Citation : 2026 Latest Caselaw 1156 Ker
Judgement Date : 4 February, 2026
2026:KER:9376
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE SATHISH NINAN
&
THE HONOURABLE MR.JUSTICE P. KRISHNA KUMAR
WEDNESDAY, THE 4TH DAY OF FEBRUARY 2026 / 15TH MAGHA, 1947
RFA NO. 387 OF 2016
AGAINST THE DECREE AND JUDGMENT DATED 23.01.2016 IN OS
NO.503 OF 2011 OF I ADDITIONAL SUB COURT, ERNAKULAM
APPELLANT/PLAINTIFF:
FACT ENGINEERING & DESIGN ORGANISATION (FEDO)
A DIVISION OF THE FERTILIZERS AND CHEMICALS
TRAVANCORE LIMITED, GOVERNMENT OF INDIA
ENTERPRISE, HAVING ITS REGISTERED OFFICE AT
UDYOGAMANDAL, REPRESENTED BY ITS PRESENT GENERAL
MANAGER, MANUAL ZACKRIAS.
BY ADVS.
SHRI.M.GOPIKRISHNAN NAMBIAR
SHRI.BENNY P. THOMAS (SR.)
SHRI.K.JOHN MATHAI
SRI.JOSON MANAVALAN
SRI.KURYAN THOMAS
RESPONDENTS/DEFENDANTS 1 AND 2:
1 CORPORATION OF COCHIN
KOCHI-682 011, REPRESENTED BY THE SECRETARY.
2 MS. ANDHRA PRADESH TECHNOLOGY DEVELOPMENT AND
PROMOTION
2026:KER:9376
R.F.A.No.387 of 2016
-: 2 :-
CENTRE (APTDC), REPRESENTED BY ITS DIRECTOR,
HAVING ITS REGISTERED OFFICE AT PLOT NO.7, 1-11-
252/9, 2ND FLOOR, REGAL HOUSE, MOTILAL NEHRU
NAGAR,BEGUMPET, HYDERABAD-500 016.
BY ADV SHRI.D.G.VIPIN
THIS REGULAR FIRST APPEAL HAVING COME UP FOR HEARING ON
04.02.2026, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
2026:KER:9376
SATHISH NINAN & P. KRISHNA KUMAR, JJ.
= = = = = = = = = = = = = = = = = =
R.F.A.No.387 of 2016
= = = = = = = = = = = = = = = = = =
Dated this the 4th day of February, 2026
JUDGMENT
Sathish Ninan, J.
Challenging the dismissal of the suit for money, the
plaintiff is in appeal.
2. The plaintiff entered into a contract with the 1 st
defendant to provide consultancy services for setting up a
solid waste treatment plant. The plaintiff was to prepare
technical and financial documents and supervising
implementation of the project. The 2nd defendant is the
contractor for the work, having entered into an agreement in
the said regard with the 1st defendant. According to the
plaintiff, the contract was performed and the project was
completed. The suit is for the unpaid value of the work done
by the plaintiff under the contract.
2026:KER:9376
3. The 1st defendant, did not deny the contract, and
that the plant was set up. The contention is that there were
various defects in the plant and that it is not functioning
properly.
4. The trial court held that the work done under the
supervision of the plaintiff was faulty, and accordingly
dismissed the suit.
5. We have heard the learned counsel on either side.
6. In the nature of the order we propose to pass, it
is unnecessary to go into the minute factual details. The
establishment of the plant pursuant to the agreement is not
in dispute. It is on record that there has been a change in
the site; though dry land was to be provided, the site
provided was marshy land. The steps suggested by the
plaintiff for developing the land, was not adhered to by the
1st defendant. The trial court has repeatedly found the 1 st
defendant at fault, of course along with the plaintiff.
Ext.B14 is the report of an expert. The report narrates the 2026:KER:9376
defective works, rectification possibilities, etc. The
relevant portions of the report, which deal with the same,
read thus:
"Defective works that can be Retained technically
(i) Those columns which have undergone settlement. However, these columns shall be monitored regularly to ensure that there is no further deterioration in the situation.
(ii) Those columns that are out of plumb.
(iii) Tie beams at roof level that are not in proper alignment may be retained.
Deduction in payment shall be effected towards rectification of these items.
Defective works to be rectified
(i) The floors of buildings in the MSWDF that are cracked and have settled are to be completely dismantled and reconstructed to the original line and levels.
(ii) Defective drains for conveying storm water and leachate have to repaired and made good or relaid.
(iii) Those parapet walls which have cracked, settled or are not in alignment are to be demolished and reconstructed to the original line and levels.
(iv) Defects in the machinery for processing, compost have to be rectified.
Incomplete works (I) Providing cladding to buildings 2026:KER:9376
(ii) Sump of the ETP
(iii) ETP
(iv) Roads
(v) Green belt development
(vi) Secured landfill
(vii) Laboratory facilities.
(viii) Manuals and documents."
7. Noticeably, the report mentions of certain defects,
which are rectifiable. The plaintiff has a case that, the
issues which contributed to the defects noted by the expert
were duly taken up with the 1 st defendant, but were not
heeded to. Exts. A17 to 20 letters and Ext.21 email
communications are some among them.
8. The fact that the plant was commissioned and had
been functioning, is not in dispute. The defect/deficiency
and the consequent loss suffered by the 1 st defendant could
have formed a subject of a claim against the plaintiff. May
be, in the given circumstances, the 1st defendant would be
entitled to challenge the claim of the plaintiff alleging 2026:KER:9376
deficiency for defects; but necessarily, that has to be with
reference to details and quantum of damages. The plant
having been commissioned and the defendants having utilised
the same, they cannot be heard to say that the plaintiff is
not entitled to raise any claim for the unpaid value of the
work done. Whether the plaintiff is entitled for the entire
value or only a part thereto, whether the damages suffered
by the first defendant exceeds the same, all depends upon
the evidence. Admittedly, there has been no such enquiry.
The plaint claim as such could not have been rejected solely
on the ground of defect/deficiency. It appears that the
trial court was carried away by Exts.B13 and B15 series
photographs which did not relate to the entire plant. The
decree and judgment of the trial court, dismissing the
plaint, is liable to be interfered with.
9. We deem it appropriate to grant an opportunity to
the parties to amend their pleadings and to adduce further
evidence regarding deficiency/defects and damages.
2026:KER:9376
In the result, the appeal is allowed. The decree and
judgment of the trial court are set aside. The suit is
remanded back to the trial court for disposal de novo. The
court fee paid on the memorandum of appeal shall be refunded
to the appellant.
Parties to appear before the trial court on 19.02.2026.
Sd/-
SATHISH NINAN JUDGE
Sd/-
P. KRISHNA KUMAR JUDGE yd
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!