Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

S.P.Senthil vs The Divisional Railway Manager ...
2021 Latest Caselaw 14015 Mad

Citation : 2021 Latest Caselaw 14015 Mad
Judgement Date : 14 July, 2021

Madras High Court
S.P.Senthil vs The Divisional Railway Manager ... on 14 July, 2021
                                                                                     O.P.No.670 of 2019

                                IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                  DATED : 14/7/2021

                                                      CORAM

                             THE HONOURABLE Mr.JUSTICE N.SATHISH KUMAR

                                                  O.P.No.670 of 2019

                      S.P.Senthil                          ...          Petitioner

                                                          Vs

                      The Divisional Railway Manager (Works)
                      Salem Division
                      Southern Railway
                      Salem 636 005.                     ...            Respondent


                             Original Petition has been filed under Section 24 of the Arbitration

                      and Conciliation Act, 1996, to set aside the Award of the learned Tribunal,

                      dated 2/8/2018, in the Arbitration proceedings between the petitioner and

                      respondent.

                             For petitioner                ...    Mr.A.Vikash

                             For respondent                ...    Mr.P.T.Ramkumar
                                                                  Standing Counsel


                                                        ------


                      1/14


http://www.judis.nic.in
                                                                                     O.P.No.670 of 2019




                                                        ORDER

This Original Petition has been filed under Section 34 of the

Arbitration and Conciliation Act, 2015, to set aside the Award of the learned

Tribunal, dated 2/8/2018, in the Arbitration proceedings between the

petitioner and respondent.

2. The brief facts leading to the filing of this Original Petition are as

follows:-

. The tender offer of the claimant for the works, such as Collecting,

supply and stocking of 50 mm machine crushed Ballasts, Loading of

Ballasts into Railway Hoppers/Wagon, Unloading of Ballast fro

Hoppers/wagon etc., at Depots such as Lalapet Depot, Kodumudi Depot

Minnampalli Depot, Kallar Depot and Ketti Depot under ED-TP, SA- VRI

and MTP-UAM section, in Salem Division, was accepted by the respondent,

i.e., DRM/Works/Salem and was issued with Letter of Acceptance

No.SA/W.148/274, dated 20/7/2020, to a total value of Rs.3,14,10,000/-.

http://www.judis.nic.in O.P.No.670 of 2019

The completion period for the work was eleven months, from the date of

issuance of Letter of Acceptance, i.e., from 20/7/2010.

3. Immediately, after Letter of Acceptance, when he wanted to

commence the work at Kodumudi Station and other places, it was noticed

that there was no space for collection of Ballast and could collect Ballast

only after four months. When the petitioner has requested the respondent to

identify the places at various depots and to earmark the same to start with

the collection of ballast, it was informed that he should wait for some more

time to get some space.

4. Similarly at Meenapalli Depot, there was no space available and

the area was full, since the ballast was being collected by some other

agencies. Similarly at Ketti and Kallar also no space is available to collect

the ballast. There was a delay of three months in allotting the place.

Thereafter, the petitioner was advised, by the Engineer, vide letter, dated

16/12/2010, to commence the work and to complete the same and further, it

was informed by the Engineer that if the measurements are recorded and

http://www.judis.nic.in O.P.No.670 of 2019

bills are prepared, due to financial constraints and non allotment of funds for

the work, the payments would be delayed. Details of ballast collected at

various depots by the petitioner are as follows:-

                               DEPOT       AGT.       SAMPLE    APPX.         REMARKS
                                           QTY         TEST    SUPPLY
                                                                MADE
                             Kodumudi      20,000      Done      10,000 Copy of test certificate
                                                                        not given
                             Lalapettai    20,000 Not done        3,000
                             Minnampalli    5,500      Done       2,600 Copy of test certificate
                                                                        not given
                             Kallar         3,000 -                  Nil Site not given
                             Ketti          3,000 -                  Nil Site not given



5. In the meanwhile, seven days notice was issued for termination of

the contract. Without assessing the exact situation and also considering the

circumstances, contract was terminated, on 16/5/2011, which was much

before expiry of currency. A new Open Tender was called, on 18/5/2011.

This itself indicate that the respondent had determined to terminate the

petitioner irrespective of any reason.

http://www.judis.nic.in O.P.No.670 of 2019

6. It is the contention of the respondent before the Arbitrator that the

petitioner has not furnished the Performance Guarantee, as a result, the

agreement could not be executed, denying that the respondent had advised

the petitioner to wait for some time. It is stated that the petitioner had

collected the first ballast sample of 100 cum for the purpose of testing. The

petitioner had collected the ballasts, on 1/10/2010, 24/4/2011 and

26/1/2011. As far as Kallar and Ketti, though depot was available for

collecting test ballasts, there was no progress. Hence, it is the contention

that despite the space is available, the work was not progressed by the

claimant. Hence it is the contention that despite earlier notices of

termination issued and several opportunities were given to the petitioner to

complete the supply of Ballasts, no progress has been shown. Vide, letter,

dated 16/5/2011, contract was terminated. The petitioner had raised the

following claims:-

CLAIMS

1 REFUND OF EMD: Since the Rs.3,45,000 department could not identify the space in the deport and also in

http://www.judis.nic.in O.P.No.670 of 2019

some of the depot the space was occupied by some of the contractors and hence I was advised not to collect the ballast there. As such the termination is totally illegal and not justified. Hence, the EMD mentioned above has to be refunded.

2 Compensation for not allowing me Rs.31,41,000 to do the work at 10% of the Agreement value if I had been allowed to do the work duly indentifying the space, I could have realized at least a minimum of 10% profit. Hence, the same is claimed i.e., 10% of Rs.3,14,10,000.

3. Idling of Machinery is calculated @ Rs.6,28,200 2% of the Agreement value i.e., I had paid advances for machinery like tipper lorries and Other machineries which will not be refunded to by them. Hence, the same is claimed

4. Idling of Man power – This is Rs.15,70,500 calculated @ 5% of the Agreement value since I had recruited supervisors and watchmen etc., and since the ballast could not be collected, I had to pay them the wages thereon hence 5% is claimed.

5. The ballast already collected at 3 ----

places i.e., Lalapet & KMN Minampally will have to be measured and payment made to Me as per actual. The value of the ballast collected as per actual will

http://www.judis.nic.in O.P.No.670 of 2019

have to be paid to be or I may be permitted to take back the ballast -

                                           Declaratory
                                  6.       The damages caused to be                  Rs.9,42,300
                                           consequent on the fact that I was
                                           not allowed to do the work by way of
                                           other aspects @ 3% of the
                                           Agreement value. Also I have lost
                                           my credentials which cannot be
                                           recouped.
                                  7.       To declare that the termination is               -----
                                           illegal - Declaratory
                                  8.       Interest @ 18% p.a., on the above is             -----
                                           to be quantified.



7. Learned Arbitrator, discussed all the claims, except column No.4,

wherein the relief was sought to take back the supply of Ballasts by the

petitioner which was allowed by the learned Arbitrator. The other aspects

for claiming the compensation has been dismissed.

8. Being aggrieved, the petitioner has come forward with the instant

Original Petition, praying for the relief as stated therein.

9. Heard Mr.A.Vikash, learned counsel for the petitioner and

Mr.P.T.Ramkumar, learned Standing Counsel for the Railways.

http://www.judis.nic.in O.P.No.670 of 2019

10. Though various grounds have been raised to challenge the award,

the main contention put forth by Mr.A.Vikash, learned counsel appearing

for the petitioner is that the respondent has not followed the procedure,

provided in the contract before invoking Clause 62 of General Conditions of

Contract.

11. Learned counsel appearing for the petitioner further submitted

that there was a delay in handing over of possession for more than three

months by the Railways, which has not been taken note of by the learned

Tribunal.

12. It is his further contention that sub-Clause 3 of Clause 17 of

General Conditions of Contract, stipulates that in the event of any failure or

delay by the Railway to handover the Contractor possession of the lands

necessary for the execution of the works, Railways has to necessarily extend

http://www.judis.nic.in O.P.No.670 of 2019

the time. 17 - B of the General Conditions of Contract also provides for

extension of time, in the event of delay caused by the Contractor. When the

General Conditions of Contract itself stipulates for extension of time, Letter

of Acceptance stipulate 11 months time, same cannot be considered, as

'Time is essence of contract'.

13. He further submitted that as long as the extension is not applied,

as per General Conditions of Contract, the termination of the contract by

invoking Clause 62 of General Conditions of Contract is not valid,

according to law.

14. In support of his submission, the learned counsel appearing for

the petitioner, relied on the judgment of the Hon'ble Supreme Court, in

AROSAN ENTERPRISES LTD. Vs. UNION OF INDIA & ORS (1999)

9 SCC – 449, wherein it was held that when the contract itself provides for

extension of time, the same cannot be termed to be the essence of contract.

15. Mr.Ramkumar, learned Standing Counsel for Railways submitted

http://www.judis.nic.in O.P.No.670 of 2019

that the petitioner has not even granted a Performance Guarantee, as agreed

in Letter of Acceptance, as a result, agreement even could not be executed.

The work has not been completed within a stipulated period and though

several opportunities were given, there was no progress done. It is not that

his conduct was terminated for the first time. Respondent has given seven

days notice and 48 days notice thrice. As there was no progress shown by

the petitioner, finally, following the procedure, by issuing 7 days notice and

48 days notice, as contemplated under Clause 62 of the General Conditions

of Contract, contract was terminated, on 16/5/2011.

16. He further submitted that Tribunal has considered the entire

aspects factually and directed the petitioner to produce documentary

evidence for idling of Men and Machinery. Since the petitioner had not

produced any documentary evidence to substantiate his claim, the Tribunal

has rightly dismissed the claim for compensation.

17. As far as the termination of the contract, the Tribunal has

http://www.judis.nic.in O.P.No.670 of 2019

factually found that prior to the termination, notices were issued thrice,

following Clause 62 of General Conditions of Contract. Despite the same,

no progress has been shown. Hence, the learned Standing Counsel for the

Railways submitted that there is absolutely no ground made out to interfere

with the well reasoned order.

18. In fact, even though the Tribunal had granted relief to the

petitioner to take back the supply of ballasts, he has not arranged for any

labour force to stack the ballast. Hence prayed for dismissal of this Original

Petition.

19. The award can be set aside, under Section 34 of the Act, only on

the following limited grounds.

(i). Incapacity of the party

(ii). Invalidity of the arbitration agreement

(iii). Absence of proper notice for appointment of an arbitrator

(iv). Non arbitrability of disputes

http://www.judis.nic.in O.P.No.670 of 2019

(v). Composition of the arbitral not being in accordance with the agreement.

(vi). Subject matter not capable of being settled by way of arbitration

(vii). Award is in conflict with the public policy of India and

(viii). the award is vitiated by the patent illegality.

20. Therefore, it is well settled that Public Policy of India would

mean the fundamental policy of Indian law, i.e, disregarding orders of

superior Courts in India would be regarded as being contrary to the

fundamental policy of Indian law.

21. Similarly, the patent illegality, as discussed in the above judgment

must go to the root of the matter. Admittedly, within the contract period,

the entire quantity was not supplied. Even sample of ballasts has not been

supplied to the depot. Arbitrary Tribunal also found that the petitioner was

issued with three seven days notices, i.e., on 22/12/2020, 25/1/2011 and

28/2/2011 and one 48 hours notice i.e., on 14/3/2011. Thereafter, contract

was terminated, on 16/5/2011. The termination has been done, taking note

of the failure, on the part of the contract to supply required quantity.

http://www.judis.nic.in O.P.No.670 of 2019

Though there is a Clause providing for extension of time, it is to be noted

that such extension of time can be applied, after the expiry of the contract

period. Therefore, it cannot be said that termination notice issued by the

respondent cannot be valid in the eye of law. Arbitral Tribunal, recorded the

factual finding and found that delay was on the part of the contractor and

he has not supplied the requisite materials, as per Letter of Acceptance.

Therefore, this Court do not find any infirmity in the order passed by the

Arbitrary Tribunal.

22 . In such a view of the matter, no ground has been made to

interfere with the well reasoned award passed by the Arbitrary Tribunal.

Accordingly, this Original Petition is dismissed. It is also stated by the

learned counsel appearing for the petitioner that the respondent is not

cooperative to remove the supplied Ballasts from yards in different depots.

Such submission was opposed by the learned counsel for the respondent and

stated that Officers sent three letters in this regard. Despite the letters sent

by the Officers, the petitioner has not removed Ballasts. Now, the learned

counsel for the Railways submitted that even now, they have no objection

http://www.judis.nic.in O.P.No.670 of 2019

for removing the ballasts.

N.SATHISH KUMAR,J

mvs.

23. In such a view of the matter, the petitioner is permitted to remove

all the ballasts from the respective depots, within a period of four months,

finally, from the date of receipt of a copy of this order and the same is

granted only, at the request of the learned counsel for the petitioner, taking

note of the pandemic situation prevailing.

14/7/2021

mvs.

Index: yes/No

Internet: yes/No

Speaking/Non-speaking order

O.P.No.670 of 2019

http://www.judis.nic.in

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter