Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

A.C. David vs Geetha V.A
2025 Latest Caselaw 8756 Ker

Citation : 2025 Latest Caselaw 8756 Ker
Judgement Date : 15 September, 2025

Kerala High Court

A.C. David vs Geetha V.A on 15 September, 2025

                                                      2025:KER:68625

W.P.(C). No.41916 of 2022          :1:



                IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                    PRESENT
                 THE HONOURABLE MR.JUSTICE VIJU ABRAHAM
   MONDAY, THE 15TH DAY OF SEPTEMBER 2025 / 24TH BHADRA, 1947
                            WP(C) NO. 41916 OF 2022
PETITIONER:
              A.C. DAVID,
              AGED 53 YEARS
              S/O. LATE A.V.CHACKO,ARIMBOOR HOUSE, ATS ROAD
              CHALISSERI, PALAKKAD DIST 679536

              BY ADV A.C. DAVID,(PARTY-IN-PERSON)
RESPONDENTS:

      1       GEETHA V.A,
              SECRETARY, CHALISSERI GRAMA PANCHAYAT,
              CHALISSERI, P.O., PALAKKAD DISTRICT - 679536

      2       SURAMYA,
              OVERSEER, ENGINEERING SECTION, CHALISSERI GRAMA
              PANCHAYAT, CHALISSERI, P.O.,
              PALAKKAD DISTRICT - 679536

      3       A.I.PAUL ,
              S/O.A.V.ITTOOP, ARIMBOOR HOUSE, CHALISSERI ANGADI,
              CHALISSERI, P.O., PALAKKAD DISTRICT - 679536


              BY ADVS.SRI.SANTHEEP ANKARATH
              SMT.ATHIRA A.MENON
              SHRI.P.ANIRUDHAN
       THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON
15.09.2025, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
                                                      2025:KER:68625

W.P.(C). No.41916 of 2022       :2:



                            VIJU ABRAHAM, J.
         --     -- -- -- -- -- -- -- -- -- -- -- --
                        W.P.(C) No.41916 of 2022
         --     -- -- -- -- -- -- -- -- -- -- -- --
                Dated this the 15th day of September, 2025

                              JUDGMENT

The petitioner has approached this Court aggrieved by Ext.P1

order in Appeal No.601/2021 passed by the Tribunal for Local Self

Government Institutions, Thiruvananthapuram.

2. The above appeal was filed against an order No.A1/3509/21

dated 17.11.2021 issued by the Secretary of the Chalisseri Grama

Panchayat, a copy of which is produced as Ext.R1(b) along with the

counter affidavit filed by the 1 st respondent. The contention of the

petitioner is that he is a co-owner of a property in Chalisseri, at

Palakkad District and residing there since 2009. The premises has

two houses, one designated for the petitioner's elder brother and

the other for the petitioner, which has no well. The position of well

earmarked for the petitioner's house is adjacent and two meters

away from the property of the 3 rd respondent. Though the

petitioner informed the 3rd respondent that he is making an 2025:KER:68625

application for construction of a well, the 3 rd respondent made an

application after a month of petitioner's application, to construct a

sewage pit adjacent to his boundary nearby the assigned position of

well for the petitioners house. Though application was submitted

by the petitioner, no action has been taken on the same. Petitioner

submits that he is entitled for a deemed permit as on 21.10.2021.

On a complaint made by the petitioner, an inspection was

conducted and the 2nd respondent informed the petitioner that the

deemed permit will be cancelled since the sewage collection pit has

been partially dug in property of the 3 rd respondent, around three

meters away from the edge of the proposed location of the

petitioner's well. Thereupon the petitioner made an enquiry and

found that on 12.10.2021 permit was granted to the 3rd respondent.

While so, the petitioner received Ext.R1(b) order dated 17.11.2021

intimating that the application submitted by the petitioner for

construction of a well is not in accordance with the provisions of

the Kerala Panchayat Building Rules, 2019( hereinafter referred to

as 'the Rules, 2019'). Further it is stated that since there is no

compliance of Rules 14(1) and 14(2) before submitting an 2025:KER:68625

application under Rule 14(3), the petitioner is not entitled for the

deemed permit. Aggrieved by the same the petitioner filed an

appeal before the Tribunal for Local Self Government Institutions

and the Tribunal by Ext.P1, dismissed the appeal preferred by the

petitioner. The Tribunal also found that the petitioner is not

entitled for the deemed permit, inasmuch as there is total non-

compliance of the provisions of Rule 14(1) of the Rules, 2019. The

Tribunal after verifying the files produced by the 1 st respondent,

entered a finding that the application for construction of a well was

submitted by the petitioner on 16.08.2021 and later an application

was submitted on 21.10.2021 stating that he filed the application

under Rule 14(3) of the Rules, 2019 after 60 days of submitting

online application, for commencement of work on 21.10.2021. The

Tribunal found that the non-compliance of Rule 14(1) makes the

receipt obtained by the petitioner under Section 14(3) invalid and

the petitioner could not produce any documents to substantiate

that he has complied with Rule 14(1) of the Rules, 2019. The

Tribunal also found that since the petitioner does not have any

deemed permit and the work was undertaken by the 3 rd respondent 2025:KER:68625

after obtaining building permit on 12.10.2021, the petitioner could

not contend that the building permit obtained by the 3 rd

respondent on 12.10.2021 is illegal. Since the soak pit has already

been constructed with a valid permit, construction of the well

within 7.5 meters radius from the soak pit cannot be permitted. It

is also found by the Tribunal that the building permit issued in

favour of the 3rd respondent as early as on 12.10.2021 has not

been challenged by the petitioner.

3. A detailed counter affidavit has been filed by the 3 rd

respondent wherein it is stated that the 3 rd respondent has

constructed a small residential building having area of 57.10 M 2, in

category II, for which no permit is required from the village

panchayath. After the construction of the basement, a sewage pit

was also constructed in the 1st week of March 2021. Ext.R3(1)

application for building permit was submitted by the 3 rd respondent

on 18.08.2021 and the Panchayat has issued Ext.R3(2) building

permit in favour of the 3 rd respondent. Pursuant to Ext.R3(2), the

construction was completed and the building was numbered. There

is absolutely no violation as alleged by the petitioner. The 2025:KER:68625

petitioner has submitted an application by suppressing the facts

that, there is another well, as well as a tube well in the petitioner's

property and the petitioner is using water from the above said well

and tube well. It is also submitted that the proposed well was not in

existence or under construction at the time of construction of the

soak pit, which was constructed based on valid permit issued by

the respondent Panchayat in favour of the 3rd respondent and

permitted the construction of the septic tank/soak pit after having

verified and satisfied that there is no well in the property of the

petitioner within a radius of 7.5 meters from the soak pit.

4. A detailed counter affidavit has also been filed by the 1 st

respondent, wherein it is stated that the petitioner made an

application for building permit online on 12.08.2021 and the

physical application was submitted by the petitioner on 16.08.2021.

The 3rd respondent submitted his application for building permit

on 18.08.2021 online and physical application was submitted by the

3rd respondent on 24.08.2021. The petitioner was contacted several

times for site inspection by the concerned authorities but the dates

always got postponed on the inconvenience cited by the petitioner.

2025:KER:68625

The application submitted by the petitioner was also defective but

the same could not be properly communicated with the petitioner

on account of non-cooperation on the part of the petitioner in

assisting the Panchayat with site inspection and other formalities.

The 3rd respondent on the other hand cooperated with the site

inspection and other formalities without any delay and thereupon

the 3rd respondent was granted with building permit on 12.10.2021.

The petitioner has also not challenged the building permit granted

to the 3rd respondent. The petitioner thereafter presented a letter

styled as an application filed under Rule 14(3) of the Kerala

Panchayath Building Rules, 2019 on 21.10.2021, produced as

Ext.R1(a). The contents in the application states that as 60 days

have passed, the petitioner is submitting an application under Rule

14(3) for commencement of the work with respect to his well. Later

site inspection with respect to the petitioner's property was

conducted on 29.10.2021. On the site inspection it was noticed that

there were two buildings in the petitioner's property and that only

the number of one building was disclosed in the application

submitted by the petitioner and also that as per the possession 2025:KER:68625

certificate, the name of the co-owner of the property was not

revealed and the co-owner has not joined the application for permit

and hence the application itself was found to be not maintainable.

In the site inspection it was also noticed that there is a septic tank

under construction under a valid permit and as such a permission

for a well cannot be granted within the prohibited distance. Later,

by order dated 17.11.2021 the Panchayat cancelled the deemed

building permit, presumed to be obtained by the petitioner for non-

compliance of the mandates under Rule 14(1) and 14(2) of the

Rules, 2019 on the ground that there is a septic tank under

construction within the prohibited distance of the well earmarked

for the petitioner. It is also submitted that the Assistant Engineer

has submitted Ext.R1(c) report with respect to the building permit

already granted to the 3rd respondent that there is no suitable area

where the soak pit in the 3rd respondent's property can be shifted

apart from the area where the permit is already granted. It is also

to be noted that the construction carried out by the 3 rd respondent

is only for a build up area of 57.10 M 2 in category II, for which even

a building permit is not required. The 3 rd respondent has already 2025:KER:68625

completed the construction of the house in the month of March and

the soak pit was also half way done before the grant of the building

permit.

5. I have heard the rival contentions on both sides.

6. The essential contention raised by the petitioner is that he

has submitted an application for construction of a well and the

same was not considered or any decision was taken on the same

and therefore, he is entitled for a deemed permit. As rightly found

by the Tribunal and by the respondent Panchayat in Ext.R1(b)

order, for getting a deemed permit as provided under Rule 14(3) of

the Rules, 2019, the petitioner has to comply with the provisions of

Rules 14(1) and 14(2) of the Rules, 2019. Rule 14(1) mandates that

the Village Panchayat shall, if the Secretary, neither approves nor

disapproves a building site, neither gives nor refuses permission to

execute any work within fifteen days from the date of receipt of the

application, on the written request of the applicant, be bound to

determine whether such approval or permission should be given or

not. Rule 14(2) mandates that where the Village Panchayat does

not, within thirty days from the date of receipt of such written 2025:KER:68625

request, determine whether such approval or permission should be

given or not, such approval or permission shall be deemed to have

been given, and the applicant may proceed to execute work, but

not so as to contravene any provision of the Act or these rules or

bye-laws made there under. It is only on complying with Rules

14(1) and 14(2) that the applicant could submit letter as provided

under Rule 14(3) of the Rules, 2019 stating that he is commencing

the work of the building, structure etc., and that he is entitled for a

deemed permit. Admittedly the petitioner could not produce any

document to show that he has made any written request as

provided under Rule 14(1) before the village panchayat in this

regard. There is no averment in the writ petition also as the date on

which he has submitted a request as provided under Rule 14(1).

7. In the light of the above, I am of the view that the Tribunal

has rightly found that the petitioner is not entitled for a deemed

permit, for the alleged non-compliance of Rule 14(1) and 14(2) of

the Rules, 2019. The 3rd respondent has already constructed a soak

pit on the basis of Ext.R3(2), valid permit issued by the local

authority. In the counter affidavit filed by the 1 st respondent, it is 2025:KER:68625

specifically stated that there is no suitable area where the soak pit

of the 3rd respondent can be shifted apart from the area where the

permit is already granted and the construction carried out by the

3rd respondent is only for a built up area of 57.10 M 2 in category II,

for which even a permit is not required. Now the soak pit has

already been constructed and if the petitioner is permitted to

construct a well in the property, it will be within 7.5 meters of the

said soak pit, which is impermissible.

In the light of the above facts and circumstances, I find no

reason to interfere with Ext.P1 order of the Tribunal for Local Self

Government Institution. Accordingly, the writ petition is dismissed.

Registry shall transit the trial court records to the Tribunal

forthwith.

Sd/-

VIJU ABRAHAM JUDGE sm/ 2025:KER:68625

APPENDIX OF WP(C) 41916/2022

PETITIONER EXHIBITS

Exhibit P1 ORIGINAL ORDER OF THE TRIBUNAL FOR LOCAL SELF GOVERNMENT INSTITUTIONS, THIRUVANANTHAPURAM DATED 31.10.2022 Exhibit P2 ORIGINAL STAY ORDER OF THE TRIBUNAL FOR LOCAL SELF GOVERNMENT INSTITUTIONS, THIRUVANANTHAPURAM DATED 25.11.2021 Exhibit P3 Proposed plan for Building Permit of R3 dated 12-08-2021 RESPONDENT EXHIBITS

Exhibit R3(1) True copy of the application for Building permit dated 18.08.2021 submitted before the 1st respondent Exhibit R3(2) True copy of the building permit No.Section A1-BA(235078)/2021 dated 12.10.2021 issued by the Panchayath Exhibit R3(3) True copy of the photographs of well and tube well in the petitioner's property Exhibit R3(4) TRUE COPY OF THE REPORT DATED 03.12.2021 ISSUED BY THE ASSISTANT ENGINEER TO THE SECRETARY TO THE CHALISSERY GRAMA PANCHAYATH EXHIBIT R 1 ( a ) A true copy of the application dated 21.10.2021 submitted by the petitioner along with its typed copy EXHIBIT R 1 ( b ) A true copy of the order dated 17.11.2021 issued by the 1st respondent EXHIBIT R 1 ( c ) A true copy of the report of the Assistant Engineer dated 03.12.2021 submitted to the Secretary of the Panchayath

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter