Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Mapaex Minerals A Partmership ... vs M/S Power Mech Projects Limited
2023 Latest Caselaw 6465 MP

Citation : 2023 Latest Caselaw 6465 MP
Judgement Date : 21 April, 2023

Madhya Pradesh High Court
Mapaex Minerals A Partmership ... vs M/S Power Mech Projects Limited on 21 April, 2023
Author: Vishal Dhagat
                                    1
            IN THE HIGH COURT OF MADHYA PRADESH
                         AT JABALPUR
                              AC No. 110 of 2022
      (MAPAEX MINERALS A PARTMERSHIP FIRM Vs M/S POWER MECH PROJECTS LIMITED)

Dated : 21-04-2023
      Shri R.S. Jaiswal - Senior Advocate with Shri Kartikeya Jaiswal -

Advocate for the applicant.
      Shri Siddharth Sharma - Advocate for respondent No.1.

Applicant has filed an application under Section 11 (6) of the Arbitration and Conciliation Act, 1996 for appointment of sole Arbitrator.

2. Applicant has entered into Memorandum of Understanding (MoU) dated 25.01.2020 in which Clause-20 stipulates arbitration clause which makes dispute between the parties arbitrable. Seat of arbitration is fixed at Bhopal.

3. Non-applicant i.e. M/S Power Mech Projects Limited was declared lowest bidder by Madhya Pradesh State Mining Corporation (MPSMC) in relation to its bid for three projects and same were related to extraction, mining of sand at Hoshangabad, Sehore and Bhind. Non-applicant was unable to bear financial obligation of Rs. 204 Crores, therefore, it approached various parties. There was agreement between applicant (Mapaex Minerals), non-applicant (M/S

Power Mech Projects Limited) and Anshika Builders for bearing burden of aforesaid financial commitment and each party was entitled to profits and loss from projects in respect of their funding percentage. Parties entered into Memo of Understanding on 25.01.2020. Non-applicant gave 60% funding, Anshika Builders gave 20% and applicant gave 20% funding amount. Obligations and liabilities of parties were laid down in said memo of understanding (MoU). It is alleged that non-applicant failed to adhere to primary and essential obligations of MoU and failed to pay its own capital commitment. Due to breach by non-

applicant, applicant was unable to perform and implement the terms to project as required by MPSMC. Hoshangabad project was cancelled. Applicant's financial contribution fund was not returned despite repeated request. Non- applicant also proposed to surrender other two mines in Sehore and Bhind. Aggrieved by aforesaid, applicant issue notice of breach dated 14.08.2022 and also a notice for invoking arbitration dated 21.09.2022 as per Clause-20.3 and Clause-20.5 of the MoU. Non-applicant rejected appointment of nominated sole Arbitrator suggested by applicant and also denied existence valid arbitration clause in MoU. In view of aforesaid circumstances, counsel appearing for applicant made a prayer for appointment of sole Arbitrator.

4. Learned Senior Counsel appearing for applicant relied on judgment reported in (2020) 2 SCC 455 {M/s. Uttarakhand Purv Sainik Kalyan Nigam Limited Vs. Northern Coal Field Limited}. He read paragraph-7.10 which is quoted as under:-

"7.10 In view of the legislative mandate contained in Section 11(6-A), the Court is now required only to examine the existence of the arbitration agreement. All other preliminary or threshold issues are left to be decided by the arbitrator under Section 16, which enshrines the kompetenz-kompetenz principle."

5. In view of same, it is submitted that matter may be referred to arbitration and other preliminary objections are to be considered by the Arbitrator.

6. Learned counsel appearing for respondent raised preliminary objection. It is submitted that there was no valid arbitration clause neither MoU was legally binding. MoU was tripartite agreement. Anshika Builder was not

impleaded as party. Case is devoid of merits and deserves to be dismissed. MoU was co-terminus with termination or expiration of contract between the MP State Mining Corporation and PMPL. Contract was never entered between three zones i.e. Hoshangabad, Sehore and Bhind. MoU was only limited to confidentiality.

7. Respondent also relied on M/s. Uttarakhand Purv Sainik Kalyan Nigam Limited (supra) and stated that if an arbitration agreement is not valid or non-existent, the Arbitral Tribunal cannot assume jurisdiction to adjudicate upon the disputes. Appointment of an Arbitrator may be refused if arbitration agreement is not in writing or the disputes are beyond the scope of arbitration agreement. Enforcement of arbitration award may be refused if there is no valid arbitration agreement. In view of aforesaid, prayer is made for dismissal of arbitration case for appointment of Arbitration.

8. Heard the counsel for the parties.

9. Principal objections raised by respondent for appointment of Arbitrator are that Memo of Understanding (MoU) is not binding, memo of understanding has been terminated and there is want of impleadment of necessary party. It is settled law that arbitration clause in agreement itself forms arbitration agreement and even if agreement is terminated, said clause can be invoked for appointment of Arbitrator for settlement of dispute. Arbitration

clause cannot be limited by provision of confidentiality and dispute resolution. Divulging data and agreement between the parties to Arbitrator will not amount to disclosure to third party and confidentiality can be maintained by Arbitrator during course of proceedings, therefore, confidentiality clause will not stop operation of arbitration clause. There is dispute regarding finances between the parties. Anshika Builders is not necessary party as dispute is between applicant

and non-applicant. Applicant is not claiming any relief against Anshika Builders, therefore, there is no defect of joining of necessary party in application for appointment of Arbitrator. Arbitration clause and agreement is binding between the parties.

10. Respondent may raise all other objections before Arbitrator appointed.

11. In view of same, parties are directed to suggest the name of mutually agreed Arbitrator to this Court within period of seven days. If parties fail to submit name of mutually agreeable sole arbitrator then after period of seven days Court will appoint sole Arbitrator in the case.

12. List the matter after seven days for passing of order for appointment of Arbitrator in the case.

VISHAL DHAGAT) JUDGE

shabana Digitally signed by SHABANA ANSARI Date: 2023.04.26 11:14:01 +05'30'

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter