Citation : 2021 Latest Caselaw 3776 MP
Judgement Date : 31 July, 2021
:: 1 :: W.P.No.3157/2017
(Smt. Brijesh Shrivastava Vs. Hindustan Petroleum Corporation Ltd.
and others)
HIGH COURT OF MADHYA PRADESH :
BENCH AT GWALIOR
Writ Petition No. 3157/2017
Smt. Brijesh Shrivastava ...PETITIONER
versus
Hindustan Petroleum Corporation
Ltd. and others ...RESPONDENTS
------------------------------------------------------------------------------------
CORAM :
Hon'ble Shri Justice Vishal Mishra
Shri Arvind Dudawat, learned counsel for the petitioner.
Shri Harish Dixit, learned counsel for the respondents.
-----------------------------------------------------------------------------------
Whether approved for reporting : Yes
------------------------------------------------------------------------------------
Date of decision : 31.7.2021
-----------------------------------------------------------------------------------
ORDER
( 31.7.2021)
Per Vishal Mishra , J.
:: 2 :: W.P.No.3157/2017 (Smt. Brijesh Shrivastava Vs. Hindustan Petroleum Corporation Ltd.
and others)
(1) The present petition is being filed against the illegal action on
the part of the respondents in not completing the formalities for
grant/establishment of Retail Outlet Dealership at Barahed Road in
between Pendra and Rayatpura, District Bhind though after holding
the interview and completing all the formalities a Letter of Intent has
been issued on 17.1.2014 in favour of the petitioner. The petitioner
has fulfilled all the required formalities as directed by the respondent-
Corporation. But despite of the same for the reasons best known to
the respondents they have not completed the formalities and not
permitting the petitioner to open the retail outlet dealership, therefore,
the petition has been filed.
(2) It has been argued that the petitioner is a citizen of India and
permanent resident of District Bhind and the respondent no.1 is a
Corporation for regulating the selection of the Retail Outlet
Dealerships and wherein certain guidelines have been issued in the
name of Guidelines for selection of Retail Outlet Dealers. An
advertisement was issued in Dainik Bhaskar newspaper on 15.9.2011
inviting applications for grant of Retail Outlet Dealership on various
locations including the location at Barahed between Pendra and
Rayatpura, District Bhind which is at S.No.85 of the advertisement.
The same was for an open category. The petitioner fulfilling the
eligibility has applied for the same and has submitted affidavits in the
prescribed format and the project report along with all the relevant :: 3 :: W.P.No.3157/2017 (Smt. Brijesh Shrivastava Vs. Hindustan Petroleum Corporation Ltd.
and others)
documents to the respondents. As the petitioner was fulfilling all the
required criteria and was found eligible, therefore, a letter dated
19.12.2011 was issued by the respondent no.2 directing the petitioner
calling for a interview on 13.1.2012 at 3:00 PM before the Hindustan
Petroleum Dealer Selection Committee. The petitioner duly appeared
before the selection committee, and the petitioner was granted 100
marks considering the candidature and the documents and she has
been placed at S.No.1 of the table of marks awarded by the Selection
Committee which is reflected from Annexure P/4. Thereafter the
matter was kept pending for almost one year and on 17.1.2014 a
Letter of Intent was issued for proposed retail outlet dealership in
favour of the petitioner. Acceptance to the proposal was submitted by
the petitioner to the respondent-Corporation. The petitioner has
submitted all the relevant documents including the documents
pertaining to ownership of the land in question that it belongs to the
petitioner and no objection certificate from the Revenue Department
was submitted, but despite of the same the respondents authorities
themselves have issued a letter to the Collector and District
Magistrate/District Bhind for issuance of no objection certificate for
development of the new Retail Outlet on the land in question. No
objection certificate was granted by the District Magistrate, District
Bhind for establishment of the retail outlet dealership of Indian Oil
Corporation Limited in favour of the petitioner on 13.5.2014. The :: 4 :: W.P.No.3157/2017 (Smt. Brijesh Shrivastava Vs. Hindustan Petroleum Corporation Ltd.
and others)
petitioner has purchased the land from Aakash Shrivastava, who has
got the aforesaid land diverted by the competent authority i.e. S.D.O.
Gohad, District Bhind and deposited the requisite diversion fees. The
S.D.O. has issued no objection certificate. The Additional District
Magistrate, District Bhind again sought a clear opinion from the
S.D.O. Gohad, District Bhind vide letter dated 16.9.2014 with respect
to the land in question. The S.D.O. Gohad after making an inquiry
into the matter has submitted a report regarding issuance of NOC by
the District Magistrate, District Bhind on 31.5.2014. It was informed
that the land in question was recorded as Charnoi land in Samvat 2039
and was thereafter converted as Kabil Kast in Samvat 2051 and vide
order dated 6.2.1995 passed in the Case No.10/Aa-19/94-95, the said
land was settled in favour of one Sohan S/o Sobaran Singh, who
later-on sold the said land to one Balvir Kaur from which the
predecessor-in-title of the petitioner purchased the said land through
registered sale deed. The aforesaid letter was forwarded to the
respondent-Corporation, but despite of the same they are sitting tight
over the matter for the reasons best known to them and are not
completing the formalities as required for establishment of the
petroleum retail outlet. The petitioner personally approached the
respondent no.2 and requested for completing the formalities, but the
same was not done. A legal notice was thereupon served through
counsel through registered post on 23.2.2016, but of no consequence.
:: 5 :: W.P.No.3157/2017 (Smt. Brijesh Shrivastava Vs. Hindustan Petroleum Corporation Ltd.
and others)
In reply to the legal notice it is submitted that the land was earlier
recorded as charnoi land, therefore, even after grant of NOC by the
competent authority as per the legal advise of the legal cell the
matter cannot be proceeded further for establishment of new retail
outlet (Annexure P/14 is the reply). It is submitted that once the
competent authority of the revenue department i.e. Collector has
issued no objection certificate in favour of the petitioner then no
question of disputed land arises. After the issuance of Letter of
Intent the proposal sent by the respondent-Corporation as well as the
acceptance letter submitted by the petitioner and after completing all
the formalities by the respondents it cannot be said that the land is a
disputed land especially in the circumstances when the Collector,
District Bhind has himself issued a NOC in favour of the petitioner
after the inquiry report being submitted by the S.D.O. The matter has
already been investigated by the Revenue Authorities that too on the
basis of the letter issued by the Corporation itself. Therefore, the
reason assigned by the Corporation declining to complete the
formalities and permit the petitioner to open the retail outlet
dealership of Hindustan Petroleum Corporation the same is perse
illegal and is contrary to Article 14, 19 and 21 of the Constitution of
India as after issuance of LOI and the no objection certificate from the
competent authority right is accrued in favour of the petitioner. In
such circumstances, the present petition is being filed. In view of the :: 6 :: W.P.No.3157/2017 (Smt. Brijesh Shrivastava Vs. Hindustan Petroleum Corporation Ltd.
and others)
aforesaid, the petition may be allowed and the respondents authorities
be directed to complete the formalities within the stipulated time
frame and permit the petitioner to open the retail outlet. It is stated at
bar that till date no other petrol pump is being opened near vicinity of
the aforesaid land. In such circumstances, petitioner still is entitled to
open the retail outlet dealership.
(3) Per contra counsel appearing for the respondents Corporation
has vehemently opposed the contentions of the petitioner and has
submitted that mere issuance of Letter of Intent does not create any
right in favour of the petitioner. He has not even impleaded the
Hindustan Petroleum Corporation Limited as a party to the
proceedings. It is submitted that the petitioner was required to
demonstrate by filing of documents with respect to his title over the
property in question for title clearance and for completing the
formalities the respondents sought 30 years title documents, but the
same was not supplied by the petitioner. During the title search and
on perusal of the khasra records for the year 1981 to 1993 it was
noticed by the respondents that the land of Khasra No.62 old new
Khasra No.101 min total comprised area of 0.560 hectare situated at
Village Chak Tumera, Tahsil Gohad, District Bhind (M.P.) originally
belongs to the Government of M.P. in the form of Nistar Charnoi
Bhumi (Reserved Bhumi under the provisions of M.P. Land Revenue
Code, 1959). Thereafter on 6.2.1995 the same was settled in the :: 7 :: W.P.No.3157/2017 (Smt. Brijesh Shrivastava Vs. Hindustan Petroleum Corporation Ltd.
and others)
name of one Sohan Singh S/o Sobren Singh. How the aforesaid land
was settled in the name of Sohan Singh is not clear from the
documents. Therefore, the petitioner was required to demonstrate his
clear title over the property by filing all the relevant documents
including the predecessor's documents. It is settled preposition of law
that at the time of settlement of the government land in favour of
private person the permission from the competent authority is required
to be taken i.e. Collector, but whether the permission from Collector
is taken or not prior to settlement of the land in question could only
be cleared from the revenue records. The petitioner could not file the
complete revenue records before the respondents authorities,
therefore, in absence of clear title in favour of the petitioner the
retail outlet of petroleum cannot be extended in favour of of the
petitioner. Time was granted to the petitioner by the respondent-
Corporation to complete the formalities with respect to the title over
the land in question, but till date it has not been done by the petitioner.
As far as contention of the petitioner with respect to issuance of NOC
by the District Magistrate/Collector is concerned, it is a settled
preposition of law as has been held by the Hon'ble Supreme Court in
the case of C. Albert Morris Versus K. Chandrashekhran, (2006)
1 SCC 228, wherein it is held by the Hon'ble Supreme Court that
while granting NOC, the Collector is not concerned about the
ownership of the land. He is concerned about the location of the land :: 8 :: W.P.No.3157/2017 (Smt. Brijesh Shrivastava Vs. Hindustan Petroleum Corporation Ltd.
and others)
and its suitability as a place for storage of petroleum. Rule 144,
which deal with the grant of NOC, do not contemplate an enquiry into
the ownership of the land nor does it require the Collector to inquire
into the nature of the right claimed by the person who has applied for
NOC. In such circumstances, merely submission of NOC by the
competent authority i.e. Collector will not suffice the terms and
conditions and will not clear the title of the petitioner. Therefore,
once the petitioner himself could not demonstrate the clear title over
the property in question, therefore, the authority has rightly decided
not to complete the formalities and permit the petitioner to open the
retail outlet of Hindustan Petroleum Corporation.
(4) The law with respect to the rights will created by issuance of
Letter of Intent is clear as has been held by the Hon'ble Supreme
Court recently in the case of South Eastern Coal Fields Limited and
others Vs. M/s. S Kumars Associates Akm (Jv) in Civil Appeal
No.4358/2016 decided on 23rd July, 2021, wherein the Hon'ble
Supreme Court has held that the contents of the Letter of Intent are
having utmost importance and merely issuance of letter of intent is not
create any right in favour of the person who has applied for the retail
outlet. There is a big difference between the condition precedent and
the condition subsequent. Relying upon the several judgments of the
Hon'ble Supreme Court, the Hon'ble Supreme Court has categorically
held that the issuance of Letter of Intent does not create any right in :: 9 :: W.P.No.3157/2017 (Smt. Brijesh Shrivastava Vs. Hindustan Petroleum Corporation Ltd.
and others)
favour of the persons like petitioner. In view of the aforesaid facts
and circumstances of the case, he has prayed for dismissal of the writ
petition.
(5) Per contra by filing a rejoinder to the return the petitioner has
denied the contents of the return and submitted that the law which has
been relied upon by the respondents is not applicable in the facts and
circumstances of the case. As far as the direction to the petitioner to
submit all the relevant documents is concerned the petitioner has
made all possible efforts by filing an application to the respondents
authorities asking for the order of settlement in favour of Sohan Singh
in the year 1995, but the same was not supplied by the authorities to
the petitioner which is clearly reflected from the NOC issued and the
enquiry done by the S.D.O. Gohad District Bhind. In absence of the
documents supplied by the State Authorities, petitioner was not in a
position to file the same before the authorities, but once the
competent authority i.e. the Collector, District Bhind has issued the no
objection certificate in favour of the petitioner with respect to the land
in question then by stretch of imagination it can be stated that the
petitioner was not having any clear title over the property in question.
In such circumstances, the stand taken by the respondents in the return
having no value and the petitioner is having clear title over the
property in question as is reflected from the documents issued by the
revenue authorities itself. In such circumstances, the petition should :: 10 :: W.P.No.3157/2017 (Smt. Brijesh Shrivastava Vs. Hindustan Petroleum Corporation Ltd.
and others)
be allowed.
(6) Heard the learned counsel for the parties and perused the
record.
(7) The principle question for consideration before this Court is that
whether the letter of intent issued by the authorities in favour of the
petitioner will create any right in favour of the petitioner seeking a
direction to the respondents to complete all the formalities and permit
the petitioner for establish a retail outlet dealership of the respondents-
Corporation. The aforesaid question has been answered by the
Hon'ble Supreme Court recently in the case of South Eastern
Coalfield Limited (supra), wherein it has been held as under:
"18. A consideration of the matter in the conspectus of the aforesaid pleas leads to a conclusion that it cannot be said that a concluded contract had been arrived at inter se the parties.
19. We have already reproduced aforesaid the terms of the letter of award and what it mandated the respondent to do. None of the mandates were fulfilled except that the respondent mobilized the equipment at site, handing over of the site and the date of commencement of work was fixed vide letter dated 28.10.2009. Interestingly this letter has been addressed to the Sub Area Manager of the appellant by the office of the appellant. The respondent, thus, neither submitted the Performance Security Deposit nor signed the Integrity Pact. Consequently, the work order was :: 11 :: W.P.No.3157/2017 (Smt. Brijesh Shrivastava Vs. Hindustan Petroleum Corporation Ltd.
and others)
also not issued nor was the contract executed. Thus, the moot point would be whether mobilization at site by the respondent would amount to a concluding contract inter se the parties. The answer to the same would be in the negative.
20. We would like to state the issue whether a concluded contract had been arrived at inter se the parties is in turn dependent on the terms and conditions of the NIT, the LoI and the conduct of the parties. The judicial views before us leave little doubt over the proposition that an LoI merely indicates a party's intention to enter into a contract with the other party in future.12 No binding relationship between the parties at this stage emerges and the totality of the circumstances have to be considered in each case. It is no doubt possible to construe a letter of intent as a binding contract if such an intention is evident from its terms. But then the intention to do so must be clear and unambiguous as it takes a deviation from how normally a letter of intent has to be understood. This Court did consider in Dresser Rand S.A. (supra) case that there are cases where a detailed contract is drawn up later on account of anxiety to start work on an urgent basis. In that case it was clearly stated that the contract will come into force upon receipt of letter by the supplier, and yet on a holistic analysis - it was held that the LoI could not be :: 12 :: W.P.No.3157/2017 (Smt. Brijesh Shrivastava Vs. Hindustan Petroleum Corporation Ltd.
and others)
interpreted as a work order.
21. Similarly if we construe the documents as discussed in the judgment of this Court in Jawahar Lal Burman (supra) case it is unequivocally mentioned that "contract is concluded by this acceptance and formal acceptance of tender will follow immediately on receipt of treasury receipt." Thus, once again, it has been stipulated as to at what time a contract would stand concluded even though it was later subject to deposit of the security amount. It was in these circumstances that the requirement of security deposit was treated not as a condition precedent but as a condition subsequent. We have to also appreciate the nature of contract which was for immediate requirement of the full quantity of coconut oil to be supplied within 21 days. It was also explicitly mentioned in the LoI itself that any failure to deposit the stipulated amount would be treated as a breach of contact. This is not the case here, where the consequence was simply forfeiture of the bid security amount, and cancellation of the 'award' and not the 'contract'.
22. If we compare the aforesaid scenario in the present case, the period for execution of the contract was one year. The respondent worked at the site for a little over the month, facing certain difficulties - it is immaterial whether the same was of the own making of the respondent or :: 13 :: W.P.No.3157/2017 (Smt. Brijesh Shrivastava Vs. Hindustan Petroleum Corporation Ltd.
and others)
attributable to the appellants. No amount was paid for the work done. The respondent failed to comply with their obligations under the LoI. It is not merely a case of the non-furnishing of Performance Security Deposit but even the Integrity Pact was never signed, nor work order issued on account of failure to execute the contract. We are, thus, of the view that none of the judgments cited by learned counsel for the appellants would come to their aid in the contractual situation of the present case. The judgments referred by learned counsel for the appellants Jawahar Lal Burman (supra) case and Dresser Rand S.A. (supra) case, if one may say so are not directly supporting either of the parties but suffice to say that to determine the issue what has to be seen are the relevant clauses of the NIT and the LoI. On having discussed the non-
compliance by the respondent of the terms of the LoI we turn to the NIT. Clause 29.2 clearly stipulates that the notification of award will constitute the formation of the contract "subject only" to furnishing of the Performance Security/Security Deposit. Thus, it was clearly put as a pre-condition and that too to be done within 28 days following notification of the award. The failure of the successful bidder to comply with the requirement "shall constitute sufficient ground for cancellation of the award work and forfeiture of the bid security" as per :: 14 :: W.P.No.3157/2017 (Smt. Brijesh Shrivastava Vs. Hindustan Petroleum Corporation Ltd.
and others)
clause 30.2. If we analyse clause 34 dealing with the Integrity Pact the failure to submit the same would make the tender bid "as not substantially responsive and may be rejected."
23. We may also add that the definition of what constitutes a contract as per clause (ix) itself includes the NIT, the acceptance of the tender, the formal agreement to be executed between the parties post contractor furnishing all the documents and the bid security amount. 24. The result of the aforesaid is that as rightly held in terms of the impugned order all that the appellants can do is to forfeit the bid security amount and, thus, it was so directed. Since as a pre-condition of any coercive action against the respondent, the High Court called upon the appellants to deposit a sum of Rs.10 lakh in terms of the interim order dated 04.08.2010, a direction is made to deduct the bid security amount out of the sum of Rs.10 lakh and to refund the balance amount to the respondent. The needful would now have to be done within two months as in terms of the interim order of this Court dated 08.02.2013 such refund has been stayed.
25. We accordingly dismiss the appeal leaving the parties to bear their own costs."
(8) The Hon'ble Supreme Court further in the case of State of
Madhya Pradesh and another Vs. Firm Gobardhan Dass Kailash
Nath, AIR 1973 SC 1164 has held where in respect of a tender for :: 15 :: W.P.No.3157/2017 (Smt. Brijesh Shrivastava Vs. Hindustan Petroleum Corporation Ltd.
and others)
Government sale initial deposit of 25% of purchase price was an
essential precondition for acceptance or sanction of tender was not
complied with. It was held that taking into consideration what was
required to enter into a contract, i.e., in writing and in prescribed form
and 25% amount not being deposited, it could not be said that any
concluded contract was arrived at between the parties."
(9) The Hon'ble Supreme Court further in the case of Bhushan
Pawar and Steel Limited Vs. State of Orissa, (2017) 2 SCC 125
has considered the question that what an LOI was the nomenclature of
the letter would not be the determinative factor, but the substantive
nature of the letter would determine whether it can be treated as an
LOI which was per the legal dictionary means preliminary
understanding between the parties who intend to make a contract or
join together in another action."
(10) The Hon'ble Supreme Court further in the case of Rajasthan
Cooperative Dairy Federation Ltd. Vs. Maha Laxmi Mingrate
Marketing Service Pvt. Ltd. and others, (1996) 10 SCC 405 has
held as under:
".......The letter of intent merely expressed an
intention to enter into a contract. There was no
binding legal relationship between the appellant
and respondent no.1 at this stage and the appellant
was entitled to look at the totality of :: 16 :: W.P.No.3157/2017 (Smt. Brijesh Shrivastava Vs. Hindustan Petroleum Corporation Ltd.
and others)
circumstances in deciding whether to enter into a
binding contract with the respondent no.1 or
not."
(11) From the perusal of the aforesaid legal preposition of law it is
seen that the letter of intent issued in favour of the petitioner does not
create any right seeking a direction to the respondents to complete all
the formalities. The letter of intent is only a proposal being sent by the
respondents Corporation to the petitioner that they are intending to
enter into an agreement but the entire contract was not completed by
the authorities. The Corporation was still having its right to decline
to enter into a contract and once the contract is not completed the
respondents authorities cannot be directed to complete all the
formalities. In the present case the Letter of Intent is issued by the
authorities on 17.1.2014 (Annexure P/5) which is filed along with the
petition, wherein condition No.a is relevant :
"a. That you will lease the suitable plot of land to HPCL for a period of 30 years with renewal option as per mutually agreed terms and conditions. In case the offered land is taken on lease by you, the head lease should contain a Clause that you should have a right to sub-lease the said plot of land to HPCL without further reference to or consent of the Head Lessor for the lease period as stipulated above, under such terms and conditions as may be agreed upon between :: 17 :: W.P.No.3157/2017 (Smt. Brijesh Shrivastava Vs. Hindustan Petroleum Corporation Ltd.
and others)
you and HPCL. In case you fail to make
available the offered land within two months, this offer is liable to be withdrawn. However, there is no commitment form HPCL for taking the said land from you."
It was further seen from the Letter of Intent that "this letter is merely a
Letter of Intent and not to be construed as a firm offer of Dealership to
you".
(12) Thus, from the Letter of Intent issued in favour of the petitioner
clearly says that aforesaid is not a complete document pointing out the
fact that the contract formalities are completed.
(13) As far as the issuance of NOC by the competent authority i.e.
Collector, District Bhind is concerned it is a settled preposition of law
that merely NOC being issued by the competent authority does not
amounts to its clearance of title which has been held by the Hon'ble
Supreme Court in the case of C. Albert Morris (supra), wherein it
is held that:
"While granting NOC, the Collector is not concerned about the ownership of the land. He is concerned about the location of the land and its suitability as a place for storage of petroleum. Rule 144, which deal with the grant of NOC, do not contemplate an enquiry into the ownership of the land nor does it require the Collector to enquire into the nature of the right claimed by the person who has applied for NOC."
:: 18 :: W.P.No.3157/2017 (Smt. Brijesh Shrivastava Vs. Hindustan Petroleum Corporation Ltd.
and others)
(14) It is seen from the records that the land in question was initially
recorded in the name of Government land as Nistar Charno Bhumi
and thereafter far back from year 1981 to 1993 and thereafter the same
land was stated to be settled in the name of Sohan Singh S/o Sobren
Singh in Revenue Case No.10/Aa-19/94-95 vide order dated
6.2.1995. The aforesaid order was directed to be placed before this
Court by the petitioner vide order dated 18.5.2017, but despite of the
same the petitioner could not produce the aforesaid order before this
Court. However, an argument is advanced by the petitioner that he
has tried to obtain the copy of the order, but the same was not supplied
to him by the revenue authorities, but the fact remains that the
authorities have asked for the documents pertaining to the ownership
for the last 30 years. The petitioner could not deposit the same to the
authorities. Thus, in the circumstances when the petitioner himself
could not demonstrate the clear title over the property in question,
therefore, on the basis of legal advise given on the basis of the search
in 30 years documents it was found that earlier the land was recorded
as Nistar Charnoi Bhumi of State of Madhya Pradesh in the records.
Therefore, the decision is taken not to extend the retail outlet
dealership to the petitioner and was denied by filing a reply to the
show cause notice issued by the petitioner to the authorities. Thus,
from the aforesaid facts and circumstances of the case, no right has
accrued in favour of the petitioner. The petitioner cannot compel the :: 19 :: W.P.No.3157/2017 (Smt. Brijesh Shrivastava Vs. Hindustan Petroleum Corporation Ltd.
and others)
authorities to enter into a contract and complete all the formalities and
permit the petitioner to open a retail outlet dealership of Hindustan
Petroleum Corporation. In such circumstances, the petition sans
merits and is accordingly dismissed.
E-copy/Certified copy as per rules/directions.
(Vishal Mishra) Judge 31/07/2021 Pawar*
ASHISH PAWAR 2021.08.07 14:47:53 +05'30'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!