

https://www.mhc.tn.gov.in/judis/ O.P.No.161 of 2017

for a sum of Rs.9,90,53,560/- (Rupees Nine crores ninety lakhs fifty three

thousand five hundred and sixty only). However the respondent had

rejected the claim of the petitioner, by letter, dated 26/6/2014, on various

grounds. Thereafter, the petitioner, made a representation to the respondent

for making the payment towards claim and dispute. Again the petitioner

was invited for negotiation by the respondent, on 9/4/2015. Negotiation

had continued till 6/10/2016. In the year 2018, the petitioner Company

went on liquidation and thereafter, the appointment of Interim Resolution

Professional was confirmed as Resolution Professional (RP) by the Tribunal

on 22/4/2019. After the appointment of Interim Resolution Professional,

Committee of Creditors was formed and steps were taken for resuming talks

with the respondent. Though the petitioner has sent a letter, dated 9/3/2021

calling upon the respondent to nominate an Arbitrator, no steps have been

taken by the respondent. Hence the petitioner has come forward with the

present Arbitration Original Petition.

4. Counter affidavit was filed by the respondent, wherein it is stated

https://www.mhc.tn.gov.in/judis/ O.P.No.161 of 2017

that the maintenance period/guarantee period of the Contract stood

completed on 13/2/2012. The arbitration clause ought to have been invoked

within three years from the said date, present Arbitration Original Petition

and the claims made by the petitioner are clearly barred by limitation.

5. It is further stated in the counter affidavit that the scope of work

was completed and all payment obligations were fulfilled by the respondent.

After seven years, all of a sudden, the petitioner has invoked the arbitration

clause, contained in the Contract, vide, its letter, dated 9/3/2021, is clearly

barred by limitation.

6. It is the further contention that this claim is only with regard to the

damages when the claim itself is repudiated and rejected in the year 2014

invoking arbitration in the year 2021 would not be permissible and the

claim is hopelessly barred.

7. The main submission of the learned counsel for the petitioner is

that the petitioner has a claim of Rs.9,90,53,560/- against outstanding bills

https://www.mhc.tn.gov.in/judis/ O.P.No.161 of 2017

and claims against the respondent for the work done as per the contract and

the same is not yet paid by the respondent.

8. From the materials available on record, it is clear that the factors

of of rejection of claims was informed to the petitioner, vide respondent's

letter, dated 26/6/2014. Appointment of an Arbitrator is sought for to enter

into the reference with regard to the dispute said to have been arisen in

respect of the damages payable by the respondent. It is not disputed by the

petitioner that the final bill has already settled as early as on 26/11/2014.

What was sought to be agitated is only for damages. The claim for damages

was rejected in the year 2014 itself. Though there are subsequent

correspondence, inviting the petitioner for negotiation, mere exchange of

correspondence and negotiation will not automatically extend the period of

limitation. The rejection was admittedly made in the year 2014. Therefore,

any such claim or damages ought to have been made within three years from

the date of rejection.

https://www.mhc.tn.gov.in/judis/ O.P.No.161 of 2017

9. The Hon'ble Supreme Court, in a judgment of UTTARKHAND

PURV SAINIK, KALYAN NIGAM LIMITED Vs. NORTHERN COAL

FIELD LIMITED (2020) 2 SCC – 455), has held that the limitation is a

mixed question of fact and law. The issue of limitation being a

jurisdictional issue, can be decided by the Tribunal, under Section 16 of the

Act.

                                   10.    In    the judgment of the Hon'ble Apex Court in

                     SECUNDERABAD                       CANTONMENT               BOARD              Vs.

B.RAMACHANDRAIAH & SONS (Civil Appeal Nos.900-902 of 2021)

dated 15/3/2021, considering the various judgments including the

UTTARAKHAND PURV SAINIK, KALYAN NIGAM LIMITED, has held

that Application under Section 11 of the Act, themselves being hopelessly

time barred, no arbitrator could have been appointed by the High Court.

11. In view of the decision rendered by the Hon'ble Supreme Court,

in SECUNDERABAD CANTONMENT BOARD Vs.

B.RAMACHANDRAIAH & SONS, this Court is of the considered view

https://www.mhc.tn.gov.in/judis/ O.P.No.161 of 2017

that appointing an arbitrator in this instant Arb.O.P., is nothing but a futile

exercise. Accordingly, this Arbitration Original Petition is dismissed.

29/7/2021

mvs.

https://www.mhc.tn.gov.in/judis/ O.P.No.161 of 2017

N.SATHISH KUMAR,J

mvs.

Arb.O.P.No.426 of 2021

29/7/2021

https://www.mhc.tn.gov.in/judis/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter