Saturday, 09, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

P.P. Mathew vs The Divisional Railway Manager(Works)
2025 Latest Caselaw 6318 Ker

Citation : 2025 Latest Caselaw 6318 Ker
Judgement Date : 27 May, 2025

Kerala High Court

P.P. Mathew vs The Divisional Railway Manager(Works) on 27 May, 2025

Author: N.Nagaresh
Bench: N.Nagaresh
               IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                  PRESENT

                 THE HONOURABLE MR.JUSTICE N.NAGARESH

        TUESDAY, THE 27TH DAY OF MAY 2025 / 6TH JYAISHTA, 1947

                          WP(C) NO. 33597 OF 2024

PETITIONER:

            P.P. MATHEW
            AGED 61 YEARS
            S/O P.C. PAILO, VATTAKUNNEL PULICKAL HOUSE,
            MUTTAMBALAM, KOTTAYAM, RESIDING AT VATTAKUNNEL
            PULICKEL, 11TH, GIRINAGAR,
            KADAVANTHARA, KOCHI, PIN - 682020


            BY ADVS.
            C.S.MANILAL
            S.NIDHEESH




RESPONDENTS:



    1       THE DIVISIONAL RAILWAY MANAGER(WORKS),
            DIVISIONAL OFFICE, SOUTHERN RAILWAY,
            TRIVANDRUM, PIN - 695014

    2       THE SENIOR SECTION ENGINEER
            OFFICE OF THE SENIOR SECTION ENGINEER,
            SOUTHERN RAILWAY, KOTTAYAM, PIN - 686001

    3       ASSISTANT DIVISIONAL ENGINEER,
            SOUTHERN RAILWAY, ERNAKULAM, PIN - 682016

    4       SENIOR DIVISIONAL ENGINEER
            CO-ORDINATION,
            SOUTHERN RAILWAY TRIVANDRUM DIVISION,
                                           2025:KER:36169
W.P.(C) No.33597/2024
                           :2:


          DIVISIONAL OFFICE, THYCAUD,
          TRIVANDRUM, PIN - 695014

    5     SENIOR DIVISIONAL ENGINEER(WORKS),
          SOUTHERN RAILWAY TRIVANDRUM DIVISION,
          DIVISIONAL OFFICE, THYCAUD,
          TRIVANDRUM, PIN - 695014


          BY ADV K.R. RAJKUMAR

     THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY
HEARD ON 22.05.2025, THE COURT ON 27.05.2025 DELIVERED
THE FOLLOWING:
                                                                2025:KER:36169
W.P.(C) No.33597/2024
                                     :3:




                          N. NAGARESH, J.

         `````````````````````````````````````````````````````````````
                     W.P.(C) No.33597 of 2024

         `````````````````````````````````````````````````````````````
               Dated this the 27th day of May, 2025


                           JUDGMENT

~~~~~~~~~

The petitioner, who is owner and

possesser of 10.38 Ares of property in Re-survey Nos.25

and 25/1 of Muttambalam Village, seeks to direct the

respondents to see that access to the property of the

petitioner is ensured removing the blockade created by the

construction of 8 cement pillars / protection guide blocks in

front of the property of the petitioner.

2. The Railway decided to close the level

cross and to construct an underpass on a municipal road

adjacent to the property of the petitioner. The respondents

acquired property on the southern side of the municipal 2025:KER:36169

road. An extent of 1.08 Ares (2.67 Cents) of the petitioner

was acquired. After acquisition, the respondents

constructed an underpass through the acquired land.

3. The petitioner states that before the

acquisition, the petitioner had direct access to the said

municipal road from his property. After the acquisition of

the underpass, the access can be only through the newly

constructed road portion. After the construction, the

petitioner was entering into his property from the said road.

In the absence of the petitioner and his family, the

respondents obstructed and prevented the petitioner's

access to public road by constructing 8 cement pillars /

protection guide blocks.

4. The petitioner made Ext.P3 request to the

1st respondent seeking to remove the obstruction and permit

the petitioner to have access to the public road. The 2nd

respondent conducted an inspection and recommended that

access be granted to the petitioner on condition that no 2025:KER:36169

obstruction should be caused to the free passage of the

vehicles through the road.

5. The 1st respondent rejected the request of

the petitioner as per Ext.P7 communication. The petitioner

challenged Ext.P7 filing W.P.(C) No.36433/2023. This

Court held that new underpass is virtually a public road and

access cannot be denied to the petitioner. The 4th

respondent was directed to reconsider the entire matter.

The 5th respondent thereupon passed Ext.P9 order stating

that the land of the petitioner is situated in a lower level. In

Ext.P9, the respondents have added additional reasons to

deny access.

6. The petitioner argued that Ext.P9 is illegal

and unsustainable and the reasons stated therein are

unreal. The denial of access to the public highway as per

Ext.P9 is illegal and arbitrary. The owner of a property on

the side of a highway or public road has a natural right to

have access at every point in the highway without any 2025:KER:36169

hindrance. Ext.P9 is therefore liable to be set aside.

7. The respondents resisted the writ petition.

The respondents stated that the property of the petitioner

has no direct access to the road leading to the subway.

The petitioner's land has been at a lower level which has

been recently filled with earth. The petitioner did not have

access to the newly constructed road. The guide blocks

along the limited use subway were constructed since the

adjoining ground was at a lower level. It is these safety

guide blocks which have been termed as "blockade" by the

petitioner.

8. As per Railway Board Guidelines, new

access cannot be granted when the petitioner has already

another access to his property. The field report also stated

that the petitioner wants to demolish the guide blocks for

additional access to the apartment building. The NOC

drawing submitted by the petitioner shows that he has

separate access to the municipality road. The writ petition 2025:KER:36169

is therefore liable to be dismissed.

9. I have heard the learned counsel for the

petitioner and the learned Central Government Counsel

representing the respondents.

10. It is not disputed that the respondents

have acquired a portion of the petitioner's land in order to

construct an underpass. After construction of underpass,

the existing road lies adjacent to the petitioner's land. The

petitioner had sold a larger extent of his property for

construction of an apartment complex. The apartment

complex has separate access.

11. The contention of the respondents is that

the land had another access before the construction of the

apartment complex. The remaining land possessed by the

petitioner was lying at a lower level. The petitioner had no

access to his property through that area earlier. The

cement blocks have been constructed in order to protect the

railway land/road.

2025:KER:36169

12. It may be true that the larger extent of area

earlier owned by the petitioner had another access. After

the sale of a portion of the land, where an apartment

complex is constructed subsequently, the remaining land in

possession of the petitioner has no separate access. The

petitioner's land is adjacent to the public road. As rightly

pointed out by the petitioner, owner of a land adjacent to the

highway / public road has every right to access the public

road. By constructing 8 cement pillars, the petitioner has

been denied access to the property.

13. It may be true that the remaining property

in the possession of the petitioner was at a lower level

earlier. But, the fact remains that the petitioner has filled up

that property which is adjacent to the public road. The

petitioner therefore has a right to access the road from his

property. The reasons stated in Ext.P9 are therefore

unsustainable.

2025:KER:36169

The writ petition is therefore disposed of

directing the respondents to remove such number of

cement pillars / protection guide blocks in front of the

petitioner's property so as to give vehicular access to the

petitioner's property.

Sd/-

N. NAGARESH, JUDGE aks/24.05.2025 2025:KER:36169

APPENDIX OF WP(C) 33597/2024

PETITIONER'S EXHIBITS

Exhibit P1 TRUE COPIES OF THE PHOTOGRAPHS OF PROPERTY OF THE PETITIONER

Exhibit P2 TRUE COPY OF THE SKETCH OF PROPERTY OF THE PETITIONER

Exhibit P3 TRUE COPY OF THE REQUEST DATED 2.6.2023 TO THE 1ST RESPONDENT

Exhibit P4 TRUE COPY OF THE RECOMMENDATION DATED 14.6.2023 OF THE 2ND RESPONDENT

Exhibit P5 TRUE COPY OF THE NOC DATED 21.12.2016 OF THE 1ST RESPONDENT

Exhibit P6 TRUE COPY OF THE REQUEST DATED 16.8.2023 TO THE 1ST RESPONDENT

Exhibit P7 TRUE COPY OF THE COMMUNICATION DATED 11.10.2023 OF THE 1ST RESPONDENT

Exhibit P8 A COPY OF THE JUDGMENT DATED 12.3.2024 IN W.P© 36433/2023

Exhibit P9 A COPY OF THE ORDER DATED 3.7.2024 OF THE 5TH RESPONDENT

Exhibit P10 A COPY OF THE SKETCH OF THE PROPERTY SHOWING THE ACCESS TO THE FLAT FROM THE WESTERN MUNICIPAL ROAD

Exhibit P11 A COPY OF THE SURVEY SKETCH OF BLOCK

Exhibit P12 A COPY OF THE PHOTOGRAPHS OF RECENT ORIGIN 2025:KER:36169

RESPONDENT'S EXHIBITS

Exhibit R1(g) The true copy of the railway Board Guidelines dated 27.11.2001

Exhibit R1(a) The true copy of the judgement dated 12-03-2024 in WP(C) 36433/2023

Exhibit R1(b) The true copy of the proceedings of Divisional Railway Manager (Works), Southern Railway, Trivandrum dated nil.


Exhibit R1(c)           The   true   copy   of   letter    No.
                        V/W.280/NOC/F.RS/1027            dated

21.12.2016 of Railway granting NOC for the construction in the name of petitioner for construction of apartment building with access from 7m wide road on the western side of the apartment building

Exhibit R1(d) The true copy of the NOC drawing dated 21.12.2016 issued to the petitioner

Exhibit R1(e) The true copy of the agreement between petitioner and M/s Confident group produced by the petitioner dated 01.12.2018

Exhibit R1(f) The true copy of the rejection letter issued by the 1st respondent on the way leave petition dated 11-10-2023

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter