Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

D. Biswas vs Bharat Sanchar Nigam Limited
2025 Latest Caselaw 3613 MP

Citation : 2025 Latest Caselaw 3613 MP
Judgement Date : 7 August, 2025

Madhya Pradesh High Court

D. Biswas vs Bharat Sanchar Nigam Limited on 7 August, 2025

         NEUTRAL CITATION NO. 2025:MPHC-JBP:36954




                                                            1                                 AC-68-2018
                             IN     THE      HIGH COURT OF MADHYA PRADESH
                                                   AT JABALPUR
                                                        BEFORE
                                           HON'BLE SHRI JUSTICE DEEPAK KHOT
                                                 ON THE 7 th OF AUGUST, 2025
                                              ARBITRATION CASE No. 68 of 2018
                                                   D. BISWAS
                                                      Versus
                                    BHARAT SANCHAR NIGAM LIMITED AND OTHERS
                          Appearance:
                                  Shri Piyush Kumar Tiwari - Advocate for the applicant.

                                  Shri Sapan Usrethe, learned counsel for the respondent No.3.

                                                                ORDER

The present application has been filed by the applicant under section 11(6) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as 'the Act of 1996') for appointment of an Arbitrator to resolve the dispute which arose between the parties pursuant to an agreement dated 28.1.2010 (Annexure A/2).

2. It is submitted by learned counsel for the applicant that a NIT was issued on 7.11.2009 in respect of work "Operation and Comprehensive

maintenance of Electro- mechanical service at TE Building, RSU and S/Qtrs, Civil Lines, Balaghat, RSU, Bharveli and MBM Waraseoni". The applicant being the successful bidder has obtained the work and an agreement dated 28.1.2010 has been issued. It is submitted that despite the applicant had completed the work, the payment was not made, therefore, a representation dated 30.12.2013 (annexure RJ-4) was issued to the respondent/non-

NEUTRAL CITATION NO. 2025:MPHC-JBP:36954

2 AC-68-2018 applicant to verify from the site and make necessary payment. In the representation it was stated that the work was completed on 1.11.2013. It is further submitted that the applicant had filed an application under section 9 of the Act of 1996 on 30.11.2011 (annexure RJ2), which was registered as Arbitration Case No.25/2011; but, the same was dismissed on the point that no interim relief as provided under section 9 can be granted as the matter is related to payment of the bill. It is further submitted that the final bill was sent vide bill dated 15.1.2014 (annexure A3). On 7.2.2015 the Sub Divisional Engineer forwarded the deviation statement to the Executive Engineer vide annexure RJ5. Again, a letter has been issued by the Sub Divisional Engineer to the Executive Engineer with regard to the recovery statement of the sites maintained by the applicant on 18.3.2016 filed as

annexure RJ6. It was informed to the applicant that the final bills were submitted to the competent Authority BSNL Electrical Division, Bhopal, and the applicant is required to remain present for his signatures. Again, a letter has been sent by Executive Engineer to the Superintendent Engineer (Electrical) by which a request was made to hand over the unpassed bills to the applicant. Thereafter, the bills were passed, however, after making some deductions without any basis. The applicant has accepted the payment under protest. Again, the applicant has preferred representation dated 18.1.2017 with regard to the outstanding amount and demand in different heads. It is further submitted that in other contracts assigned to the applicant of the similar nature some dispute arose and the applicant had filed an application for appointment of an arbitrator in A.C.No.56/2017. In the said application

NEUTRAL CITATION NO. 2025:MPHC-JBP:36954

3 AC-68-2018 also the facts were similar. The notice for invocation of arbitration was of the year 2017 and the objections of the non-applicants were also identical. This Hon. Court after considering all objections of the parties, had decided the said application for appointment of an Arbitrator vide order dated 16.4.2019, annexure RJ7. It is further submitted that the present case is exactly similar and identical to the facts of the earlier case. Thus, no different view can be taken.

3. Per Contra, refuting the submissions made by learned counsel for the applicant, learned counsel for the non-applicant has vehemently opposed the application on the ground that the application is time barred. It is submitted that the application ought to have been filed within three years from the date when cause of action arose. It is submitted that for the first time the cause of action arose in the year 2014 when the applicant had submitted an application dated 31.7.2014 and 2.9.2015 by which the applications were submitted for appointment of an Arbitrator. It is further submitted that the Hon. Apex Court in the case of BSNL and others Vs. M/s Nortel Networks India Pvt. Ltd. vide judgment dated 10.3.2021 in SLP (C) No.1531-32/2021 had decided the issue of limitation and on the basis of aforesaid legal proposition, it is stated that though the arbitration clause /agreement has been executed between the parties but because the claim/ dispute of the applicant became stale, the application under section 11(6) is barred by limitation.

4. The only question which has been raised is in regard to the issue of

limitation that whether the present application is barred by limitation or not.

NEUTRAL CITATION NO. 2025:MPHC-JBP:36954

4 AC-68-2018 Other factual aspects of the matter have not been denied by the non-applicant and arbitrability of the dispute and intention of the parties were acknowledged by the non-applicant. However, in regard to deduction no Arbitrator has been appointed The only objection is that now Arbitrator cannot be appointed on the ground that application is barred by limitation.

5. Heard the learned counsel for the parties and perused the record.

6. This Court in an identical set of facts between the same parties and in fact the dates were also more or less same as in that case also the last notice was of 18.1.2017, decided the application in favour of the applicant by directing appointment of an Arbitrator. This Court in the order dated 16.4.2019 passed in A.C.No.56/2017 in para 8 has held as under :-

"(8) The case of the applicant is that although the work of NIT was over in the year 2011, the bills arising thereto were not settled. The correspondences filed with the rejoinder as Annexure-RJ/4, Annexure-

RJ/5, Annexure-RJ/6 & Annexure-RJ/7 show that correspondence regarding remaining payment continued and applicant was even directed to remain present before the Office of Electrical Division at Bhopal, which is evident from the communication dated 09.02.2016 (Annexure-RJ/6). The pivotal question in this matter is whether limitation is to be counted from the date of completion of work i.e., 2011 or from the date the final bill was settled and applicant felt aggrieved therefrom. As noticed, the parties have taken a diametrically opposite stand on the aspect of limitation. In Clause 25(1) it is mentioned that the applicant may submit his claim to Engineer-In-Chief within 30 days from the date of disallowances. The word "Disallowances", in the context it is used in Sub-clause (i) of Clause 25, makes it clear that it includes the grievance and dispute in relation to less payment etc. The question of less payment etc. emerged when final bill was settled in 2016. Thereafter, applicant promptly preferred the application dated 18.01.2017. After completion of work in 2011, the question of payment continued. There were continuous correspondence in this regard which culminated with payment of final bill. The actual grievance and cause of action for applicant emerged when he felt dissatisfied with final payment. Thus, he sent a notice dated 18.01.2017 (Annexure-A/4) for appointment of arbitrator. In this view of the matter, earlier correspondence for appointment of arbitrator pales into insignificance. The grievance of the applicant falls within the ambit of "dispute" because one party is claiming something which has been denied by the other party."

NEUTRAL CITATION NO. 2025:MPHC-JBP:36954

5 AC-68-2018

7. From the above analysis of the facts when the facts of the present case are verified / cross checked, then this Court has found that in that case also final bill was prepared in the year 2016 and prior to that there were applications by the applicants in regard to appointment of an Arbitrator. But, this Court holding that after notices which were sent earlier, non-applicant satisfied the demand by making payment, so as such there was no dispute till the final payment was made and when in the final bills deductions were made dispute arose. The Court has held that as such the date of dispute would be from the date of deduction and payment of final bill and after that thereafter immediately notice on 18.1.2017 was sent.

8. In the present case also, the final bills were settled in the year 2016 and on 18.1.2017 notice was sent showing dissatisfaction and appointment of an Arbitrator by the applicant in regard to resolution of the dispute for making deduction in the final bill and non payment of legitimate dues. The earlier notice was in regard to non payment of entire bill and resolution of dispute but the non-applicant has chosen to resolve the dispute at their end and ultimately passed the bill in the year 2016. So, as such when the claim of the applicant was satisfied in the year 2016, if any notice was issued prior to it, has got no significance because later, on the basis of deduction made in the final bill, dispute arose. This Court in the earlier litigation A.C.No.56/2017 vide order dated 16.4.2019 has dealt with clause 25(1) and sub clause (i) of clause 25 of agreement stating that the intention of the parties as per the agreement is in regard to settlement of dispute even after the payment of bills because the word 'disallowances' has been used. This

NEUTRAL CITATION NO. 2025:MPHC-JBP:36954

6 AC-68-2018 Court in total agreement with the order passed in earlier litigation is also of the opinion that the dispute has arisen only because of deduction in the final bill in the year 2016, therefore, as per clause 25(1)(i) of the agreement annexure A/2 dated 28.1.2010, the dispute is arbitrable and deserves to be resolved by the mechanism provided under the agreement, which provides for an appointment of an Arbitrator.

9. The Hon. Apex Court in the case of Uttarakhand Purv Sainik Kalyan Nigam Ltd. v. Northern Coal Field Ltd., (2020) 2 SCC 455 , while over-ruling the order of this Court in the case of Uttarakhand Purv Sainik Kalyan Nigam Limited Vs. Northern Coalfield Limited, 2018 (4) MPLJ 45, has held that after the amendment in the Act of 1996, section 6A has been inserted which provides that all the questions in regard to jurisdiction, limitation or which goes to the root shall be decided by the Arbitrator and those are not to be decided by this Court at the referral stage. For ready reference the principal laid down in Para 7 is reproduced here and below :-

"7. We have heard the learned counsel for the parties and perused the pleadings.

7.1. Section 21 of the 1996 Act provides that arbitral proceedings commence on the date on which a request for disputes to be referred to arbitration is received by the respondent.

7.2. In the present case, the notice of arbitration was issued by the petitioner Contractor to the respondent Company on 9-3-2016. The invocation took place after Section 11 was amended by the 2015 Amendment Act, which came into force on 23-10-2015, the amended provision would be applicable to the present case. 7.3. The 2015 Amendment Act brought about a significant change in the appointment process under Section 11: first, the default power of appointment shifted from the Chief Justice of the High Court in arbitrations governed by Part I of the Act, to the High Court; second, the scope of jurisdiction under sub-section (6-A) of Section 11 was confined to the examination of the existence of the arbitration agreement at the pre-reference stage.

7.4. Prior to the coming into force of the 2015 Amendment Act, much controversy had surrounded the nature of the power of appointment by the Chief Justice, or his designate under Section 11. A seven-Judge

NEUTRAL CITATION NO. 2025:MPHC-JBP:36954

7 AC-68-2018 Constitution Bench of this Court in SBP & Co. v. Patel Engg. Ltd. [SBP & Co. v. Patel Engg. Ltd., (2005) 8 SCC 618] defined the scope of power of the Chief Justice under Section 11. The Court held that the scope of power exercised under Section 11 was to first decide:

(i) whether there was a valid arbitration agreement; and

(ii) whether the person who has made the request under Section 11, was a party to the arbitration agreement; and

(iii) whether the party making the motion had approached the appropriate High Court.

7.5. Further, the Chief Justice was required to decide all threshold issues with respect to jurisdiction, the existence of the agreement, whether the claim was a dead one; or a time-barred claim sought to be resurrected; or whether the parties had concluded the transaction by recording satisfaction of their mutual rights and obligations, and received the final payment without objection, under Section 11, at the pre-reference stage. The decision in Patel Engg. [SBP & Co. v. Patel Engg. Ltd., (2005) 8 SCC 618] was followed by this Court in Boghara Polyfab [National Insurance Co. Ltd. v. Boghara Polyfab (P) Ltd., (2009) 1 SCC 267 : (2009) 1 SCC (Civ) 117] , Master Construction [Union of India v. Master Construction Co., (2011) 12 SCC 349 :

(2012) 2 SCC (Civ) 582] , and other decisions.

7.6. The Law Commission in the 246th Report [ Amendments to the Arbitration and Conciliation Act, 1996, Report No. 246, Law Commission of India (August 2014), p. 20.] recommended that:

"33. ... the Commission has recommended amendments to Sections 8 and 11 of the Arbitration and Conciliation Act, 1996. The scope of the judicial intervention is only restricted to situations where the court/judicial authority finds that the arbitration agreement does not exist or is null and void. Insofar as the [Ed.: The matter between two asterisks has been emphasised in original.] nature [Ed.: The matter between two asterisks has been emphasised in original.] of intervention is concerned, it is recommended that in the event the court/judicial authority is prima facie satisfied against the argument challenging the arbitration agreement, it shall appoint the arbitrator and/or refer the parties to arbitration, as the case may be. The amendment envisages that the judicial authority shall not refer the parties to arbitration only if it finds that there does not exist an arbitration agreement or that it is null and void. If the judicial authority is of the opinion that prima facie the arbitration agreement exists, then it shall refer the dispute to arbitration, and leave the existence of the arbitration agreement to be finally determined by the Arbitral Tribunal."

(emphasis supplied) 7.7. Based on the recommendations of the Law Commission, Section 11 was substantially amended by the 2015 Amendment Act, to overcome the effect of all previous judgments rendered on the scope of power by a non obstante clause, and to reinforce the kompetenz- kompetenz principle enshrined in Section 16 of the 1996 Act. The 2015 Amendment Act inserted sub-section (6-A) to Section 11 which provides that:

NEUTRAL CITATION NO. 2025:MPHC-JBP:36954

8 AC-68-2018 "(6-A) The Supreme Court or, as the case may be, the High Court, while considering any application under sub-section (4) or sub-

section (5) or sub-section (6), shall, notwithstanding any judgment, decree or order of any court, confine to the examination of the existence of an arbitration agreement."

(emphasis supplied) 7.8. By virtue of the non obstante clause incorporated in Section 11(6- A), previous judgments rendered in Patel Engg. [SBP & Co. v. Patel Engg. Ltd., (2005) 8 SCC 618] and Boghara Polyfab [National Insurance Co. Ltd. v. Boghara Polyfab (P) Ltd., (2009) 1 SCC 267 :

(2009) 1 SCC (Civ) 117] , were legislatively overruled. The scope of examination is now confined only to the existence of the arbitration agreement at the Section 11 stage, and nothing more.

7.9. Reliance is placed on the judgment in Duro Felguera S.A. v. Gangavaram Port Ltd. [Duro Felguera S.A. v. Gangavaram Port Ltd., (2017) 9 SCC 729 : (2017) 4 SCC (Civ) 764. Refer to TRF Ltd. v. Energo Engg. Projects Ltd., (2017) 8 SCC 377 : (2017) 4 SCC (Civ) 72] , wherein this Court held that: (SCC p. 759, para 48) "48. ... From a reading of Section 11(6-A), the intention of the legislature is crystal clear i.e. the court should and need only look into one aspect--the existence of an arbitration agreement. What are the factors for deciding as to whether there is an arbitration agreement is the next question. The resolution to that is simple -- it needs to be seen if the agreement contains a clause which provides for arbitration pertaining to the disputes which have arisen between the parties to the agreement."

(emphasis supplied) 7.10. In view of the legislative mandate contained in Section 11(6-A), the Court is now required only to examine the existence of the arbitration agreement. All other preliminary or threshold issues are left to be decided by the arbitrator under Section 16, which enshrines the kompetenz-kompetenz principle.

7.11. The doctrine of "kompetenz-kompetenz", also referred to as "compétence-compétence", or "compétence de la recognized", implies that the Arbitral Tribunal is empowered and has the competence to rule on its own jurisdiction, including determining all jurisdictional issues, and the existence or validity of the arbitration agreement. This doctrine is intended to minimise judicial intervention, so that the arbitral process is not thwarted at the threshold, when a preliminary objection is raised by one of the parties. The doctrine of kompetenz-kompetenz is, however, subject to the exception i.e. when the arbitration agreement itself is impeached as being procured by fraud or deception. This exception would also apply to cases where the parties in the process of negotiation, may have entered into a draft agreement as an antecedent step prior to executing the final contract. The draft agreement would be a mere proposal to arbitrate, and not an unequivocal acceptance of the terms of the agreement. Section 7 of the Contract Act, 1872 requires the acceptance of a contract to be absolute and unqualified [Dresser Rand S.A. v. Bindal Agro Chem Ltd. , (2006) 1 SCC 751. See

NEUTRAL CITATION NO. 2025:MPHC-JBP:36954

9 AC-68-2018 also BSNL v. Telephone Cables Ltd. , (2010) 5 SCC 213 : (2010) 2 SCC (Civ) 352. Refer to PSA Mumbai Investments Pte. Ltd. v. Jawaharlal Nehru Port Trust , (2018) 10 SCC 525 : (2019) 1 SCC (Civ) 1] . If an arbitration agreement is not valid or non-existent, the Arbitral Tribunal cannot assume jurisdiction to adjudicate upon the disputes. Appointment of an arbitrator may be refused if the arbitration agreement is not in writing, or the disputes are beyond the scope of the arbitration agreement. Article V(1)( a) of the New York Convention states that recognition and enforcement of an award may be refused if the arbitration agreement "is not valid under the law to which the parties have subjected it or, failing any indication thereon, under the law of the country where the award was made".

7.12. The legislative intent underlying the 1996 Act is party autonomy and minimal judicial intervention in the arbitral process. Under this regime, once the arbitrator is appointed, or the tribunal is constituted, all issues and objections are to be decided by the Arbitral Tribunal. 7.13. In view of the provisions of Section 16, and the legislative policy to restrict judicial intervention at the pre-reference stage, the issue of limitation would require to be decided by the arbitrator. Sub-section (1) of Section 16 provides that the Arbitral Tribunal may rule on its own jurisdiction, "including any objections" with respect to the existence or validity of the arbitration agreement. Section 16 is as an inclusive provision, which would comprehend all preliminary issues touching upon the jurisdiction of the Arbitral Tribunal. The issue of limitation is a jurisdictional issue, which would be required to be decided by the arbitrator under Section 16, and not the High Court at the pre-reference stage under Section 11 of the Act. Once the existence of the arbitration agreement is not disputed, all issues, including jurisdictional objections are to be decided by the arbitrator.

7.14. In the present case, the issue of limitation was raised by the respondent Company to oppose the appointment of the arbitrator under Section 11 before the High Court. Limitation is a mixed question of fact and law. In ITW Signode (India) Ltd. v. CCE [ITW Signode (India) Ltd. v. CCE, (2004) 3 SCC 48] a three-Judge Bench of this Court held that the question of limitation involves a question of jurisdiction. The findings on the issue of limitation would be a jurisdictional issue. Such a jurisdictional issue is to be determined having regard to the facts and the law. Reliance is also placed on the judgment of this Court in NTPC Ltd. v. Siemens Atkeingesellschaft [NTPC Ltd. v. Siemens Atkeingesellschaft, (2007) 4 SCC 451] , wherein it was held that the Arbitral Tribunal would deal with limitation under Section 16 of the 1996 Act. If the tribunal finds that the claim is a dead one, or that the claim was barred by limitation, the adjudication of these issues would be on the merits of the claim. Under sub-section (5) of Section 16, the tribunal has the obligation to decide the plea; and if it rejects the plea, the arbitral proceedings would continue, and the tribunal would make the award. Under sub-section (6) a party aggrieved by such an arbitral award may challenge the award under Section 34.

In Iffco Ltd. v. Bhadra Products [Iffco Ltd. v. Bhadra Products, (2018) 2 SCC 534 : (2018) 2 SCC (Civ) 208] this Court held that the issue of limitation being a jurisdictional issue, the same has to be decided by the

NEUTRAL CITATION NO. 2025:MPHC-JBP:36954

10 AC-68-2018 tribunal under Section 16, which is based on Article 16 of the Uncitral Model Law which enshrines the kompetenz principle.

10. This view has also been taken by the Larger Bench of the Hon'ble Apex Court in the case of Central Organisation for Railway Electrification v. ECI SPIC SMO MCML (JV), (2025) 4 SCC 641, wherein it is held that at the stage of deciding an application for appointment of an Arbitrator, the Court must not conduct an intricate enquiry into the matter, where the claim raised by the applicant is time barred and should be left open for determination by the Arbitrator. Such an approach gives true meaning to the view taken in the case of Interplay Between Arbitration Agreements under Arbitration, 1996 & Stamp Act, 1899, In re, (2024) 6 SCC 1.

11. When the case of the applicant is tested on the anvil of the law laid down by Hon. Apex Court and the law cited by the non-applicant, this court is of the considered opinion that now the consistent view of the Hon. Apex court is that all the questions going to the root including limitation and jurisdiction are to be decided by the Arbitrator.

12. In the case of BSNL (supra) the Hon. Apex Court in Para 38-39 has discussed about the limitation on the ground of breach of contract. However, in the present case, the question is only that whether the payment of bills made by the non-applicant constitutes a dispute between the parties which can be settled as per the mechanism provided under the agreement.

13. The Apex Court in the case of SBI General Insurance Co. Ltd. Vs. Krish Spinning, 2024 SCC Online 1754 has held as under :-

108. Section 11 of the Act, 1996 is provided to give effect to the mutual intention of the parties to settle their disputes by arbitration in situations where the parties fail to appoint an arbitrator(s). The parameters of judicial review laid down for Section 8 differ from those

NEUTRAL CITATION NO. 2025:MPHC-JBP:36954

11 AC-68-2018 prescribed for Section 11. The view taken in SBP & Co. (supra) and affirmed in Vidya Drolia (supra) that Sections 8 and 11 respectively of the Act, 1996 are complementary in nature was legislatively overruled by the introduction of Section 11(6-A) in 2015. Thus, although both these provisions intend to compel parties to abide by their mutual intention to arbitrate, yet the scope of powers conferred upon the courts under both the sections are different.

110. The scope of examination under Section 11(6-A) is confined to the existence of an arbitration agreement on the basis of Section 7.

The examination of validity of the arbitration agreement is also limited to the requirement of formal validity such as the requirement that the agreement should be in writing.

111. The use of the term 'examination' under Section 11(6-A) as distinguished from the use of the term 'rule' under Section 16 implies that the scope of enquiry under section 11(6-A) is limited to a prima facie scrutiny of the existence of the arbitration agreement, and does not include a contested or laborious enquiry, which is left for the arbitral tribunal to 'rule' under Section 16. The prima facie view on existence of the arbitration agreement taken by the referral court does not bind either the arbitral tribunal or the court enforcing the arbitral award.

14. Taking guidance from the decision of the Hon. Apex court in the case of SBI General Insurance Co. Ltd. (supra) , this Court is of the view that application is within limitation from the date of notice dated 18.1.2017 and, therefore, even if non applicant has raised any question in regard to the limitation can be resolved by the Arbitrator. Non-applicants are free to take all the objections before the Arbitrator and the Arbitrator as per the scheme and legislative intent of section 11 (6)(a) would decide all the questions.

15. Considering the totality of the case and the enunciation of law laid down by the Hon. Apex court, the application is allowed.

16. With the consent of learned counsel for the parties and considering the list of empanelled Arbitrator issued by the M.P. Arbitration Centre, Jabalpur, following order is passed :-

(i) Justice Shri S.S.Jha, Former Judge, High Court of M.P., 914-915, Gol Bazar, Jabalpur, Mob. No.94251-10066 e-mail [email protected] is

NEUTRAL CITATION NO. 2025:MPHC-JBP:36954

12 AC-68-2018 appointed as sole Arbitrator to resolve the dispute between the parties in the case.

(ii) Arbitrator shall issue the notices and fix the date and suitable venue for arbitration. Said arbitration will take place at Jabalpur.

(iii) Parties are directed to deposit necessary charges and fees as per M.P. Arbitration Center (Domestic and International) Rules, 2019.

(iv) Director of Madhya Pradesh Arbitration Centre [Domestic and International, Jabalpur (M.P.D.I.A.C.)] shall communicate the decision of this Court to the Sole Arbitrator.

(v) Other provisions of Section 15(3)(4) of the Arbitration and Conciliation Act, 1996 will apply to Substitute Arbitrator.

17. Arbitration case is disposed of.

(DEEPAK KHOT) JUDGE

HS

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter