Sunday, 10, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Shri.K.K.Philip, S/O.K.P.Kuriyan vs State Of Kerala, Rep. By The Public
2026 Latest Caselaw 1076 Ker

Citation : 2026 Latest Caselaw 1076 Ker
Judgement Date : 3 February, 2026

[Cites 12, Cited by 0]

Kerala High Court

Shri.K.K.Philip, S/O.K.P.Kuriyan vs State Of Kerala, Rep. By The Public on 3 February, 2026

               IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                PRESENT

               THE HONOURABLE MR. JUSTICE A. BADHARUDEEN

     TUESDAY, THE 3RD DAY OF FEBRUARY 2026 / 14TH MAGHA, 1947

                         CRL.A NO. 106 OF 2011

     CC NO.15 OF 2002 OF ENQUIRY COMMISSIONER & SPECIAL JUDGE,

THIRUVANANTHAPURAM

APPELLANT/ACCUSED NO.2:

             T.O.ABRAHAM,
             GOVT.CONTRACTOR,ONMOOTAN THOTTATHIL, PUTHENPURA,
             URUMBIKUNNEL, THIRUVALLA,, PATHANAMTHITTA (DIST).

             BY ADVS.
             SHRI.AMITH KRISHNAN H.
             SHRI.B.G.HARINDRANATH (SR.)
             SHRI.SUNDEEP ABRAHAM
             SMT.ANNA MARY MATHEW
             SMT.MANAVI MURALEEDHARAN


RESPONDENT/COMPLAINANT:

             STATE OF KERALA
             REP.BY THE PUBLIC PROSECUTOR, HIGH COURT OF
             KERALA,ERNAKULAM

             SPECIAL PUBLIC PROSECUTOR SRI RAJESH.A,
             SENIOR PUBLIC PROSECUTOR SMT.REKHA.S


     THIS CRIMINAL APPEAL HAVING BEEN FINALLY HEARD ON 04.12.2025,
ALONG WITH CRL.A.9/2011, THE COURT ON 03.02.2026 DELIVERED THE
FOLLOWING:
                                                                    2026:KER:9212
Crl.Appeal No.106 & 9 of 2011              2




                        IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                        PRESENT

                       THE HONOURABLE MR. JUSTICE A. BADHARUDEEN

          TUESDAY, THE 3RD DAY OF FEBRUARY 2026 / 14TH MAGHA, 1947

                                  CRL.A NO. 9 OF 2011



      CC NO.15 OF 2002 OF ENQUIRY COMMISSIONER & SPECIAL JUDGE,
THIRUVANANTHAPURAM

APPELLANT & ADDL.APPELLANTS 2 TO 4/ACCUSED NO.1 & HIS L/Hs



        1          SHRI.K.K.PHILIP, S/O.K.P.KURIYAN
                   S/O.K.P.KURIAN (ACCUSED NO.1), 23 CHACKO HOMES,, UC
                   COLLEGE.P.O., ALUVA.

ADDL.2             MR.VINOD GEORGE PHILIP,
                   AGED 48 YEARS
                   S/O LATE. K.K.PHILIP, 184, CANTONMENT SOUTH NAGAR,
                   BEACH ROAD, KOLLAM-691001.

ADDL.3             MR.MANOJ KURIAN PHILIP
                   AGED 50 YEARS
                   S/O LATE. K.K.PHILIP, PONVANIBHAM, POORAM NAGAR,
                   ASRAMAM, KOLLAM.

ADDL.4             MS.VINITHA RACHEL PHILIP
                   AGED 46 YEARS
                   D/O LATE K.K.PHILIP, 59, AROKIA NAGAR, 4TH CROSS,
                   CRAWFORD, TRICHY, TAMILNADU-620012.

                   (ADDITIONAL APPELLANTS 2 TO 4 IMPLEADED AS PER ORDER
                   DATED 24/7/2020 IN CRL.MA NO.1/2020)

                   BY ADV SHRI.JOY THATTIL ITTOOP
                                                               2026:KER:9212
Crl.Appeal No.106 & 9 of 2011           3




RESPONDENT/COMPLAINANT:



                   STATE OF KERALA, REP. BY THE PUBLIC
                   REPRESENTED BY THE PUBLIC PROSECUTOR,, HIGH COURT OF
                   KERALA, ERNAKULAM.

                   SPECIAL PUBLIC PROSECUTOR SRI RAJESH.A
                   SENIOR PUBLIC PROSECUTOR SMT.REKHA.S


         THIS CRIMINAL APPEAL HAVING BEEN FINALLY HEARD ON 04.12.2025,
ALONG WITH CRL.A.106/2011, THE COURT ON 03.02.2026 DELIVERED THE
FOLLOWING:
                                                                           2026:KER:9212
Crl.Appeal No.106 & 9 of 2011                   4




                                                                       "C.R"

                             A. BADHARUDEEN, J.
                   ================================
                       Crl.Appeal Nos.9 and 106 of 2011
                 ================================
                     Dated this the 3rd day of February, 2026

                                COMMON           JUDGMENT

These appeals have been filed by the 1 st and 2nd accused in C.C.No.15

of 2002 on the files of the Enquiry Commissioner and Special Judge,

Thiruvananthapuram. The respondent herein is the State of Kerala represented

by VACB.

2. During the pendency of this appeal, the appellant/1 st accused

in Crl.Appeal No.9/2011 died and accordingly his legal-heirs got impleaded as

additional appellants 2 to 4.

3. Heard the learned Senior Counsel Sri B.G.Hareendranath

for the appellant/2nd accused in Crl.Appeal No.106/2011 and Advocate Sri

Babu S.Nair, the learned counsel for the additional appellants in

Crl.Appeal No.9 of 2011. Also heard the learned Special Public Prosecutor

Sri Rajesh A. and Senior Public Prosecutor Smt.Rekha.S in detail. Perused the 2026:KER:9212

relevant documents and the decisions placed by both sides.

4. The prosecution case is that the 1st accused who worked as

Superintending Engineer, [SE] KIP RB Circle, Kottarakkara for the period

from 6.7.1990 to 28.2.1991. 2nd accused, who was the Contractor for the

work relating to KI & TCDP RBC formation of Kulasekharapuram

Distributory from Ch. 1700 M to 2400 M including CD works hatched

criminal conspiracy with the common object of deriving undue pecuniary

advantage and by adopting corrupt or illegal means and in pursuance of the

said conspiracy and by misutilizing clauses 31 and 32 of LCB

specifications negotiated rates on 21.2.1991 for 5 items of work viz. (1)

Construction of a road crossing at Ch.1950 M, (2) C.C.1:3:6 for making up

foundation, (3) Constructing flume canal from Ch. 1700 M to 1715 M with

bed width of 2.7 meter, (4) Supplying PVC water stopper 305 MM wide

and (5) Providing shoring etc. and executed Supplemental Agreement

(hereinafter `SA' for short) No.3 on 25.02.1991 ignoring the fact that the

2nd accused was eligible for the agreed rate only as per the original

agreement for item Nos. 1 to 4 and not eligible for any extra rate for item

No.5, awarded extra rates and thereby obtained undue pecuniary advantage 2026:KER:9212 Crl.Appeal No.106 & 9 of 2011 6

to the tune of Rs.7,01,380/-. It is further alleged by the prosecution that the

1st accused in pursuance of the above conspiracy hatched with the 2 nd

accused obtained a request from the 2 nd accused on 23.02.1991 demanding

higher rates for RCC 1:2:4 and re-inforcement for the construction of

flume canal with tie beam, negotiated rates with the 2 nd accused on

27.02.1991 and allowed a rate of Rs.1,590/M3 for the total quantity of

1000 M3 of RCC 1:2:4 and also allowed a rate of Rs.11,750/T for a total

quantity of 100 T of re-inforcement for RCC work whereas the Contractor

was eligible only the rate of Rs.1,150/M3 for RCC 1:2:4 and Rs.7,500/T

for re-inforcement for RCC work as per the original agreement and the 1 st

accused had done these acts neglecting the recommendation of his

subordinates and executed supplemental agreement No.6 on 28.2.1991 the

last day of the service of the 1 st accused and thus allowed a total excess

amount of Rs.8,65,000/- to the 2nd accused resulting in corresponding loss

to the Government. Finally it is alleged by the prosecution that the 3 rd

accused, who had worked as Executive Engineer, KIP RB Division No.III,

Kayamkulam from 10/1990 to 10/1991 by abusing his official position,

hatched criminal conspiracy with the 2 nd accused with the same common 2026:KER:9212

object of deriving undue pecuniary advantage and the 3 rd accused, who

should have rejected CC Bill No.IV, V and VI prepared in favour of the 2 nd

accused on the basis of SA Nos.3 & 6 executed on 25.2.1991 and

28.2.1991 respectively by the 1st accused in violation of the LCB

conditions, passed CC Bill No. IV on 21.3.1991 for Rs.6,55,450/-, CC Bill

No.V on 27.3.1991 for Rs.5,22,473/-, CC Bill No. VI on 24.10.1991 for

Rs.7,54,774/- and issued cheque to the 2nd accused and paid a total excess

amount of Rs.15,32,809.69 to the 2nd accused and corresponding loss to the

Government. Thus it is alleged that due to the aforesaid illegal acts the 2 nd

accused obtained undue pecuniary advantage to the tune of

Rs.16,04,908.36 and thereby both accused committed offences punishable

under Section 13(2) r/w 13(1)(d) of the Prevention of Corruption Act,

1988 (`PC Act, 1988' for short hereafter) and Section 120B of the Indian

Penal Code (`IPC' for short). Thereafter, accused Nos.3 and 4 also were

arrayed in this matter alleging commission of the same offences, but the 4 th

accused died before trial.

5. After framing charge, the learned Special Judge recorded

evidence. PWs1 to PW7 were examined and Exts.P1 to P32 were marked 2026:KER:9212

on the side of the prosecution. Exts.D1 to D3 were marked on the side of

defence. On appreciation of evidence, the learned Special Judge found

that accused Nos.1 and 2 committed offences punishable under Section

13(1)(d) r/w 13(2) of the PC Act, 1988 and under Section 120B of IPC

while acquitting the 3rd accused. Accordingly, accused Nos.1 and 2 are

sentenced to undergo rigorous imprisonment for a period of three years

each and in addition they shall pay a fine of Rs.17,00,000/- (Rupees

Seventeen Lakhs only) each and in default of payment of fine, they shall

undergo rigorous imprisonment for a period of one year each, for the

offence under S.120-B I.P.C, they are sentenced to undergo rigorous

imprisonment for a period of one year each. The bail bond executed by

them are cancelled. The substantive sentences shall run concurrently.

6. The learned Senior Counsel appearing for the 2 nd

accused vehemently argued that none of the offences would be attracted in

the present case. The prime contention raised is that even though

Ext.P3(a), the original agreement executed in 1988, fixed the amount for

completing the work at Rs.23,15,000/-, without properly considering the

shiny and slushy nature of the soil, and even though Rs.23,15,000/- was 2026:KER:9212 Crl.Appeal No.106 & 9 of 2011 9

fixed as the expenditure, taking into account the odorous nature of the soil,

the work could not be completed for the said sum because extra works had

to be carried out due to the slushy soil. For this reason, Ext.P4(p) SA No.3

dated 25.02.1991 and Ext.P4(q) SA No.6 dated 28.02.1991 were executed.

It is also pointed out that although the number of tie-beams originally

proposed in Ext.P3(a) was 46, a total of 78 tie-beams were actually

constructed, and in this regard reliance is placed on the evidence of PW1

supported by PW7. Apart from this, it is contended that as evident from

Ext.P7(b), Ext.P7(g) and Ext.P7(e), water stoppers having a width of 45

cm were agreed to be provided, but due to non-availability during the

construction period, water stoppers having a width of 30.5cm were used,

entitling the 2nd accused to claim additional amounts under the head `extra

items'. The learned Senior Counsel further contended that as per item No.1

in Ext.P3(a), the extra work was done as a result of an agitation initiated

by Nanoo Master, the then MLA of the locality, and due to the

intervention of the Irrigation Minister, to make additional constructions,

since only a footpath was provided at Ch.No.1930 m. Thus the contractor

was compelled to construct a motorable road crossing the canal during the 2026:KER:9212

execution of the work.

7. Regarding this contention, the learned Special Public

Prosecutor pointed out that this item had already been accepted as an extra

item in favour of the 2nd accused by the Special Court, and the prosecution

had no dispute in that regard. According to the learned Special Public

Prosecutor, for this additional work, the 2nd accused was entitled to

payment determined through negotiation between the 1 st accused

(Superintending Engineer) and the 2nd accused.

8. The learned Senior Counsel for the 2nd accused also

submitted that as per clause 32 of Ext.P3(a) and as per SA Nos.3 and 6, the

amounts sanctioned by the 1st accused and obtained by the 2nd accused

were within the powers of the 1st accused and the said amount was entitled

by the 2nd accused. Therefore, there is no conspiracy in granting and

encashing the bills. Therefore, there is no misappropriation as alleged by

the prosecution and the prosecution case in its entirety is based merely on

surmises and conjectures, without support from any convincing evidence.

9. The learned Senior Counsel also submitted that when

this Court considered Crl.Appeal No.2/2002 arising out of 2026:KER:9212

C.C.No.29/2009, where similar allegations were raised, this Court by

judgment dated 04.09.2019 acquitted all the accused on the finding that

when excavation of "hard narikkal" work was carried out in deviation

from the agreement, the Superintending Engineer was found empowered to

approve the work done for constructing the "hard narikkal" as an extra

item and accordingly by setting aside the judgment of the Special Court all

the accused were acquitted. He has also pointed out the decision of another

Single Bench of this Court reported in [2008 (3) KLJ 165 : 2006 ICO

11532 : 2008 (3) KHC 817], Varghese Mathew & Ors. v. State of Kerala,

wherein this Court acquitted the accused therein. He also cited the

judgment in Crl.Appeal No.2/2004 in K.G.Ashokan v. State of Kerala, in

this regard. Therefore, applying the ratio of the above decisions and the

submissions made, it is contended that the impugned verdict would require

interference and the 2nd accused is entitled to acquittal, after revising the

verdict impugned.

10. Similar contentions were raised by the learned counsel

appearing for the legal heirs of the 1st accused while seeking interference

in the verdict of the Special Court.

2026:KER:9212

11. Zealously opposing the contentions raised by the

respective counsel for the accused, the learned Special Public Prosecutor

pointed out that originally Ext.P3(a) was executed to complete the work

appended therein for a total sum of Rs.23,15,000/-. According to him,

except item No.1 in SA3 [Ext.P3(b)], all other items of work for which

SA3 and SA6 agreements were executed, were completed, and thereby

amounts of Rs.7,13,415/- (SA3) and Rs.27,65,000/- (SA6) became

payable. Thus, a total of Rs.34,78,415/- was the amount entitled by the

contractor for the work provided in the agreement at the agreed rate fixed

as per Ext.P3(a) original agreement. Therefore, there is no question of

invocation of clause 32 of Ext.P3(a) to grant any additional amount for the

said work, treating it as `extra work' done in deviation from Ext.P3(a)

original agreement.

12. It is specifically argued by the learned Special Public

Prosecutor that item Nos.2 to 4 covered by SA3 and two items covered by

SA6 were the works originally included in Ext.P3(a) original agreement.

According to the learned Special Public Prosecutor, regarding item No.2 in

SA3, PW1 categorically had given evidence that item No.2 was included 2026:KER:9212 Crl.Appeal No.106 & 9 of 2011 13

as item No.5 in appendix G and the same is a part of Ext.P1(a) estimate.

The learned Special Public Prosecutor further pointed out that, for this

work, the 1990 schedule of rates was applied and the AEE fixed the rate at

Rs.817.61 per m³. Then the Executive Engineer worked it out at Rs.681/-

per M³, the 1st accused granted Rs.1,400/- per m³ in SA No.3 item No.2

and that was agreed upon by the 2 nd accused. Similarly, item No.3 in SA3

was also a work originally included and the work was agreed to be done at

the rate of Rs.531.48/- per M³, Rs.1,186/- per M³ and Rs.7,567.40 per

tonne. According to the learned Special Public Prosecutor, as per

Ext.P4(m), for item No.1 in SA3, instead of Rs.681/- per m³, the rate was

enhanced to Rs.1,400/- per m³ through Ext.P3 negotiation between the 1 st

and 2nd accused and for item No.2, the rates were increased to Rs.850/- per

M³, Rs.1,700/- per M³ and Rs.11,000/- per tonne as against Rs.531.48 per

M³, Rs.1,186/- per M³ and Rs.7,567.40 per tonne, as stated in paragraph 11

of the judgment. He also pointed out that regarding the water stoppers

mentioned in SA3, the agreed size was 45 cm and according to the accused

persons, the size was reduced to 30.5cm. In this connection, it is submitted

by the learned Special Public Prosecutor that, in fact, the shortage of water 2026:KER:9212

stoppers having size of 40 cm was found after completion of 90% of the

work, and as per Ext.P1(h), as pointed out by the learned Senior Counsel

for the 2nd accused, only water stopper to a size of 30.5cm was permitted.

It is also pointed out by the learned Special Public Prosecutor that

originally the amount agreed for a water stopper was at Rs.100/M, but as

per Ext.Pl(m) negotiation, the rate for the same was increased to the tune

of Rs.750/- per metre. According to the learned Special Public Prosecutor,

regarding item No.5 in SA3, as per the evidence given by PW1, claim for

shoring was not entitled, as the work was included in the original

agreement. However, after granting the same, Rs.1,169/- per metre was

negotiated between the 1st and 2nd accused for a total length of 217 metre,

as seen from paragraph 13 of the judgment. It is also submitted that

regarding item No.1 in SA6, the said item also was agreed upon in the

original agreement @ Rs.1,150/- per metre. But the same was enhanced

by the 1st accused as per Ext.P4(m) negotiation to the tune of Rs.1,169.50

per metre.

13. According to the learned Special Public Prosecutor, in

this case, the prosecution has no case that there was conspiracy in between 2026:KER:9212

the accused persons at the time of execution of the original agreement or at

the time of commencement of the work. But the prosecution case

specifically is that after completion of the work as agreed, the 1 st and 2nd

accused conspired together to misappropriate Government funds and as a

result of the said conspiracy, both of them decided to put up and act upon

unwanted claims, as discussed herein above for obtaining a huge amount

as enhancement and the Government money to the tune of Rs.34,78,415/-

was encashed by the 2nd accused and thereby the 2nd accused

misappropriated the said sum with the aid of the 1st accused and

accordingly both of them committed the offences as alleged.

14. The learned Special Public Prosecutor anxiously argued

that, in fact, the work was taken on tender by the 2 nd accused, who is an

experienced contractor, after knowing the nature of the soil, the work to

be carried out, etc. for an amount of Rs.23,15,000/-. Thereafter, SA3

and SA6, were vexatiously created for claims which were not at all

entitled by the 2nd accused and the amounts were encashed. The learned

Special Public Prosecutor further pointed out that, for a work originally

agreed upon for an amount of Rs.23,15,000/-, an amount of ₹34,78,455/-

2026:KER:9212

was altogether obtained by claiming the same as `extra works'. Therefore,

the prosecution case as to misappropriation of Rs.34,78,455/- is proved

beyond reasonable doubts. According to the learned Special Public

Prosecutor, as far as the decisions placed by the learned Senior Counsel for

the 2nd accused are concerned, the said decisions in no way addressed the

agreement or the conditions thereof in its proper perspective and also, the

facts and claims therein were totally different. Therefore, the above

decisions have no binding effect when independently considering the work

done herein based on Ext.P3(a) for which an exorbitant amount was

granted by executing SA3 and SA6.

15. The learned Special Public Prosecutor has placed a

decision of the Apex Court in Rajiv Kumar v. State of U.P. [2017 KHC

6522 : AIR 2017 SC 3772 : 2017 (8) SCC 791 : 2017 CriLJ 4734],

particularly paragraphs 10 and 44, wherein the Apex Court extracted the

ingredients to constitute the offence of forgery as under:

"10. S.13 of the P.C. Act in general lays down that if a public servant, by corrupt or illegal means or otherwise abusing his position as a public servant obtains for himself or for any other person any valuable thing or pecuniary advantage, he would be guilty of 'criminal 2026:KER:9212

misconduct'. Sub-section (2) of S.13 speaks of the punishment for such misconduct. S.13(1)(d) read with S.13(2) of P.C. Act lays down the essentials and punishment respectively for the offence of 'criminal misconduct' by a public servant. S.13(1)(d) reads as under:

"13. Criminal misconduct by a public servant. - (1) A public servant is said to commit the offence of criminal misconduct, (d) if he, -

(i) by corrupt or illegal means, obtains for himself or for any other person any valuable thing or pecuniary advantage; or

(ii) by abusing his position as a public servant, obtains for himself or for any other person any valuable thing or pecuniary advantage; or

(iii) while holding office as a public servant, obtains for any person any valuable thing or pecuniary advantage without any public interest; or"

A perusal of the above provision makes it clear that if the elements of any of the three sub-clauses are met, the same would be sufficient to constitute an offence of 'criminal misconduct' under S.13(1)(d). Undoubtedly, all the three wings of clause (d) of S.13(1) are independent, alternative and disjunctive. Thus, under S.13(1) (d) (i) of P.C. Act obtaining any valuable thing or pecuniary advantage by corrupt or illegal means by a public servant in itself would amount to criminal misconduct. On the same reasoning under S.13(1) (d) (ii) of P.C. Act "obtaining a valuable thing or pecuniary advantage" by abusing his official position as a public servant, either for himself or for any other person would amount to criminal misconduct."

"44. The essential ingredients of the offence of criminal conspiracy are:

(i) an agreement between two or more persons; (ii) the agreement must 2026:KER:9212

relate to doing or causing to be done either (a) an illegal act; or (b) an act which is not illegal in itself but is done by illegal means. It is,therefore, plain that meeting of minds of two or more persons for doing or causing to be done an illegal act or an act by illegal means is sine qua non of criminal conspiracy. It is extremely difficult to adduce direct evidence to prove conspiracy. Existence of conspiracy and its objective can be inferred from the surrounding circumstances and the conduct of the accused. In some cases, indulgence in the illegal act or legal act by illegal means may be inferred from the knowledge itself."

16. Having considered the arguments on the issue, the points

arise for consideration are :

(i) Whether the Special Court is justified in holding that

accused Nos.1 and 2 committed the offence punishable under Section

13(1)(d) r/w 13(2) of the PC Act, 1988?

(ii) Whether the Special Court is right in holding that the

accused committed the offence punishable under Section 120B of IPC?

(iii) Whether the contention raised by the 2nd accused that

there was no prosecution sanction to prosecute the accused is sustainable?

(iv) Is it necessary to interfere with the judgment in any

manner?

              (v)           The order to be passed?
                                                                2026:KER:9212


Points (i) to (v)

              17.           In this case for formation of Kulasekharapuram

Distributory from Ch.1700M to 2400 M including CD works as part of

Kulasekharapuram Irrigation Project, an estimate was prepared by PW5,

who was the Assistant Engineer of KIP RB Section during the said period.

Ext.P10 is the file relating to the preparation of estimate with respect to the

aforesaid work which was maintained at the office of PW5 (AE). PW5

deposed that the estimate of this work was prepared by him and he had

sent the estimate to the Assistant Executive Engineer. The first item

covered in Ext.P10(a), that is the estimate, is earth work excavation in all

classes of soil with foundation and depositing on banks with all leads and

lifts including back filling using the spoil, watering etc. The second item of

work is bailing out water with 5 H.P oil engine including conveying

erecting, cost of fuel, pay of staff etc. The 3 rd item of work is cement

concrete 1:4:8 using 40 mm metal including watering, curing etc. complete

as per specifications and drawing or as directed by the Engineer-in-charge.

The 4th item of work is RR in CM 1:6 including pointing the exposed face

simultaneously with the same mortar including watering, curing etc. The 2026:KER:9212

5th item of work is RRC 1: 5:6 using graded metal for road crossing etc.

The 6th item of work is RCC 1:2:4 using 20 mm metal including all

watering, curing etc. complete in road crossing and foot path. The 7 th item

of work is providing reinforcement for RCC work bent, tied and placed in

position as per specification and drawing or as directed by the Engineer-in-

charge. The 8th item of work is filling and forming approaches of road way

using contractor's own earth etc. The 9 th item of work is plastering with

CM 1:4 15mm thick one coat floated hard.

18. The evidence of PW5 further is that in the estimate the

earth work excavation of flume canal RCC 1:2:4 using 20mm metal size,

bed, haunches and tie beam are included. PW5 stated that for each item

estimate was prepared for concrete and reinforcement. The said estimate

prepared by PW5 was forwarded to the Executive Engineer (EE) through

the Assistant Executive Engineer (AEE). This estimate was then forwarded

to the Superintending Engineer (SE) by the EE.

19. It is discernible that PW1 was the S.E of KIP, RBC from

22.06.1997 to 02.03.1999. PW1 identified Ext.P1 file as the file relating to

this work maintained at his office. Ext. P1(a) is pages 1 to 15 of the said 2026:KER:9212

file which is the estimate forwarded to him by the E.E. PW1 identified his

initials in page 15 of Ext. P1(a). Two major items of work could be found

from Ext.P1(a), the first one is canal formation as per Appendix L. It is

stated in Ext.P1(a) that the canal proposed was an open flume of RVV

1:2:4 as per approved hydraulic particulars.

20. It is further stated that in this estimate the flume is

starting in a transition of 5 m length from Ch.1700 to 1705M. As per items

1 and 2, provisions had been made for uprooting of trees in the alignment.

Item No.3 is earth work excavation for foundation of flume canal. It is

stated that the canal reach passes through sandy soil and paddy field and so

the rate for ordinary soil with necessary additional leads and lifts had been

provided. Item No.4 is bailing out water with 5 H.P Engine and pump set,

approved rate was given in the estimate. Item No.5 is provision has been

made in this estimate for CC 1:4:8 using 40mm metal for foundation of the

flume for the entire length. Item No.6 was RR block masonry in cement

mortar 1:6 proposed over the CC 1:4:8 for the flumed portion to with stand

the heavy load over it. The minimum depth of RR 1:6 in paddy field was

fixed as 40cm and varies in filling. It is noted that necessary openings are 2026:KER:9212 Crl.Appeal No.106 & 9 of 2011 22

proposed in masonry blocks in paddy field to allow water to flow. Item

No.7 is provided for the construction of flume with RCC 1:2:4 using 20

mm metal. Necessary reinforcement is also provided. Item No.8 covers

necessary provisions in this estimate for providing reinforcement for RCC

work. Reinforcement at 100kg is proposed. Item No.9 mentioned that

water tight expansion joints at 30 M intervals is proposed by using rubber

water seal and the joints filled with bitumen mastic filler. The second

major head is Appendix-G that is road crossing culvert and foot paths. It is

noted therein that the alignment of the canal crosses 7 m wide roads at

Ch.2310 and 2M wide road 3 Nos. at different chainages. Necessary

provisions such as earth work excavation, bailing out water, CC 1:4:8 for

foundation and CC 1:3:6 for abutments have been made in this estimate for

constructing the road crossings. A clear road way of 7 m are provided by

30cm thick RCC 1:2:4 deck slab over the abutments and 15cm thick for

foot slab provisions have been made for constructing parapet and retaining

walls, step footing in RR 1:6 and in DR packing. Necessary earth fillings

to raise the road way so as to get approaches to the road way have also

been made in this estimate. The attached drawing and the estimates are self 2026:KER:9212

explanatory. Finally it is noted that the estimate is prepared based on the

current schedule of rates. Further it is again noted that the LS sheets, data

and conveyance statement, detailed estimate and drawings are appended to

the same. The total estimate amount was shown as Rs.25 lakhs, and later

corrected to Rs.24,45,000/- at the office of PW1 as could be gathered from

page 30 of Ext.P1.

21. PW1 also testified regarding Ext.P2 file. According to

PW1, Ext.P2 is the file relating to the said work maintained at the office of

the Chief Engineer. The said file is identified by PW1. Ext.P2(a) is sheet

Nos.1 to 21 of the said file which is identified by PW1 as the estimate sent

from his office to the Chief Engineer (C.E). for this particular item of

work. Drawings are also included in Ext.P2. PW1 stated that these

drawings were received by him from the office of the S.E. and he

forwarded the same to the C.E. along with the estimate. This drawings are

contained in page 1 to 5 of Ext. P2 file. Pages 6 to 17 of the file relates to

conveyance statement and detailed estimate. Scrutiny was conducted at the

office of C.E. and it was sanctioned for a total amount of Rs.23,15,000/-.

Ext.P1(b) is page 25 of Ext. P1 file showing that the technical sanction 2026:KER:9212 Crl.Appeal No.106 & 9 of 2011 24

was given for the said work from the office of the C.E. Ext.P1(c) is sheet

Nos.22 to 24 which is the abstract of the estimate prepared at the office of

the C.E. In this abstract the total quantity of work for RCC 1:2:4 was fixed

as 1000M3 and reinforcement was fixed at 100T. The total amount for

Appendix-L canal formation that is flume canal is fixed at Rs.21,22,950.

For road crossing at Ch.2310 and foot path that is Appendix-G the total

amount is fixed as Rs.1,57,651/-. Thus the general abstract prepared at the

office of the C.E. would go to show that the final sanction was given for

Rs. 23,15,000/-. In page 11 of Ext.P1(a) the details of the construction of

flume canal is shown. The total quantity is mentioned as 1008M3 that was

converted into 1000M3 at the office of the C.E. In Ext.P1(a) different

items of work in item No.7 including the berl, size, haunches and tie

beams of the flume canal are shown. The total number of tie beams

mentioned as 46 and the total quantity for the said tie beam work is shown

as 2.9M3. It is further shown that the tie beams should be constructed at

15m intervals. The length of the tie beams is shown as 2.8m width of the

beam is shown as 0.15m and depth is shown as 0.15m. He stated that the

total number of tie beams fixed is 46 and so the total quantity of the tie 2026:KER:9212

beam is arrived at 2.900m3. The item No.8 is also mentioned in Ext.P1(a).

The item of work in this item No.8 is providing reinforcement for RCC

work bend, tie and placed in position as per specification and drawing or

as directed by the Engineer-in-charge.

22. According to PW1, the reinforcement of the bed flume

canal, sides, tie beams and any other RCC work of same specification.

100kg of steel/M3 was fixed. The length of the flume was reduced to 7.8m

and so the total quantity was reduced to 1000M3 from 1008M3. The said

length reduced was included in Appendix-G. PW1 stated that when the

C.E. scrutinized the said estimate the quantity of the tie beam was not

changed. At the office of the C.E. also the total quantity of the concrete

portion was fixed at 1000M3 and the quantity of the reinforcement was

fixed at 100T. So far the said work tenders were invited from the office of

PW1. PW1 deposed further that the lowest tender was submitted by the 2nd

accused. Ext.P1(d) is the letter sent by PW1 to the Director of Public

Relations, Thiruvananthapuram for publishing the short tender notice. As

stated above, the 2nd accused submitted the lowest tender and accordingly

this tender was accepted and agreement was entered by PW1 with the 2nd 2026:KER:9212

accused. Ext.P3 is the agreement file maintained at the office of PW1.

23. Now it is necessary to look into Ext.P3(a). Ext.P3(a) is

the original agreement No.9/88-89/SC/KIP executed between PW1 and the

2nd accused. This agreement was executed on 19.7.1988. Ext. P3(a) is sheet

Nos. 1 to 75 which contains the original agreement schedule etc. Sheet

No.73 is the memorandum of work. The sanctioned estimate is

shown as Rs.22,78,566/- and the accepted tender is shown as Rs.

23,62,858/-, the date of commencement of work is mentioned as the date

of issue of order to start the work. The date of completion of work is 9

months from the date of issue of order to start the work. Ext.P3(a-1) is

sheet Nos.67 to 71 of Ext.P3(a) which is the accepted agreement schedule.

Appendix-L-1 in Ext.P3(a-1) is constructing flume canal. Item No.1 is

earth work excavation in all classes of soil with foundation and depositing

on banks with all leads and lifts including back filling using the spoil,

watering etc. Item No.2 is bailing out water with 5 H.P oil engine

including conveying erecting, cost of fuel, pay of staff etc. Item No.3 is

cement concrete 1:4:8 using 40 mm metal including watering, curing etc.

to be completed as per specifications and drawing or as directed by the 2026:KER:9212

Engineer-in-charge.

24. As per Ext.P3(a), the 4th item is RR in CM 1:6 including

pointing the exposed face simultaneously with the mortar including

watering, curing etc. The 5th item is RRC 1:5:6 using graded metal for road

crossing etc. The total quantity mentioned is 412/M3. The rate fixed is

500/M3. Item No.6 is Random Rubble in cement mortar 1:2:4 for

foundation and super structure including pointing the exposed faces of

masonry simultaneously with the same mortar including watering, curing

etc. complete as per specification. The total quantity mentioned is

564M3 and the rate fixed is Rs.100/M3. The 7 th item is RCC 1:2:4

using 20mm broken stone for flume canal including all form work

watering, curing etc. complete but excluding cost and labour for

reinforcement as per specification. The quantity is 1000M3 and the rate

fixed is Rs. 1150/M3.

25. Coming to reinforcement for RCC work, bent, tied

and placed in position as per specification. The total quantity mentioned

is 100T and the rate is Rs.7,500/T. Coming to supply and fixing of PVC

water stopper 45cm wide and filling the gaps with 25mm thick machine 2026:KER:9212

pressed bitumen pad of approved quality including all cost and conveyance

etc. complete. The total quantity is 250M and the rate fixed is Rs.100/M.

Appendix-G is construction of road crossing at Ch.2310M and foot path at

different chainages.

26. Reverting back to item No.1, the same is earth work

excavation in all classes of soil to lines and grades for foundation of canal

structure and depositing the spoil on banks and back filling with the spoil

with all leads and lifts, watering, ramming and consolidating etc. complete.

The total quantity mentioned is 185M3 and the rate fixed is Rs.5/M3. The

second item is bailing out water using 5HP Engine and pump set including

conveying to site, Erection charges, cost of fuel, lubricating oil and all

other stores, pay of staff etc. complete. The total time is 24 Hr and the rate

is Rs.10/Hr. The third item is cement concrete 1:4:8 approx using 40mm

metal (nominal size) for foundation to lines and grades and dimension as

shown in the drawing including hire and labour for fixing to lines and

grades, the form work staging scaffolding etc. including removing the

same after the concrete has set or as directed by the Engineer-in-charge

including all boxing, compacting curing, dewatering etc. complete as per 2026:KER:9212

specification. The total quantity is 19M3 and the rate fixed is 400/M3.

27. Item No.4 is random rubble cement mortar 1:6 including

pointing the exposed spaces simultaneously wherever necessary or as

directed by the Engineer-in-charge including watering, curing etc.

complete. The total quantity is 54M3 and the rate fixed is Rs.300/M3. The

item No.4(a) is dry rubble masonry for retaining wall, wherever necessary

as directed by the Engineer-in-charge. The total quantity is 48M3 and the

Rs.50/M3.

28. Item No.5 is cement concrete M100 (1:3:6 approx) for

super structure using graded metal, lines and grades and dimension as

shown in the drawing including hire and labour for fixing to lines and

levels all form work, staging, scaffolding etc. for concrete including

removing the same after the concrete has set or as directed by the

Engineer-in-charge including all boxing, compacting, curing, watering,

etc. complete as per specification. The quantity mentioned is 82M3 and the

fate fixed is Rs.725/M3.

29. Item No.6 is reinforcement cement concrete M150 (1:2:4

approx) with 20 mm broken stone for slab as per the dimension shown in 2026:KER:9212

the drawing including hire and labour for fixing to lines and levels, all

form work, staging, scaffolding etc. for concrete including removing the

same after concrete has set or as directed by the Engineer-in-charge,

compacting, curing etc. complete, but excluding cost and labour for

reinforcement. The total quantity mentioned is 30M3 and the rate fixed is

1200/M3.

30. Item No.7 is in relation to providing reinforcement for

RCC work, bent, tied and placed in position as shown in the drawing or as

directed by the Engineer-in-charge etc. as per specification. The quantity

mentioned is 2.35T and the rate fixed is Rs.7500/T. Item No.8 is filling

and forming the approach road to lines and levels with earth available from

flume excavation including spreading in layers having a thickness of not

more than 15 cm when compacted watering and consolidating with power

roller or other approved equipment and the quantity is stated 55 M³ at

Rs.15/ M³. The 9th item is plastering with CM 1:4, 15 mm thick one coat

floated hard and trowelled smooth including all charges for watering,

curing etc. complete as per specification. The total quantity mentioned is

61M2 and the rate is Rs. 13/M2.

2026:KER:9212

31. During examination of PW1, PW1 identified his

signature in Ext.P3(a) agreement and he also identified the signature of the

2nd accused in this agreement. PW1 deposed that the item of work

mentioned is the bed, sides, haunches, tie beam of flume canal. Drawing

are also appended to Ext.P3(a). PW1 further testified that the LCB

specifications appended to Ext.P3(a) agreement would form the part of the

agreement. This aspect is not in dispute. Sheet Nos. 25 to 32 of Ext.P3(a)

is the Local Competitive Bidding Specification. Ext. P3(a-2) is the

statement of departmental materials proposed to be issued for the work.

Cement, Tore steel are included as Departmental materials supplied for the

said work. The quantity of cement allowed is 471.20T and the total

quantity of tore steel allowed is 102.35 Т. The recovery rate is fixed at Rs.

1200/-T for cement and Rs. 6500T for tore steel.

32. PW1 stated that the copy of the agreement was sent to

the Accountant General, EE, AEE and AE and also to the Contractor and

Ext.P1(e) is the copy of the letter showing that the same was sent to these

persons. Ext.P1(f) is the initial level proposed and sent to PW1 by the E.E.

33. When the evidence of PW1 is analysed in the above line 2026:KER:9212

the prosecution proved Ext.P3(a), otherwise also the execution of

Ext.P3(a) is not disputed by the 2nd accused. It is not in dispute that the

LCB Specifications appended to Ext.P3(a) is applicable to this contract in

question. The period fixed was 9 months and so clause 32(A) the price

adjustment clause was struck off at the time of executing the agreement.

The work was carried on at the site under the supervision of PW5 who was

the A.E. during the said period.

34. Regarding the use of water stopper having a width of 45

cm. Ext.P1(g) is the letter sent by the 2 nd accused to PW1. In Ext.P1(g) it is

stated by the 2nd accused that as per item No.9 of the accepted schedule

supplying and fixing PVC water stopper of size 45 cm wide was specified.

But such size was not available in the market and the only available size is

30.5 cm. The said letter ie Ext.P1(g) is dated 18.10.1988. PW1 stated that

this water stopper is a rubber pad fixed in the joints on two sides of the

flume to prevent leakage of water. Ext.P1 (h) is the reply sent by PW1 to

Ext.P1(g) letter of the contractor. As per Ext. P1(h), the 2 nd accused was

permitted to use 30.5 cm wide PVC water stopper instead of 45 cm

provided in the agreement. The copy of the said letter was forwarded to the 2026:KER:9212 Crl.Appeal No.106 & 9 of 2011 33

E.E., KIP RB Division No.lI, Adoor with request to submit the data and

the supplemental schedule for this item for executing SA. Again Ext.P1 (i)

letter was sent by the Contractor PW1. It is stated in Ext.P1 (i) letter that

during the earth work excavation both banks of the canal found slipping

down because of sandy soil and he was now excavating at 1:1 side slope. It

was further stated that they were providing shoring at 1.5 m height and

round the clock bailing out of water with 5 HP pump would be required.

So he requested to issue necessary orders for the payment for additional

earth work for side slope, shoring and for bailing out of water to proceed

with work. To Ext. P1 (i) letter PW1 had endorsed that any unauthorized

modification in side slopе providing shoring without approval or extra

pumping not duly approved at site by the site Engineer would not be paid

for. Ext.P1(j) is the reply sent by PW1 to the accused for Ext.P1(i) letter. It

is stated in Ext.P1(j) that any unauthorized modification in side slope

providing shoring without approval or extra pumping not duly approved at

site by the Site Officers would not paid for. Copy of the said letter was

seen forwarded to the E.E., KIP, RB Division No.III, Adoor. As stated

earlier as per Ext.P1(h) letter sent by PW1 to the Contractor he was 2026:KER:9212 Crl.Appeal No.106 & 9 of 2011 34

permitted to use 30.5cm wide PVC water stopper and PW1 had

recommended for executing supplemental agreement with respect to the

said work. PW1 identified Ext. P4 as the file maintained at his office. Ext.

P4(a) is identified by PW1 as the letter sent to him by the E.E. Along with

the said letter the E.E. submitted the data for providing PVC water stopper

305 mm wide and refilling the gap with 25mm thick machine pressed

bitumen pad. He stated that the cost of materials provided in the data were

the current market rate. He requested for approval of the said data and

execution of Supplemental agreement. Ext.P4(a-1) is the data for PVC

water stopper. The cost of the water stopper was arrived at Rs.205.42/M in

Ext.P4(a-1). Ext.P5 is the note file of Ext.P1 and P4. Ext.P5(a) is the sheet

Nos.38 and 39 of Ext. P5 file. In Ext.P5(a-1) the Draftsman had noted that

the E.E. in his letter dated 12.1.1989 had submitted the data and

supplemental schedule for the above extra item and the data was checked

and put up for approval and rate come Rs.205.42/M. Не requested for the

approval of the said data. PW1 had directed the E.E. to certify the

reasonableness of the cost of PVC water stopper in the data. In Ext. P5(b)

it was noted that some proposals were received in the office and also some 2026:KER:9212 Crl.Appeal No.106 & 9 of 2011 35

quotations had been received in Division No.1 and it was directed to

compare the rates and put up the file. PW1 deposed that till he left the said

office no decision was taken in the said matter. During cross-examination

PW1 stated that only after perusing the records he could say whether trial

pit was taken. In Ext. P2(a) it is noted that the canal reach passes though

sandy soil and paddy field and in the LS drawing between 2000M to

2100M a pond is shown and in Ch. 2310M to 2400M paddy field is also

shown. He admitted that flume canal was purely structural work/RCC with

reinforcement. When the execution work started PW1 was there in the

office as S.E. He admitted that Ext. P3(a-3) was the drawing of typical

flume canal with flume section. Ext.P3(a-4) is the drawing of foot path at

Ch.1930m. Ext. P3(a-5) is the drawing of road crossing at Ch.2310M and

Ext.P3(a-6) is the foot path at Ch.2100M to 2106M. He further admitted

that if during soil excavation it could be found that the vertical execution

would not practical, because the Site Engineer could direct to give slope.

According to him in this case it was not revealed that vertical excavation

was not practical. He testified further that he had visited the site and he

had also seen the excavation done at the spot. He added that it was the duty 2026:KER:9212

of the Contractor to give side protection at the time of excavation of soil

and for bailing out water. He stated that there was provision for the same

in the estimate. The total width of the acquired land according to him was

6m and the canal width was 2.8m. He admitted that the contractor could

envisage what all particulars were there in the structure on seeing the

drawings and the specifications.

35. Item No.2 in Ext.P3(b-1) pertaining to S.A. No.3 was

cement concrete 1:3:6 using graded metal 60% 40mm and 40% 20mm to

alignment, grade and dimension for making up in slushy including all

forming, watering, curing etc. The total quantity for the same was 98M3

and the rate arrived at in negotiation was 1400/M3. It was admitted by

PW1 that nowhere in Ext.P1 file it was stated that trial pit was taken. He

further admitted that in Ext.P2(a) it was noted that the canal reach portion

was sandy soil and paddy field. He again stated that in LS drawing it was

noted in 2000M and 2100M there was a pond. He further admitted that

from Ch.2310 M to 2400M there was paddy field and for making up the

said portion this item of work was done. The same item of work was

included as item No.5 in Appendix-G to the original agreement. The said 2026:KER:9212 Crl.Appeal No.106 & 9 of 2011 37

item was also cement concrete 1:3:6 using graded metal 60% 40mm and

40% 20mm Ext. P4(i) is sheet Nos. 113 to 115 of Ext.P4 file. It could be

seen from Ext.P4 that by adopting 1990 schedule of rates for this item the

AEE had recommended Rs.817.61/M3 which was finalized by E.E. as

Rs.681/M3. Ignoring all these matters at the time of negotiation as seen

from Ext.P4(m) negotiation statement the amount arrived by the 1 st

accused on negotiation with the 2nd accused was Rs. 1,400/M3. In that case

the rate allowed was Rs.725/M3. He also testified that for the said item an

amount of Rs.1,400/M3 was granted in S.A. No.3 by the 1 st accused. So in

this place clause 32 of the LCB conditions would not apply since it was

not an `extra item' but an item already covered in the original agreement.

In the said circumstances as per clause 31 of LCB specifications revised

rates should not exceed the rate quoted even when the quantities of work

actually done exceeded by more 30% of the agreed quantity. So with

respect to item No.2 in Ext.P3(b-1) the said item could not be treated as an

`extra item' and the amount of Rs.1400/M3 was awarded by the 1 st

accused to the 2nd accused in violation of clause 31 and 32 of LCB

conditions.

2026:KER:9212

36. Item No.3 in the S.A. No.3. Ext.P3(b-1) was the

construction of flume canal from Ch. 1700M to 1715M with a bed width

of 2.70M. PW2 stated that as per the original proposal the width of the

flume canal was 2.4m and the length was 15m, but the width was

increased to 2.7M. The first item under Item III was C.C.1:4:8 using 40

mm broken stone for foundation. The said item was same as Item No.5 in

Appendix L-1 of Ext.P3(a-1) original agreement. The item No.2 of RCC

1:2:4 using 20 mm broken stone for flume canal including all form work

watering & curing etc. The said item was item No.7 in Ext.P3(a-1), the

schedule of original agreement. The third item was reinforcement of RCC

work, bent, tied and placed in position as per specification and it was item

No.8 in Ext.P3(a-1). It is discernible that for item No.1 the amount

awarded in the original agreement was Rs.500/M3; for item No.2 the

amount awarded in the original agreement was Rs.1,150/-; for item No.3

the amount awarded in the original agreement was Rs.11,000/-. PW2

further stated that Ext.P4(g) was the proposal sent by the E.E to the S.E.

with respect to the aforesaid three items. In Ext. P4(g), it was stated by the

EE that as per the original agreement the Contractor was supposed to 2026:KER:9212 Crl.Appeal No.106 & 9 of 2011 39

construct barrel of inside width 2.4.M between Ch.1700M to 1705M. But

the off take of Oachira Minor Distributory was fixed at Ch.1720M. The

contractor had to alter all the shuttering arrangement which was originally

suited for casting barrel of 2.4m width resulting in considerable additional

expenditure to the Contractor. There was a change in the dimension of the

flume canal and it may be treated as extra and relying on 1990 schedule of

rates, he has refixed the rate in Ext.P4(h) that is Rs.531.48/M3 for the first

item, Rs.1,186/M3 for the second item and Rs.7567.40/T for the third

item. As already stated the said rates were fixed by adopting the 1990

schedule of rates. The 1st accused had negotiated with the 2nd accused for

fixing the rates for these items also. Ext.P4(1) were the rates claimed by

the 2nd accused. Ext.P4(m) was the negotiation statement prepared by

PW2. PW2 deposed that the negotiated rates in Ext.P4(m) were arrived by

the 1st accused. According to him, for the first item the amount arrived by

the 1st accused was Rs.850/M3, instead of Rs.531.48/M3 suggested by

E.E. as per 1990 schedule of rates. The rate fixed for item No.2 by the 1 st

accused on negotiation is Rs. 1,700/M3, instead of Rs.1,186/M3 suggested

by the E.E. The rate fixed by the 1 st accused on negotiation as seen from 2026:KER:9212

Ext.P4(m) for third item was Rs.11.000/Tonne against the amount of

Rs.7,567.40/T suggested by the E.E. It was only an extra quantity of work

done by the accused. So he can claim the amount only within the purview

of clause 31 of the LCB conditions. Thus PW2 categorically given

evidence that clause 31 and 32 of LCB conditions were violated to execute

SA and to grant exorbitant amount. PW2 further asserted that there was

violation of the delegation of financial powers of the S.E. provided under

Appendix II(a) of the Public Works Department Manual.

37. The next item was supplying and fixing PVC water

stopper 45cm wide and filling the gaps with 25mm thick machine pressed

bitumen pad of approved quality including all cost and conveyance etc.

complete. The item rate fixed in the original agreement for this item was

100/M. It is true that in the original agreement, the water stopper

mentioned was 45 cm wide. The evidence would show that Ext.P1(g) letter

was sent by the 2nd accused to PW1 stating that water stopper of 45 cm

width was not available in the market and accordingly permission was

sought to use water stopper of 30.5cm size which was the only one

available in the market. Ext.P1(h) letter was sent by PW1 permitting the 2026:KER:9212 Crl.Appeal No.106 & 9 of 2011 41

2nd accused to use 30.5cm width of water stopper and also suggesting for

execution of SA. The E.E. had submitted the data of providing PVC water

stopper of 30.5 cm wide and refilling the gaps with 25mm thick machine

pressed bitumen pad. He had stated that the cost of materials provided by

him in the data were the current market rates. He had requested for

approving the said data and execution of S.A. Ext.P4(a-1) would go to

show that the data so suggested by the E.E. was Rs.205.42/M. Ext. P4(b) is

the letter sent by the S.E. to the 2nd accused calling upon him to offer the

minimum rate for the extra rate for supplying and fixing 30.5cm width of

PVC water stopper. Ext. P5(a) is the notes submitted by the Draftsman to

PW1 with respect to this item. In Ext.P5(a) it was stated that the sanction

to use 30.5cm wide PVC water stopper instead of 45 cm wide PVC water

stopper was issued to the 2 nd accused, the E.E. in his letter dated 12.1.1989

had submitted the data and supplemental schedule for the above extra item

and the data was checked and put up for approval and the rate would come

to Rs.205.42/M and there was request for approval of the said item. As per

Ext.P5(a-1) PW1 had suggested certifying the reasonableness of the costs

of PVC water stopper. It is admitted by PW1 that till he left the said office, 2026:KER:9212 Crl.Appeal No.106 & 9 of 2011 42

no S.A was executed for the said item. Ext.P4(c) is the letter sent by the 2 nd

accused to S.E. claiming rate for the water stopper. In Ext.P4(c) the rate

claimed by the 2nd accused was Rs.435/running Metre for 30.5cm wide

water stopper. In Ext.P4(m) PW2 stated that the rates suggested was

Rs.372.34 since the same was the rate sanctioned for the water stopper in

the same nature of work in another reach at Kulasekharapuram. Ext.P4(m)

is a negotiation statement wherein the amount arrived on negotiation was

Rs.750/M. So it was evident that the amount sanctioned by the 1 st accused

was much higher than the amount of Rs.435/-, that is the amount claimed

by the 2nd accused or the amount of Rs.205.42/-, the amount suggested by

E.E on the amount of Rs.372.34/-, the amount sanctioned for another

reach. It was admitted by PW2 that when the same was executed about

90% of the work was already over. In this regard it is relevant to note that

PW1 testified that water stopper was a PVC pad fixed in the joints on two

sides of the flume to prevent leakage of water. Thus the prosecution

clearly established that the price for water stopper had been fixed even

from the beginning of the work and 90% of the said work was over when

S.A. No.3 was executed for the said item. So the amount was awarded by 2026:KER:9212

the 1st accused to the 2nd accused in violation of clause 31 & 32 of LCB

conditions and also in excess of the financial powers conferred on S.E. by

the Kerala Public Works Department Manual.

38. Item No.5 in S.A. No.5 was providing shoring to the

sides of the canal using half split coconut piles etc. during foundation

excavation and during concreting of the structure so as to protect both

sides from slipping at the portions wherever required and removing the

same after the completion of the structure. PW1 testified that it was the

responsibility of the contractor to provide side protection at the time of

digging the canal. PW1 deposed further that he had visited the site and

slope excavation had not done and even there was no space available there

for slope excavation. Ext.P1(i) was the letter sent by the Contractor - the

2nd accused to PW1. Ext. P1(i) would show that the contractor raised claim

that during the earth work excavation both banks of the canal were

slipping down because of sandy soil and now we were excavating at 1:1

side slope and they were providing shoring at 1.5m height and round clock

bailing out of water with 5 HP pump and he had requested issuance of

necessary orders for the payment for additional earth work for side slope, 2026:KER:9212

shoring and bailing out of water. Ext.P1(j) is the reply sent by PW1 who

was the then S.E. to the 2nd accused. In Ext.P1(j) it is stated by PW1 that

any unauthorized modification in side slope, providing shoring without

approval or extra pumping not duly approved at site by the site officers

would not be paid at all.

39. In terms of clause 54 of the LCB conditions of contract,

the contractor is bound to keep machine numbered well bound spot work

order book at the site of work. All instructions given to the contractor by

inspecting officers should be recorded in the book and initialled by the

officers. No oral orders said to have been issued would be accepted as a

claim for payment. A reading of the said clause taken along with Ext.P1(g)

letter would make it clear that the 2nd accused was not eligible for any

claim under the head shoring as an extra item of work unless the same

work was done as per clause 54 of LCB conditions. As per report of the

E.E, ie. Ext.P5(e-1), it was noted that the length of the shoring done was

measured as Rs.2700/m3 and the contractor demanded rate @ of

Rs.2,000/M3. But the E.E. had not submitted data and details for shoring

done. The 1st accused had suggested that the shoring had to be treated as 2026:KER:9212 Crl.Appeal No.106 & 9 of 2011 45

`extra item' and rate had to be called for from the Contractor. Ext. P4(k) is

the letter sent to the 2nd accused on the basis of the recommendation of the

1st accused. Ext.P4(1) is the reply submitted by the 2 nd accused wherein he

had claimed Rs.3,000/Rm for providing shoring, consolidating of earth

during consolidating of flume canal. Accordingly as per Ext.P4(m)

demand was negotiated and Rs.1,169.50/RM for shoring was granted by

the 1st accused. Accordingly as per S.A. No.3 the said amount was granted

per running metre to the 2nd accused for a total length of 217M. Clause 35

of Specification for Canal Works issued by the Kerala Public Works

Irrigation Department for KIP dealt with Excavation for structures. It has

been provided that "except as otherwise provided all excavation for

structures will be measured for payment to lateral dimensions 15 cm

outside the foundation footing or slab or where foundation footings or

projecting slabs are not used lateral dimensions 30cm outside of exterior

walls or surfaces of the structures and to side slopes 1 to 4 provided that

when the character of the material cut into is such that it can be trimmed

to the required lines of the concrete and the need for intervening forms

eliminated payment will be made only for the excavation within the neat 2026:KER:9212 Crl.Appeal No.106 & 9 of 2011 46

lines of the concrete. Provided further that for any part of the work where

in the opinion of the Engineer-in-charge the conditions will be measured

for payment to the most practicable dimensions and lines staked out or

otherwise established by the Engineer-in-charge. The contractor shall

prepare the excavated surface in a manner, suitable for forming

foundations or concrete structures. The bottom and side slopes of

excavation upon or against which concrete is to be placed shall be

accurately finished by hand to the dimensions shown on the drawings or

prescribed by the Engineer-in-charge and the surface so prepared shall be

moistened with water and tamped with suitable tools for the purpose of

thoroughly compacting them and forming firm foundation upon or against

which to place the concrete. If at any point in excavation, the foundation

materials are excavated beyond the neat lines required to receive the

structure, or specified lines, grades and dimensions the over excavation

shall be filled with the same material as that of the foundation footing at

the cost of contractor. If any point in excavation, the natural foundation

material is disturbed or loosened during the process, it shall be

consolidated to a degree satisfactory to the Engineer- in-charge or 2026:KER:9212 Crl.Appeal No.106 & 9 of 2011 47

otherwise it shall be removed and replaced with selected material

compacted to the satisfaction of the Engineer-in-charge. Any and all

excess excavation or over excavation performed by the contractor for any

purpose or reason except as may be ordered in writing by the Engineer-in-

charge and whether or not due to the fault of the contractor shall be at the

expense of the contractor. No blasting that might injure the work will be

permitted and any damage done to the work by blasting including

shattering of the material beyond the required excavation lines shall be

repaired by and at the expense of the contractor and in a manner

satisfactory to the Engineer-in-charge. The schedule for excavation for

structures shall include unless otherwise specifically provided for the cost

of all labour and materials for ring bund and other temporary

construction and of all pumping, bailing, draining and all other work

necessary to maintain the excavation in good order during construction

and of removing such temporary construction where required". PW1

categorically given evidence that claim for shoring was not at all

sustainable as it was included in the excavation and he had turned down

that request of the Contractor. So the said item could never be treated as an 2026:KER:9212

`extra item' and no amount could be granted for the said item. Thus in

violation clause 31 and 32 of LCB conditions and in violation of the

financial powers confirmed on S.E. under Appendix II(a) he had awarded

amount for this item. Thus with respect to S.A. No.3 except item No. 1, all

other items were executed violating provisions of clause 31 & 32 of the

LCB conditions and total amount of Rs.71,24,015/- was gained unlawfully

by the 2nd accused at the instance of the 1st accused and corresponding loss

was suffered by the Government.

40. Coming to execution of S.A. No.6. S.A. No.6 was

executed on 28.2.1991 which according to the prosecution is the date of

retirement of the 1st accused. This was executed for 1000M 3 of RCC 1:2:4

using 20m metal (nominal size) for flume canal including constructing tie

beams to protect the side walls wherever necessary as directed by the

Engineer-in-charge including all form work staging scaffolding etc. for

curing etc. (1st item) complete but excluding cost and labour for providing

concrete had set or as directed by the Engineer-in-charge watering

reinforcement in view of item No.7 of Appendix-L in the original

agreement. The second item treated as extra item in S.A. No.6 was 2026:KER:9212 Crl.Appeal No.106 & 9 of 2011 49

reinforcement for RCC work, bent, tied and placed in position as per

specification for flume canal, tie beam etc. in lieu of item No.8 of

Appendix-L in original agreement. It is argued by the learned Senior

Counsel for the 2nd accused that the tie beams were neither provided in the

detailed estimate nor in the diagram supplied to the 2 nd accused and the

parties were not at consensus in idem with respect to the construction of tie

beams. In this regard the evidence of PW5 is relevant, since the estimate

for the same was prepared by PW5 who was the then A.E. He deposed that

he had prepared the estimate for the work of RBC formation of

Kulasekharapuram Distributory from Ch.1700M to 2400M including CD

works and sent estimate to the A.E.E. According to him in the estimate

there was earth work excavation and the flume canal RCC 1:2:4 using

20mm metal sides, bed, haunches, tie beams along with reinforcement. He

admitted that for each item for the concrete reinforcement, the estimate

was prepared. The drawing was also prepared by him but he admitted that

he could not recollect whether in the drawing the tie beam was shown. He

admitted that the tie beams take only very small quantity when compared

to the quantity of the total work. It is only a minute portion of the flume 2026:KER:9212 Crl.Appeal No.106 & 9 of 2011 50

canal and so when the cross section was prepared the same was not

included. He further stated that it was he who got the work executed by the

2nd accused at the site. According to him, first of all the work of excavation

was done followed by concreting of the foundation. He added Thereafter

the flume canal was constructed and for that purpose the form work was

done. Thereafter the tore steel, bent, tied and fixed and the form work was

done inclusive of the shutter, haunches etc., then the haunches from the

sides and the bed work were completed. He testified further that the tore

steel were kept for construction of the tie beams and gap was given for

portion with wooden plank. According to him after cast of several barrels

of flume was over, the tie beams were constructed. Ext.P11 is the file kept

at the office of the E.E. In Ext.P11(a) the consolidated reinforcement of

the cement and tore steel is mentioned. In sheet No.55 of Ext.P11(a) the

tore steel required for construction of the tie beam was shown as 51.528M.

In sheet No.53, which is Ext.P11(a-1), the quantity of the main rod,

stirrups etc. required for the tie beam was shown. The same was signed by

the A.E.E. He added that as per 1986 schedule of rates the estimate was

prepared. PW1 the S.E deposed that in Ext.P1(c), 46 tie beams were 2026:KER:9212 Crl.Appeal No.106 & 9 of 2011 51

included at an interval of 15m, the length of the tie beams mentioned as

2.8m, width of 0.15M and depth of 0.15m. So the total quantity of tie

beams required were 2.9M3. He also admitted that as per the specifications

he could not understand whether the tie beam was included in the schedule

appended to Ext.P3(a) the original agreement. He further admitted that in

the drawings appended to the agreement as well as in the cross section tie

beam was not specifically mentioned. According to him since the tie

beams were constructed only at 15m intervals the same were not included

in the digging section. He further deposed that the total quantity of 1000M3

and 100T tore steel would include the tie beams also and if it was not

included in the drawings, the contractor was bound to construct the tie

beams. According to PW1 pre-bid conference was convened only for the

purpose of giving an opportunity to the prospective tenderers to understand

fully about nature of work to be executed by them. Page 53 of Ext.P3(a) is

the minutes of the pre bid conference held at KIP RBC Office in

Kottarakkara at 11 am on 2.3.1988. PW1 further stated that the 2 nd accused

did not attend the said conference or in other words failed to avail the said

opportunity. In page 122 of Ext.P4(n) there was a letter sent by the 2 nd 2026:KER:9212

accused to the C.E and forwarded to the S.E. The same was seen signed by

Al the S.E. on 22.2.1991. This was sent to the E.E for his remarks and he

was directed to offer his report with rate and quantity for these items. In

Ext.P4(n), the 2nd accused had claimed that the construction of tie beams

was not mentioned in the original agreement and there was change of

design due to the construction as an `extra item' and the same had to be

treated as an `extra item' and payment had to be effected. Ext.P5(f) is the

note put up in relation to Ext. P4(n). In Ext.P5(f), it was noted that no

reply was received from the E.E. The same was dated 23.2.1991. In

Ext.P5(g) the 1st accused had put up the note to treat RCC 1:2:4 and

reinforcement as purely extra item and contractor should be called upon to

approach him for negotiation. The said letter was seen served to the

Contractor on 23.2.1991 as could be discernible from Ext.P4(o). In

Ext.P4(o), the 2nd accused had claimed Rs.3/dm3 for RCC 1:2:4 barrel and

Rs.18/kg including cost of steel for reinforcement. Ext.P4(p) is the

negotiation statement for the said item. The negotiation was done on

27.2.1991.

41. PW2 deposed that even on the date of negotiation the 2026:KER:9212 Crl.Appeal No.106 & 9 of 2011 53

report of the E.E on Ext.P4(m) was not obtained. In the negotiation

statement Ext.P4(p) the column of rate allowed on negotiation and remarks

were filled up by the 1st accused. He had noted that negotiated with the

Contractor and obtained his concurrence. According to him, for RCC 1:2:4

instead of the agreed rate of Rs.1,150/-, the amount arrived was

Rs.1,590/M3. Like wise for reinforcement instead of the agreed rate of

Rs.7,500/T, the rate allowed was Rs.11,750/Tonne. In the original

agreement for RCC 1:2:4 the amount allowed was Rs.1,150/- and the cost

of the cement supplied by the Government was Rs.396/-. So the labour and

material portion would come to Rs.754/-. So as per the original agreement

the contractor would get Rs.754/- as labour and material portion. But

during negotiation the amount was fixed at Rs.1,590/-, the cost of

departmental material remaining the same as Rs.396/- and the labour and

material portion which the contractor get would come to Rs. 1.194/M3.

Like wise regarding the reinforcement for RCC work as per the original

agreement, the agreed rate was Rs.7,500/T and the recovery rate of tore

steel per Ton as per the original agreement was Rs.650/-. So the labour

portion of the contractor as per the original agreement would come to 2026:KER:9212

Rs.1,000/T. In Ext.P4(p) negotiation statement or in other words in

Ext.P3(c-1) S.A. No.6 this amount was raised to Rs. 11,750/-. Then also

the recovery rate of the tore steel remained the same as in the original

agreement that is Rs.6,500/T. Then the contractors labour portion will

come Rs.5,250/-.

42. No doubt, as per clause 10 of the LCB conditions of

contract the contractor had to do the work in accordance with the drawings

and specifications. Clause 10 mentioned the purpose of drawing and

specifications and conformance. It could be seen that the contract drawings

read together with the contract specifications were intended to show and

explain the manner of executing the work and to indicate the type and

class of materials to be used. In this case the evidence would show that tie

beams were not included in the drawings and specifications. So the

construction of tie beams could be treated as `extra item' apart from the

construction of flume canal. The total quantity of tie beams to be

constructed was 2.9m. It was the definite case of the prosecution that

though it was omitted to be mentioned in the drawings, the total quantity

of 1000M3 and 100T of tore steel provided in the estimate and drawings 2026:KER:9212 Crl.Appeal No.106 & 9 of 2011 55

would take in the tie beams also. This contention is found to be sustainable

since in the original agreement as well as in the S.A.No.6 the total quantity

of RCC 1:2:4 using 20mm metal and the reinforcement for RCC work,

bent, tied and placed in position was one and the same that is 1000M 3 and

100T respectively. Apart from all these facts even if the tie beams were

taken as not in the contemplation of the contracting parties then the tie

beams alone could be treated as an `extra item' of work for which excess

amount could be granted, the quantity of which was 2.9 M3. But the 1 st

accused awarded huge amount for the entire quantity of 1000M 3 of RCC

1:2:4 and entire quantity of 100T reinforcement of RCC work. Apart from

that PW3 the A.B.E deposed that for RCC work, the rate for reinforcement

was fixed on the basis of the weight. According to him, whatever be the

nature of the work that was done, the rate would be fixed on the basis of

the weight and the same was provided in the PWD Data Standard Book.

He added that even if there was change in the structure or design, then also

the amount would be awarded on the basis of the weight of tore steel for

reinforcement work. The said amounts were awarded in violation of clause

31 and 32 of LCB conditions and also in violation of the financial powers 2026:KER:9212

of the 1st accused. This aspect to be borne out from page 17 serial Nos. 130

and 130(a) of PWD Standard Data Book wherein it has been provided that

for reinforcement of RCC work, bent, tied and placed in position the rate

would be on the basis of weight and not otherwise.

43. The crucial question poses is whether the 1 st accused

granted excess amount legally for the work in dispute and the contention

of the 1st and 2nd accused claiming that the work for which excess amounts

were granted would come within the purview of extra-work, i.e, `extra

item'? In this connection the evidence adduced would show that those

woks are not `extra items'. If the contention of the accused that those

works to be considered as `extra-items', then next is the mode for claiming

`extra item' to be found in Ext.P3(a), the original agreement, and LCB

specifications should have been followed scrupulously without fail.

44. Clauses 31 and 32 of LCB specifications in Ext.P3(a)

agreement deals with `schedule of quantities' and `extra items'. Clause 31

reads as under:

"31. Schedule of Quantities : Variation in the quantities of work in the bill of quantities shall not vitiate the contract. The rates quoted for the individual items shall apply for the quantities of work increased or 2026:KER:9212

decreased by not more than thirty percent for each of the items. Should quantities of work actually involved under any item exceed quantities provided in the tender by more than thirty percent the rate of such excess over thirty percent of quantity provided in the tender may be revised in accordance with the procedure indicated under clause "extra items".

However, the said revised item rate shall not exceed the item rate quoted, subject to adjustment in accordance with price adjustment clauses. Should the quantity of work actually involved under any items be reduced by more than thirty percent of quantity provided in the tender, the bid unit price of the affected item may be revised in accordance with the procedure indicated under "extra items". However, the total cost of such item should not exceed the cost of seventy percent of the item quoted, subject to adjustment in accordance with price adjustment clauses. The payment of the item will continue to be made at the original rate until the revised rate is decided."

Clause 32 reads as under:

"32. Extra Items : Extra items of work shall not vitiate the contract. The contractor shall be bound to execute extra items of work as directed by the Superintending Engineer. The rates for extra item to be mutually agreed."

45. The prime contention raised by the learned counsel for

the accused is that clause 32 empowers the S.E to address extra items of

works and the rates for extra item to be mutually agreed by negotiation

and, therefore, the amount in excess obtained by the 2 nd accused, which is 2026:KER:9212

the amount alleged to be misappropriated by accused Nos.1 and 2, in fact,

was granted by the 1st accused by exercising his power under clause 32.

In this connection, clauses 31 and 32 of LCB specifications to be read

together. Clause 31 provides that `extra items' of works shall not vitiate

the contract and the contractor shall be bound to execute the extra items of

work as directed by the S.E and the rates for extra item to be mutually

agreed. In this connection, it is relevant to note that the 1 st accused

worked as S.E, KIP RB Circle, Kottarakkara from 06.07.1990 to

28.02.1991. That is to say, he had retired after 6 months' of service as on

28.02.1991. The prosecution case is that on 23.02.1991, i.e 5 days before

retirement of the 1st accused, the 2nd accused pressed for claims under the

extra items for the works which were conducted by Ext.P3(a) and it was

acted upon by the 1st accused within 5 days even though almost all the

works for which claims for extra rate raised by the 2 nd accused would

require thorough verification to ensure whether the works were actually

done or not or the same would fall in the category of `extra items'. Thus

even a cursory look at the evidence available would show that the claim

for extra work was considered by the 1 st accused on 23.02.1991 in a hurry-

2026:KER:9212

burry manner and prior to that, there was negotiation on 21.01.1991 for 4

items of work and according to accused Nos.1 and 2, those were `extra

items', though the evidence discussed in detail would show the same as

items covered by Ext.P3(a) original agreement.

46. In this connection, it is relevant to note clause 31 and

32; clause 32 could not be read in isolation and clause 32 is to be read

along with clause 31, as already observed. The learned counsel for the

accused given much emphasis to clause 32 even without referring clause

31. Clause 31 provides that variation in the quantities of work in the bill

of quantities shall not vitiate the contract. Should the quantities of work

actually involved under any item exceed the quantities provided in the

tender by more than 30%, the rate for such excess work beyond 30% of

the quantity provided in the tender may be revised in accordance with the

procedure indicated under clause 32 `extra items'. However, the said

revised item shall not exceed the rate of the item quoted, subject to

adjustment in accordance with the price adjustment clauses. In Ext.P3(a),

the price adjustment clause provided as 32/A was struck off and therefore

the same would not apply in the present contract, as already found. Thus 2026:KER:9212

the revised rate shall not exceed the item rate quoted though a maximum

of 30% of such excess quantity, could be negotiated in terms of clause 32.

So, when reading clause 31 and 32 together, the application of clause 32

is subject to clause 31.

47. Here the prosecution alleges that, as part of conspiracy

hatched between accused Nos.1 and 2, they had misutilised clauses 31

and 32, which do form part of Ext.P3(a) original agreement and

negotiated 5 items of work, viz. (1) Construction of a road crossing at

Ch.1950 M, (2) C.C.1:3:6 for making up foundation, (3) Constructing

flume canal from Ch. 1700 M to 1715 M with bed width of 2.7 meter, (4)

Supplying PVC water stopper 305 MM wide and (5) Providing shoring

etc.

48. Regarding the application of clauses 31 and 32 of LCB

specifications, the learned Special Judge, meticulously addressed the

same in para.10 of the judgment and the said finding is found to be

justifiable. Relevant observation in paragraph 13 is extracted as under:

"PW2 further admitted that what was contemplated in the original agreement is foot bridge whereas the newly constructed bridge whereas the newly proposed one is a motorable bridge. The construction of the said road crossing at Ch. 1950M was brought to the notice of the C.E. through Ext.P4(e) letter. It is stated 2026:KER:9212

in Ext.P4(e) that an estimate amounting Rs.2,36,800/- has been prepared and submitted by the S.E. for road crossing at Ch.1950M as per the request of Sri.T.M.Nanu Master MLA and hence the E.E. was directed to see that the work should be done through the same agency. Ext.P4(e) was approved and initialled by A1 as identified by PW2. Ext.P4(f) is data submitted by A3 to the S.E. It is based on the 1990 schedule of rates. The said data was scrutinized by PW2 and the corrected data was approved by the S.E. So it has come out in evidence that this is clearly an extract work which was not contemplated at the time of execution of original agreement. Hence there is no violation of any clauses of LCB conditions in execution of S.A. No.3 for construction of road crossing at Ch. 1950M. The total amount covered by this item No.1 in Ext.P3(b-1) is Rs.3,36,743/- The second item in Ext.P3(b-1) that is S.A. No.3 is cement concrete 1:3:6 using graded metal 60% 40mm and 40% 20mm to alignment grade and dimension for making up in slushy including all forming, watering, curing etc. The total quantity for the same is 98M3 and the rate arrived at in negotiation was 1400/M3. It is admitted by PW1 that nowhere in Ext.P1 file it is stated that trial pit was taken. He further admitted that in Ext.P2(a) it is noted that the canal reach portion is sandy soil and paddy field. He again stated that in LS drawing it is noted in 2000M and 2100M there was a pond. He further admitted that from Ch.2310 M to 2400M there was paddy field. For making up the said portion this item of work was done. The same item of work was included as item No.5 in Appendix-G to the original agreement. The said item is also cement concrete 1:3:6 using graded metal 60% 40mm and 40% 20mm Ext. P4(i) is sheet Nos. 113 to 115 of Ext.P4 file. By adopting 1990 schedule of rates for this item the AEE has recommended Rs.817.61/M3 which was finalized by E.E. as Rs.681/M3. Ignoring all these matters at the time of negotiation as seen from Ext.P4(m) negotiation statement the amount arrived by Al on negotiation with A2 was Rs. 1,400/M3. In that case the rate allowed was Rs.725/M3. For the said item an amount of Rs. 1,400/M3 was seen granted in S.A. No.3 by Al. So in this place clause 32 of the LCB conditions will not apply since it is not a pure extra item but an item already covered in the original agreement. In the said circumstances as per clause 31 of LCB specifications revised rates shall not exceed the rate quoted even when the quantities of work actually done exceeded by more 30% of the agreed quantity. So 2026:KER:9212

with respect to item No.2 in Ext.P3(b-1 the said item could not be treated as an extra item and the amount of Rs. 1400/M3 was awarded by A1 to A2 in violation of clause 31 and 32 of LCB conditions."

49. According to the learned Senior Counsel for the

accused, all the items are covered under extra items of clause 32 of LCB

and, therefore, the S.E exercised his power under Section 32, negotiated

the case and granted the same. It is interesting to note that the entire

claim, in fact, was put up and finalised on the last week of February, 1991

and thereafter on 28.02.1991 the 1st accused retired from service and as

pointed out by the learned Special Public Prosecutor, in a hurry-burry

manner, for a work for which the original expenditure fixed as

Rs.23,15,000/-. That is to say, apart from Rs.23,15,000/- originally

agreed and granted, an additional sum of Rs.34,78,458/- had been

sanctioned by the 1st accused and obtained by the 2nd accused and both of

them derived due pecuniary advantage over the same.

50. On re-appreciation of the evidence discussed, it would

appear that as far as item Nos.2 to 4 covered by SA3 and 2 items covered

by SA6, the said works were originally included in Ext.P3(a) original

agreement, for the said work, no claim under the head `extra item' could

be granted. That apart, item No.2 in SA3, as deposed by PW1, the same 2026:KER:9212

also was included as item No.5 in appendix G and also the same was made

part of Ext.P1(a) estimate. As pointed out by the learned Special Public

Prosecutor, the 1st accused fixed much higher rates in excess of the agreed

rate as extracted hereunder above for the works and the 1st accused was

not empowered to do so by clause 32 of LCB specification, which do form

part of Ext.P3(a). Most importantly clause 32 of LCB has no application

for these works already agreed upon in Ext.P3(a) original agreement. Thus

it is proved that the 1st and 2nd accused entered into criminal conspiracy

and by violating clause 31 and 32 of LCB conditions executed S.A. No.6

also thus by awarding an excess amount of Rs.27,65,000/-. It was proved

by the prosecution that S.A Nos.3 and 6 were executed as a result of the

conspiracy entered between the 1st and 2nd accused in violation of clause

31 and 32 of LCB conditions resulting in pecuniary advantage of

Rs.34,78,415/- to the 2nd accused and corresponding loss to the

Government.

51. Thus the conclusion to be reached by the Court is that

regarding the above items, as part of a conspiracy hatched between the 1 st

and 2nd accused, before the retirement of the 1 st accused, some claims were 2026:KER:9212

raised by the 2nd accused and in a hurry-burry manner the 1st accused

granted the same on the date of his retirement. It is judicially noticeable

that the 1st accused also granted amounts to various contractors on the last

date of his retirement in a similar fashion and caused huge loss to the State

exchequer.

52. The contention raised by the learned Senior Counsel for

the 2nd accused that the shiny and slushy nature of the soil and thereby

extra work was exercised also could not be countenanced since Ext.P3(a)

agreement was executed after understanding the nature of the sand in the

same fashion and even the 2nd accused failed to attend the pre-bid meeting.

It is true that though the tie beams originally agreed were 46, 72 tie beams

were constructed and for which the 2nd accused is entitled for the amount,

as per the agreed rate. In the instant case, even though the 2nd accused is

entitled to get 26 items of tie beams extra constructed, the construction

should be quantified at the rate agreed and not in excess of that. Despite

this, huge amounts were granted by the 1 st accused by misusing clause 32

of the LCB specifications. Even though the learned Senior Counsel for the

2nd accused relied on two decisions of this Court in Varghese Mathew & 2026:KER:9212

Ors. v. State of Kerala 's case (supra) and K.G.Ashokan v. State of Kerala

(supra), the facts dealt in those cases and the facts of this case are totally

different. Further, in the above cases interpretation of clause 31 and 32 of

LCB not at all properly addressed. Therefore, the said ratio cannot be

applied to the facts of this case. In addition to that another learned Single

Judge of this Court in Crl.Appeal No.1112/2002 as per judgment dated

04.03.2011 considered the decision in N.E.Abraham v. State of Kerala and

Varghese Mathew & Ors. v. State of Kerala 's case (supra) and thereafter

interpreted clause of 31 and 32 of LCB form part of Ext.P3(a) the original

agreement and observed in para.26 as under:

""26. Going by the above decision it is seen that in that case the conviction was reversed on a conclusion that the payment made thereon cannot be found illegal merely because of the violation of the orders or circulars. The facts of that case revealed in evidence was not at all discussed in the reported judgment. It is also seen that the learned Single Judge had given reliance to the decisions of the Apex Court in Major S.K.Kale v. State of Maharashtra [AIR 1977 SC 822], C.Chenga Reddy and others v. State of A.P. [1996 (10) SCC 193] and Abdulla Mohammed Pagarkar v. State (1980(3) SCC 110]. Going by the above decisions, it is seen that those decisions are with reference to a particular set of facts which has absolutely no bearing with the case on hand. Here, it is not the question of any violation of the circulars or procedures or government orders. But the issue is relating to the clandestine manner in which the appellant had lodged a claim one year and four months after the complete execution of the work and the manner in which the supplemental agreement was executed on the eve of the retirement of the 2026:KER:9212

Superintending Engineer and the passing of the bills by the 2nd accused on the eve of his retirement. The evidence on record in this case would convincingly establish that there was abuse of office by the Superintending Engineer and the Executive Engineer in executing Ext.P2(b) agreement and in passing the bills for payment a high and exorbitant rate, namely 240 times of the originally agreed rate. As concluded by the Special Judge, the appellant is not entitled to any extra rate other than the rate in Ext.P2(a). It is knowing that aspect, the appellant also agreed in Ext.P2(c) dated 20.3.1990 that he is not entitled to claim any extra rate. The Superintending Engineer and the 2nd accused were also aware of it. But to agree for a higher rate, Superintending Engineer and the appellant conspired together and Ext.P2(b) agreement was executed on 30.4.1991. The 2nd accused also knowing the fact that the appellant was not entitled to extra claim additional bills were prepared and passed overruling the objection by the Subordinate officers. Conspiracy between the appellant and 2nd accused is also evident. Bills were passed very hastily and last payment was on the date of retirement of the 2nd accused."

In N.E.Abraham v. State of Kerala 's case (supra) the learned Single

Judge of this Court correctly stated the law regarding grant of extra items

in consensus with the view taken in this judgment, as I already found.

53. Thus the prosecution succeeded in proving that the 1 st

and 2nd accused hatched criminal conspiracy with the common object of

deriving undue pecuniary advantage and by adopting corrupt or illegal

means and in pursuance of the said conspiracy and by misutilising clauses

31 and 32 of LCB executed S.A Nos.3 and 6 resulting in pecuniary

advantage of Rs.34,78,415/- to the 2nd accused and corresponding loss to 2026:KER:9212

the Government.

54. It is surprising to note that the learned Senior Counsel for

the appellant raised challenge regarding sanction under Section 19 of the

PC Act, 1988 in the instant case. The learned Senior Counsel while

raising this contention, failed to take note of the fact that, admittedly the 1 st

accused, for whom sanction under Section 19 of the PC Act, 1988 is

required for taking cognizance of the PC Act offences, retired on

28.02.1991 and the investigation and cognizance for the PC Act offences

against the 1st accused was taken after his retirement and Section 19(1) of

the PC Act, 1988 doesn't provide for sanction in the case of an employee

who retired from service at the time of cognizance. Therefore, this

contention is found to be untenable.

55. To sum up, it is found that the Special Court rightly

appreciated the evidence and came to the conclusion that the appellant

Nos.1 and 2 committed offences punishable under Section 13(2) r/w 13(1)

(d) of the PC Act, 1988 (`PC Act, and Section 120B of the IPC. Thus the

conviction imposed by the learned Special Judge is liable to be confirmed.

56. Coming to the sentence, taking into consideration of the 2026:KER:9212

gravity of the offences, the sentence imposed against the 2 nd accused is

confirmed. As far as the sentence imposed on the 1 st accused is concerned,

since he is no more, the execution of the substantive sentence stood abated.

Therefore the execution of the sentence in relation to the 1 st accused shall

be confined to realisation of fine from the accounts, if any, inherited by the

legal heirs of the 1st accused, including the additional appellants in

Crl.Appeal No.106/2011.

57. In the result, Crl.Appeal No. 106 of 2011 is dismissed,

while partly allowing Crl.Appeal No.9 of 2011 by modifying the same as

stated in para.56 above. As a sequel thereof, the order suspending

sentence and granting bail to the 2nd accused stands cancelled and the bail

bond also stands cancelled. The 2nd accused is directed to appear before the

Special Court to undergo the sentence forthwith, failing which the Special

Court is directed to execute the sentence without fail. As regards to

realisation of the fine from the legal heirs of the 1 st accused, the learned

Special Judge is specifically directed to proceed with the same without

fail.

Registry is directed to forward a copy of this judgment to the 2026:KER:9212 Crl.Appeal No.106 & 9 of 2011 69

Enquiry Commissioner and Special Judge, Thiruvananthapuram, for

compliance and further steps.

Sd/-

A. BADHARUDEEN, JUDGE

rtr/ 2026:KER:9212

CRL.A.NO.106 OF 2011

APPELLANT'S EXHIBITS

NIL.

2026:KER:9212

CRL.A.NO.9 OF 2011

APPELLANT'S EXHIBITS

ANNEXURE-A: A TRUE COPY OF THE JUDGMENT IN CC.28/2002.

ANNEXURE-B: A TRUE COPY OF THE CHARGES IN C.C.NO.15 OF 2002.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter