Citation : 2021 Latest Caselaw 1580 MP
Judgement Date : 27 April, 2021
HIGH COURT OF MADHYA PRADESH PRINCIPAL SEAT AT JABALPUR
WRIT PETITION NO. 19459 /2020
Parties Name M/S AEROPLAST LIMITED
Vs.
MADHYA PRADESH STATE AGRO INDUSTRIES
DEVELOPMENT CORPORATION LIMITED &
OTHERS.
Bench Constituted Single Bench
Judgment delivered By HON'BLE SHRI JUSTICE VISHAL DHAGAT
Whether approved for YES/NO
reporting
Name of counsel for parties For petitioner: Shri Varun Tankha, Advocate with Shri
Rahul Gupta, Advocate.
For Respondents: Shri P.K. Kaurav, Advocate General
with Shri Aditya Khandekar, Advocate.
Law laid down -
Significant paragraph number -
(O R D E R)
27/04/2021
Petitioner has filed this writ petition calling in question order dated
02.07.2020 (Annexure-P/7) and order dated 24.07.2020 (Annexure-P/9)
passed by respondent No.1. By said orders, technical bid of petitioner for
registration as supplier of laminated sheets to respondent No.1 i.e. M.P.
Agro Industries Development Corporation Limited was rejected.
2. Respondent No.1 has issued a tender on 09.03.2020 (Annexure-P/3)
inviting technical bids for registration of suppliers for supply of laminated
sheets. Technical qualification which was required as per tender document
was "the manufacturer having valid manufacturing registration certificate
license/acknowledgement EM part II/IEM Udyog Aadhaar issued by
District Trade Industries Centre (DTIC) or Statutory Competent Authority
for manufacturing films with valid PAN and GSTN number". Later on
technical qualification required for registration of suppliers was amended
by corrigendum dated 21.03.2020 (Annexure-P/4). As per amended
technical qualification, manufacturer must have production capacity of
1000 metric tonnes per annum. Last date for submission of bid was
31.03.2020 but due to lock down last date of bid was extended many
times. Finally, by notice dated 18.05.2020, last date for submission of bid
was fixed to 16.06.2020. Petitioner submitted its bid on 15.06.2020.
Petitioner also deposited EMD of Rs.35 lakhs.
3. In compliance of notice, petitioner had submitted manufacturing
Registration Certificate both acknowledgement EM part II and Udyog
Aadhaar Memorandum. Additionally petitioner submitted self certified
letter acknowledging its annual production capacity of 7000 metric tonnes.
4. Respondent No.1 rejected bid of petitioner on 02.07.2020. Technical
bid was rejected on grounds that manufacturing registration certificate
submitted by petitioner did not mention production capacity of petitioner
and authority letter was not supported by board resolution.
5. Petitioner preferred a representation against rejection order on
03.07.2020. Representation preferred by petitioner was rejected vide order
dated 24.07.2020.
6. Counsel appearing for petitioner argued that rejection is illegal,
arbitrary and violative of Article 14 of the Constitution of India. It is
submitted by him that Government of Haryana as per fixed format in form
of acknowledgement. EM part II does not mention production capacity.
There is no mention in the corrigendum that annual production capacity
(hereinafter referred to as APC) should be mentioned in manufacturing
registration certificate/EM II/Udyog Aadhaar memorandum or document
ought to have been issued by Statutory body, therefore, petitioner has filed
self certified APC letter. There was ambiguity in wording of contract and,
therefore, same is to be resolved against party who prepared it. Though
eligibility clause was amended by corrigendum but no such corrigendum
was issued in respect of list of documents to be uploaded/submitted
therefore, ambiguity persisted, as words were not clear therefore, the
intention is to prevail. Documents filed by petitioner along with
representation are not considered. EM part II was no longer valid
document as same was abolished by Ministry of Micro Small and Medium
Enterprises by notification dated 10.01.2017 and UAM has taken its place.
UAM does not reflect production capacity. It was also argued that
Authority letter submitted by petitioner ought to have been accepted.
Though resolution of company was not filed but authority letter was
signed by two directors out of three, therefore, it ought to have been
accepted by respondents. Same was only a technical flaw and respondent
could have asked to submit resolution of company.
7. It is further argued that procedure is only device for justice and same
shall not be used to thought justice. Relying on judgement of Poddar steel
Corporation Vs. Ganesh Engineering Works and Others [(1991) 3 SCC
273], petitioner submitted that eligibility conditions are of two categories:
one essential conditions of eligibility which requires rigid enforcement
and second is ancillary or subsidiary conditions which do not require strict
literal compliance. Dispute was more of form than substance. Defects
were curable and does not affect substance of tender. Rejection was harsh
and oppressive and voilates fundamental rights enshrined in Part III of the
Constitution and Article 30 (9-A) and 41 of Directive Principles of
Constitution of India. Decision not only smacks of mala fide but same was
given only to eliminate petitioner from arena of competition. No ratio was
given in order dated 24.07.2020 and opportunity of hearing was also not
provided while deciding the representation. In view of the same, orders
rejecting technical bid was bad in law and deserves to be quashed.
8. Learned Advocate General appearing for respondent No.1 and 2
submitted that NIT was issued on 09.03.2020 and corrigendum was issued
on 21.3.2020 thereafter repeatedly last date to submit tender document
was extended due to lock down. Last date for submitting tender document
was 16.06.2020. There was three months time for petitioner to comply
with amended condition but same was not done. It was further argued that
there was prescribed format in tender document, therefore, there is no
question of ambiguity. Learned Advocate General appearing for
respondents submitted that matter is covered by order dated 24.08.2020
passed by Division Bench in WP No.26919/2019. A Division Bench
considered case of Poddar Steel Corporation (supra) and dismissed the
petition. It is submitted by the counsel appearing for respondents No.1 and
2 that soundness of decision maybe questioned if it is irrational or
malafide or intended to favour someone or a decision that no responsible
authority acting reasonably and in accordance with relevant law could
have reached. In case of Sanuraga Hosiery Pvt. Ltd. question before
Court was "whether furnishing of "Pradhikar Patra" with stamp duty of
Rs.1000/- was an essential condition of tender or not". This Court held
that whether a term of NIT is essential or not is a decision taken by
employer which should be respected. Even if that time is essential, the
employer has inherent authority to deviate from it provided the deviation
is made applicable to all bidders and potential bidders as held in case of
Ramana Dayaram Shetty Vs. International Airport Authority of India
[(1979) 3 SCC 489]. However, if the term is held by employer to be
ancillary or subsidiary even that decision should be respected. The
lawfulness of that decision can be questioned on very limited grounds, as
mentioned in various decisions discussed above, but soundness of decision
cannot be questioned, otherwise this Court would be taking over function
of tender issuing authority, which it cannot. Relying on aforesaid
judgements, Advocate General appearing for respondent No.1 and 2
prayed for dismissal of writ petition.
9. Heard the counsel for petitioner as well as respondents.
10. Question for consideration before this court is "1. whether order
dated 02.07.2020 and order dated 24.07.2020 suffer from malafide? 2.
Whether said orders suffer from arbitrariness and unreasonableness? 3.
Whether public interest is affected?"
11. From perusal of order dated 02.07.2020, it is clear that out of six
applications received for registration for supplier of laminated films, three
applications were rejected on the ground that copy of board resolution has
not been filed along with authorisation letter and documents were not filed
to state annual production capacity. In case of petitioner, resolution was
not filed and documents which were filed issued by District Industrial
Centre does not mention production capacity. All the builders who were
not having aforesaid qualification, their technical bid for registration was
rejected. It is not a case that petitioner company has been singled out i.e.
case of pick and choose. Other companies who are also not having
aforesaid eligibility suffered rejection therefore, it cannot be said that
action of respondent suffers from malafide.
12. Whether order suffers from unreasonableness and arbitrariness.
Mentioning annual production capacity may have direct nexus with the
quantity of material which is to be supplied to the employer. It was
essential for employer to know the production capacity to ascertain
whether bidder can supply requisite quantity or not, therefore, it cannot be
said that orders suffer from arbitrariness or there is wednesbury
unreasonableness.
13. Said orders also cannot be said to be against public interest.
14. Petitioner has also raised the issue that grounds raised in
representation was not considered and without opportunity of hearing
representation of petitioner was dismissed. It was also submitted that there
was ambiguity in wording and it was not mentioned that annual
production capacity of bidder should be mentioned in manufacturing
registration certificate/EM part II/UAM or document issued by Statutory
Competent Body. Though eligibility was amended by Corrigendum but
list of documents was not amended, therefore, petitioner's self verified
document of annual production capacity ought to have been considered by
respondents. Corrigendum was issued on 21.03.2020 and first condition of
eligibility was amended. Amended corrigendum of eligibility reads as
under:-
"the manufacturer having valid manufacturing registration certificate(license/acknowledgement of EM part ll/IEM Udyog Aadhaar) issued by District Trade Industries Centre or Statutory Competent Authority for manufacturing films with valid pan and GSTN number with a production capacity of 1000 metric tonne per annum."
15. Amended eligibility clearly shows that documents of eligibility must
have mention of production capacity of 1000 metric tonnes per annum. In
view of same, there is no force in argument raised by counsel for
petitioner that there is ambiguity in terms of contract and self certified
annual production letter filed by petitioner ought to have been accepted
and his bid was wrongly rejected by respondents.
16. In view of above, writ petition filed by the petitioner is dismissed.
(VISHAL DHAGAT) JUDGE shabana Digitally signed by SHABANA ANSARI Date: 2021.04.28 11:43:40 +05'30'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!