Sunday, 10, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Chief Project Manager vs Trimurthi Hi-Tech Company Pvt. ...
2021 Latest Caselaw 15076 Mad

Citation : 2021 Latest Caselaw 15076 Mad
Judgement Date : 28 July, 2021

Madras High Court
The Chief Project Manager vs Trimurthi Hi-Tech Company Pvt. ... on 28 July, 2021
                                                         1




                                   IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                DATED : 28.07.2021

                                                      CORAM:

                                   THE HONOURABLE MR.JUSTICE N. SATHISH KUMAR

                                                 O.P.No.638 of 2019

                1. The Chief Project Manager,
                   Railway Electrification,
                   Egmore, Chennai – 600 008.

                2. Central Organisation for
                   Railway Electrification
                   No.1, Nawab Yusuf Road,
                   Civil Lines, Allahabad- 211 001.
                   Uttar Pradesh State.                                   ..            Petitioners

                                                          .Vs.

                Trimurthi Hi-Tech Company Pvt. Ltd.,
                Rep. by its Director,
                Old No.56, New No.88,
                1st Floor, Maddox Road,
                Choolai, Chennai – 600 112.                               ..           Respondent

                                                        ***

                Prayer: Petition filed under Section 34 (2) (a) (iv), (b) (ii) of the Arbitration and
                Conciliation Act, 1996 praying to set aside the Arbitral Award passed by the
                learned Arbitrator herein dated 29.07.2019 made in relation to disputes arising out
                of Letter of Acceptance No.ELCORE/T/OHE/Gr.126(R&C)-1 dated 09.03.2009.
                                                       ***


https://www.mhc.tn.gov.in/judis/
                                                           2




                                   For Petitioners   :   Mr.P.T.Ramkumar

                                   For Respondent    :   Mr.S.Raghavan


                                                        ORDER

This Petition has been filed challenging the Award dated 29.07.2019 passed

by the learned Sole Arbitrator in respect of the dispute that arose between the 1st

respondent and claimant with regard to agreement dated 15.05.2009. The letter of

Acceptance (LOA) relating to Design, Supply, Erection, Testing and

Commissioning of 25 KV single Phase AC 50 Hz Traction Overhead Equipments,

Switching Stations, Booster Transformer Stations and LT Supply Transformer

Stations in Two chords between Bangalore-Chennasnadra loop via Hebbal Section

and Yeshwantpur Chikbanavar Section along with bypass line between

Lottergollahalli and Chikbanavar Section of S.W.Railway Group.126 (R&C) – 1.

2. Though the work had to be completed within six months, due to delay in

the project, the work could not be completed and therefore, several extensions

were granted. These extensions were granted under Clause 17 (B) of the General

Conditions of Contract. Hence, it is the contention of the claimant that the levy of

liquidated damages and also the penalty as per the contract is not correct and

https://www.mhc.tn.gov.in/judis/

hence sought refund of a sum of Rs.47,26,310/- levied by the respondent.

3. The respondent filed a counter stated that the entire delay had to be

attributed to the contractor and despite several extensions having been granted,

nearly 11 extensions, finally, the work came to be concluded only on 18.07.2011.

While granting extensions under General Conditions of Contract as per the

contract, the claimant was ordered notice with regard to the penalty that could be

imposed as per the contract and these extensions were granted invoking the Clause

17 (A) of General Conditions of Contract without imposing any penalty and these

extensions have been sought by the respondent. The learned Sole Arbitrator

framed the issues and finally passed the award directing the respondent to return a

sum of Rs.47,26,310/- on the ground that delay was not entirely due to fault of the

claimant. Further no evidence was let in by the applicant to prove loss.

Challenging the same present application filed.

4. Mr.P.T. Ramkumar, learned counsel appearing for the petitioners would

mainly canvass that though the General Conditions of Contract provides for

levying Liquidated Damages, there is no evidence available on record to prove the

https://www.mhc.tn.gov.in/judis/

loss of damages. As far as the penalty imposed in this regard, the contract clearly

provides for the imposition of such penalty. The learned Arbitrator ignored the

contractual terms agreed between the parties while passing award. Therefore, he

prays to set aside the award.

5. The learned counsel relied upon the judgment of the Hon'ble Supreme

Court reported in AIR 2003 SC 2629 (Oil & Natural Gas Corporation Ltd., Vs.

Saw Pipes Ltd.,) and contended that the terms clearly and unambiguously

stipulate the liquidated damages in case of breach of the contract. The employer

is entitled to recover from the contractor the penalty as agreed.

6. The learned counsel for the respondent submitted that the learned

Arbitrator has considered the entire aspect and also the evidence and found that

there is no evidence for legal injury or damages sustained by the Railways on

account of delay. The learned Arbitrator has recorded the factual findings. This

Court exercising its powers under Section 34 of the Arbitration and Conciliation

Act cannot interfere with the award by re-appreciating the entire evidence. Hence,

submitted the award cannot be interfered with and relied upon the judgment of the

https://www.mhc.tn.gov.in/judis/

Hon'ble Apex Court reported in AIR 1963 SC 1405 (Fateh Chand Vs. Balkishan

Das) and 2005 (4) MLJ 86 (Ennore Port Limited (Successor of Chennai Port

Trust with regard to the Ennore Port Project) Vs. Hindustan Construction

Company Limited and Ors). It is not disputed by both sides that though the

original contract stipulates the period of six months to complete, the work on

account of various factors, the work came to be completed only on 18.07.2011. In

the mean while, 11 extensions were granted by the Railways and six extensions

were granted under Clause 17 (a) of General Conditions of Contract. It is relevant

to extract Clause 1.2.45 which reads as follows:

“Extension of Time 1.2.45:

If such a failure as aforesaid shall have from any cause which the

Purchaser may admit as being a reasonable ground for extension of time,

the General Manager/ Chief Electrical Engineer or his successor (s) /

nominee shall allow such additional time as he may in his absolute

discretion consider to be reasonably justified by the circumstances of the

case. Such extension shall be granted by the Purchaser in the Form No.18

(Part – V). The Contractor will apply for extension at least two months

before the expiry of the period of completion.

https://www.mhc.tn.gov.in/judis/

The Competent Authority while granting extension to the currency of the

contract under Clause 17 (B) of the GCC may also consider levy of token

penalty as deemed fit based on the merit of the case”

Clause 1.2.44 which reads as follows:

If the Contractor fails to execute and complete the work within the time

specified in the Agreement or within the period of extension granted under

Para 1.2.45 except, in so far as the delay is on the Purchaser's account, the

Contractor shall accept reduction in the total amount payable to him by the

Purchaser upto the maximum rate of Rs.4,000/- per day for the actual

delay occasioned beyond the appointed time by which the work shall have

been completed under the contract. Such reduction shall be accepted by

the Purchaser in full satisfaction of the Contractor's liability arising from

delay only. This recovery for delay in completion will be applicable

separately for each stage of completion of overhead equipment, switching

stations or booster transformer stations when two or more stages of

completion are specified in the contract. The General Manager or his

successor shall at his sole discretion specify a time limit within which the

unfinished portion of the work shall be completed after serving on

contractor a notice of the Purchase's intention to effect the said recovery in

https://www.mhc.tn.gov.in/judis/

the Form 17 (Part-IV). In the event of failure of the Contractor, the

Purchaser shall be at liberty to take action in accordance with provisions

in Para 1.2.29 and 1.2.30.

7. The above Clause stipulates that total amount payable by the purchaser as

a penalty at the maximum rate of 4,000/- per day for the actual delay of 61 days.

The power of the competent authority while granting the extensions under Clause

17 (b) of the General Conditions of Contract, is not absolute. Only on taking into

consideration of the facts and circumstances, the competent authority can levy a

token penalty, on the basis of the merit of every case. The learned Arbitrator has

also taken note of Performance Certificate issued by the Railways and has

observed that “the work was stopped intermittently on Railway's account and not

on Contractor's account due to abnormal increase in quantities of work in certain

cases and subsequent delay in approval of assessment. Further, there were cases

where works could not be progressed for want of Tower Wagon and blocks from

the Railway's side. On the whole performance to do the OHE works at the rate of

3 Kms per month on an average is hereby acknowledged” by Railways.

https://www.mhc.tn.gov.in/judis/

8. The learned Arbitrator finally on the basis of the evidence found that

there is no legal injury or loss sustained by the Railways. Though, the General

Conditions of Contract provides the penalty as well as damages, the learned

Arbitrator took note of law declared in the case of Fateh Chand Vs. Balkrishnan

Das reported in AIR 1963 SC 1405 which reads as follows:

.... It does not justify the award of compensation when in consequence of

the breach no legal injury at all has resulted, because compensation for

breach of contract can be awarded to make good loss or damage which

naturally arose in the usual course of things, or which the parties knew

when they made the contract, to be likely to result from the breach.

.... The Court has to adjudge in every case reasonable compensation to

which the plaintiff is entitled from the defendant on breach of the contract.

Such compensation has to be ascertained having regard to the conditions

existing on the date of the breach. There is no evidence that any loss was

suffered by the plaintiff in consequence of the default by the defendant save

as to the loss suffered by him by being kept out of possession of the

property.

https://www.mhc.tn.gov.in/judis/

... The plaintiff failed to prove the loss suffered by him in consequence of

the breach of the contract committed by the defendant, and we are unable

to find any principle on which compensation equal to ten percent of the

agreed price could be awarded to the plaintiff”

9. In the Judgment reported in 2005(4) MLJ 86 (Ennore Port Limited,

(Successor of Chennai Port Trust with regard to the Ennore Port Project) Vs.

Hindustan Construction Company Limited and Ors.) Hon'ble Division Bench of

this Court found that invoking the Clause under General Conditions of Contract

and Clause as well as penalty without proving the legal injury or loss by the

Railways is not sustainable under law and passed an award.

10. Though the learned counsel appearing for the Railway has placed much

emphasis on the ONGC & Sawpipes and the same is not applicable to the facts of

the present case It is to be noted that in the above case, nature of legal injuries

suffered by ONGC was clearly established on record and the Hon'ble Apex Court

taking note of the contractual terms, allowed the imposition of the penalty as per

the contract. Whereas, in this case as noted by the learned Arbitrator, no evidence

was let in by the respondent at any point of time that there was any legal injury or

https://www.mhc.tn.gov.in/judis/

loss. In such view of this matter, when the law in this aspect is very clear that

without establishing legal injury or loss, liquidated damages is not permissible and

the liquidated damages by way of penalty is also not permissible. This Court finds

no infirmity in the order passed by the learned Arbitrator and none of the ground is

made out under Section 34 of Arbitration and Conciliation Act to interfere with

the award by the learned arbitrator.

Accordingly, this Original Petition is dismissed. No costs.

28.07.2021

Index : Yes / No Internet: Yes Speaking/Non-speaking order dh

https://www.mhc.tn.gov.in/judis/

N. SATHISH KUMAR, J.

dh

order in:

O.P.No.638 of 2021

28.07.2021

https://www.mhc.tn.gov.in/judis/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter