Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The State Of Madhya Pradesh vs Kamal Nayan Agrawal
2025 Latest Caselaw 2372 MP

Citation : 2025 Latest Caselaw 2372 MP
Judgement Date : 1 August, 2025

Madhya Pradesh High Court

The State Of Madhya Pradesh vs Kamal Nayan Agrawal on 1 August, 2025

Author: Vivek Rusia
Bench: Vivek Rusia
         NEUTRAL CITATION NO. 2025:MPHC-IND:20361




                                                              1                               AR-29-2023
                            IN      THE      HIGH COURT OF MADHYA PRADESH
                                                    AT INDORE
                                                       BEFORE
                                          HON'BLE SHRI JUSTICE VIVEK RUSIA
                                                          &
                                     HON'BLE SHRI JUSTICE BINOD KUMAR DWIVEDI
                                                  ON THE 1 st OF AUGUST, 2025
                                            ARBITRATION REVISION No. 29 of 2023
                                     THE STATE OF MADHYA PRADESH AND OTHERS
                                                      Versus
                                              KAMAL NAYAN AGRAWAL
                         Appearance:
                                  Shri Sudeep Bhargava - Deputy Advocate General for the applicant /
                         State.

                                                                  ORDER

Per: Justice Binod Kumar Dwivedi

Heard on I.A.No.3579/2023, which is an application under Section 5 of the Limitation Act for condonation of delay.

02. There is a delay of 113 days in filing the revision.

03. On due consideration, application is allowed for the reasons stated therein and delay in filing the revision is hereby condoned.

04. Heard on admission.

05. Feeling aggrieved by the award dated 11/10/2022 (Annex.-A/1) passed in Reference Case No.332024 by Madhya Pradesh Arbitration Tribunal, Bhopal (for short hereinafter referred as, 'Tribunal'), this revision petition under Section 19 of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983 (for short hereinafter referred as, 'Adhiniyam') has been

NEUTRAL CITATION NO. 2025:MPHC-IND:20361

2 AR-29-2023 filed.

0 6 . Facts necessary for disposal of this revision petition are that respondent / Contractor entered into an agreement with the applicants for the work of construction of "120 Seater ITI Hostel Building at Ujjain including Electrification Work". The agreement No.27/2012 was executed between the parties and consequently work order was issued to the respondent Company on 29/11/2012. The work was to be completed within a period of 12 months including the rainy season. As per the Works Department Manual appendix 2.10 Clause 8 Special Condition, which is the part of contract / agreement as per the circular No.4386/3849/19/Yo/2011, dated 19/03/2011 issued by the Madhya Pradesh Public Works Department, the respondent was required to

prepare a working and structural drawing and get them approved from the competent authority.

07. The respondent / Contractor could not complete the project as he did not get the drawings approved from the applicants for the period of more than eight months, which caused a huge delay in completion of the project. Looking to the said delay, the applicants rescinded the contract as per rescinding Clause No.3-C of the contract / agreement. Multiple letters were issued to the respondent to appear before the competent authority, but respondent neither appeared before the competent authority nor filed any reply. Thereafter, the respondent / contractor has filed a claim / reference before the Tribunal for an amount of Rs.15,80,000/- and the same was refute by filing written statement on the part of the applicants.

0 8 . Learned Tribunal on the basis of pleadings after affording

NEUTRAL CITATION NO. 2025:MPHC-IND:20361

3 AR-29-2023 opportunity of adducing documentary as well as oral evidence, by the impugned order rejected all the claims except the Claim No.33/2014 by awarding an amount of Rs.2,00,000/- to the respondent with an interest @ 4% per annum, which gave rise to this arbitration revision.

09. Learned counsel for the applicants / State submits that there was no fault on the part of the applicants. It was the respondent / Contractor, who has committed error in complying with the terms and conditions of the agreement, which caused loss to the applicants, but without giving heed to the aforesaid, claim against the applicants have been passed, which is bad in law, therefore, pray for allowing the revision petition by setting aside the impugned award.

10. Heard and considered the submission raised by learned counsel for the applicants / State and perused the record.

11. Learned Tribunal has rejected all other claims raised by respondent / Contractor except claim No.3 with regard to loss of profit and in this claim Rs.2,00,000/- with interest @ 4% per annum from 26/02/2014 has been awarded. The aforesaid claim No.3 has been dealt with in para No. 57 to 61 dealing with the pleadings and evidence adduced in support of the pleading.

12. Relying upon the judgment by Apex Court in Maula Bux vs. Union of India (1969) 2 SCC 554 and Dwaraka Das vs. State of M.P. (1999) 3 SCC 500 , learned Tribunal has reached to the conclusion that had structural drawing and design been submitted by the respondent and has been approved by the applicants in time, certainly he would have been in a position to complete the work in stipulated time and would have earned that much profit which he was legally

expecting. Delay caused by the applicants in approval of the aforesaid structural

NEUTRAL CITATION NO. 2025:MPHC-IND:20361

4 AR-29-2023 drawing and design and after that as per Clause 14 of the agreement and Clause 3(C) of the same by Ex.P/13 agreement was cancelled which deprived the respondent from getting the due profit, therefore, looking to the facts and circumstances of the case, learned Claims Tribunal reached to the conclusion that an amount of Rs.2,00,000/- with interest @ 4% per annum from the date of filing of Reference Petition i.e. 26/02/2014 should be awarded to the respondent / Contractor for the loss of the profit and accordingly allowed the claim with respect to the above.

13. In the considered opinion of this Court, no illegality, irregularity or impropriety has been found in allowing the aforesaid Claim No.3 for compensating the respondent. As held by the Hon'ble Apex Court in Nalakath Sainuddin Vs. Koorikadan Sulaiman reported in (2002) 6 SCC 1 , the scope of revisional Court for interfering with the order under challenge is limited one, therefore, it is not expected of the Court to interfere unless exceptional circumstances wherein admissible evidence has not been considered and inadmissible evidence has taken into consideration for passing the award / order / judgment. The paragraph 17 of the aforesaid judgment can aptly be reproduced which runs as under:-

"17........

.........

(ii) Once a revision petition is entertained by the High Court, whichever by the party invoking the revisional jurisdiction, the High Court acquires jurisdiction to call for and examine the records of the authority subordinate to it. The records relating to "any order" and/or any proceedings, are available to be examined by the High Court for the purpose of satisfying itself as to the (a) legality, (b) regularity, or

(c) propriety of the impugned order, including any part of the order, or proceedings. The only limitation on the scope of the High Court's

NEUTRAL CITATION NO. 2025:MPHC-IND:20361

5 AR-29-2023 jurisdiction is that the order or proceedings sought to be scrutinized must be of the subordinate authority. Any illegality, irregularity or impropriety coming to its notice is capable of being corrected by the High Court by passing such appropriate order or direction as the law requires and justice demands."

14. Resultantly, this revision is sans merit, fails and is hereby dismissed.

                                   (VIVEK RUSIA)                                (BINOD KUMAR DWIVEDI)
                                       JUDGE                                            JUDGE
                         Tej / Soumya

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter