Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Madhya Pradesh Paschim Kshetra ... vs G.R. Infraprojects Ltd. Through ...
2023 Latest Caselaw 3044 MP

Citation : 2023 Latest Caselaw 3044 MP
Judgement Date : 20 February, 2023

Madhya Pradesh High Court
Madhya Pradesh Paschim Kshetra ... vs G.R. Infraprojects Ltd. Through ... on 20 February, 2023
Author: Sushrut Arvind Dharmadhikari
1

      IN    THE    HIGH COURT         OF MADHYA
                         PRADESH
                       AT INDORE
                           BEFORE
           HON'BLE SHRI JUSTICE SUSHRUT ARVIND
                     DHARMADHIKARI
                              &
    HON'BLE SHRI JUSTICE PRAKASH CHANDRA GUPTA

               ON THE 20th OF FEBRUARY, 2023




                  WRIT APPEAL No. 167 of 2023

BETWEEN:-
   MADHYA PRADESH PASCHIM KSHETRA VIDYUT VITRAN COMPANY
1. LTD. THROUGH SUPERINTENDING ENGINEER MPPKVV COMPANY
   LIMITED DISTRICT JHABUA (MADHYA PRADESH)
   MADHYA PRADESH PASCHIM KSHETRA VIDHYUT VITRAN
2. COMPANY LTD. THR MANAGING DIRECTOR MPPKVV R/O MPPKVV
   GPH COMPOUND POLO GROUND INDORE (MADHYA PRADESH)
   MADHYA PRADESH PASCHIM KSHETRA VIDHYUT VITRAN
3. COMPANY LTD. THROUGH SUPERITENDING ENGINEER HT
   BILLING CELL MPPKVV CO. LTD. INDORE (MADHYA PRADESH)
                                                .....APPELLANT
(SHRI ANSHUMAN SHRIVASTAVA, LEARNED COUNSEL FOR THE
APPELLANTS)

AND
   G.R. INFRAPROJECTS LTD. THROUGH AUTHORIZED PERSON MOTI
   BHATNAGAR S/O SHRI MAHENDRA SINGH BHATNAGAR
1.
   WHITEWOOD 202ND FLOOR MALIBU TOWNE GURGRAM
   (HARYANA)
   THE STATE OF M.P. THROUGH PRINCIPAL SECRETARY ENERGY
2.
   DEPARTMENT VALLABH BHAWAN, BHOPAL (MADHYA PRADESH)
                                           .....RESPONDENTS
 2

       This appeal coming on for admission this day, JUSTICE
SUSHRUT ARVIND DHARMADHIKARI passed the following:

                                  ORDER

Heard on the question of admission and interim relief. This intra-court appeal under Section 2 (1) of the M.P. Uchcha Nyayalaya (Khand Nyaayapeeth Ko Appeal) Adhiniyam 2005 assails the final order dated 14.09.2022 passed in W.P. No.9654/2021. In the writ petition, the petitioner had prayed for the following reliefs:-

"(i) That this petition may kindly be allowed and an appropriate writ, order of direction be issued to quash the impugned demand dated 22.03.2021 (Annexure P-1) with annexed Audit Report Para and Notice dated 13.05.2021 (Annexure P-2) issued by respondent No. 2.

(ii) That, any other relief as deemed fit may kindly be granted by the Hon'ble Court."

2. The facts giving rise to filing of this appeal are that the appellants are the partnership firms and own a stone crusher unit. The appellants had applied for permanent electricity HT connection of 500 KVA. An agreement was entered into between the parties on 30.06.2020. The requisite deposit and fees etc. have also been deposited by the appellants at the time of execution of the agreement. However, on the basis of some report of the Comptroller and Auditor General of India (CAG) conducted at different places, demand notice was issued to the appellants, which was challenged in the writ petitions whereby the appellants were made liable to pay the amount as per audit recovery and that the connections granted were treated as temporary connection for billing purposes. The learned single Judge while deciding the batch of writ petitions held as under:-

"10] On due consideration of submissions and perusal of the documents filed on record as also the decision rendered by the Supreme Court in the case of U.P. Power Transmission Corporation Limited (Supra), this Court finds that so far as

the audit recovery on the basis of the report of Comptroller and Auditor General of India is concerned, the Supreme Court in the aforesaid case has held as under:-

"60. As observed above, UPPTCL demanded and partly realized cess on the supply Contract, solely on the basis of report of the CAG. In our considered view, in the absence of any adjudication, it was impermissible for UPPTCL to issue the impugned communication to realize cess solely on the basis of the report of the CAG.

61. In Centre of Public Litigation v. Union of India reported in (2012) 3 SCC 1, this Court held that when CAG report was subject to scrutiny of the Public Accounts Committee and the Joint Parliamentary Committee, it would not be proper to refer to to findings and conclusions contained therein. In this context, reference may also be made to the decision of this Court in Arun Kumar Agrawal v. Union of India and Others reported in where this Court held:-

"56. CAG may be right in pointing out that public monies are to be applied for the purposes prescribed by Parliament and that extravagance and waste are minimised and that sound financial practices are encouraged in estimating and contracting, and in administration generally.

67. The question that is germane for consideration in this case is whether this Court can grant reliefs by merely placing reliance on the CAG's Report. The CAG's Report is always subject to parliamentary debates and it is possible that PAC can accept the ministry's objection to the CAG Report or reject the report of the CAG. The CAG, indisputably is an independent constitutional functionary, however, it is for Parliament to decide whether after receiving the report i.e. PAC to make its comments on the CAG's Report."

(emphasis supplied)

11] In view of the above, this Court is of the considered opinion that the aforesaid finding recorded by the Supreme Court applies mutatis-mutandis to the facts of the present case as well. It is also found that although the demand has been raised by taking exception to the agreement executed between the parties itself, holding that the connection granted to the petitioner ought to have been temporary in nature instead to permanent but, till date even the aforesaid agreement has not been repudiated by the respondents. It is also found that although the petitioner is involved in the business of stone crushing, but it cannot be said that the aforesaid unit is for the construction purpose as the construction purpose would mean, construction of buildings/power plants etc. and for the purpose of setting up of industrial units as is prescribed in Rule 4.43 of the M.P. Electricity Supply Code, 2013 which reads as under:-

"4.43 Any person requiring power supply for purpose that is temporary in nature, may apply for temporary power supply for a period of less than two years in the Form as required by the Licensee. The period of temporary connection can be extended up to five years for construction of buildings/power plants and for the purpose of setting up of industrial units. Requisition for temporary supply shall normally be given 7 days before the day when supply is required for loads up to 10 kW and 30 days before for higher the said loads Under no circumstances, permanent connection be allowed for construction purposes."

12] It might be that the need of the petitioner was temporary, but as the agreement has been executed by the respondent Licensee who is a State within the ambit of Art.12 of the Constitution of India, for permanent connection, no retrospective recovery can be made on the basis that the agreement was wrongly

executed as it was supposed to be for temporary connection. This is for the reason that as the subsequent denial on the part of the respondent would be in violation of the doctrine of promissory estoppel, as the petitioner has altered his position on the basis of the agreement between the parties. Thus, on this count, as also on the ground that the impugned demand notice has been issued by the respondents without complying with the provisions of the Comptroller and Auditor-General's (Duties, Powers and etc.) Act, 1971 or any violation of the order passed by the Supreme Court in the case of U.P. Power Transmission Corporation Limited (Supra), the impugned demand notice cannot be sustained. 13] Resultantly, the petitions stand allowed and the impugned demand notices are hereby set aside. It is found that the petitioner has paid certain amount to the respondents as directed by this Court while granting interim relief vide order dated 13.07.2021 and 18.08.2021, it is directed that the amount paid by the petitioner shall also be remitted back to the petitioner with the applicable bank interest rate within a period of one month from the date of receipt of certified copy of this order."

3. Learned counsel for the appellants contended that the respondent has straightway issued the demand notice even without there being any adjudication merely on the basis of Comptroller & Auditor General's report. He further contended that the respondents have been found to be involved in the construction business and were carrying on its business for the purposes of providing raw material to contractors constructing the roads, therefore, the respondent's business is closely connected with the construction work as per Clause 4.43 of the M.P. Electricity Supply Code, 2013 and, that permanent connections cannot be given for construction

purposes. The learned single Judge erred in allowing the writ petitions without considering the nature of work being carried out by the respondents, hence, the writ appeals deserve to be allowed.

4. Learned counsel for the respondents have vehemently opposed the prayer and submitted that the respondents have already applied for electricity disconnection. They have placed reliance upon the judgment of the Apex Court delivered in the case of U.P. Power Transmission Corporation Limited and Another Vs. CG Power and Industrial Solutions Limited and Another reported as (2021) 6 SCC 15 wherein the Apex Court in no uncertain terms held that "in the absence of any adjudication, it is impermissible for the power generating company to issue the communication to realize cess solely on the report of the CAG".

5. Learned single Judge relying on the judgment delivered in the case of U.P. Power Transmission Corporation Limited and Another (supra) allowed the writ petitions and directed the appellants herein to refund the amount to the respondents with applicable bank interest rate within a period of one month from the date of receipt of certified copy of the order.

6. This Court does not find any error in the order passed by the learned single Judge particularly in view of the fact that the agreement is still in existence. Moreover, instead of issuing show-cause notice to the respondents, the appellants have straightway issued the demand notice without there being any adjudication or following the principles of natural justice. Learned single Judge has not committed any error so as to interfere in the order passed in the batch of writ petitions. However, the learned single Judge ought to have granted liberty to the appellants to proceed in accordance with law against the respondents.

7. In view of the aforesaid, the order passed by the learned single Judge is modified to the extent that the appellants would be at liberty to take action in accordance with law prospectively, if so advised.

Accordingly, this writ appeal is disposed of.

(S.A.Dharmadhikari) (Prakash Chandra Gupta) Judge Judge

Patil Digitally signed by SHAILESH PATIL DN: c=IN, o=HIGH COURT OF MADHYA PRADESH BENCH INDORE, ou=JUDICIAL, postalCode=452001, st=Madhya Pradesh, 2.5.4.20=837fe9c27fdece0f7f4ec7150827760f68 beff4d709b9f59439e1d51ace79637, pseudonym=663F17CE27594B9E54AA3BAB05B 4295B155F651B, serialNumber=3E01C00D600649CCA413655933 37DEF53CC3D6A3E63493017489D6D6B6975E7 F, cn=SHAILESH PATIL Date: 2023.02.21 10:07:00 +05'30'

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter