Sunday, 10, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Union Of India vs M/S.J.Venkatesan
2021 Latest Caselaw 10644 Mad

Citation : 2021 Latest Caselaw 10644 Mad
Judgement Date : 26 April, 2021

Madras High Court
The Union Of India vs M/S.J.Venkatesan on 26 April, 2021
                                                                              O.S.A.No.170 of 2021



                                    IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                               DATED:      26.04.2021

                                                     CORAM :

                                THE HON'BLE MR.SANJIB BANERJEE, CHIEF JUSTICE
                                                          AND
                            THE HON'BLE MR.JUSTICE SENTHILKUMAR RAMAMOORTHY


                                               O.S.A.No.170 of 2021

                      1. The Union of India,
                         rep. by the General Manager,
                         Southern Railway,
                         Park Town, Chennai – 600 003.

                      2. The Divisional Railway Manager/Works,
                         Southern Railway, Park Town,
                         Chennai – 600 003.                             ...   Appellants


                                                   Vs.

                      1. M/s.J.Venkatesan,
                         No.25/16, 3rd Street, T.Nagar,
                         Arakonam,
                         Vellore District.

                      2. Hon'ble Justice K.M.Natarajan,
                         Sole Arbitrator,
                         136, L.B.Road,
                         Kamraj Nagar, Chennai.                         ... Respondents


                      PRAYER: Appeal filed under Order XXXVI Rule 1 of the Original Side
                      Rules, 1956 read with Clause 15 of the Letters Patent and Section


                      ____________
                      Page 1 of 7


http://www.judis.nic.in
                                                                             O.S.A.No.170 of 2021



                      13(1) of the Commercial         Courts Act against the order dated
                      15.07.2019 passed in O.P.No.72 of 2011.


                                    For Appellants          : Mr.M.Vijay Anand

                                    For Respondents         : Mr.Amalaraj S.Penikilapatti
                                                              for respondent No.1


                                                      JUDGMENT

(Delivered by the Hon'ble Chief Justice)

Only two grounds have been urged on behalf of the railways in

challenging the judgment and order of July 15, 2019 rendered on a

petition challenging an arbitral award dated April 20, 2008.

2. The second respondent is the arbitrator, who has been

needlessly impleaded.

3. By the impugned order, the quantum awarded by the

arbitrator has been reduced. It is submitted on behalf of the first

respondent that following the first respondent's concession before the

arbitration Court that the first respondent was not entitled to

pendente lite interest in view of clauses 64.5 and 16.2 of the general

____________

http://www.judis.nic.in O.S.A.No.170 of 2021

conditions governing railway contracts, such reduction was made. The

first respondent is willing to accept the modified award.

4. The two grounds raised by the railways are that the

arbitrator failed to appreciate the documents that were carried by the

railways before him and the arbitrator failed to recognise that the

first respondent contractor had abandoned the work and had left the

site without issuing any notice, even though a mandatory notice in

such regard was required to be issued.

5. It is evident that the value of the work to be executed in

terms of the contract dated April 29, 2005 was in excess of Rs.1.64

crore. The work pertained to the collection and supply of stone

ballast bearing 50MM size and included the loading and unloading

charges. The tenure of the contract ran out by January 28, 2006, but

the railways purported to terminate the contract in January, 2007

upon the contractor allegedly not completing the work.

6. The railways seek a re-assessment of the matter at this

level, which is impermissible. It is evident from the judgment

____________

http://www.judis.nic.in O.S.A.No.170 of 2021

impugned that the contention of the railways before the arbitration

Court was that the arbitrator had not considered the general

conditions of the contract and that the arbitrator failed to notice that

the contractor had violated the contract and not discharged the

obligations as per the contract. It was also asserted before the first

Court that the arbitrator had not considered the entire evidence and

allowed the claim without any or adequate material in support

thereof.

7. The arbitration Court found that the arbitrator had referred to

the facts and the evidence before the arbitrator and sufficient reasons

were apparent from the award which justified the same. The

arbitration Court recorded that it was not for a Court in seisin of a

petition under Section 34 of the Arbitration and Conciliation Act, 1996

to re-assess the matter and only the grounds made out had to be

looked into. The exercise undertaken by the railways at this

appellate stage is the same. No case has been made out that the

award is opposed to public policy or otherwise unconscionable or

palpably erroneous. On the basis of the facts as the arbitrator

noticed, the arbitrator found in favour of the contractor and indicated

____________

http://www.judis.nic.in O.S.A.No.170 of 2021

cogent reasons to justify the findings.

8. The Court of the first instance applied the appropriate

principles and found that no legal grounds had been made out under

Section 34 of the Act to interfere with the award. The Court deleted

the award of pendente lite interest on the concession of the

contractor. More than this, the arbitration Court could not have

interfered with the award in the light of the prevailing law and the

limited authority available under Section 34 of the Act.

9. The judgment and order impugned dated July 15, 2019 do

not call for any interference. It is recorded that the first respondent

has no grievance against the award as modified by the order

impugned.

10. O.S.A.No.170 of 2021 is dismissed. C.M.P.No.7498 of 2021

is closed. There will be no order as to costs.

                                                                (S.B., CJ.)       (S.K.R., J.)
                                                                           26.04.2021

                      Index : No

                      ____________



http://www.judis.nic.in
                                                                  O.S.A.No.170 of 2021



                      bbr



                      To:

                      1. The General Manager,
                         Union of India,
                         Southern Railway,
                         Park Town, Chennai – 600 003.

2. The Divisional Railway Manager/Works, Southern Railway, Park Town, Chennai – 600 003.

3. The Hon'ble Mr. Justice K.M.Natarajan, Sole Arbitrator, 136, L.B.Road, Kamraj Nagar, Chennai.

Copy to:

The Sub Assistant Registrar, Original Side, High Court, Madras.

____________

http://www.judis.nic.in O.S.A.No.170 of 2021

THE HON'BLE CHIEF JUSTICE AND SENTHILKUMAR RAMAMOORTHY, J.

bbr

O.S.A.No.170 of 2021

26.04.2021

____________

http://www.judis.nic.in

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter