Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Tuaman Engineering Limited vs The Fertilizers And Chemicals ...
2025 Latest Caselaw 8506 Ker

Citation : 2025 Latest Caselaw 8506 Ker
Judgement Date : 9 September, 2025

Kerala High Court

Tuaman Engineering Limited vs The Fertilizers And Chemicals ... on 9 September, 2025

Author: N.Nagaresh
Bench: N.Nagaresh
                                                        2025:KER:66360

               IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                PRESENT

                 THE HONOURABLE MR.JUSTICE N.NAGARESH

    TUESDAY, THE 9TH DAY OF SEPTEMBER 2025 / 18TH BHADRA, 1947

                        WP(C) NO. 28771 OF 2025

PETITIONER

             TUAMAN ENGINEERING LIMITED
             REGISTERED OFFICE AT FORTUNA TOWERS,
             8TH FLOOR, 23A, NETAJI SUBHAS ROAD,
             SUIT-16, KOLKATA, PIN - 700001
             REPRESENTED BY ITS RESIDENT CONSTRUCTION MANAGER:
             KURIAKOSE V.M,


             BY ADVS.
             SRI.NITHIN GEORGE
             SRI.M.V.HARIDAS MENON
             SRI.VIZZY GEORGE KOKKAT
             SRI.RITHU JOSE
             SRI.M.R.HARIRAJ (SR.)




RESPONDENTS:

    1        THE FERTILIZERS AND CHEMICALS TRAVANCORE LIMITED (FACT)
             ELOOR, UDYOGAMANDAL, KOCHI.,
             KERALA STATE, PIN - 683501
             REPRESENTED BY ITS CHAIRMAN AND MANAGING DIRECTOR.

    2        THE FACT ENGINEERING AND DESIGN ORGANIZATION (FEDO)
             UDYOGAMANDAL, KOCHI,
             KERALA STATE. PIN - 683501
             REPRESENTED BY THE RESIDENT CONSTRUCTION MANAGER.
                                          2025:KER:66360
W.P.(C) No.28771/2025
                             :2:


           BY ADVS.
           SHRI.M.GOPIKRISHNAN NAMBIAR
           SRI.K.JOHN MATHAI
           SRI.JOSON MANAVALAN
           SRI.KURYAN THOMAS
           SRI.PAULOSE C. ABRAHAM
           SRI.RAJA KANNAN


     THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY
HEARD ON 27.08.2025 AND THE COURT ON 09.09.2025
DELIVERED THE FOLLOWING:
                                                                2025:KER:66360
W.P.(C) No.28771/2025
                                      :3:




                           N. NAGARESH, J.

          `````````````````````````````````````````````````````````````
                      W.P.(C) No.28771 of 2025

          `````````````````````````````````````````````````````````````
             Dated this the 9th day of September, 2025


                            JUDGMENT

~~~~~~~~~

The petitioner, which is a construction company,

seeks to quash Ext.47 termination notice and to direct the

respondents not to give effect and/or further effect to the

impugned Ext.P47 termination notice.

2. The petitioner submitted tender for the work of

construction of Additional Phosphoric Acid Storage Tanks at

Q10 Birth, Willington Island, Cochin for the 1st respondent-

FACT Limited. The petitioner was issued Ext.P1 work order

dated 12.02.2021 for an amount of ₹25,09,55,440/-. The

petitioner submitted security deposit bank guarantee of 2025:KER:66360

₹2,50,95,944/- on 26.02.2021. Agreement was executed on

11.03.2021.

3. The petitioner states that "Work to Proceed" notice

was issued to the petitioner on 09.04.2021. The duration of

the contract was ten months and work had to be completed by

08.02.2022. The worksite was not hindrance free. There

were underground obstructions like old PCC structure below

the finished ground level. The 1st respondent did not appraise

the petitioner of such obstacles before entering the contract

though the 1st respondent had knowledge of the extra work

need to be carried out.

4. There was inordinate delay to release of work

fronts. Work front around the mechanical workshop was

handed over only in January, 2023 after the stipulated

deadline. Work front for TRI, BTI, structural columns and

trestle bridge was released only on 14.02.2024, which was 36

months after the period of contract. Portion of the dyke wall, 2025:KER:66360

pump foundation, sump, rain water pit and pipes sleeper

foundations works were kept under hold during this period.

20 piles out of the 65 piles were kept under hold. In view of

such restrictions, there was no enough area for working and

storage of materials.

5. When the Corona pandemic broke, supply of

industrial oxygen was stopped from 22.04.2021. The

petitioner therefore could not proceed with the work. The

agreement provided for mechanical use of piling works using

DMC tractor method. The respondents, however, insisted for

manual work for lowering the pipes using tripods and chisels.

6. The petitioner issued RA Bill No.1 on 09.06.2021.

The bill was not honoured till 05.08.2021. The 1st respondent

chose to hold 20% retention amount though the petitioner had

provided bank guarantee for 10%. In spite of sending Ext.P7

letter dated 11.08.2021, the respondents did not release

payments. In the meanwhile, the petitioner sent letter dated 2025:KER:66360

16.04.2022 for extension of time to complete the work. The

respondents extended the time by five months from the work

restart date 11.04.2022 as per Ext.P11. The 1st respondent

further extended the time till 10.12.2022 as per Ext.P13.

However, the respondents continued to withhold the bill

amounts.

7. Finally, the petitioner sent Ext.P20 representation

to invoke Clause 16 of the special conditions of contract

providing for arbitration and short for amicable settlement as a

prelude to reference of the dispute to arbitration. Thereupon,

the petitioner and the respondents came to a set of terms

recorded as per Ext.P22 minutes. On 26.11.2024, the

respondents issued Ext.P29 letter insisting for revalidation of

the bank guarantee and threatened to terminate the contract

at the risk and cost of the petitioner.

8. On 21.01.2025, the respondents issued Ext.P35

letter by way of show-cause notice. The petitioner gave 2025:KER:66360

Ext.P36 explanation. The petitioner was called upon to attend

a meeting on 03.03.2025. By Ext.P40, the respondents asked

the petitioner to provide the tentative date for completion,

inspection and handover the PA tanks at the site.

9. Ultimately, the petitioner filed an arbitration petition

being AR No.30/2025 before this Court seeking appointment

of Arbitrator. This Court, by Ext.P44, appointed Hon'ble Mr.

K.M. Joseph (Former Judge, Supreme Court) as sole

Arbitrator. The petitioner filed Section 7 application before the

Arbitrator seeking appropriate orders against coercive steps

by the respondents including encashment of bank guarantee.

On 07.07.2025, the Arbitrator dismissed the application. On

10.07.2025, the respondents terminated the contract as per

Ext.P47. The petitioner fears that respondents having

terminated the contract will take steps to illegally confiscate

the materials and machinery of the petitioner. The petitioner

apprehends that he will be deprived of huge amount of money 2025:KER:66360

due to the petitioner. Hence, the petitioner seeks to quash

Ext.P47 termination notice.

10. The respondent filed counter affidavit. A writ

petition is not maintainable if instrumentality of State has

issued arbitrary orders. The petitioner filed application before

the Arbitrator seeking to direct the respondent not to invoke

bank guarantee. The application was dismissed. The said

order was challenged before the commercial court,

Ernakulam. The commercial court did not grant interlocutory

order on invocation of bank guarantee. The petitioner filed a

civil suit before the Civil Judge, Fourth Court, Alipore for

permanent injunction restraining HDFC Bank from encashing

bank guarantee. The said court did not grant interim

injunction. In appeal, the District Judge, Alipore passed ex-

parte interim injunction order. The petitioner has approached

this Court without clean hands. The writ petition is therefore

liable to be dismissed.

2025:KER:66360

11. I have heard the learned counsel for the petitioner

and the learned Standing Counsel appearing for the

respondents.

12. The petitioner was awarded with the work of

construction of Additional Phosphoric Acid Storage Tanks at

Q10 Birth, Willington Island, Cochin for the 1st respondent for

an amount of ₹25,09,55,440/- as per Ext.P1. Work to

Proceed notice was issued to the petitioner on 09.04.2021.

The work had to be completed by 08.02.2022.

13. The petitioner states that the site handed over to

the petitioner was not hindrance free. Large quantity of work

which was not envisaged by the agreement had to be carried

out in order to start the work. The respondents were aware of

this issue. The shortage of industrial oxygen due to Covid-19

pandemic also affected the progress of the work. The

respondents deliberately delayed release of Bill payments,

contends the petitioner. Huge amounts were illegally withheld 2025:KER:66360

as retention amount.

14. The petitioner would state that knowing the

difficulties faced in completion of work, the respondents had

extended the time for completion of work till 10.12.2022. The

work could not be carried out by the petitioner within that time.

There were subsequent agreements between the parties

regarding completion of work. The respondents, however,

terminated the contract on 10.07.2025 as per Ext.P47.

15. Ext.P47 would indicate that even after four years of

signing the agreement, the petitioner has completed only 40%

of the work. The time for completion of work was provisionally

extended upto 10.12.2022 and later it was further extended

upto 28.03.2025. In spite of that, the petitioner has not

completed the work.

16. During this time, the petitioner had invoked remedy

under the Arbitration and Conciliation Act and this Court has

appointed Justice K.M. Joseph (Former Judge, Supreme 2025:KER:66360

Court of India) as Arbitrator. The disputes leading to the

issuance of Ext.P47 termination notice are subject of

arbitration now pending. The issues raised by the petitioner

involve disputed questions of fact which cannot be gone into

in writ proceedings.

In the afore circumstances, the writ petition is

dismissed leaving liberty to the petitioner to prosecute his

claims in the arbitration proceedings.

Sd/-

N. NAGARESH, JUDGE aks/01.09.2025 2025:KER:66360

APPENDIX OF WP(C) 28771/2025

PETITIONER'S EXHIBITS

Exhibit P1 TRUE COPY OF THE WORK ORDER NO.

4800014487 DATED 12.02.2021 ISSUED BY THE 1ST RESPONDENT TO THE PETITIONER Exhibit P2 TRUE COPY OF THE MINUTES OF THE MEETING DATED 27.05.2021 Exhibit P3 TRUE COPY OF THE MINUTES OF THE MEETING DATED 25.06.2021.

Exhibit P4 TRUE COPY OF THE RA BILL NO.1 DATED 09.06.2021 Exhibit P5 TRUE COPY OF THE LETTER DATED 15.07.2021 ISSUED BY THE PETITIONER TO THE 2ND RESPONDENT Exhibit P6 TRUE COPY OF THE LETTER DATED 09.08.2021 ISSUED BY THE PETITIONER TO THE 2ND RESPONDENT Exhibit P7 TRUE COPY OF THE LETTER DATED 11.08.2021 ISSUED BY THE PETITIONER TO THE 2ND RESPONDENT Exhibit P8 TRUE COPY OF THE LETTER DATED 24.08.2021 ISSUED BY THE PETITIONER TO THE 2ND RESPONDENT Exhibit P9 TRUE COPY OF THE EMAIL DATED 16.12.2021 ISSUED BY THE 2ND RESPONDENT TO THE PETITIONER Exhibit P10 TRUE COPY OF THE LETTER DATED 17.12.2021 ISSUED BY THE PETITIONER TO THE 2ND RESPONDENT Exhibit P11 TRUE COPY OF THE LETTER DATED 26.04.2022 ISSUED BY THE RESPONDENT TO THE PETITIONER Exhibit P12 TRUE COPY OF THE EMAIL DATED 13.08.2022 ISSUED BY THE 2ND RESPONDENT TO THE PETITIONER 2025:KER:66360

Exhibit P13 TRUE COPY OF THE EMAIL DATED 04.11.2022 ISSUED BY THE 2ND RESPONDENT TO THE PETITIONER Exhibit P14 TRUE COPY OF THE LETTER DATED 24.01.2023 Exhibit P15 TRUE COPY OF THE LETTER DATED 12.05.2023 ISSUED BY THE PETITIONER TO THE RESPONDENTS Exhibit P16 TRUE COPY OF THE LETTER DATED 17.05.

2023 ISSUED BY THE PETITIONER TO THE RESPONDENT Exhibit P17 TRUE COPY OF THE LETTER DATED 14.06.2023 ISSUED BY THE PETITIONER TO THE RESPONDENTS Exhibit P18 TRUE COPY OF THE LETTER DATED 27.07.2024 ISSUED BY THE PETITIONER TO THE RESPONDENTS Exhibit P19 TRUE COPY OF THE LETTER DATED 13.05.2024 ISSUED BY THE PETITIONER TO THE RESPONDENTS Exhibit P20 TRUE COPY OF THE LETTER DATED 13.05.2024 ISSUED BY THE PETITIONER AND ADDRESSED TO THE CHAIRMAN AND MANAGING DIRECTOR OF THE FIRST RESPONDENT WITH COPY TO THE SECOND RESPONDENT Exhibit P21 TRUE COPY OF THE LAWYERS NOTICE DATED 03.09.2024 Exhibit P22 TRUE COPY OF THE MINUTES OF THE MEETING DATED 24.09.2024 Exhibit P23 TRUE COPY OF THE LETTER DATED 08.11.2024 ISSUED BY THE PETITIONER TO THE RCM OF THE SECOND RESPONDENT Exhibit P24 TRUE COPY OF THE LETTER DATED 11.11.2024 ISSUED BY THE 1ST RESPONDENT TO THE PETITIONER.

Exhibit P25 TRUE COPY OF THE LETTER DATED 19.11.2024 ISSUED BY THE PETITIONER TO THE RESPONDENTS 2025:KER:66360

Exhibit P26 TRUE COPY OF THE MINUTES OF THE MEETING DATED 25.11.2024.

Exhibit P27 TRUE COPY OF THE LETTER DATED 26.11.2024 Exhibit P28 TRUE COPY OF THE MINUTES OF THE MEETING DATED 28.11.2024 SENT BY THE PETITIONER TO THE RESPONDENTS UNDER EMAIL DATED 28.11.2024 Exhibit P29 TRUE COPY OF THE LETTER DATED 26.11.2024 ISSUED BY THE 2ND RESPONDENT Exhibit P30 TRUE COPY OF THE LETTER DATED 03.12.2024 ISSUED BY THE PETITIONER TO THE RESPONDENT Exhibit P31 TRUE COPY OF THE LETTER DATED 11.12.2024 Exhibit P32 TRUE COPY OF THE LETTER DATED 12.12.2024 Exhibit P33 TRUE COPY OF THE LETTER DATED 21.12.2024 Exhibit P34 TRUE COPIES OF THE ORDERS DATED 27.12.2024, 06.01.2025 AND 06.02.2025 IN WP(C) 46444 OF 2024 Exhibit P35 TRUE COPY OF THE LETTER DATED 21.01.2025 ISSUED BY THE RESPONDENTS TO THE PETITIONER.

Exhibit P36 TRUE COPY OF THE LETTER DATED 29.01.2025 Exhibit P37 TRUE COPY OF THE EMAIL DATED 20.02.2025 ISSUED BY THE PETITIONER TO THE RESPONDENTS.

Exhibit P38             TRUE COPIES OF THE EMAILS DATED 28
                        FEBRUARY     2025     ISSUED     BY   THE
                        RESPONDENTS TO THE PETITIONER.
Exhibit P39             TRUE COPY OF THE EMAIL DATED 6 MARCH

2025 ISSUED BY THE PETITIONER TO THE RESPONDENTS.

2025:KER:66360

Exhibit P40 TRUE COPY OF THE EMAIL DATED 07.03.2025 ISSUED BY THE 2ND RESPONDENT TO THE PETITIONER Exhibit P41 TRUE COPY OF THE LETTER DATED 15.03.2025 ISSUED BY THE PETITIONER TO THE RESPONDENTS.

Exhibit P42 TRUE COPY OF THE EMAIL DATED 18.03.2025 ISSUED BY R2 TO PETITIONER. Exhibit P43 TRUE COPY OF THE LETTER DATED 15.04.2025 ISSUED BY THE PETITIONER. Exhibit P44 TRUE COPY OF THE ORDER DATED 28.03.2025 IN A.R NO. 30 OF 2025.

Exhibit P45 TRUE COPY OF THE ORDER DATED 7.04.2025 IN A.R NO. 30 OF 2025.

Exhibit P46 TRUE COPY OF THE ORDER DATED 07.07.2025 ISSUED BY THE LEARNED ARBITRATOR.

Exhibit P47 TRUE COPY OF THE LETTER DATED 10.07.2025 ISSUED BY THE 1ST RESPONDENT TO THE PETITIONER.

EXHIBIT P48 THE RELEVANT PAGES OF THE CONTRACT CONTAINING ARTICLE 43 OF THE GENERAL CONDITIONS OF CONTRACT RESPONDENTS' EXHIBITS

Exhibit R1(a) TRUE COPY OF THE AGREEMENT DATED 12.2.2021 EXECUTED BETWEEN PETITIONER AND THIS RESPONDENT PURSUANT EXHIBIT P1 WORK ORDER Exhibit R1(b) TRUE COPY OF THE APPLICATION DATED 21.7.2025 FILED BY THE PETITIONER BEFORE THE HON'BLE ARBITRATOR UNDER SECTION 17 OF THE ARBITRATION AND CONCILIATION ACT, 1996, WITHOUT ANNEXURES THERETO 2025:KER:66360

Exhibit R1(c) TRUE COPY OF I A NO.2 OF 2025 IN MA (ARB.) NO. 236 OF 2025 DATED 09.07.2025 FILED BY THE PETITIONER BEFORE COMMERCIAL COURT, ERNAKULAM, WITHOUT DOCUMENTS Exhibit R1(d) TRUE COPY OF ORDER DATED 9.7.2025 OF CIVIL JUDGE (SR. DIVN), 4TH COURT, ALIPORE IN TITLE SUIT NO. 1021/2025 Exhibit R1(e) TRUE COPY OF ORDER DATED 10.7.2025 DISTRICT JUDGE, ALIPORE IN MISC.

APPEAL NO. 218 OF 2025 (R-218)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter