Citation : 2021 Latest Caselaw 1681 MP
Judgement Date : 30 April, 2021
HIGH COURT OF MADHYA PRADESH PRINCIPAL SEAT AT JABALPUR
ARBITRATION APPEAL 35/2014
NO.
Parties Name MADHYA PRADESH MADHYA KSHETRA VIDYUT
VITRAN CO. LTD.
VS.
M/S SHYAM INDUS POWER SOLUTION PVT. LTD.
Bench Constituted Single Bench
Judgment delivered By HON'BLE SHRI JUSTICE VISHAL DHAGAT
Whether approved for YES/NO
reporting
Name of counsel for parties For petitioner: Shri Shobhit Aditya, Advocate.
For Respondent no.1 : Shri Pankaj Kumar Singh,
Advocate with Shri Aditya Khampariya, Advocate.
Law laid down
Significant paragraph
number
(O R D E R )
30/04/2021
Appellant has filed this appeal under section 37 of
Arbitration and Conciliation Act, 1996 calling in question order
dated 11.07.2014 passed in Arbitration Case No.24/2012 by 10th
Additional District Judge, Bhopal by which application filed by
appellant/defendant for setting aside arbitration award was
dismissed.
2. Brief facts of the case are that appellant invited tenders on
27.07.2007 for distribution of electricity for Chhola Zone, North
Bhopal. Letter of intent was issued in favour of respondent on
06.11.2007. Respondent accepted letter of intent on 12.11.2007
and contract was executed between the parties on 22.12.2007.
Thereafter respondent worked as Authorized Franchise for
2 A.A No.35/2014
distribution of electricity in Chhola Zone, Bhopal from 1.02.2008
to 31.05.2012.
(i) Differences/dispute arose between appellant and
respondent over application of input rate formula. Respondent
company insisted on following base input rate as mentioned in
tender document and opposed following base input rate as
mentioned in distribution agreement clause 5.3.3 which was 1.80
per unit.
(ii) Respondent company invoked the Arbitration Clause
21.1 and issued legal notice to appellant company on
27.04.2010. After issuance of notice Arbitrators were appointed
by appellant as well as respondent who appointed Shri S.K.
Dubey as Presiding Arbitrator on 26.08.2010. Respondent filed its
claim before Arbitrator on 04.09.2010. Appellant company
submitted written statement on 15.10.2010. Both the parties
adduced documentary as well as oral evidence in the case.
(iii) Respondent company filed an application for
amendment of statement of claim on 13.3.2011 which was
allowed by Tribunal on 09.04.2011. By said amendment
respondent company was allowed to amend pleadings and
include grounds of coercion and economic duress adopted by
appellant due to which respondent company signed distribution
agreement on 22.12.2007. Pursuant to amendment, two
additional issues were framed and parties were given opportunity
to lead evidence on it.
3 A.A No.35/2014
(iv) After hearing the parties final award was passed on
04.02.2012 and directed appellant to pay an amount of
Rs.1,56,80,554/- along with interest @ 9.5%.
(v) Appellant filed an application under Section 34 of
Arbitration and Conciliation Act, before 10th Additional District
Judge, Bhopal in Arbitration Case No.24/2012 for setting aside
the award. Award passed by Arbitration Tribunal was affirmed by
order dated 11.07.2014.
(vi) Being aggrieved by order passed by 10th Additional
District Judge, Bhopal in Arbitration Case, appellant filed an
appeal under Section 37 of Arbitration and Conciliation Act, 1996
before this Court.
3. Appellant challenged the order passed by Additional District
Judge, Bhopal on the ground that tribunal had committed an error
in allowing amendment application on 09.04.2011 at a belated
stage permitting them to raise new plea of economic duress and
coercion. Arbitrator had misdirected himself in advising
respondent to file an application for amendment. Not only
Arbitration tribunal allowed amendment application but also
permitted respondent to adduce additional evidence to fill up the
lacuna and improve its case. It was submitted that impugned
order passed by the Additional District Judge as well as award
passed by Arbitration Tribunal are patently illegal and are not
sustainable in the eyes of law.
4 A.A No.35/2014
4. During pendency of appeal appellant has filed an
application for proposed amendment in memo of appeal. By said
proposed amendment appellant wants to incorporate the ground
that Tribunal while passing impugned award dated 4.2.2012
exceeded its jurisdiction by declaring clauses of agreement as
not binding upon respondent and also inserted new clauses and
conditions in the agreement.
5. Counsel appearing for respondent had opposed the
application for allowing amendment in memo of appeal. It is
submitted by him that appeal has been filed in the year 2014 and
amendment application has been filed in the year 2021 after a
long delay and, therefore, same may be dismissed. No reply has
been filed on the said application by respondent and vide order
dated 21.01.2021 it was ordered that application for proposed
amendment will be considered at the time of final hearing.
6. Claim made by respondent was allowed by Arbitration
Tribunal. Claim was allowed holding that respondent company
was forced to sign distribution agreement dated 22.12.2007
under economic duress and coercion. Base input rate as
mentioned in tender document ought to have been made
applicable. In view of same proposed amendment is material in
dispute between appellant and respondent. Facts
regarding the
aforesaid amendment is already on record and documents have
also been filed by both the parties. No further evidence is
required in respect of said pleadings. Award has been passed on
basis of tender document and not on the basis of contract i.e
distribution agreement dated 22.12.2007.
7. In view of the same proposed amendment application is
allowed and proposed ground "J" is treated as one of the ground
in arbitration appeal. Appellant shall incorporate the amendment
in arbitration appeal within fifteen days from passing of this
order.
8. Counsel appearing for appellant has relied on AIR 2016 SC
1441, Union of India Vs. Ambica Construction. Counsel for
appellant placed reliance on para-6 of said order which is quoted
below as under: -
"6. "Court" has been defined in Section 2(c) of the Act to
mean a civil court having jurisdiction to decide the questions
forming the subject-matter of the reference. Section 41 of the
Act is extracted hereunder:
"41. Procedure and powers of Court. - Subject to the provisions of this Act and of rules made thereunder:
(a) The provisions of the Code of Civil Procedure, 1908 (5 of 1908), shall apply to all proceedings before the Court, and to all appeals, under this Act, and
(b) The Court shall have, for the purpose of, and in relation to arbitration proceedings, the same power of making orders in respect of any of the matters set out in the Second Schedule as it has for the purpose of, and in relation to any proceedings before the Court:
Provided that nothing in CI. (b) shall be taken to prejudice any power which may be vested in an Arbitrator or umpire for making orders with respect to any of such matters."
The court can exercise the power specified in Second Schedule of the Act. However, Arbitrator is not a court. Arbitrator is the outcome of agreement. He decides the disputes as per the agreement entered into between the
parties. Arbitration is an alternative forum for resolution of disputes but an Arbitrator ipso facto does not enjoy or possess all the powers conferred on the courts of law."
9. In view of same it is submitted that Arbitrator has to decide
the dispute as per agreement entered into between the parties,
i.e. on the basis of agreement of distribution dated 22.12.2007
and Arbitrator committed an error in relying on tender document
i.e. clause 35.1.4. Appellant has also placed reliance on paras-16
to 21 of judgement reported in AIR 2010 Supreme Court
3543, M/s Rashtriya Chemicals and Fertilizers Ltd. Vs. M/s
Chowgule Brothers and others. Said paragraphs are quoted
as under: -
"16. That brings us to the question whether an Arbitrator can make an award contrary to the terms of the contract executed between the parties. That question is no longer res integra having been settled by a long line of decisions of this Court. While it is true that the Courts show deference to the findings of fact recorded by the Arbitrators and even opinions, if any, expressed on questions of law referred to them for determination, yet it is equally true that the Arbitrators have no jurisdiction to make an award against the specific terms of the contract executed between the parties. Reference may be made, in this regard, to the decision of this Court in Steel Authority of India Ltd. v. J.C. Budharaja, Government and Mining Contractor (1999) 8 SCC 122 where this Court observed:
"...that it is settled law that the arbitrator derives authority from the contract and if he acts in manifest disregard of the contract, the award given by him would be an arbitrary one; that this deliberate departure from the contract amounts not only to manifest disregard of the authority or misconduct on his part, but it may tantamount to mala fide action...."
"...It is true that interpretation of a particular condition in the agreement would be within the jurisdiction of the arbitrator. However, in cases where there is no question of interpretation of any term of the contract, but of solely reading the same as it is and still the arbitrator ignores it and awards the amount despite the prohibition in the
agreement, the award would be arbitrary, capricious and without jurisdiction. Whether the arbitrator has acted beyond the terms of the contract or has travelled beyond his jurisdiction would depend upon facts, which however would be jurisdictional facts, and are required to be gone into by the court. The arbitrator may have jurisdiction to entertain claim and yet he may not have jurisdiction to pass award for particular items in view of the prohibition contained in the contract and, in such cases, it would be a jurisdictional error..."
17. It was further observed:
"...Further, the Arbitration Act does not give any power to the arbitrator to act arbitrarily or capriciously. His existence depends upon the agreement and his function is to act within the limits of the said agreement...."
18. In W.B. State Warehousing Corporation and Anr. v. Sushil Kumar Kayan and Ors. (2002) 5 SCC 679, again this Court observed:
"...If there is a specific term in the contract or the law which does not permit the parties to raise a point before the arbitrator and if there is a specific bar in the contract to the raising of the point, then the award passed by the arbitrator in respect thereof would be in excess of his jurisdiction...."
19. In Bharat Coking Coal Ltd. v. Annapurna Construction, (2003) 8 SCC 154, this Court reiterated the legal position in the following words:
"There lies a clear distinction between an error within the jurisdiction and error in excess of jurisdiction. Thus, the role of the arbitrator is to arbitrate within the terms of the contract. He has no power apart from what the parties have given him under the contract. If he has travelled beyond the contract, he would be acting without jurisdiction, whereas if he has remained inside the parameters of the contract, his award cannot be questioned on the ground that it contains an error apparent on the face of the record."
20. In MD, Army Welfare Housing Organisation v. Sumangal Services (P) Ltd. (2004) 9 SCC 619 also this Court took the similar view and observed:
"An Arbitral Tribunal is not a court of law. Its orders are not judicial orders. Its functions are not
judicial functions. It cannot exercise its power ex debito justitiae.
The jurisdiction of the arbitrator being confined to the four corners of the agreement, he can only pass such an order which may be the subject- matter of reference."
21. Reference may also be made to the decisions of this Court in Associated Engineering Co. v. Government of Andhra Pradesh and Anr. (AIR 1992 SC 232); Jivarajbhai Ujamshi Sheth and Ors. v. Chintamanrao Balaji and Ors. (AIR 1965 SC 214); State of Rajasthan v. Nav Bharat Construction Co. (AIR 2005 SC 4430); Food Corporation of India v. Surendra, Devendra & Mahendra Transport Co. (2003) 4 SCC 80, which sufficiently settle the law on the subject."
10. On strength of said judgement it is argued by learned
counsel for the appellant that Arbitrator has committed an error
of jurisdiction in not relying on agreement of distribution between
the parties dated 22.12.2007 and passed the award contrary to
it. Appellant has further relied on judgement reported in AIR
2013 Supreme Court 3182, V.L.S Finance Ltd. Vs. Union
of India and others. Relying on the said judgement counsel for
appellant argued that new plea which is a pure question of law
can be raised at any stage of proceedings. It is submitted that
this Court can look into the question of law raised by the
appellant by way of amendment though there being no pleading
before Arbitral Tribunal or before this Court. For enforcing this
argument counsel for appellant has also relied on judgement
reported in M/s Ariane Orgachem Pvt. Ltd. Vs. Wyeth
Employees Union and Ors., AIR 2016 Supreme Court
1761, para-29 which is as under:-
"29. The appellant-Company has also contended that the respondent-Union has also raised the legal question
regarding the competency of the Deputy Labour Commissioner in passing the order of reference for the first time before this Court and the same was not raised before the High Court, therefore, the same shall not be permitted to be raised in these proceedings and this Court need not go into this aspect of the matter which is wholly untenable in law. This contention raised by the learned senior Counsel for the Appellant is rejected as the said contention is contrary to the issues/principles laid down by the Privy Council and this Court in the following judgments:
In Connecticut Fire Insurance Co. v. Kavanagh (1892) A.C. 473, 480 (PC), Lord Watson has observed as under:
"When a question of law is raised for the first time in a court of last resort, upon the construction of a document, or upon facts either admitted or proved beyond controversy, it is not only competent but expedient, in the interests of justice, to entertain the plea."
The aforementioned view of the Court of Appeal have been relied upon by this Court in Gurcharan Singh v. Kamla Singh (1976) 2 SCC 152. Therefore, with regard to the above mentioned aspect regarding the plea of the competency of the Deputy Labour Commissioner to pass an order of refusal to make a reference, although is being raised before this Court for the first time, is based on admitted facts. Hence, in accordance with the view taken by the Court of Appeal in Connecticut Fire Insurance Company case (supra) and this Court in Gurcharan Singh case (supra), the argument advanced by the first Respondent-Union deserves to be considered by this Court. Similar view has also been taken by this Court in the cases of VLS Finance Limited v. Union of India (2013) 6 SCC 278 and Greater Mohali Area Development Authority v. Manju Jain (2010) 9 SCC 157, wherein it has been held that pure question of law can be raised at any stage of litigation. In National Textile Corporation v. Naresh Kumar Jagad (2011) 12 SCC 695, it has been held by this Court that a new ground raising pure legal issue for which no inquiry or proof is required, can be raised at any stage. Further, in the case of Port Trust v. Hymanshu International (1979) 4 SCC 176, this Court has held thus:
"2...The plea of limitation based on this section is one which the court always looks upon with disfavour and it is unfortunate that a public authority like the Port Trust should, in all morality and justice, take up such a plea to defeat a just claim of the citizen. It is high time that governments and public authorities adopt the practice of not relying upon technical pleas for the
purpose of defeating legitimate claims of citizens and do what is fair and just to the citizens. of course, if a government or a public authority takes up a technical plea, the Court has to decide it and if the plea is well-founded, it has to be upheld by the court, but what we feel is that such a plea should not ordinarily be taken up by a government or a public authority, unless of course the claim is not well-founded and by reason of delay in filing it, the evidence for the purpose of resisting such a claim has become unavailable...."
11. Counsel appearing for respondent submitted that this Court
has very limited scope in interfering with an order passed under
Section 34 of Arbitration and Conciliation Act, 1996. He relied on
the judgement reported in the case of MMTC Limited vs.
Vedanta Limited (2019) 4 SCC 163. Paras 14 to 16 of said
judgement are quoted below as under: -
"14. As far as interference with an order made under Section 34, as per Section 37, is concerned, it cannot be disputed that such interference under Section 37 cannot travel beyond the restrictions laid down under Section 34. In other words, the Court cannot undertake an independent assessment of the merits of the award, and must only ascertain that the exercise of power by the Court under Section 34 has not exceeded the scope of the provision. Thus, it is evident that in case an arbitral award has been confirmed by the Court under Section 34 and by the Court in an appeal under Section 37, this Court must be extremely cautious and slow to disturb such concurrent findings.
15. Having noted the above grounds for interference with an arbitral award, it must now be noted that the instant question pertains to determining whether the arbitral award deals with a dispute not contemplated by or not falling within the terms of the submission to arbitration, or contains decisions on matters beyond the scope of the submission to arbitration. However, this question has been addressed by the Courts in terms of the construction of the contract between the parties, and as such it can be safely said that a review of such a construction cannot be made in terms of reassessment of the material on record, but only in terms of the principles governing interference with an award as discussed above.
16. It is equally important to observe at this juncture that while interpreting the terms of a contract, the conduct of parties and correspondences exchanged would also be relevant factors and it is within the arbitrator's jurisdiction to consider the same. (See McDermott International Inc. v. Burn Standard Co. Ltd. (supra); Pure Helium India (P) Ltd. v. ONGC, (2003) 8 SCC 593, D.D. Sharma v. Union of India, (2004) 5 SCC 325)."
12. To fortify the aforesaid arguments counsel appearing for
respondent further relied on judgement reported in 2018 SCC
Online Delhi 6780, NHAI versus M/s BSC-RBM-Pati Joint
Venture; and judgement reported in Manupatra/DE/0459/2015,
High Court of Delhi in the matter of Mahanagar Telephone
Nigam Limited Vs. Fujitshu India Private Limited. Counsel
for respondent has relied on other judgements but for sake of
brevity all the judgements relied on by the respondent fortified
the same arguments and, therefore, they are not mentioned in
this order.
13. Counsel appearing for respondent also relied on judgement
reported in (2001) 8 SCC 97, Estralla Rubber vs. Dass
Estate (P) Ltd. and argued that amendment application filed by
respondent before Arbitral Tribunal was rightly allowed. He relied
on para-8 of said judgement which is quoted as under: -
"8. It is fairly settled in law that the amendment of pleadings under Order 6, Rule 17 is to be allowed if such an amendment is required for proper and effective adjudication of controversy between the parties and to avoid multiplicity of judicial proceedings, subject to certain conditions such as allowing amendment should not result in injustice to the other side; normally a clear admission made conferring certain right on a plaintiff is not allowed to be withdrawn by way of amendment by a defendant resulting in prejudice to such a right of plaintiff, depending on facts
and circumstances of a given case. In certain situations a time barred claim cannot be allowed to be raised by proposing an amendment to take away valuable accrued right of a party. However, mere delay in making an amendment application itself is not enough to refuse amendment, as the delay can be compensated in terms of money. Amendment is to be allowed when it does not cost serious prejudice to the opposite side. This Court in recent judgment in B.K. Narayana Pillai vs. Parameswaran Pillai and another [(2000) 1 SCC 712], after referring to number of decisions, in para 3 has stated, thus: -
"3. The purpose and object of Order 6 Rule 17 CPC is to allow either party to alter or amend his pleadings in such manner and on such terms as may be just. The power to allow the amendment is wide and can be exercised at any stage of the proceedings in the interests of justice on the basis of guidelines laid down by various High Courts and this Court. It is true that the amendment cannot be claimed as a matter of right and under all circumstances. But it is equally true that the courts while deciding such prayers should not adopt a hyper technical approach. Liberal approach should be the general rule particularly in cases where the other side can be compensated with the costs. Technicalities of law should not be permitted to hamper the courts in the administration of justice between the parties. Amendments are allowed in the pleadings to avoid uncalled-for multiplicity of litigation."
In para 4 of the same judgment this Court has quoted the following passage from the judgment in A.K. Gupta and Sons Ltd. Vs. Damodar Valley Corporation [1966 (1) SCR 796]: -
"The general rule, no doubt, is that a party is not allowed by amendment to set up a new case or a new cause of action particularly when a suit on new case or cause of action is barred: Weldon v. Neal [(1887) 19 QBD 394 : 56 LJ QB 621]. But it is also well recognized that where the amendment does not constitute the addition of a new cause of action or raise a different case, but amounts to no more than a different or additional approach to the same facts, the amendment will be allowed even after the expiry of the statutory period of limitation: See Charan Das v. Amir Khan [AIR 1921 PC 50 : ILR 48 Cal 110] and L.J. Leach and Co. Ltd. V. Jardine Skinner and Co. [AIR 1957 SC 357 :1957 SCR 438]."
This Court in the same judgment further observed that the principles applicable to the amendment of the plaint are
equally applicable to the amendment of the written statement and that the courts are more generous in allowing amendment of the written statement as the question of prejudice is less likely to operate in that event. It is further stated that the defendant has a right to take alternative plea in defence which, however, is subject to an exception that by the proposed amendment the other side should not be subjected to serious injustice and that any admission made in favour of the plaintiff conferring right on him is not withdrawn."
14. Heard the counsel appearing for appellant as well as
respondent.
15. Basic grievance of the appellant is that Arbitration Tribunal
has misdirected itself in advising the respondent of the proposed
amendment and allowing proposed amendment at the fag end
of the case. The said amendment has allowed the respondent to
introduce a new plea as an afterthought to fill up the lacuna and
further Tribunal committed an error in allowing respondent to
lead evidence on said amendment.
16. It is to be seen whether order allowing amendment dated
09.04.2011 was in conflict with basic notion of morality or justice
and whether the arbitration award is vitiated by patent illegality
apparent on face of record. Arbitration Tribunal has dealt with the
application for proposed amendment in great detail and
considered the arguments raised by appellant. It has been held
by Arbitral Tribunal that by said proposed amendment new plea
has not been introduced but it is only elaboration of plea already
made. After allowing application for proposed amendment issues
were framed and both parties were given opportunity to adduce
evidence. Respondent was also given an opportunity to do
consequential amendment. Respondent had denied that there
was any advice on part of Arbitrator to amend the pleadings.
Only because amendment application has been allowed after
some delay it cannot be said that there is a patent illegality
apparent on the face of record. The order allowing application for
proposed amendment does not suffer from patent illegality. This
court will not meticulously examine erroneous application of law
or re-appreciate the evidence regarding finding that there was
economic duress and coercion on respondent.
17. In view of same there is no scope for interference in
arbitration appeal in order dated 09.04.2011 by which application
for proposed amendment was allowed by Arbitral Tribunal.
18. Now ground "J" incorporated by amendment in Arbitration
Appeal that arbitration tribunal exceeded its jurisdiction by not
only declaring the clauses of agreement as not binding upon
respondent but also inserted new clauses and conditions in the
agreement by causing amendment of agreement is considered.
Arbitration Tribunal has already held that agreement of
distribution dated 22.12.2007 was based on economic duress and
coercion. Respondent was made to sign the agreement under
aforesaid influences. In tender document input rate which was
given was different on the basis of which the respondent
company had made tender bid but in agreement of
distribution/contract dated 22.12.2007 base input rate was
mentioned as 1.80 per unit which was contrary to clause
mentioned in the tender document. Respondent had raised
objection to it at initial stage itself but due to economic duress
and coercion it was forced to sign the contract on the last date
i.e. on 22.12.2007. Inducement was made to respondent to sign
the contract by letter dated 22.12.2007 by which they were
given assurance that input rate formula shall be considered and
may be changed. On basis of evidence and facts available on
record it cannot be said that arbitration tribunal has exceeded its
jurisdiction. Arbitration tribunal can take into consideration the
conduct of parties and correspondence between the parties and
said fact can be examined by Arbitration Tribunal though same
may not be part of the contract. Thus, ground "J" has no force
and same is rejected.
19. In view of the above it is clear that award passed by
Arbitration Tribunal does not suffer from any findings which are
arbitrary, capricious or perverse and no patent illegality has been
committed by Arbitration Tribunal in passing the award.
20. In view of the same arbitration appeal filed by the appellant
is dismissed.
(VISHAL DHAGAT) JUDGE mms
Digitally signed by MONSI M SIMON Date: 2021.04.30 15:18:33 +05'30'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!