Sunday, 10, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Dharani Hi-Tech Projects (P) ... vs The General Manager
2021 Latest Caselaw 23648 Mad

Citation : 2021 Latest Caselaw 23648 Mad
Judgement Date : 2 December, 2021

Madras High Court
M/S. Dharani Hi-Tech Projects (P) ... vs The General Manager on 2 December, 2021
                                                                    O.S.A.(CAD) No. 120 of 2021



                                  IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                DATED: 02.12.2021

                                                    CORAM :

                                  THE HON'BLE MR.MUNISHWAR NATH BHANDARI,
                                             ACTING CHIEF JUSTICE
                                                       AND
                                    THE HON'BLE MR.JUSTICE P.D.AUDIKESAVALU


                                           O.S.A.(CAD) No. 120 of 2021

                     M/s. Dharani Hi-tech Projects (P) Ltd.,
                     Railway Contractors,
                     No. 28, Annavasal Street,
                     Maargudi - 614 001,
                     Tiruvarur District,
                     Tamil nadu,
                     Represented by its Managing Director           .. Appellant/Respondent

                                                        vs

                     1. The General Manager,
                        Southern Railway,
                        Head Quarters Office,
                        Park Town,
                        Chennai - 600 003.

                     2. The Deputy Chief Engineer/II,
                        Gauge Conversion,
                        Southern Railway, Construction,
                        Thiruchirappalli - 620 001.             .. Respondents/Petitioners




                     ___________
                     Page 1 of 11


https://www.mhc.tn.gov.in/judis
                                                                          O.S.A.(CAD) No. 120 of 2021



                     Prayer: Appeal under Clause 15 of the Letter Patent read with Order
                     XXXVI, Rule 1 of O.S. Rules to set aside the Judgment and Decree
                     dated 11.05.2020 passed by the Learned Judge passed in O.P. No.
                     1045 of 2017 on the file of the Original Side of this Court and thereby
                     upholding the award of the Learned Arbitrator dated 11.09.2017 as far
                     as the award related to claim for damages for non-execution of the
                     contract, Claim No. 3 concerned.


                                      For the Appellant        : Ms. K.Aparna Devi

                                      For the Respondents     : Mr. P.T.Ramkumar,
                                                                Standing Counsel
                                                           ORDER

(Order of the Court was made by the Hon'ble Acting Chief Justice)

The appeal has been filed under Section 37 of the Arbitration and

Conciliation Act, 1996 to challenge the order dated 11.05.2020 in

O.P.No.1045 of 2017 passed by the learned single Judge on an

application under Section 34 of the Act of 1996.

2. It is a case where the appellant after invoking the clause of

arbitration, made an application thereupon submitting a claim. After

completion of the pleading, the learned Arbitrator framed the issues

___________

https://www.mhc.tn.gov.in/judis O.S.A.(CAD) No. 120 of 2021

and considered the matter in reference to different claims. An award

thereupon was passed on 11.09.2017 accepting the claim in the

manner indicated therein.

3. The respondents herein made an application under Section 34

of the Act of 1996 raising objection against the award. While pressing

the application, the respondents restricted the application under

Section 34 of the Act of 1996 only in reference to claim no.3 decided

by the learned arbitrator. The learned single Judge accepted the

application and, accordingly, the claim awarded by the learned

Arbitrator in regard to claim no. 3 was set aside.

4. The facts of the case show that the agreement between the

parties was for performance of work. It is stated that the railways

defaulted in making the land available for performance of the work

and, accordingly, they granted seven extensions from time to time to

perform the work. The appellant had undertaken the work and even

completed the same to the extent of 80%, but thereupon the

agreement was terminated by the railways in an arbitrary and

unreasonable manner. The learned Arbitrator was approached not only

___________

https://www.mhc.tn.gov.in/judis O.S.A.(CAD) No. 120 of 2021

to challenge the termination of the agreement, but to claim

consequential benefits, apart from claims made towards loss of profit

occurred due to termination of the agreement by the railways in an

illegal manner. The learned Arbitrator found the termination of the

contract to be illegal and, accordingly, allowed the claim for loss of

profit assessing it to be 15% of the amount of unexecuted value of

work. The determination of the amount of loss of profit was after

recording the finding that the termination of the contract was illegal

and considering the facts given therein. However, the learned single

Judge interfered with the award and held that there was no pleading to

show basis for the claim for loss of profit and even no factual basis was

disclosed by the learned Arbitrator for the award of amount towards

loss of profit. Accordingly, the application under Section 34 of the Act

of 1996 was accepted to that extent, while not accepting the prayer of

the appellant for remand of the case to the learned Arbitrator if no

reason was assigned for the same.

5. Learned counsel for the appellant submits that once the

termination of contract was held to be illegal, the appellant was

entitled to get the claim on loss of profit as determined by the learned

___________

https://www.mhc.tn.gov.in/judis O.S.A.(CAD) No. 120 of 2021

Arbitrator. It was after taking into consideration the finding with regard

to issue in claim nos. 1 and 2 holding that the termination of contract

is illegal that the claim no.3 was allowed by the learned Arbitrator and,

therefore, the order of the learned single Judge should be set aside

making award of the learned Arbitrator to be absolute. Reference of

few judgments was given to justify the award of loss of profit to the

extent of 15% of the amount of unexecuted value of work. Those

judgments could be considered by the Court while dealing with the

argument of the non-appellants.

6. The appeal has been opposed by learned counsel for the

non-appellants. It is submitted that the learned Single Judge did not

find any pleading or evidence to allow loss of profit and even

otherwise, no reason was assigned by the learned Arbitrator to award

15% of the amount of unexecuted value of work towards loss of profit

and thereby, the learned single Judge rightly set aside the award in

regard to claim no. 3. It is further stated that so far as the award of

other amounts to the appellant is concerned, that has already been

satisfied other than the amount awarded towards loss of profit. The

prayer is to dismiss the appeal for the aforesaid reason.

___________

https://www.mhc.tn.gov.in/judis O.S.A.(CAD) No. 120 of 2021

7. We have considered the rival submissions of the parties and

perused the records carefully.

8. The main issue for our consideration is as to whether the

learned Arbitrator has disclosed any basis to award loss of profit. It is

in a case where termination of agreement by the railways is held to be

illegal by the learned Arbitrator and as a consequence thereof, the

appellant may be entitled to claim loss of profit, but it is only after

supplying the basis and pleading for it. The award of the amount

towards loss of profit cannot be without any basis. To examine the

aforesaid, we have carefully gone through the award and find that

while considering the claim towards loss of profit, the following facts

were taken into consideration:

"i) Delay caused in the progress of the work during the execution by the default of the employer;

ii) Failure on the part of the employer to fulfill his obligations under the contract which has an impact upon the profitability of the contract;

iii) Non-completion within the stipulated time due to the default of the employer;

___________

https://www.mhc.tn.gov.in/judis O.S.A.(CAD) No. 120 of 2021

iv) Abandonment of the work wholly or partly by the employer."

After recording the facts aforesaid, the learned Arbitrator awarded

15% of the amount of unexecuted value of work. It is after referring to

a judgment where similar benefit was extended by the Court, ignoring

the fact that award of 15% of the amount in the case relied by the

learned Arbitrator was based on the facts earlier considered by the

High Court while determining the amount inter se in other case

between the same parties. Therefore, the award of 15% of the amount

was on the given facts applicable to that case. The award of loss of

profit in this case is not after discussion of facts but in reference to the

judgment referred in award ignoring that award therein was on the

facts of that case. The interference in the award was made by the

learned Single Judge exercising his powers within the four corners of

Section 34 of the Act of 1996. It is in view of the fact that the award of

the amount by the learned Arbitrator, if remains without the reasons,

then can be interfered by the learned single Judge exercising

jurisdiction under Section 34 of the Act of 1996.

___________

https://www.mhc.tn.gov.in/judis O.S.A.(CAD) No. 120 of 2021

9. It is, no doubt, true that whenever it was found that

termination of the agreement is found to be illegal, the Court can

award reasonable amount towards loss of profit, but before awarding

the benefit, the Court need to disclose the basis and it cannot be

awarded in vaccum. The learned single Judge found that no basis has

been disclosed in the award, apart from the fact that no pleading to

disclose the basis for the claim of loss of profit was made by the

appellant followed by material. The award of loss of profit was not

accepted and, accordingly, interference was made in the award.

10. We do not find any illegality in the order of the learned single

Judge and otherwise, we are having limited jurisdiction while

exercising the appellate jurisdiction under Section 37 of the Act of

1996. Accordingly, we are not inclined to cause interference in the

order passed by the learned single Judge. It is even for the prayer of

the appellant for the remand of case to the learned Arbitrator. The

remand of case can be made only when a case is made out. The

learned counsel for the appellant was given chance to show pleading or

any material forming the basis for the Court to determine the loss of

profit, but despite time granted by the Court, pleading or material

___________

https://www.mhc.tn.gov.in/judis O.S.A.(CAD) No. 120 of 2021

could not be referred before the Court. Learned counsel for the

appellant though submits that when detailed reasonings have been

given by the learned Arbitrator holding the termination of the contract

to be illegal, the reasonings there may be the basis for determination

of the amount of loss of profit. We have considered the aforesaid

argument also, but find that there is no discussion of that nature in the

award. The learned Arbitrator has not referred to any finding in

reference to other issues and more specifically, regarding termination

of the agreement to be illegal and there is no pleading or material to

make it as the basis for the award of benefit of 15% of the amount of

unexecuted value of work towards the loss of profit.

Accordingly, the appeal fails and the same is dismissed. There

will be no order as to costs.

                                                               (M.N.B., ACJ.)       (P.D.A., J.)
                                                                         02.12.2021
                     Index : Yes/No

                     vjt




                     ___________



https://www.mhc.tn.gov.in/judis
                                                          O.S.A.(CAD) No. 120 of 2021




                     To:

                     1. The General Manager,
                        Southern Railway,
                        Head Quarters Office,
                        Park Town,
                        Chennai - 600 003.

                     2. The Deputy Chief Engineer/II,
                        Gauge Covnersion,
                        Southern Railway, Construction,
                        Thiruchirappalli - 620 001.


                     3. The Sub Assistant Registrar,
                        Original Side,
                        Madras High Court,
                        Chennai - 600 104.




                     ___________



https://www.mhc.tn.gov.in/judis
                                          O.S.A.(CAD) No. 120 of 2021



                                             M.N.BHANDARI, ACJ
                                                   AND
                                           P.D.AUDIKESAVALU,J.




                                     O.S.A.(CAD) No. 120 of 2021




                                                       02.12.2021



                     ___________



https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter