Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Vijaya Energy Equipment, ... vs West Central Railway Jabalpur
2022 Latest Caselaw 16018 MP

Citation : 2022 Latest Caselaw 16018 MP
Judgement Date : 5 December, 2022

Madhya Pradesh High Court
M/S Vijaya Energy Equipment, ... vs West Central Railway Jabalpur on 5 December, 2022
Author: Sushrut Arvind Dharmadhikari
                                                 A.C. No. 24/2020
                             1

      IN THE HIGH COURT OF MADHYA PRADESH

                     AT J A B A L P U R
                           BEFORE
          HON'BLE SHRI JUSTICE SUSHRUT ARVIND
                   DHARMADHIKARI

               ON THE 05th OF DECEMBER, 2022

              ARBITRATION CASE No. 24 of 2020

BETWEEN:-
M/S VIJAYA ENERGY EQUIPMENT, BHOPAL,
PLOT NO. 102-A, SECTOR-F, INDUSTRIAL
AREA,    GOVINDPURA,     BHOPAL-462023
THROUGH PROPRIETOR SHYAM S. VERMA,
S/O MOTI LAL VERMA, OCCUPATION-
CONTRACTOR, R/O G-147, GAUTAM NAGAR,
BHOPAL.462023.    FAX   NO.0755-4262997,
EMAIL-       [email protected]
(MADHYA PRADESH)

                                                .....APPLICANT
(BY SHRI RAJESH KUMAR SONI - ADVOCATE)
AND
     WEST CENTRAL RAILWAY, JABALPUR
     THROUGH GENERAL MANAGER, WEST
     CENTRAL RAILWAY, INDIRA MARKET,
1.   JABALPUR-482001
     FAX NO.- NOT KNOWN, EMAIL-NOT-
     KNOWN

     DEPUTY CHIEF ENGINEER (BRIDGE)
     LINE,  WEST     CENTRAL RAILWAY,
     JABALPUR-482001
2.
     FAX NO. NOT KNOWN, EMAIL-NOT
     KNOWN

                                           .....RESPONDENTS
(BY SHRI SANJAY SARWATE - ADVOCATE)
                                                             A.C. No. 24/2020
                                 2

      This petition coming on for orders this day, the court passed the
following:


                                ORDER

Heard finally with the consent of both the parties.

This application has been filed by the applicant - M/s Vijaya Energy Equipment, Bhopal under Section 11(6) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as 'the Act of 1996') with the prayer that this Court may appoint an independent Arbitrator as the applicable clause in the agreement between the parties is in conflict with the prevailing law.

2. Brief facts leading to filing of the case are that the respondent- Railway floated a tender for the following work: "Regirdering of Niwar Bridge, DN Road, 3/33.53M Span @ KM 1067/2-3 (Non Standard Riveted Open Web Through Girder Span With Non Standard Welded Open Web Through Girder Span) on Jabalpur- Manikpur Section of Jabalpur Division." The total contract value of the work was Rs.3,90,56,113.00. The date and time for submission of tender was 10.02.2015 at 16:00 hours, and the date of opening of the tender was 10.02.2015 at 16:15 hours. The applicant submitted its tender which was accepted and Letter of Acceptance (LOA) dated 09.04.2015 was issued to the applicant. An agreement was executed between the applicant and the respondent-Railway. As per the agreement, the work had to commence w.e.f. 09.04.2015 and was required to be completed by 08.10.2016. The total completion period of work was 18 months. As per tender conditions, the applicant was required to deposit Security Deposit A.C. No. 24/2020

of Rs.19,52,810/-. The applicant was also required to submit Performance Guarantee in the form of BG (Bank Guarantee). In this case, the old bridge girders of DN line were required to be changed and the proposed course of action was to slide the newly constructed girders to UP line; and the UP line girders were to be slided to DN line, while the DN line old girders were to be junked to scrap. For this purpose, the flow of water (water way) in the river below, was to be regulated through large pipes installed in the riverbed, and over the pipes earth filling was done over which staging was erected for positioning of new girders at respective spans.

3. For the purpose of stopping the passing of train, Mega Block was to be handed over to the applicant for 6:00 hours. As per the procedure, the new girders were to be kept parallel to the UP side girders. New girders would replace UP side girders, which will replace DN side girders and DN side girders were to be junked as scrap. For this purpose Launching pad was constructed parallel to UP side and dismantling pad was constructed parallel to DN side. But as per this existing scheme Mega Block was not made available to the applicant. It is pertinent to mention here that since launching of span No. 1 was being planned by mid of March-2018, the applicant hoped to complete launching of second span by mid of April-2018, and third span by 15 th June, 2018. Apart from this, further ancillary works would be completed by 15.07.2018. Therefore, the applicant submitted an application for extension of time on 07.03.2018 and in such application it was submitted that the work will be completed by 15.07.2018. The applicant submitted Bar Chart for completion of work of regirdering of Niwar A.C. No. 24/2020

Bridge over Jabalpur-Manikpur Section of Jabalpur Division vide letter dated 20.03.2018. The respondent-Railway granted extension up to 15.07.2018, vide letter dated 28.03.2018. As per letter received from Assistant Engineer, Bridge Line dated 20.05.2019, the applicant was again required to lower the girder from span S1 and move it to safe location, considering the coming monsoon. This lowering of girders and moving to safe location was required due to block not given by the Railway.

4. It was also found that as per the drawing given by the railway, the bearing was purchased in accordance with the drawing of the railway, but it was found that the newly purchased bearing was fouling with the old bearing and, therefore, a new design was given. But, in-spite of that Mega Block was not made available. Due to commencing of rainy season, the entire Launching Pad had to be dismantled on account of which an expenditure of Rs.19,11,758/- was incurred by the applicant. Vide letter dated 22.05.2019, the applicant informed that by his letter dated 12.06.2018 the applicant had demanded reimbursement of Rs.19,11,758/- for additional work incurred by the applicant on account of lowering of girder of 2 spans moving the assembled span out of the river bed, removal of earth from middle span to clear river flow waterway and removal of Hume pipes and to re-do the above procedure in reverse for repositioning of girders. No reply has been received from the railway to show that the letter dated 12.06.2018 regarding reimbursement has been considered.

5. It is pertinent to mention here that after rainy season, on the second time also, the Launching Pad was constructed but again Mega A.C. No. 24/2020

Block was not made available, and again on account of commencing of rainy season, the entire Launching Pad had to be dismantled, upon which, an expenditure of Rs.21,370,58/- was incurred by the applicant. Now, the respondent/Railway is stating that the entire work is to be done by crane. The applicant submitted its bill for reimbursement of Rs.40,15,518/-, which was refused and rejected, by the respondents, without assigning any reason. Therefore, the applicant has filed the present application before this Court under Section 11(6) of the Act of 1996 requesting to appoint a sole Arbitrator.

6. Per contra, the prayer for appointment of Arbitrator is vehemently opposed by the learned counsel for the respondents. Learned counsel contended that it is an admitted position that the Act of 1996 was amended in the year 2015. At the same time, Section 12(5) of the Act and VIIth Schedule were also amended. The Railway Administration has also suitably amended Clause-64(3) of the General Conditions of Contract (GCC) after the year 2015. It is submitted that under Clause- 64(3) of GCC, the Railway Board will offer a panel of three retired railway personnel out of whom, the applicant has to choose two. Thereafter, one out of them shall be appointed as the nominee Arbitrator. The applicant failed to invoke the aforesaid provision, whereas the respondent Railways was ready to invoke the aforesaid provision. It was further submitted that the applicant had not waived of the applicability of Section 12(5) of the amended Act, therefore, the present case falls under the category of Clause-64(3)b of GCC. Therefore, the independent Arbitrator cannot be appointed by ignoring the aforesaid provision. It is further submitted that in an identical matter, this Court in A.C. No. 24/2020

A.C. No.64/2018 (Vijay Energy Equipments Vs. West Central Railway), reported in 2021(2) MPLJ 443 has held that GCC will prevail. In view of the aforesaid submissions, the application under Section 11(6) of the Act of 1966 being devoid of merits, is liable to be rejected.

7. In reply, learned counsel for the applicant contended that the judgment passed by this Court in the case of Vijay Energy Equipments (supra) would not be applicable to the facts of the present case since, similar issue was raised before the Apex Court in the case of Union of India Vs. M/s Tantia Construction Limited passed in Special Leave to Appeal (c) No. 12670/2020, wherein, the similar issues had cropped up. The Apex Court had prima facie disagreed with the contentions of the respondents for the reason that once the appointing authority itself is incapacitated from referring the matter to arbitration, it does not then follow that notwithstanding this yet appointments may be valid depending on the facts of the case and has referred the matter to the Larger Bench. The correctness of the judgment of Apex Court rendered in the case of Central Organisation For Railway Electrification Vs. ECL-SPIC-SMO-MCML (JV), A Joint Venture Company, (2020) 14 SCC 712 was doubted, therefore, the request has been made to constitute a Larger Bench. In view of the aforesaid, the contention of the respondents cannot be accepted. It is further contended that in a similar situation the Delhi High Court in the case of Gangotri Enterprises Ltd. Vs. General Manager Northern Railways, reported in 2022 SCC Online Del 3556 has held that a detailed consideration has been done and the Court had come to the conclusion that the application under A.C. No. 24/2020

Section 11(6) of the Act is maintainable and there no impediment in appointment of a nominee Arbitrator on behalf of the applicant. In another judgment the Apex Court in the case of Continental India Private Limited Vs. General Manager Northern Railway, 2022 SCC Online SC 922 by setting aside the orders passed by the High Court directing to constitute an Arbitral Tribunal in terms of Clause 64(3)(b) of the GCC has been quashed and the matter has been remanded back to the High Court for appointment of sole Arbitrator under Section 11(6) of the Act of 1996. Therefore, this application deserves to be allowed.

8. Heard learned counsel for the parties.

9. In view of the judgments delivered by the Apex Court in the case of Continental India Private Limited (supra), M/s Tantia Constructions Limited (supra) and the judgment delivered by the Delhi High Court in the case of Gangotri Enterprises Ltd.(supra), the application deserves to be allowed. The applicant is well within his right to get the Arbitrator nominated by invoking Section 11 (6) of the Act of 1996.

10. Considering the discussion made hereinabove, this Court nominate Shri S.N. Khare, Former District Judge as a sole Arbitrator to adjudicate and resolve the dispute between the parties.

11. The present application is accordingly allowed.

No order as to costs.

(S.A. DHARMADHIKARI) JUDGE ashish Digitally signed by ASHISH KUMAR LILHARE Date: 2022.12.07 12:50:58 +05'30'

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter