Citation : 2026 Latest Caselaw 1769 MP
Judgement Date : 19 February, 2026
NEUTRAL CITATION NO. 2026:MPHC-JBP:14679
1 MA-1336-2004
IN THE HIGH COURT OF MADHYA PRADESH
AT JABALPUR
BEFORE
HON'BLE SHRI JUSTICE VIVEK JAIN
ON THE 19th OF FEBRUARY, 2026
MISC. APPEAL No. 1336 of 2004
M/S MODERN BUILDERS & CONST.,BHOPAL
Versus
NEHRU SCIENCE CENTRE & ANR AND OTHERS
Appearance:
Shri Ashok Lalwani Senior Advocate with Shri Aakash Lalwani- Advocate for the
petitioner.
Shri Anoop Kumar Shrivastava- Advocate for the respondent.
ORDER
By way of this appeal under Section 37 of Arbitration and Conciliation Act 1996, the order of the District Court dated 26.03.2004 is under challenge whereby the district court has rejected the application of the petitioner for challenging the award of the Arbitrator which was filed under section 30 of the Act of 1940 and then went on to hold that the award of the Arbitrator be made rule of the court.
2. The necessary facts for the purpose of disposal of present appeal
are that initially an agreement was executed in the year 1990 between the appellant and the respondent in relation to some construction work in Regional Science Centre, Shyamla Hills, Bhopal and thereafter certain controversies and disputes arose between the parties in relation to which the parties went for arbitration and Dr. P. K. Chaudhary was appointed arbitrator on 13-09-1999. Thereafter the appellant approached to the District Court in M.J.C. 88 of 1994 contending therein that the earlier arbitrator be
NEUTRAL CITATION NO. 2026:MPHC-JBP:14679
2 MA-1336-2004 discharged and a fresh arbitrator be appointed. The said application was rejected by the District Court with direction that the arbitrator earlier appointed namely Dr. P. K. Chaudhary should complete the arbitration process within 6 months. This was vide order was 25-04-2000. Thereafter the arbitrator entered into the reference and passed the award dated 15-10-2001.
3. From a perusal of the aforesaid award, it is seen that the arbitrator has written in the said award that he is seriously sick and remained hospitalized for major portion of the year 2001 and still is undergoing surgical operations and that has led to the delay in passing of the award. The only consideration in the award is in the following terms.
"Now I, Dr. PK Chaudhuri having taken upon myself the burden of the Reference and having carefully examined and considered the pleadings of the parties, the documentary evidence produced before me, the arguments of the parties and such other information as was considered necessary and obtained, do hereby record my findings as below:"
4. After quoting the said consideration in the award, the arbitrator went ahead to pass the award in tabular form mentioning the issues and findings there upon. The entire award is written in tabular form. The entire award is as under:-
"AWARD In the matter of Arbitration under Indian Arbitration Act, 19406 BETWEEN MODERN BUILDERS AND CONTRACTORS, BHOPAL and NEHRU SCIENCE CENTRE, MUMBAI WHEREAS certain differences arose between the two parties out of the Contract for Land Development Work at the Regional Research Centre, Bhopal made between them.
AND WHEREAS Dr. Pranab Kumar Chaudhuri of VII-14 Purbachal, Salt Lake City, Sector III, Kolkata 700 091 (New Postal Code 700 097) was
NEUTRAL CITATION NO. 2026:MPHC-JBP:14679
3 MA-1336-2004 appointed Arbitrator by the Director General, National Council of Science Museums, Block-GN, Sector-V, Bidhannagar, Kolkata 700 091. AND WHEREAS the Arbitrator being sick and hospitalised throughout the second fortnight of May had first advised the two parties that his award would be given in July 2001 (to which advice no reply or objection has been submitted by either party) and subsequently advised the parties again that due to a fresh hospitalization and surgical operation in the first fortnight of August 2001, the Award would now be made by 15.10.2001. Now I, Dr. PK Chaudhuri having taken upon myself the burden of the Reference and having carefully examined and considered the pleadings of the parties, the documentary evidence produced before me, the arguments of the parties and such other information as was considered necessary and obtained, do hereby record my findings as below:
Sl.No. Issue Finding
The Claimant is not
entitled to any
Is the claimant entitled to payment of final bill further amount amount as claimed viz. Rs.1,30,706.00?
1. beyond what they (Paragraph 17.1 of Claimant's Argument dated have been paid 1.4./18.4.2001) against their running bills.
Is the Claimant entitled to payment of The Claimant is not compensation amount of Rs.2,32,820.00?
2. entitled to any (Paragraph 17.2 of Claimant's Argument dated payment.
1.4/18.4.2001) Is the Claimant entitled to payment of amount The Claimant is not
3. of compensation Rs.8,500.00 (Paragraph 17.3 entitled to any of Claimant's Argument dated 1.4/18.4.2001) payment. Is the Claimant entitled to additional payment of Rs.44,057.00 towards making good of The Claimant is not underpayment against quantity of Earth Work?
4. entitled to any (item no.1 of schedule)(Paragraph 17.3 of payment.
Claimant's Argument dated 1.4/18.4.2001)
Is the Claimant entitled to payment ofRs.39,260.00 towards making good of under The Claimant is not payment due to alleged mistake in entitled to this
computation against E.I No.1? amount or any part of (Paragraph17.4(b) of Claimant's Argument it. dated1.4/18.4.2001) Is the Claimant entitled to payment ofRs.39,668.00 towards making good of The Claimant is not
6. alleged underpayment against labour for entitled to anything boulder filling? (Paragraph 17.4 (c) of on this account Claimant's Argument dated 1.4/18.4.2001)
NEUTRAL CITATION NO. 2026:MPHC-JBP:14679
4 MA-1336-2004 The Respondent is Is the Respondent entitled to the recovery entitled to the ofRs.42,612.17 from the final bill against
7. payment of overpayment? (Paragraph E of Respondent's Rs.42,612.17 by the counterclaim dated 12.8.94) Claimant.
Is the Respondent entitled to a compensation amount of Rs.1,72,922.17 as from the The Respondent is
Claimant as alleged in the Counter Argument not entitled to any dated:16.05.2001? payment.
5. In the said award the issues have been framed and the final one line conclusions have been recorded against the issues but there is no finding or consideration part in the entire award. The only finding in consideration part is that the arbitrator has gone through the pleadings of the parties, documentary evidence and arguments of the parties and all necessary information. Such an award is utterly non-speaking award and there is not a single word of consideration on the pleadings of the parties and the documents placed before him. The arbitrator has went ahead to reject all of the eight claims made before him by the appellant but while non-suiting the appellant for all of the claims and did not give a single word of consideration in the entire award.
6. In this case, even no application under Section 34 (4). Had been filed by the respondent before the District Court. The defect does not seem curable under Section 34, and now it is impossible to be cured as the Arbitrator has died long ago. The Hon'ble Supreme Court in the case of I- Pay Clearing Services Vs. ICICI Bank and others, 2022 (3) SCC 121 has held as under :-
40. Merely because an application is filed under Section 34(4) of the Act by a
NEUTRAL CITATION NO. 2026:MPHC-JBP:14679
5 MA-1336-2004 party, it is not always obligatory on the part of the Court to remit the matter to Arbitral Tribunal. The discretionary power conferred under Section 34(4) of the Act, is to be exercised where there is inadequate reasoning or to fill up the gaps in the reasoning, in support of the findings which are already recorded in the award.
41. Under the guise of additional reasons and filling up the gaps in the reasoning, no award can be remitted to the arbitrator, where there are no findings on the contentious issues in the award. If there are no findings on the contentious issues in the award or if any findings are recorded ignoring the material evidence on record, the same are acceptable grounds for setting aside the award itself. Under the guise of either additional reasons or filling up the gaps in the reasoning, the power conferred on the Court cannot be relegated to the arbitrator. In absence of any finding on contentious issue, no amount of reasons can cure the defect in the award.
42. A harmonious reading of Sections 31, 34(1), 34(2-A) and 34(4) of the Arbitration and Conciliation Act, 1996, make it clear that in appropriate cases, on the request made by a party, Court can give an opportunity to the arbitrator to resume the arbitral proceedings for giving reasons or to fill up the gaps in the reasoning in support of a finding, which is already rendered in the award.
But at the same time, when it prima facie appears that there is a patent illegality in the award itself, by not recording a finding on a contentious issue, in such cases, Court may not accede to the request of a party for giving an opportunity to the Arbitral Tribunal to resume the arbitral proceedings.
7. In the case of Union of India v. Sudershan Gupta, (2009) 6 SCC 298 it has been held by the Hon'ble Supreme Court that if quasi-judicial authority which passes some order has to retain the records for some reasonable time. However, in this case, even the record of the Arbitrator has been lost.
8. In the present case, it is not in dispute that the records of the arbitrator have been misplaced and lost and it has been alleged by the appellant that the arbitrator handed over the records of the arbitration proceedings to the respondent department and in pursuance to an order passed by this court on 12-11-2014, the respondent department has stated that the sole arbitrator has now expired many years ago and only some
NEUTRAL CITATION NO. 2026:MPHC-JBP:14679
6 MA-1336-2004 documents are traceable with the respondent department which are as under:-
"i) Letter dated 12.08.1994 i.e. Statement of Counterclaim submitted by Respondent No.1 before the Arbitrator - P/1
ii) Letter of appointment of Arbitrator dated 15.11.1993 - P/2.
iii) Copy of award dated 15.10.2001 passed by Arbitrator - P/3
iv) Minutes of First sitting of Arbitration proceedings held on 5.09.1994 -P/4
v) Minutes of Second sitting of Arbitration proceedings held 3.10.1994 P/5 on
vi) Minutes of Third sitting of Arbitration proceedings held on 26.2.2001-P/6
vii) Parawise comments of Respondent No. 1 dated 16.5.2001 P/7 & P/8.
viii) Agreement dated 14.8.1990 between the Respondent No. 1 and Appellant for the work of Land Development at Regional Science Centre, Bhopal - P/9
ix) Order dated 26.3.2004 of 5th Additional District Court, Bhopal - P/10
x) Order dated 15.4.2014 of Hon'ble High Court of Madhya Pradesh, Jabalpur - P/11 (on record)
xi)Order dated 11.8.2014 of Hon'ble High Court of Madhya Pradesh, Jabalpur-
P/12 (on record)"
9. This is the entire record which is now available with both of the parties in case and it is certain that the record of the arbitration has been lost which cannot now be traced in view of the death of the arbitrator. The arbitrator himself decided not to give any reason for rejection of claims and has passed the utterly non-speaking award which cannot be sustained in judicial scrutiny. Even as per the limited grounds of challenge to the award under Section 34 of the New Act of 1996, the award is against the public policy of India because the right to get a fair and a reasoned judicial order is one of the hallmarks of public policy and legal policy, and that has been denied in the present case to the present appellant.
10. The counsel for the respondent has relied on the judgment of the
Hon'ble Supreme Court in Gujarat Water Supply and Sewerage Board v. Unique Erectors (Gujarat) (P) Ltd., (1989) 1 SCC 532 to contend that the arbitrator is not obliged to give reasons for his decision. This court has gone
NEUTRAL CITATION NO. 2026:MPHC-JBP:14679
7 MA-1336-2004 to the aforesaid judgment of the Hon'ble Supreme Court and in the aforesaid judgment, the plea that the award is non-speaking was not taken before the district court and before the High Court and this plea was for the first time taken before the Supreme Court, which the Supreme Court repelled. The Hon'ble Supreme Court held that award of arbitrator should be read reasonably as a whole to find out the implication and meaning thereof and short intelligible indications of the grounds should be discernible to find out the mind of the arbitrator for his action and if that short reasons are there which are intelligible so as to clarify the grounds of acceptance or rejection of the claims, then that can be said to be reasonably speaking award. The Hon'ble Supreme Court held as under:-
"9. The scope and extent of examination by the court of the award made by an arbitrator has been laid down in various decisions. It has to be noted that there is a trend in modern times that reasons should be stated in the award though the question whether the reasons are necessary in ordinary arbitration awards between the parties is pending adjudication by the Constitution Bench of this Court. Even, however, if it be held that it is obligatory for the arbitrator to state reasons, it is not obligatory to give any detailed judgment. An award of an arbitrator should be read reasonably as a whole to find out the implication and the meaning thereof. Short intelligible indications of the grounds should be discernible to find out the mind of the arbitrator for his action even if it be enjoined that in all cases of award by any arbitrator reasons have to be stated. The reasons should not only be intelligible but should also deal either expressly or impliedly with the substantial points that have been raised. Even in a case where the arbitrator has to state reasons, the sufficiency of the reasons depends upon the facts and the circumstances of the case. The court, however, does not sit in appeal over the award and review the reasons. The court can set aside the award only if it is apparent from the award that there is no evidence to support the conclusion or if the award is based upon any legal proposition which is erroneous. See the observations of this Court in Indian Oil Corpn. Ltd. v. Indian Carbon Ltd. [(1988) 3 SCC 36]"
11. In the present case, the award is totally unintelligible because this court cannot discern the reasons for acceptance or rejection of the claims of
NEUTRAL CITATION NO. 2026:MPHC-JBP:14679
8 MA-1336-2004
the rival parties and apart from writing in a single line that the claimant has not been found entitled to any payment, not a single word of consideration is there in the award to reject the claims of the appellant contractor.
12. Therefore, it is a fit case where the award of the arbitrator should be set aside as it suffers from non-application of mind and from the vice of not containing a single reason, it is utterly unreasoned award, and thus there is legal misconduct by the Arbitrator.
13. Now the question arises that what relief can be granted in the present case and what consequential directions can be issued. The arbitrator has undisputedly expired long ago and therefore it is not possible to remand the matter to the arbitrator.
14. Therefore the impugned order of the District Court as well as the Award are set aside and the appellant is set at liberty to seek appointment of a new arbitrator as per the provisions of law applicable to the case.
15. With the aforesaid directions, the appeal is allowed.
(VIVEK JAIN) JUDGE
MISHRA
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!