Citation : 2021 Latest Caselaw 702 MP
Judgement Date : 15 March, 2021
1
THE HIGH COURT OF MADHYA PRADESH
RP-274-2021
(SUBODH KUMAR JAGGI vs VINOD KUMAR JAGGI (DEAD) THROUGH l..R.S &
ANOTHER)
JABALPUR
DATED : 15.03.2021
Shri Bharat Singh, learned counsel for the petitioner.
Heard on I.A. No.2182/2021, which is an application for
condonation of delay.
There is a delay of 813 days in filing this review petition.
The petitioner is seeking review of the judgment dated
23.11.2017
whereby the Second Appeal No.931/2004 was dismissed and the concurrent judgments of the Trial Court as well as the First Appellate Court were affirmed.
Submission of counsel for the petitioner is that delay was caused due to bona fide reason and on merit the petitioner has good case because sixty days' notice was required to be given to the Society, which was not given and no question of law in this regard was framed, therefore, re-hearing is required.
Having examined the matter, it is noticed that no proper explanation for the delay has been furnished by the review petitioner. The delay is inordinate and a perusal of the application reveals that the delay has not been explained at all. A plea has been taken that the petitioner had suffered some heart ailment but neither nature of such ailment is disclosed nor the time or duration of such ailment has been mentioned. No medical document in support of such a plea has been enclosed. There is no details given in the application for condonation of delay as to what the petitioner had done after 23.11.2017 and as to what had prevented and what are the relevant dates when the petitioner
was prevented from approaching this Court for filing the review petition. That apart, the record reflects that the questions of law were framed in the appeal on 12.08.2013 and thereafter the appeal was heard on 23.11.2017 deciding the aforesaid questions of law. If there was any additional question of law involved in the matter, the petitioner could have raised a submission in this regard at the time of final hearing of the second appeal. The same was not done.
The Supreme Court in the matter of G. Ramegowda, Major and others Vs. Special Land Acquisition Officer, Bangalore, (1988) 2 SCC 142 has held as under :
"14. The contours of the area of discretion of the courts in the matter of condonation of delays in filing appeals are set out in a number of pronouncements of this Court. See: Ramlal, Motilal and Chhotelal v. Rewa Coalfield Ltd.; Shakuntala Devi Jain v. Kuntal Kumari; Concord of India Insurance Co. Ltd. v. Nirmala Devi; Lala Mata Din v. A. Narayanan; Collector, Land Acquisition v. Katiji etc. There is, it is true, no general principle saving the party from all mistakes of its counsel. If there is negligence, deliberate or gross inaction or lack of bona fides on the part of the party or its counsel there is no reason why the opposite side should be exposed to a time- barred appeal. Each case will have to be considered on the particularities of its own special facts. However, the expression 'sufficient cause' in Section 5 must receive a liberal construction so as to advance substantial justice and generally delays in preferring appeals are required to be condoned in the interest of justice where no gross negligence or deliberate inaction or
lack of bona fides is imputable to the party seeking condonation of the delay."
The Supreme Court in the matter of Maniben Devraj Shah vs. Municipal Corporation of Brihan Mumbai (2012) 5 SCC 157 has held as under :
"23. What needs to be emphasised is that even though a liberal and justice oriented approach is required to be adopted in the exercise of power under Section 5 of the Limitation Act and other similar statutes, the Courts can neither become oblivious of the fact that the successful litigant has acquired certain rights on the basis of the judgment under challenge and a lot of time is consumed at various stages of litigation apart from the cost. 24. What colour the expression be "sufficient cause" would get in the factual matrix of a given case would largely depend on bona fide nature of the explanation. If the court finds that there has been no negligence on the part of the applicant and the cause shown for the delay does not lack bona fides, then it may condone the delay. If, on the other hand, the explanation given by the applicant is found to be concocted or he is thoroughly negligent in prosecuting his cause, then it would be a legitimate exercise of discretion not to condone the delay."
The Supreme court in the matter of Meera Bhanja (Smt) Vs. Nirmala Kumari Choudhary (Smt) reported in (1995) 1 SCC 170 considering the limited scope of review has held that scope of review is confined to error apparent on the face of the record. The error must be such as would be apparent on mere looking of the record without requiring any long drawn process
of reasoning. It is also settled position in law that review power may not be exercised on the ground that the decision was erroneous on merits as that would be a province of a Court of appeal and the review power should not be confused with the appellate power.
Having regard to the aforesaid, I am of the opinion that there is no justifiable reason exists for condoning such an inordinate delay in filing the review petition.
Hence, in the aforesaid circumstances, I.A. No.2182/2021 is rejected and review petition is dismissed on the ground of delay.
(PRAKASH SHRIVASTAVA) JUDGE DV
Digitally signed by DINESH VERMA Date: 2021.03.18 16:34:58 +05'30'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!