Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Phaloudi Constructions And ... vs Indore Smart City Development ...
2023 Latest Caselaw 13801 MP

Citation : 2023 Latest Caselaw 13801 MP
Judgement Date : 23 August, 2023

Madhya Pradesh High Court
Phaloudi Constructions And ... vs Indore Smart City Development ... on 23 August, 2023
Author: Pranay Verma
                                                    1


                          IN THE HIGH COURT OF MADHYA PRADESH
                                       AT INDORE
                                                  BEFORE
                                   HON'BLE SHRI JUSTICE SUSHRUT ARVIND
                                             DHARMADHIKARI
                                                     &
                                   HON'BLE SHRI JUSTICE PRANAY VERMA
                                        WRIT PETITION No. 15445 of 2022

                          BETWEEN:-
                          PHALOUDI       CONSTRUCTIONS        AND
                          INFRASTRUCTURE     PVT.   LTD. THROUGH
                          DIRECTOR MANISH S/O SHRI BALKRISHNA
                          GUPTA, AGED ABOUT 47 YEARS, OCCUPATION:
                          BUSINESS ADDRESS -203 PANAMA TOWER NEAR
                          HOTEL CROWN PALACE KANCHAN BAGH,
                          INDORE (MADHYA PRADESH)
                                                                             .....PETITIONER
                          (BY SHRI SUNIL JAIN- SENIOR ADVOCATE WITH SHRI
                          AYUSHMAN CHOUDHARY - ADVOCATE)

                          AND

                          1.    INDORE SMART CITY DEVELOPMENT
                                LTD., THROUGH    CHIEF  EXECUTIVE
                                OFFICER, SMART CITY OFFICE, NEHRU
                                PARK   CAMPUS,   INDORE  (MADHYA
                                PRADESH)

                          2.    STATE OF MADHYA PRADESH THROUGH
                                THE PRINCIPAL SECRETARY, ADDRESS-
                                URBAN    DEVELOPMENT,     VALLABH
                                BHAWAN, BHOPAL (MADHYA PRADESH)
                                                                           .....RESPONDENTS
                          (BY SHRI MANOJ MUNSHI - ADVOCATE FOR RESPONDENT NO.1 )

                                        WRIT PETITION No. 19451 of 2022

                          BETWEEN:-


Signature Not Verified
Signed by: JYOTI
CHOURASIA
Signing time: 23-Aug-23
4:52:28 PM
                                                         2


                          SARTHAK INDUSTRIES LTD. THROUGH ITS
                          DIRECTOR YOGENDRA MOHAN SHARMA
                          S/O SHRI SHANTI LAL SHARMA, AGED
                          ABOUT 70 YEARS, OCCUPATION: SERVICE,
                          ADDRESS - 214 TRADE CENTRE SOUTH
                          TUKOGANJ, INDORE (MADHYA PRADESH)

                                                                                 .....PETITIONER
                           (BY SHRI SUDHANSHU DIXIT - ADVOCATE)

                               AND

                          1.      INDORE SMART CITY DEVELOPMENT
                                  LTD. THROUGH CHIEF EXECUTIVE
                                  OFFICER SMART CITY OFFICE NEHRU
                                  PARK CAMPUS INDORE (MADHYA
                                  PRADESH)

                          2.      THROUGH      THE      PRINCIPAL
                                  SECRETARY URBAN DEVELOPMENT
                                  VALLABH     BHAWAN     DISTRICT
                                  BHOPAL. (MADHYA PRADESH)

                                                                              .....RESPONDENTS
                          (BY SHRI MANOJ MUNSHI - ADVOCATE FOR RESPONDENT NO.1 )

                          Reserved on   : 24.07.2023
                          Pronounced on : 23.08.2023


                                    These petitions having been heard and reserved for orders,
                          coming on for pronouncement this day, HON'BLE JUSTICE PRANAY
                          VERMA pronounced the following.

                                                         ORDER

Since common questions of facts and law are involved in both the petitions, they have been heard together and are being decided by a common order. Facts are being taken from Writ Petition No.15445 of 2022.

Signature Not Verified Signed by: JYOTI CHOURASIA Signing time: 23-Aug-23 4:52:28 PM

2. By this petition preferred under Article 226 of the Constitution of India, the petitioner has challenged the letter/order dated 29.06.2022 issued by respondent No.1 whereby the Notice Inviting Tender dated 01.07.2020 has been cancelled and the earnest money deposited by the petitioner company has been directed to be refunded. The petitioner has also challenged the order dated 08.07.2022 passed by respondent No.1 by which the Letter of Acceptance issued in favour of the petitioner has also been cancelled.

3. As per the petitioner, respondent No.1/Indore Smart City Development Limited issued a notice inviting tender (For short 'NIT') dated 01.07.2020 for the work of -"Real Estate Mixed Use Redevelopment Projects at MOG Lines- Old Government Quarters Land Parcel for sale on freehold basis for construction of mixed used High Rise Towers, for plot No.3" The last date for purchase of tender and its submission online was 04.08.2020 and the technical bid was to be opened online on 05.08.2020. The said dates were amended by respondent No.1 from time to time by issuing various corrigendum and eventually the last date for purchase of tender form (online) and submission of tender online was 27.10.2020 up to 5:30 pm. The date for opening technical bid (online) was 28.07.2020. The petitioner Company submitted its application/bid along with all necessary requisites documents and details as required under the NIT on 12.10.2020 along with earnest money of Rs.50,00,000/-. The financial bid of the petitioner was of Rs.25,88,88,888/-.

4. After opening of the technical and financial bid the petitioner Company was orally informed by Officer of respondent No.1 that its bid has been accepted and letter of acceptance (For short 'LOA') will be

Signature Not Verified Signed by: JYOTI CHOURASIA Signing time: 23-Aug-23 4:52:28 PM

issued in its favour very soon. Thereafter, the petitioner Company acquired knowledge that residents of MOG lines have preferred a PIL bearing W.P. No.14656 of 2020 before this Court against directions issued by the State Government for vacating their respective allotted units. In the petition, by order dated 03.03.2021 three months' time was granted to the residents for vacating their allotted residential units. The said period was further extended by order dated 13.08.2021 and 12.11.2021 passed in Review Petition No.425 of 2021 and Review Petition No.659 of 2021 respectively. In the meanwhile, the application/bid submitted by the Petitioner Company was accepted by respondent No.1 and LOA was communicated to the petitioner on 02.07.2021. The petitioner was asked to initiate process as directed in the LOA and was directed to submit bank guarantee of Rs.2,58,88,889/- and to sign the contract agreement at stamp value of Rs.2,58,889/- within thirty days.

5. Upon receiving the LOA, the petitioner vide its letter dated 03.07.2021 informed respondent No.1 that in light of clarification/circular issued by office of Inspector General Registration and Superintendent of Stamp M.P., the Stamp Duty for Works Contract has been fixed at minimum Rs.500/- and maximum Rs.25,000/- subject to be calculated at the rate of 0.25% of contract amount. The petitioner requested respondent No.1 to issue a fresh LOA after carrying out the necessary amendment as suggested. No communication was received from respondent No.1 hence the petitioner issued reminder letters on 12.11.2021 and 03.05.2021 to it requesting for issuance of revised LOA at an early date so that the requisite agreement could be executed between the parties. The respondent No.1 however, by the impugned order dated 29.06.2022 has

Signature Not Verified Signed by: JYOTI CHOURASIA Signing time: 23-Aug-23 4:52:28 PM

cancelled the NIT itself and has refunded the earnest money to the petitioner on 01.07.2022. During pendency of the petition, by order dated 08.07.2022 the LOA issued in favour of the petitioner has also been cancelled.

6. Learned senior counsel for the petitioner has submitted that respondent No.1 has acted arbitrarily and illegally in recalling the NIT and cancelling the bid of the petitioner and the LOA issued in its favour. No reasons have been assigned for the same in the impugned orders which are non-speaking orders and the cancellation is without application of mind. The impugned order has been issued by respondent No.1 unilaterally and without following principles of natural justice. Before withdrawal of LOA and cancellation of tender no opportunity of hearing was given to the petitioner nor was any show cause notice issued to it. After issuance of LOA the contract was completed/concluded hence there was no question of withdrawal of the NIT and the bid submitted by the petitioner. Upon issuing such letter respondent No.1 crossed the stage of cancelling the NIT and bid submitted by the petitioner. Due to the action of respondent No.1 petitioner has suffered huge financial loss as in anticipation of starting the project it kept ready the funds required for the project which otherwise could have been utilized in some other project. The impugned orders hence cannot be legally sustained. Reliance has been placed on the decisions of the Supreme Court in Vice Chairman & Managing Director, City and Industrial Development Corporation of Maharashtra Ltd. and Another vs. Shishir Realty Private Limited and Others 2021 SCC Online SC 1141, Mohinder Singh Gill and another Vs. Chief Election Commissioner New Delhi and others (1978) 1 SCC 405, State of Punjab Vs. Bandeep Singh and others

Signature Not Verified Signed by: JYOTI CHOURASIA Signing time: 23-Aug-23 4:52:28 PM

(2016) 1 SCC 724 and of the Orissa High Court in M/s Krishik Infrastructure Developers Pvt. Ltd. vs. Orissa Industrial Infrastructure Development Corporation and others AIR 2018 Ori 139 and SRB Transport, Sambalpur vs. Union of India and Ors., W.P.(C) NO.2430 of 2022 decided on 14.02.2022.

7. Reply has been filed by respondent No.1 and learned counsel for respondent No.1 has submitted that during tender process a PIL bearing W.P. No.14656 of 2020 was filed before this Court in which an interim order was passed on 29.09.2020 directing not to evict any person from M.O.U. lines over which the Smart City Project has to be developed. This was the project covered under the present NIT. The PIL was finally disposed off by order dated 03.03.2021 granting the occupants of the accommodation three months' time for vacating the same. The said period was extended by six months vide order dated 13.08.2021 passed in R.P. No.425 of 2021. Thereafter, another Review Petition No.659 of 2021 was preferred which was disposed off vide order dated 12.11.2021 granting liberty to respondent No.1 to proceed in respect of the building which have been vacated completely. After disposal of the PIL on 03.03.2021, LOA in favour of the petitioner was issued on 08.06.2021 directing it to submit 10% quoted amount as per payment schedule of Rs.2,58,88,889/- in the form of bank guarantee and to sign contract agreement on stamp value of Rs.2,58,889/- within 30 days. The agreement however, could not be executed between the parties due to pendency of the aforesaid Review Petitions. Respondent No.1 was hence constrained to take the decision to cancel the NIT and to issue fresh NIT due to pendency of litigation before this Court for a period of almost one and a half year in respect of eviction of M.O.J. Lines Government

Signature Not Verified Signed by: JYOTI CHOURASIA Signing time: 23-Aug-23 4:52:28 PM

quarters. Due to non-execution of the agreement and non-submission of bank guarantee by petitioner no legal right has been created in its favour. Reliance has been placed on the decisions of the Supreme Court in Silppi Constructions Contractors vs. Union of India and Another (2020) 16 SCC 489, State of Jharkhand and Others vs. M/s CWE - SOMA Consortium, (2016) 14 SCC 172, South Eastern Coalfields Ltd. and Others vs. S. Kumar's Associates AKM (JV), (2021) 9 SCC 166 and of the High Court of Delhi in Manmeet Singh Vs. South Delhi Municipal Corporation WP(C) 3811/2020 and Rajesh Kumar Singh Vs. South Delhi Municipal Corporation WP(C) 4020/2020 decided on 21.07.2020.

8. In rejoinder, the learned senior counsel for the petitioner has submitted that the agreement could not be executed between the parties due to fault/lapses on part of respondent No.1. Merely for non-furnishing of bank guarantee by the petitioner it cannot be said that no right had accrued in its favour. Petitioner was ready to submit the bank guarantee but its repeated requests to issue a fresh LOA and to execute the agreement fell on deaf ears. The ground of non-submission of bank guarantee by the petitioner has been raised by respondent No.1 for the first time in the reply hence it cannot be permitted to supplement the reasons at this stage.

9. We have heard the learned counsel for the parties at length and have perused the record.

10. The Supreme Court in a catena of judgments has laid down the principles with regard to judicial review in contractual matters. They have been summed up in a recent decision in the case of Silppi Constructions

Signature Not Verified Signed by: JYOTI CHOURASIA Signing time: 23-Aug-23 4:52:28 PM

Contractors (Supra) in which after referring to several decisions on this issue it has been eventually held in paragraph No.19 and 20 as under:-

"19. This Court being the guardian of fundamental rights is duty-bound to interfere when there is arbitrariness, irrationality, mala fides and bias. However, this Court in all the aforesaid decisions has cautioned time and again that courts should exercise a lot of restraint while exercising their powers of judicial review in contractual or commercial matters. This Court is normally loathe to interfere in contractual matters unless a clear-cut case of arbitrariness or mala fides or bias or irrationality is made out. One must remember that today many public sector undertakings compete with the private industry. The contracts entered into between private parties are not subject to scrutiny under writ jurisdiction. No doubt, the bodies which are State within the meaning of Article 12 of the Constitution are bound to act fairly and are amenable to the writ jurisdiction of superior courts but this discretionary power must be exercised with a great deal of restraint and caution. The Courts must realise their limitations and the havoc which needless interference in commercial matters can cause. In contracts involving technical issues the courts should be even more reluctant because most of us in Judges' robes do not have the necessary expertise to adjudicate upon technical issues beyond our domain. As laid down in the judgments cited above the courts should not use a magnifying glass while scanning the tenders and make every small mistake appear like a big blunder. In fact, the courts must give "fair play in the joints" to the government and public sector undertakings in matters of contract. Courts must also not interfere where such interference will cause unnecessary loss to the public exchequer.

20. The essence of the law laid down in the judgments referred to above is the exercise of restraint and caution; the need for overwhelming public interest to justify judicial intervention in matters of contract involving the state

Signature Not Verified Signed by: JYOTI CHOURASIA Signing time: 23-Aug-23 4:52:28 PM

instrumentalities; the courts should give way to the opinion of the experts unless the decision is totally arbitrary or unreasonable; the court does not sit like a court of appeal over the appropriate authority; the court must realise that the authority floating the tender is the best judge of its requirements and, therefore, the court's interference should be minimal. The authority which floats the contract or tender, and has authored the tender documents is the best judge as to how the documents have to be interpreted. If two interpretations are possible then the interpretation of the author must be accepted. The courts will only interfere to prevent arbitrariness, irrationality, bias, mala fides or perversity. With this approach in mind we shall deal with the present case."

11. The present matter has hence to be examined in light of the above settled legal principles. The contention of the petitioner is that upon issuance of the LOA in its favour, a concluded contract came into existence between the parties and the same could not have been unilaterally cancelled by respondent No.1 in the manner as it has been done. Prior to the same it was imperative for respondent No.1 to have followed the principles of natural justice and issued notice to the petitioner and afforded it opportunity of hearing. Thus, it has to be seen whether any concluded contract came into existence between the parties.

12. The principles as regards a concluded contract coming into existence between the parties has been considered by the Supreme Court in the matter of South Eastern Coalfield Ltd. and Others (Supra) in which it has been held in paragraph No.20 as under:-

"20. We would like to state the issue whether a concluded contract had been arrived at inter se the parties is in turn dependent on the terms and conditions of the NIT, the LOI and the conduct of

Signature Not Verified Signed by: JYOTI CHOURASIA Signing time: 23-Aug-23 4:52:28 PM

the parties. The judicial views before us leave little doubt over the proposition that an LOI merely indicates a party's intention to enter into a contract with the other party in future. No binding relationship between the parties at this stage emerges and the totality of the circumstances have to be considered in each case. It is no doubt possible to construe a letter of intent as a binding contract if such an intention is evident from its terms. But then the intention to do so must be clear and unambiguous as it takes a deviation from how normally a letter of intent has to be understood. This Court did consider in Dresser Rand S.A. case that there are cases where a detailed contract is drawn up later on account of anxiety to start work on an urgent basis. In that case it was clearly stated that the contract will come into force upon receipt of letter by the supplier, and yet on a holistic analysis - it was held that the LOI could not be interpreted as a work order."

13. Thus, the issue is as to whether by issuance of LOA in favour of the petitioner a concluded contract came into existence between the parties. In the LOA the petitioner was directed to submit 10% of quoted amount as per payment schedule of Rs.2,58,88,889/- in the form of bank guarantee and sign the contract agreement on stamp value of Rs.2,58,889/- within 30 days of its issue. A plain reading of the aforesaid stipulations contained in the LOA leaves no room for doubt that no concluded contract came into existence between the parties merely on the basis of its issuance. It was not stated in the LOA that by mere issuance of the same, the contract would be deemed to have been entered into between the parties or that the contract is concluded by acceptance of the bid of petitioner and formal acceptance of tender will follow. On the contrary, the petitioner was directed to furnish bank guarantee as directed therein and to sign the contract agreement on a particular stamp value and that too within a period of 30 days. By mere issuance of the LOA binding

Signature Not Verified Signed by: JYOTI CHOURASIA Signing time: 23-Aug-23 4:52:28 PM

agreement came into existence which as per terms of the LOA would have come into existence only upon fulfillment of the conditions enumerated therein by the petitioner.

14. The petitioner admittedly did not furnish the bank guarantee as directed in the LOA and for the purpose of execution of the agreement raised a dispute as regards the amount of stamp on which the agreement was to be executed. Thus, in the facts and circumstances of the case, we have no hesitation in holding that no completed/concluded and binding contract came into existence between the petitioner and respondent No.1 by mere issuance of the LOA. The decisions relied upon by the learned senior counsel for the petitioner do not help him in any manner since in all of them an agreement had in fact been executed between the parties therein subsequent to issuance of the LOA hence a concluded contract had actually come in existence. In the present case no agreement has been executed between the parties. Moreover, the LOA issued in favour of the petitioner has been cancelled subsequent to withdrawal of the entire NIT itself hence there was no necessity or occasion for issuing any notice to the petitioner or affording it any opportunity of hearing. It is not a case where the NIT has been kept in existence and only the LOA issued in favour of the petitioner has been cancelled.

15. The further contention of the petitioner has been that the communication dated 29.06.2022 issued by respondent No.1 is a non- speaking order and hence is not sustainable in the eye of law in view of the judgments relied upon by him. The reasons which have been attempted to be supplied by respondent No.1 along with its reply and in the affidavit cannot be read into the communication to make good the

Signature Not Verified Signed by: JYOTI CHOURASIA Signing time: 23-Aug-23 4:52:28 PM

default. The said contention is wholly without merit. The communication dated 29.06.2022 is not a judicial order passed by respondent No.1 on the administrative side. It is only intimation to the petitioner of the decision taken to recall the entire tender process the consequence of which is that the LOA issued in favour of the petitioner also stood withdrawn.

16. In Ghanshyam Das Aggrawal Vs. Delhi Development Authority 1996 SCC Online Del 193 it was held by the Division Bench of the High Court of Delhi in paragraph No.15 as under:-

"(15) The observation made by the Supreme Court is binding on us, but we do not think it is going to make any difference in the case at hand. Firstly, the Rules and the Terms and Conditions of the Public Auction did not contemplate reasons for rejection of highest bid being communicated to the concerned bidders. There is a distinction between existence of reasons and assigning of reasons (see Shrilekha Vidyarthi ). The former is a requirement of natural justice, the later is a dictate of law. Reasons need not be assigned in the sense of being communicated to a party unless required to be so done by any Rule having force of law. Secondly, the reasons could have been made available if asked for. Thirdly, the reasons for rejection though not communicated and though not asked for by the petitioners before filing the petitions have been made available in the Court in response to the show cause notice issued and it would serve no useful purpose if we may dispose of the petitions merely by directing the respondents- DDA to communicate the reasons to the petitioner. The reasons now having been made known to the petitioners, they have been heard thereon. Whatever they had to say on such reasons they have said and we have also tested the validity of the reasons and have found nothing unreasonable therewith. That is an end of the matter."

17. In Sillpi Construction Contracts (Supra) also it was held in paragraph No.25 as under:-

"25. That brings us to the most contentious issue as to whether the learned single judge of the

Signature Not Verified Signed by: JYOTI CHOURASIA Signing time: 23-Aug-23 4:52:28 PM

High Court was right in holding that the appellate orders were bad since they were without reasons. We must remember that we are dealing with purely administrative decisions. These are in the realm of contract. While rejecting the tender the person or authority inviting the tenders is not required to give reasons even if it be a state within the meaning of Article 12 of the Constitution. These decisions are neither judicial nor quasi judicial. If reasons are to be given at every stage, then the commercial activities of the State would come to a grinding halt. The State must be given sufficient leeway in this regard. The Respondent nos. 1 and 2 were entitled to give reasons in the counter to the writ petition which they have done."

18. In the present case also, there is no term or condition in the tender document which may cast an obligation upon respondent No.1 to furnish reasons in case the entire tendering process is recalled. The petitioner has also not approached respondent No.1 for soliciting the reasons for recalling of the tender and withdrawal of its LOA. Instead, it has filed the petition with a grievance against the communication dated 29.06.2022 and 08.07.2022.

19. For the purpose of ascertaining as to why the entire tender process has been scraped by respondent No.1, the CEO of respondent No.1 was directed to furnish an affidavit and also to keep the record present. In compliance of the said order affidavit of Divyank Singh, Chief Executive Officer of respondent No.1 was filed on 28.01.2022 and at the time of hearing of this petition the original record of the case was also kept present. We have carefully perused the contents of the affidavit and have found the same to be factually correct from the record. In the

Signature Not Verified Signed by: JYOTI CHOURASIA Signing time: 23-Aug-23 4:52:28 PM

affidavit, the reasons which have been given for the cancellation of the NIT have been stated the relevant portions of which is as under:-

"7. I say that after opening of the financial bid, Letter of Acceptance dated 08/06/2021 have been issued to these successful bidders with the conditions of deposit of performance security amounting to 10%of the bid amount and execution of agreement. I say that the present petitioner 'did not comply these: conditions even till date after expiry of over 18 months period, whereas they were supposed to comply the same within 30 days. |

8. I say that during the tender Process, various writ petitions and review petitions were filed by the occupants of the Govt. houses and this Hon'ble Court vide order dated 29/09/2020 passed in W.P. No. 14656 of 2020 directed the Respondent Company not to evict the residents. This interim protection was vacated by this Hon'ble Court vide order dated: 03/03/2021 allowing the petitioners to vacate their houses within a period of 3 months i.e. up to 03/06/2021. However, this Hon'ble Court once again vide order dated 18/06/2021 and 13/08/2021 passed in R.P.No. 425 of 2021 extended the interim protection up to 31/12/2021. Finally, on an application filed by the Respondent Company, this Hon'ble Court vide order dated 12/11/2021 passed in. R.P. No. 651 of 2021 allowed the Respondent Company to use the vacant building for the purpose of redevelopment. Therefore; the entire project got delayed firstly, due to various interim orders passed by this Hon'ble Court and secondly due to Covid pandemic as the entire city was under lockdown.

9. I say that due to aforesaid reasons and more particularly due to non-deposition of performance security and execution of agreement as per LoA and delay of more than 1 years to implement the LoA, the Respondent Company decided to cancel the entire process of auction of Plot Nos. 2, 3 and 4 and to call fresh invitation as per Note Sheet nos. 63, 64 dated 18/06/2022 which is reproduced herein below:-

"NSP पर प्राप्‍त स्‍वीकृतत के क्रम में Real Estate mixed use redevelopment project at MOG line Old-quarters land parcel for sale on free hold basis for construction of mixed the high rise tower for Block No. 01,02,03 and 04 के व्‍यपन हेतु तिनाांक 01.07.2020 को तनतविाऐां जारी की गई, उक्‍त तनतविाओां में पृथक-पृथक ब्‍लॉक हेतु तनतविाकरोां द्वारा भाग तलया गया, तजसमें ब्‍लॉक क्रां. 02, 03, 04 हेतु तनम्‍नतलखित

Signature Not Verified Signed by: JYOTI CHOURASIA Signing time: 23-Aug-23 4:52:28 PM

तनतविाए प्राप्‍त हुई अतिकतम िर प्रस्‍तुत तकए गए तनतविाकरोां को तनतविा सतमतत द्वारा प्राप्‍त अनुशांसा के आिार पर Letter of Acceptance तिनाांक 08.06.2021 को जारी तकया गया तजसका तववरण तनम्‍नानुसार है:-

                               स. ब्‍लॉक        सफल निनिदाकार                         LOANo./Date
                               क्रं. क्र.
                               01     02    मेससस तीथसगोपीकॉन प्रा. 03/ISCDL/2021-22 Dated 08.06.2021
                                                            तल.
                               02     03           मेससस फलौिी            05/ISCDL/2021-22 Dated 08.06.2021

                                               कांस्‍ट्र क्‍शन एण्‍ड           .

                                              इन्‍फ्रास्‍ट्र चर प्रा. तल.
                               03     04    मेससस साथसक इण्‍डस्‍ट्र ीज 04/ISCDL/2021-22 Dated 08.06.2021
                                                       प्रा. तल.

उक्‍त तववरणानुसार सफल तनतविाकारोां को तिनाां क 08.06.2021 LOA जारी तकया गया तत्‍समय वैतिक स्‍तर पर चल रहे कोतवड-19 माहामारी के कारण स्‍माट्स तसट्ी तवभाग को एम.ओ.जी. लाईन खसथत आवां तट्त कायसस्‍थल पर तनवासरत शासकीय कमस चाररयोां द्वारा उच्‍च न्‍यायालय में यातचका िायर की जाकर स्‍थगन प्राप्‍त तकया गया। उच्‍च न्‍यायालय द्वारा तिनाां क 31.03.2022 तक का स्‍थगन आिे श पाररत तकया गया तथा इसके पश्‍चात् तवभाग द्वारा एम.ओ.जी. लाईन खसथत कायसस्‍थल पर खसथत सरकारी भवनोां को िाली तकए जाने हेतु तवतभन्‍न सरकारी तवभागोां को पत्र के माध्‍यम से सूतचत तकया जाकर कायसस्‍थल पर खसथत पुराने भवनोां को पत्र के माध्‍यम से सूतचत तकया जाकर कायसस्‍थल पर खसथत पुराने भवनोां को तोड़ने का कायस प्रगतत परी है , उक्‍त सांबांि में तवतित हो तक तवभाग द्वारा सफल तनतविाकारोां को जारी LOA को एक वर्स से भी अतिक समय व्‍यतीत हो चुका है एवां पूवस से उच्‍च न्‍यायालय में प्रकरण लांतबत होने के कारणवांश एजेतसांयोां द्वारा अनुबांि कायसवाही हेतु जमा की जाने वाले परामेंस बैंक ग्‍यारां ट्ी भी आज तिवस तक जमा नही ां की जाने कारण कायसवाही पू णस नही ां की जा सकती है। प्रकरण में उक्‍त तथ्‍योां को दृतिगत रिते हुए एवां तनतविा में उल्‍लेखित समयसीमा समाप्‍त होने के कारण ब्‍लॉक क्रमाां क 02,03,04 हेतु जारी LOA पर को तनरस्‍त कर पू वस में तैयार की गई तनतविा का पुन: आकलन तकया जाना उतचत होगा। अत: प्‍लाट् क्रां. 02, 03 एवां 04 हेतु जारी तकए गए LOA को तनरस्‍त तकया जाकर एवां समस्‍ते कायस योजना का नवीन प्रस्‍ताव तैयार कर नीवन तनतविा आमांतत्रत तकया जाना प्रस्‍तातवत हैा''

Signature Not Verified Signed by: JYOTI CHOURASIA Signing time: 23-Aug-23 4:52:28 PM

10. I say that after cancellation of the old bid for Plot Nos. 2, 3 and 4, a fresh tender was proposed on 23/07/2022 as per Note Sheet nos. 71 and 72 for auction of Plot nos. 3, 4, 10 and 11.

12. Tenders issued for Plot No. 3, 4, 11 vide NIT no. 25/ISCDL2022- 23 dated 03/09/2022 have been cancelled for the reasons stated in the Note Sheet no. 77 and 78 dated 08/12/2022 which is reproduced herein below:-

"Sub: Regarding cancellation of 'tenders and appointment of real 'estate transaction consultant for tendering process

In reference to the ongoing tendering process. of the Sale of MOG lines plots, the entire chronology of events is stated hereunder.

Tender for Plot 1234 were invited vide NIT No.18/ISCDL/2019- 20 Dated 01.07.2020. Subsequently, due to non-participation and request of the bidders "Key Dates" were extended multiple times till 27.10.2020. Further, the technical bid for plot 2, 3 and 4 were opened on 28.10.2020 wherein the no. of participating bidders is: Plot 2- One (01) Bidder, Plot 3-One (01) Bidder, Plot 4-Three (03) Bidders.

LOAs were issued to successful bidders for plot No. 2, 3 and 4 on 08.06.2021. However, due to the encroachments on the said land and ongoing case in the Hon'ble High Court - Indore Bench in reference to the petition filed by the residents of the land, Indore Smart City Development Limited was unable to give the possession of land of the successful bidders.

Further, the successful bidders did not submit the requisite bank guarantee of amount equal to 10% of the Quoted value within 30 days of the issue date of LOAs. Furthermore, the bid validity period of 180 Days as stated in the RFP was also expired. Hence the tenders were cancelled.

Furthermore, due to the ongoing COVID situation and considering the fact that Indore Smart City Development Limited was unable to give the possession of land, 'relaxation on EMD forfeiture was done.

Tender for Plot No. 3, 4 & 11 were invited vide NIT 24/ISCDL/2022-23 dated 03.09.2022 for the duration of 30 Days with the bid submission date of 06.10.2022 and due to zero bidders,

Signature Not Verified Signed by: JYOTI CHOURASIA Signing time: 23-Aug-23 4:52:28 PM

the dates for block No. 3, 4 & 11 were extended by 21 Days till 27.10.2022 vide Corrigendum#2 Dated 07.10.2022 and further timelines of tender for block No. 11 was extended vide Corrigendum#3 Dated 28.10. 2022 till 28.11.2022.

Additionally, technical bid for block #3 and Block #4 was opened on 28.10.2022 and technical evaluation was done. Further to the technical, evaluation of block # 3, both the participating bidders were technically disqualified and hence tender was cancelled.

Additionally, subsequent to the technical evaluation of block # 4, Clarification notices were issued to both the participating bidders, however, response submitted by the bidders being unsatisfactory and not in line with the RFP requirements. Hence, i& is hereby proposed to cancel the tender.

Keeping in view all the above scenarios, enough competition in the tenders is. not evident. Hence, it is recommended 'to consult Real Estate Transaction/expert(s)/Department(s)/ Institute(s) to review the present tender document and suggest amendments if required to enable wider participation in the tender process which will ultimately result in the monetary benefit for the organization.

Further, retendering of all the blocks is proposed on the basis of received recommendations of the appointed. Real Estate Transaction Consultant(s).

xxxxxxxx

D. EXTRACT OF THE RELEVANT RESOLUTION PASSED IN THE 194 MEETING OF THE BOARD OF DIRECTORS OF M/S INDORE SMART CITY DEVELOPMENTLIMITED HELD ON SATURDAY, THE 26" DAY OF DECEMBER, 2020

37. TO CONSIDER AND RATIFY THE BID PROCESS FOR 'MIXED USE REAL ESTATE REDEVELOPMENT PROJECTS AT MOG LINES-OLD GOVT. QUARTERS LAND PARCEL FOR DIFFERENT TOWERS ON FREEHOLD BASIS, AS PER MASTER PLAN FOR HIGH RISE TOWERS'

Signature Not Verified Signed by: JYOTI CHOURASIA Signing time: 23-Aug-23 4:52:28 PM

The Board was informed that development of MOG line project is an important component of Indore Smart City Proposal. Tenders were invited on PPP model thrice for both the lands. In the invitation of tender, there was a provision to give the entire land to one builder, in which the period of about 10 to 14 years was occupied for construction. Due to the high cost of work in the tender, the prospective builder is required to have turnover of Rs. 250 crore and Net-worth of Rs. 100 crore; but in view of the recession in real estate at present, no builder has participated in the tender.

In view of the present market situation, a detailed master plan of allotted lands was prepared and proposal was also prepared for inviting tenders in various small parts of the built up area. Under which 14 to 15 towers ate planned on different lands, the builder will need less turnover and nets worth than the original proposal. In previous Board Meeting held on 02.03.2020 the matter for redevelopment of public land (MOG Line) was discussed and Board decided to tender the work of development - of MOG lines with offering small land parcels.

In view of above, ISCDL has invited bids for 'Mixed Use Real Estate Redevelopment Projects at MOG Lines-Old Govt. Quarters Land Parcel for Different towers on Freehold basis, as per Master Plan for High Rise Towers' through NIT No. 18/ISCDL/20- 21 dtd. 01.07.2020. The NIT was published on 02.07.2020 in Hindi daily newspaper (Dainik Bhaskar) and English daily newspaper (Free Press) having wide circulation. The completion period of work is 5 years.

Online bid submission date was 25.10.2020 and bid was opened On 28.10.2020. After opening of bid on due dates, the Technically Qualified Bidders was informed for opening of Financial Proposals. A Tender Committee is formed for bid evaluation and recommendation for award of land(s) to H1 bidder(s).

Table below summarizes the results of the bidding process and the actions taken:

Name of 'Mixed Use Real Estate Redevelopment Projects at MOG Lines-Old Work Govt. Quarters Land Parcel for Different towers on Freehold basis, As per Master Plan for High Rise Towers' NIT No. 18/ISCDL/2020-21;Dated01.07.2020

Total Rs.59.63 Rs.59.57 Rs. 24.89 Crore Rs.23.83Crore Estimated Crore Crore ·cost Plot No. ForPlot-1 ForPlot-2- ForPlot-3 ForPlot-4

Signature Not Verified Signed by: JYOTI CHOURASIA Signing time: 23-Aug-23 4:52:28 PM

Name of NIL M/s M/s Phaloudi 1. M/s Phaloudi Bidder/s Teerth Constructions Constructions submitted Gopicon and and the bids and Private Infrastructure Infrastructure found Limited Pvt. Ltd. Pvt. Ltd.

Technically 2. M/s Sarthak Qualified Industries Limited. JV with .. M/s RRHL

Realty Limited AndM/s Solitaire Creations

3. M/s Teerth GopiconPrivate

-Limited Technical ---------------------------- 28.10.2020 28.10.2020 28.10.2020 BidOpeningD ate Financial Bid - -- 20.11.2020 20.11.2020 20.11.2020 Opening Date H 1 Bidder -- M/s M/s Phaloudi M/s Sarthak

-Teerth Constructions Industries Gopicon and Limited. JVwith Private Infrastructure M/s RRHL Limited Pvt. Ltd. Realty Limited And M/s Solitaire Creations Price -- Rs.60.60 Rs.25.89 Crore Rs.26.80 Crore Quoted Crore Status -- LoA to LoA to issue LoA to issue Issue Completion -- 5 Years 5 Years 5 Years ·.

Period

The same has been considered and approved by the Board.

After considering the facts and due deliberation following resolution was passed unanimously:- .

RESOLVED THAT the Board be and is hereby consider and ratify the bid process for 'Mixed Use Real Estate Redevelopment Projects at MOG Lines-: Old Govt. Quarters Land Parcel for Different towers on Freehold basis, as per Master Plan for High Rise

Signature Not Verified Signed by: JYOTI CHOURASIA Signing time: 23-Aug-23 4:52:28 PM

Towers'; and leading to selection' of agency and implementation of work;

RESOLVED FURTHER THAT the Board be and is hereby gives its approval to appoint and award the work to technically qualified and Highest Bidder (H1) for the work, subject to recommendation of' the committee formed for evaluation of bid;

RESOLVED FURTHER THAT Executive Director of the Company and/or Chief Executive Officer of the Company be and is hereby authorized to do all such acts, deeds and things as may be necessary in this regard."

14. I say that, the above Tender in dispute. before this Hon'ble Court | & was issued by the Office of Respondent company on 01/07/2020 and during the tender process, one of the petitioner Rahul Yadav has filed the PIL on 29/09/2020 seeking indulgence from the Hon'ble High Court Of M.P., Bench at Indore in the form of protection against eviction of such number of employees working in different department of State of M.P. who have been frontline warriors during Covid-19 pandemic from the quarters which are Govt. accommodations. It is respectfully submitted here that quarters/houses built on the land in question were the part of tender which has been cancelled by the Respondent by passing the impugned order dated 29/06/2022 due to non-compliances of the term of LOA.

15. I say that, the above mentioned PIL, Writ Petition No. 14656 of 2020 was firstly listed before the Hon'ble High Court on 29/09/2020 and the Hon'ble High Court was granted following interim relief in the PIL:-

"Resultantly by way of interim relief the respondents are directed not to evict any person from M.O.U. Lines over which the Smart City Project has to be developed until further orders. All notices issued to all employees shall remain in abeyance and the respondents will not take any steps in the matter in respect of eviction, without leave of this Court. The respondent State shall also submit details of number of alternative accommodations available in the township of Indore (vacant Government Quarters). The respondent shall also

Signature Not Verified Signed by: JYOTI CHOURASIA Signing time: 23-Aug-23 4:52:28 PM

furnish details of Government accommodations in which private person/private bodies are residing or occupying.

16. I say that, the above mentioned PIL W.P. No. 14656/2020 was finally disposed of by the Hon'ble Court vide order dated 03/03/2021 by passing the following directions:-

"Upon consideration of submissions advanced by both the parties in fitness of things. We are of the view that such employees occupying the Government accommodation and covered under the instant Public Interest Litigation shall continue to occupy the premises for three months and thereafter shall peacefully handover the possession to the concerned Authority.

With aforesaid observation petition stands disposed of."

17. I say that, being aggrieved by the order dated 03/03/2021 passed in W.P. No. 14656 of 2020. The petitioner Rahul Yadav filed: the Review Petition No. 425 of 2021 before this Hon'ble High Court on 09/06/2021 and the Hon''ble High Court vide order dated 18/06/2021 passed in R.P. No. 425 of 2021 has directed as under: -

"In the meantime parties are directed to maintain status quo as it exists today."

18. I say that, the R.P. No. 425 of 2021 was finally disposed of by this Hon'ble Court vide order dated 13/08/2021 and the Hon''ble Court by passing the said order extended the time limit up to 31/12/2021 to evict the premises as mentioned in order dated 03/03/2021 passed in W.P. No. 14656 of 2020 by passing the following directions:

"Upon consideration of rival contentions, we find it expedient to extend this order for six months commencing from 08.06.2021 and six months expiring on 31.12.2021,"

19. I say that, thereafter assailing the order dated 13/08/2021 passed in Review Petition No. 425 of 2021, the respondent no. 1 has filed the Review Petition No. 659 of 2021 before this Hon'ble High Court on 28/08/2021. The said review petition was disposed of by this Hon'ble High Court on 12/11/2021 by passing the following order:

Signature Not Verified Signed by: JYOTI CHOURASIA Signing time: 23-Aug-23 4:52:28 PM

"During the course of hearing, learned counsel for the parties reached a consensus. It is agreed that the order dated 13.09.2021 giving extension to the previous order may remain intact but it may be clarified that accommodations which have been vacated resulting into vacation of the entire building, the petitioners may utilize those building for the purpose of starting the work. In other words, it is agreed between the parties that building which have already been vacated by the employees can be used for an appropriate purpose in the Smart City Project by the petitioner."

In view of consensus arrived at between the parties, the review petition is disposed of. Parties shall act in accordance with the stand taken herein above.

20. 1 further say that, the Respondent after disposal of the Public Interest Litigation W.P. No. 14656 of 2020 vide order dated 03/03/2021 issued the Letter of Acceptance (LOA) in the favour of the petitioner vide letter dated 08/06/2021 to execute' the said work/project. The financial bid quoted by the petitioner for the purchase of Plot No. 03 was Rs. 25, 88, 88 888/-, therefore vide LOA dated 08/06/2021 petitioner was required performance guarantee equivalent to 10% of the quoted amount as per 'payment schedule of Rs.2,58,88,889/- in the form of bank guarantee and to sign the contract agreement at the stamp value of Rs.2,58,889/- within 30 days of issue of the LOA.

21. I further say that, after issuance of the LOA in the favour of the Petitioner the Contact agreement was not executed by the petitioner and also performance security was also not submitted. Therefore, it is respectfully submitted that due to non-execution of the agreement and non-submission of bank-Guarantee no legal right have been created in the favour of the Petitioner."

20. When the reasons as furnished by respondent No.1 for cancellation of the tender process are objectively considered, it is apparent that even prior to issuance of the LOA in favour of the petitioner, a Public Interest Litigation was filed before this Court in which there was an order of status-quo in respect of the buildings which were to be handed over to the petitioner in furtherance of the terms and conditions

Signature Not Verified Signed by: JYOTI CHOURASIA Signing time: 23-Aug-23 4:52:28 PM

of the NIT. The petition as well as the Review Petition filed after its decision remained pending for about one and a half year during which period respondent No.1 was not in a position to deliver possession of the plot to the petitioner for no fault of its own. Moreover, the petitioner did not furnish the performance guarantee as it was directed to do under the LOA itself. The petitioner also raised a dispute as regards the amount of stamp required for execution of the agreement between the parties. Even if it is assumed that the said grievance of the petitioner was genuine, then also it is apparent that it did not deposit the performance guarantee within the stipulated period of 30 days as was directed in the LOA itself. Taking into consideration the fact of non-execution of the agreement between the petitioner and respondent No.1 and non-submission of bank guarantee by the petitioner and the delay in the entire tender process due to pendency of litigation before this Court, respondent No.1 has validly decided to recall the entire tender process and to issue a fresh NIT. In doing so it cannot be said that respondent No.1 has acted arbitrarily or unreasonably in any manner.

21. When the entire decision-making process adopted by respondent No.1 for recalling the NIT, cancelling the LOA issued in favour of the petitioner and issuing a fresh NIT is examined, we do not find any illegality or infirmity therein. On the contrary, the NIT has been recalled/cancelled by respondent No.1 for just and valid reasons. The decision taken by it is rational and bona fide. The ground raised by the petitioner that it would suffer huge financial losses on account of losing the tender would not be a sufficient ground to exercise powers of judicial review in its favour.

Signature Not Verified Signed by: JYOTI CHOURASIA Signing time: 23-Aug-23 4:52:28 PM

22. In view of the aforesaid discussion, we do not find any merit in the instant petitions and they are accordingly dismissed however without any order as to costs.

                          (S. A. DHARMADHIKARI)                                   (PRANAY VERMA)
                                   JUDGE                                              JUDGE




                          jyoti




Signature Not Verified
Signed by: JYOTI
CHOURASIA
Signing time: 23-Aug-23
4:52:28 PM
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter