Tuesday, 19, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M.P.M.K.V.V. Company Limited ... vs Geeta Devi
2025 Latest Caselaw 9030 MP

Citation : 2025 Latest Caselaw 9030 MP
Judgement Date : 10 September, 2025

Madhya Pradesh High Court

M.P.M.K.V.V. Company Limited ... vs Geeta Devi on 10 September, 2025

Author: Gurpal Singh Ahluwalia
Bench: G. S. Ahluwalia
                           NEUTRAL CITATION NO. 2025:MPHC-GWL:21063




                                                               1                        SA No. 1909/2024




                            IN THE HIGH COURT OF MADHYA PRADESH
                                        AT GWALIOR
                                                     BEFORE
                                       HON'BLE SHRI JUSTICE G. S. AHLUWALIA

                                              SECOND APPEAL No. 1909 of 2024
                             M.P.M.K.V.V. COMPANY LIMITED GOVINDPURA BHOPAL AND
                                                    OTHERS
                                                     Versus
                                             GEETA DEVI AND OTHERS

                           Appearance:

                                 Shri Anand V. Bhardwaj - Advocate for appellants.

                                 Shri Sanjay Singh Kushwaha - Govt. Advocate for State.


                                       Reserved on         :       09/09/2025
                                       Pronounced on       :       10/09/2025
                                                          JUDGMENT

This second appeal under Section 100 of CPC has been filed against

the judgment and decree dated 29.11.2023 passed by First District Judge,

Seondha, District Datia in RCA No. 16/2018, as well as judgment and decree

dated 30.1.2018 passed by Civil Judge, Class I, Seondha, District Datia in

Civil Suit No. 2A/2014.

NEUTRAL CITATION NO. 2025:MPHC-GWL:21063

2. Heard on I.A. No. 5242/2024. This is an application under Section 5

of the Limitation Act for condonation of delay in filing this appeal.

3. According to appellants, the judgment was pronounced on 29.11.2023

and a legal opinion was received on 04.01.2024 to the effect that an appeal

should be filed. Accordingly, a letter was written to General Manager

(O&M), Datia on 10.01.2024 for grant of permission and permission was

granted on 17.01.2024 and the same was forwarded to the Chief General

Manager, MPMKVV Co. Ltd., Gwalior. It is alleged that from January 2024

till second week of July 2024 time was consumed in collecting the record of

the file, and accordingly, appeal could not be filed within time and appeal

was filed on 29.07.2024. Therefore, it is prayed that the delay in filing the

appeal may be condoned.

4. Considered the submissions made by counsel for appellants.

5. Permission to file an appeal was granted on 17.01.2024, whereas the

appeal was filed on 29.07.2024. From the certified copy of the impugned

judgment, it is clear that application for obtaining the certified copy of the

said judgment was filed on 12.12.2023 and copy was supplied on

30.12.2023. Therefore, it is clear that appellants were already in possession

NEUTRAL CITATION NO. 2025:MPHC-GWL:21063

of all the relevant documents for filing an appeal and explanation given by

appellants that six months' time was consumed for collecting the record is

false on the face of it. Furthermore, according to the suit filed by plaintiffs,

contractor of the appellants was carrying out certain works and accident took

place which resulted in the death of Hakeem Singh. Ultimately, a suit for

recovery of damages/compensation was filed.

6. Solitary ground raised by appellants during the course of argument is

that since the contract was given to the contractor, therefore appellants are

not responsible to pay the compensation amount.

7. Aforesaid submission made by counsel for appellants is not worth

acceptance in the light of the agreement arrived at between the appellants

and contractor. As per the agreement Exhibits D/11 and D/12, supervision of

work was of AE (STCO&M), MPMKVV Company Ltd., Datia. It was also

mentioned that the work of the contractor shall be inspected by the Junior

Engineer/Assistant Engineer/ Division Engineer at any time. Therefore, it is

clear that the position of appellants was that of a principal contractor as it

was having complete control over the execution of work.

NEUTRAL CITATION NO. 2025:MPHC-GWL:21063

8. If appellants are of the view that contractor is responsible for payment

of compensation, then it can recover it from the contractor, but being the

principal contractor, appellants cannot run away from its liability to pay

compensation to the plaintiffs.

9. Thus, the Court is of considered opinion that not only the appellants

have failed to give plausible/sufficient cause for condonation of delay, but

even otherwise has no substance in the appeal.

10. Accordingly, I.A. No. 5242/2024 for condonation of delay is hereby

rejected, and appeal is dismissed as barred by time.

11. As a consequence thereof, judgment and decree dated 29.11.2023

passed by First District Judge, Seondha, District Datia in RCA No. 16/2018,

as well as judgment and decree dated 30.1.2018 passed by Civil Judge, Class

I, Seondha, District Datia in Civil Suit No. 2A/2014 are hereby affirmed.

12. The appeal fails and is hereby dismissed.

(G.S. Ahluwalia) Judge AKS

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter