Sunday, 10, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Kothamangalam Municipality vs P.P.Ajithkumar
2025 Latest Caselaw 6389 Ker

Citation : 2025 Latest Caselaw 6389 Ker
Judgement Date : 28 May, 2025

Kerala High Court

Kothamangalam Municipality vs P.P.Ajithkumar on 28 May, 2025

Author: Amit Rawal
Bench: Amit Rawal
WA NO. 520 OF 2024              1              2025:KER:36356

              IN THE HIGH COURT OF KERALA AT ERNAKULAM

                               PRESENT

               THE HONOURABLE MR. JUSTICE AMIT RAWAL

                                    &

            THE HONOURABLE MR.JUSTICE MURALEE KRISHNA S.

    WEDNESDAY, THE 28
                        TH DAY OF MAY 2025 / 7TH JYAISHTA, 1947


                          WA NO. 520 OF 2024

        AGAINST THE JUDGMENT DATED 29.02.2024 IN WP(C) NO.30648 OF

2012 OF HIGH COURT OF KERALA

APPELLANTS/RESPONDENTS 1 & 2 IN THE W.P.(C):

    1      KOTHAMANGALAM MUNICIPALITY,
           REPRESENTED BY ITS SECRETARY, KOTHAMANGALAM-686 691,
           PIN - 686691.

    2      THE SECRETARY
           KOTHAMANGALAM MUNICIPALITY, KOTHAMANGALAM-686 691,
           PIN - 686691.


           BY ADVS.
           D.KISHORE
           SHRI.JOICE GEORGE, SC, KOTHAMANGALAM MUNICIPALITY
           TOM E. JACOB



RESPONDENTS/PETITIONER & ADDITIONAL 3RD RESPONDENT IN THE
W.P.(C):

    1      P.P.AJITHKUMAR,
           AGED 46 YEARS,
           P.W.D. CONTRACTOR, PUTHENPURACKAL HOUSE, NELLAD P.O.,
           MUVATTUPUZHA-686 721, PIN - 686721.

    2      ADDL.R3.
           REGIONAL JOINT DIRECTOR,
           URBAN AFFAIRS, BROADWAY ERNAKULAM, PIN - 682031.

              ●   ADDL.R3 IS SUO MOTU IMPLEADED AS PER ORDER DATED
                  11.08.2022 IN WP(C)30648/2012.
 WA NO. 520 OF 2024           2           2025:KER:36356


          R1 BY ADV DEEPU LAL MOHAN
          R2 BY SR.GOVERNMENT PLEADER SRI T K VIPINDAS


      THIS WRIT APPEAL HAVING BEEN FINALLY HEARD ON 20.05.2025,
THE COURT ON 28.05.2025 DELIVERED THE FOLLOWING:
 WA NO. 520 OF 2024             3          2025:KER:36356

                        JUDGMENT

Muralee Krishna, J.

This is an appeal filed under Section 5(i) of the Kerala High

Court Act, 1958, by respondents 1 and 2 in W.P.(C) No.30648 of

2012 against the judgment of the learned Single Judge dated

29.02.2024 in the writ petition.

2. The 1st respondent herein is a PWD contractor, who

successfully secured the construction work of the first Phase of

'Kothamangalam Municipal Bus Stand' from the 1st appellant

Municipality, by quoting the lowest rate and subsequently by

reducing it on negotiation. Accordingly, Ext.P1 agreement dated

09.03.2009 was entered into between the 1st respondent and the

Municipality. According to the 1st respondent, the work could not

be commenced immediately after the execution of Ext.P1

agreement due to reasons beyond his control. The initial work,

such as the excavation of soil, was done under the supervision of

the Assistant Engineer of the 1st appellant. At that time, it was

found that against the total quantity of 660 M3 earth work

excavation specified in the schedule to the agreement, around

13000 M3 of earth work excavation had to be done. Similarly, it

was found that since hard rock was noticed beneath the soil, WA NO. 520 OF 2024 4 2025:KER:36356

around 5000 M3 of rock blasting had to be done at the site. The

Assistant Engineer reported this to the Municipal Engineer, who in

turn reported the same to the 2nd appellant Secretary and

subsequently, the matter was placed before the Chairperson of

the 1st appellant Municipality. The then Chairperson of the 1st

appellant Municipality granted sanction for carrying out earth work

excavation of 13900 M3 and medium rock blasting of 1900 M3 by

the 1st respondent as extra items by invoking the emergency

power conferred on him under Section 15(4) of the Kerala

Municipality Act, 1994 (the 'Municipality Act' in short).

2.1. According to the 1st respondent, he immediately

commenced the said additional works and carried on earth

excavation of 12417 M3 and medium rock blasting of 1894 M 3 at

the site. Meanwhile, the Municipality entrusted the removal of

hard rock from the site to third parties. At that juncture, the

Department of Mining and Geology directed the Municipality to

stop the quarrying work and to remit an amount of Rs.21,000/-

towards royalty and fine for the granite quarried. In spite of

repeated requests by the 1st respondent, the Municipality did not

take any steps to recommence the work. Meanwhile, the contract

period for completion of the work expired on 09.03.2010. Though WA NO. 520 OF 2024 5 2025:KER:36356

the 1st respondent submitted Ext.P7 request, dated 07.07.2011 to

the 2nd appellant to take appropriate steps for re-commencing the

work after extending the period of contract or to relieve him of the

subject work after paying the amount due to him, no response

was followed. Hence, the 1st respondent approached this Court by

filing W.P.(C) No.29403 of 2011, which was disposed of by Ext.P8

judgement dated 11.11.2011, directing the 2nd appellant to

consider and pass orders on Ext.P7 request within a time frame.

Thereafter, as per Ext.P13 resolution dated 13.09.2012 of the

Municipal Council, the 1st respondent was decided to be relieved

from the work. It was further resolved by the Council not to grant

payment to the 1st respondent for execution of the aforesaid two

extra items of work and also resolved to recover from him the cost

of earth that was removed from the site. Hence, the 1st respondent

filed the writ petition seeking the following reliefs:

"(i) To issue of Writ of Certiorari or other appropriate writ, order or direction calling for the records leading to Ext.P13 and quash the same to the extent it resolves not to grant payment to the Petitioner for the execution of the two extra items of work in question and also to recover from the Petitioner the cost of the earth that was removed from the site at 2007 schedule of rates.

(ii) To declare that since the Petitioner has executed the two extra items of work in question on the basis of the sanction WA NO. 520 OF 2024 6 2025:KER:36356

granted by the Chairperson of the 1st Respondent Municipality in invocation of the emergency power provided under Section 15 (4) of the Kerala Municipality Act 1994, the Respondents are bound to make payment to the Petitioner for execution of the said two extra items of work, dehors, lack of approval by the Municipal Council of the 1st Respondent Municipality.

(iii) To issue a Writ of Mandamus or other appropriate writ, order or direction directing the Respondents to disburse to the Petitioner the entire amounts due to the Petitioner in respect of the subject work including payment for the execution of the two extra items in question within a time frame to be fixed by this Hon'ble Court."

3. In the impugned Judgment, the learned Single Judge

found that the 1st respondent is entitled for the additional work

carried out by him and if any illegality is committed by the

Chairperson by not placing the matter before the Municipal

Council, the Chairperson or the Municipality has to suffer and the

1st respondent cannot be penalised for the same. Having found so,

the learned Single Judge disposed of the writ petition with the

following directions:

"1. The petitioner is free to file a representation narrating his grievance before the additional 3rd respondent, within three weeks from the date of receipt of a copy of this judgment.

2. Once such a representation is received, the additional 3rd respondent will consider the same and pass appropriate WA NO. 520 OF 2024 7 2025:KER:36356

orders in it, after giving an opportunity of hearing to the petitioner and the Municipality, as expeditiously as possible, at any rate, within three months from the date of receipt of the representation.

3. The additional 3rd respondent will issue notice to the then Chairperson also before deciding the matter.

4. The disbursal of the amount due to the petitioner will be subject to the above decision to be taken by the additional 3rd respondent."

4. Heard Adv. D.Kishore, the learned Standing Counsel

for the appellants, Adv. Deepu Lal Mohan, the learned counsel for

the 1st respondent and the learned Government Pleader appearing

for the 2nd respondent and perused the paper book.

5. The learned Standing Counsel raised twofold

arguments. His first argument is based on Section 15(4) of the

Municipality Act read with Rule 14(5) of the Kerala Municipality

(Execution of Public Works and Purchase of Materials) Rules, 1997

('the Rules 1997' for short), which he raised before the learned

Single Judge also. His second submission is that even if the

Municipality is liable to pay any amount to the 1st respondent, the

burden may not be cast upon the Chairperson who acted in

accordance with the power granted to him under Section 15(4) of

the Municipality Act.

WA NO. 520 OF 2024 8 2025:KER:36356

6. The learned counsel for the 1st respondent/writ

petitioner maintained his stand that was taken before the learned

Single Judge.

7. There is no dispute between the parties on the factual

aspects. Admittedly, the 1st respondent carried out additional two

works other than that covered by Ext.P1 agreement, such as earth

work excavation and medium rock blasting of some quantity on

the strength of the permission granted by the Chairperson of the

1st appellant Municipality, invoking his power conferred under

Section 15(4) of the Municipality Act. The contention of the

appellants is that as per Proviso (b) to Section 15(4) of the

Municipality Act, the Chairperson shall report the steps taken by

him and the reasons therefore to the council at the next meeting

and obtain its approval. The same is not done by the Chairperson.

Similarly, by relying on Rule 14(5) of the Rules 1997, the

appellants contend that where an item of work done, which has

not been included in the estimate, an estimate for such excess

work shall be prepared and prior sanction, both administrative and

technical shall be obtained from the authorities who had given

administrative and technical sanction to the original estimate and

therefore, the 1st respondent ought to have waited till this WA NO. 520 OF 2024 9 2025:KER:36356

procedural compliance, even though he was permitted by the

Chairperson to carry out additional works treating it as an

emergency.

8. As per Section 15(4) of the Municipality Act, a

Chairperson may, in emergent circumstances, direct the execution

of any work or performance of any Act, in respect of which

sanction of the Council is necessary and in his opinion, the

immediate execution or performance of which is necessary for the

safety of the public and may also direct that the expenses incurred

for the execution of such work or performance of such act be paid

from the fund of the Municipality. Proviso (b) of Section 15(4) of

the Municipality Act says that the steps taken under this sub-

section by the Chairperson shall be reported at the next meeting

of the council and its approval obtained. By Section 15(4) of the

Municipality Act, discretion is given to the Chairperson to decide

the urgency of the work and the necessity to grant sanction to

carry out the said work without the prior sanction of the council.

It is invoking this power, the Chairperson entrusted two additional

works to the 1st respondent. Whether the Chairperson reported

the steps taken by him to the council on its next meeting or not is

not the lookout of the 1st respondent, since there is no stipulation WA NO. 520 OF 2024 10 2025:KER:36356

in Section 15(4) of the Municipality Act that he can proceed with

the work only after obtaining the assent of the council. If that is

the intention behind the Proviso (b) to Section 15(4) of the

Municipality Act, then the very purpose of the Section will become

otiose, since the work will be halted and it will not be possible to

meet the emergent situation, convinced by the Chairperson.

9. It is true that Rule 14(5) of the Rule 1997 says that,

where an item of work done which has not been included in the

estimate for unforeseen reason or an item of additional work has

to be executed while the execution of a public work in accordance

with the estimate is being carried on, an estimate for such excess

work shall be prepared and prior sanction, both administrative and

technical, shall be obtained from the authorities who had given

administrative and technical sanction to the original estimate. On

a combined reading of Section 15(4) of the Municipality Act and

the aforesaid Rule would lead us to the opinion that the additional

work mentioned in Rule 14(5) is not the one covered under

Section 15(4) of the Municipality Act, but it applies to the

additional works ordinarily carried out. If an emergent situation

has arisen, then waiting for compliance with the procedure

stipulated under Rule 14(5) of the Rules 1997, will make the WA NO. 520 OF 2024 11 2025:KER:36356

emergent situation covered under Section 15(4) of the

Municipality Act meaningless. Therefore, we find no sufficient

ground to say that the learned Single Judge failed in properly

appreciating the contentions of the 1st respondent regarding his

entitlement to the amount for the additional work carried out by

him as permitted by the Chairperson of the 1st appellant

Municipality.

10. While coming to the observation made by the learned

Single Judge regarding the liability of the Chairperson of the cost

of construction carried out by the 1st respondent on the basis of

the permission granted by the Chairperson under Section 15(4) of

the Municipality Act, the said section make it clear that the

expenses incurred for the execution of such work be paid from the

fund of the Municipality. Merely for the reason that the

Chairperson failed to place the steps taken before the council in

its next meeting, the Chairperson cannot be held liable to pay the

expenses to the 1st respondent, especially when no such

contention was raised by any of the parties before the learned

Single Judge and no material has been placed to the effect that

the council has taken any such stand. In such circumstances, we

hold the observation made by the learned Single Judge regarding WA NO. 520 OF 2024 12 2025:KER:36356

the liability of the Chairperson only as an obiter dicta. We do not

propose to interfere with the directions of the learned Single Judge

in the impugned judgment except to the above extent.

The Writ appeal is therefore disposed of with the above

observations. The 1st respondent is granted further three weeks

time from the date of receipt of a copy of this judgment to submit

his representation before the 2nd respondent/additional 3rd

respondent in the writ petition as directed in the impugned

judgment, if the same is not already submitted. The 2nd

respondent/additional 3rd respondent in the writ petition shall take

a decision in the representation within a period of one month from

the date of receipt of the same, if submitted afresh or within a

period of one month from the date of receipt of a copy of this

judgment if the representation has already been submitted by the

1st respondent.

Sd/-

AMIT RAWAL, JUDGE

Sd/-

MURALEE KRISHNA S., JUDGE

DSV/-

 WA NO. 520 OF 2024            13           2025:KER:36356



PETITIONERS' ANNEXURES

Annexure -I          TRUE COPY OF THE COUNTER AFFIDAVIT DATED
                     3.8.2022 FILED BY THE RESPONDENTS IN
                     W.P.(C) 30648/2012
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter