Citation : 2025 Latest Caselaw 1329 Ker
Judgement Date : 9 June, 2025
2025:KER:39435
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE N.NAGARESH
MONDAY, THE 9TH DAY OF JUNE 2025 / 19TH JYAISHTA, 1947
WP(C) NO. 23477 OF 2024
PETITIONER:
VASUDEVAN K.M.,
AGED 46 YEARS,
S/O. T.E.SREEKUMARANTHIRUMUMBU,
OLORA MADAM,
PAYYANUR, PO. PAYYANUR
KANNUR DISTRICT,
PROPRIETOR, M/S. V.ASSOCIATES,
DEFENCE CONTRACTOR & CONSULTING ENGINEER,
RAMANTHALI PO,
KANNUR DISTRICT,
PIN - 670308
BY ADVS.
SRI.M.V.AMARESAN
SRI.S.S.ARAVIND
RESPONDENTS:
1 CHIEF ENGINEER (NAVAL WORKS) KOCHI,
OFFICE OF THE CHIEF ENGINEER (NAVAL WORKS)
KOCHI KATARIBAGH, NAVAL BASE P.O.,
KOCHI,
PIN - 682004
2 CHIEF ENGINEER,
OFFICE OF THE CHIEF ENGINEER SOUTHERN COMMAND,
SIR MANECKJI MEHTA ROAD, CAMP,
PUNE, MAHARASHTRA,
PIN - 411001
2025:KER:39435
W.P.(C) No.23477/2024
:2:
*ADDL.3 M/S.CREATIVE BUILDERS,
CREATIVE TOWER, EROOR P.O.,
VYTTILA- 682 306,
REPRESENTED BY ITS MANAGING PARTNER,
VISHNU T.P.
*(ADDITIONAL 3RD RESPONDENT IS IMPLEADED AS PER
ORDER DATED 22.05.2025 IN IA NO.1/2025 IN WP(C)
NO.23477/2024.)
BY ADVS.
SRI.P.R.AJITH KUMAR, CGC
SRI.DEEPU THANKAN
SMT.UMMUL FIDA
SMT.LAKSHMI SREEDHAR
SMT.LEKSHMI P. NAIR
SMT.VINEETHA BOSE
SMT.CINDIA S.
SMT.GAYATHRI G.
SMT.O.M.SHALINA, DSGI
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD
ON 02.06.2025, THE COURT ON 09.06.2025 DELIVERED THE
FOLLOWING:
2025:KER:39435
W.P.(C) No.23477/2024
:3:
N. NAGARESH, J.
`````````````````````````````````````````````````````````````
W.P.(C) No.23477 of 2024
`````````````````````````````````````````````````````````````
Dated this the 9th day of June, 2025
JUDGMENT
~~~~~~~~~
Petitioner, who is a C Class Contractor
enlisted under the Chief Engineer, Southern Naval Command,
Pune, is before this Court seeking to quash Exts.P9 and P11
and to declare that the petitioner is eligible to submit his bid in
response to Ext.P6 re-tender issued pursuant to Ext.P1.
2. The petitioner states that the 1st respondent-
Chief Engineer (Naval Works, Kochi) invited tender for
"Completion of incomplete works for setting up single offices
accommodation as a part augmentation of infrastructure and 2025:KER:39435
facilities at INA, Ezhimala (Phase-II)" as per Ext.P1 notice of
tender. As the estimated cost of work is ₹6,10,00,000/-, only
Contractors having A Class and above registration were eligible
to bid. As INA, Ezhimala is a remote station, Contractors
one/two Class below the eligible Class were also permitted to
bid the tender as per Ext.P1. The petitioner submitted Ext.P2
bid. When technical bid was opened, only two participants
were found qualified. Price bid could not be opened due to
administrative reasons. Subsequently, the tender was
cancelled and Ext.P6 re-tender notification was issued.
3. The petitioner again submitted Ext.P7 bid.
There were more bids this time. The 1st respondent, as per
Ext.P9, rejected the petitioner's bid on the ground that number
of enlisted Contractors of eligible Class exceeds 7. The
petitioner states that Ext.P9 rejection is liable to be quashed.
The bid of a Contractor having MSME registration is liable to be
considered. The petitioner therefore filed Ext.P10 appeal 2025:KER:39435
before the 2nd respondent-Chief Engineer. The 2nd respondent
rejected the appeal as per Ext.P11. The petitioner states that
Exts.P9 and P11 are liable to be set aside.
4. The counsel for the petitioner argued that the
number of bids came responding to the second call followed by
Ext.P1 is fake. Without considering the number of bids, the
petitioner's bid is also liable to be considered. Treating Ext.P6
re-tender as continuation of the first call pursuant to Ext.P1, the
petitioner's bid ought to have been accepted. The act of
respondents in revoking the tender unilaterally is illegal and
without bona fide. The counsel for the petitioner relied on the
judgment of the Hon'ble Patna High Court in M.K. Enterprises,
Patna v. State of Bihar [2023 KHC OnLine 4139] and argued
that not providing opportunity to the petitioner before
cancellation of bid is violative of principles of natural justice.
Relying on the judgment of the Hon'ble Gauhati High Court in
G.B. Chaudhuri Holdings Private Limited (M/s.) v. Food 2025:KER:39435
Corporation of India and another [2019 KHC 4002], the
counsel for the petitioner argued that cancellation process of
first tender is vitiated by lack of transparency and fairness.
5. Counsel for the 3rd respondent entered
appearance and resisted the writ petition. The 3rd respondent
submitted that only Contractors enlisted with MES in Class A
and above are eligible to bid the work in question. As per Note
1 of Ext.P1 NIT, in case after opening the Cover 1, the number
of MES enlisted Contractors of eligible Class as well as
unenlisted Contractors is less than 7, then applications of MES
Contractors one/two Class below the eligible Class shall also be
considered.
6. Since there were 11 bidders who participated
in the tender and 8 of them are enlisted in Class A and above,
bidders below the Class A are ineligible to participate. The
counsel for the 3rd respondent relied on the judgment of the
Hon'ble Apex Court in Afcons Infrastructure Limited v.
2025:KER:39435
Nagpur Metro Rail Corporation Limited and another [(2016)
16 SCC 818] and argued that unless the threshold of malafides,
intention to favour someone or arbitrariness, irrationality or
perversity exists, constitutional courts shall not interfere in the
decision making process or the decision of the authorities.
7. Respondents 1 and 2 also filed counter
affidavit. In respect of the first bid, there were two Firms eligible
for consideration. After opening the technical bid but before
opening the price bid, the defaulted Contractor filed a writ
petition before this Court against cancellation of the contract. In
W.P.(C) No.27285/2023, this Court passed an interim order
directing to maintain status quo. In the meanwhile, one of the
bidders intimated that they were not in a position to extend the
validity of bid. In such circumstances, re-tender was resorted
to.
8. Thereafter, the tender was republished on
05.02.2024. The Technical bid (Cover 1) was opened.
2025:KER:39435
Eleven bidders had submitted their bids. More than 7 Class A
bidders were found qualified to make the bid. Therefore, the
bids of one/two Class below enlisted Contractors were not
considered. The bid of the petitioner was therefore not
entertained. In the facts and circumstances, the allegations
made in the writ petition are wrong and unfounded. The
petitioner is not entitled to any reliefs, urged the 1st respondent.
9. I have heard the learned counsel for the
petitioner, the learned Central Government Counsel
representing respondents 1 and 2 and the learned counsel
appearing for the 3rd respondent.
10. The petitioner responded to Ext.P1 notice of
tender. Clause 8 of Appendix A to Ext.P1 mandated that
Contractor shall be listed with MES in Class A and above. Note
1 below the Appendix stated that in case after opening of Cover
1, the number of MES enlisted Contractors of eligible Class as
well as unlisted Contractors, if any, fulfilling the other eligibility 2025:KER:39435
criteria given in NIT is less than 7, applications in respect of
MES Contractors one/two Class below the eligible Class shall
also be considered subject to fulfillment of other eligibility
criteria given in the NIT.
11. In response to Ext.P1, only two persons
submitted bids. As there were less than 7 Class A Contractors
who bid, the bid of the petitioner could have been considered.
However, a defaulted Contractor filed W.P.(C) No.27285/2023
before this Court and this Court passed an interim order and
directed to maintain status quo on risk and cost tender.
Therefore, the respondents could not open the price bid. The
two bidders were requested for extension of validity of their
offer. Though the petitioner submitted willingness, the other
bidder did not agree to extend the validity of the bid.
Consequently, there remained only one bid.
12. In the circumstances, respondents 1 and 2
re-published the tender. In the subsequent tender, there were 2025:KER:39435
11 bidders. Out of the 11 bidders, only 3 bidders were found
ineligible. As there were 7 bidders of the eligible Class A, the
petitioner's bid could not have been considered as the petitioner
is only a Class-C Contractor. It is in such circumstances that
respondents 1 and 2 did not consider the bid of the petitioner.
13. In the afore circumstances, I do not find any
illegality in Exts.P9 or P11. Judicial review in the matter of
tenders is confined to issues as to whether any illegality,
irrationality or procedural impropriety committed by the decision
making authority and to prevent arbitrariness and favouritism.
14. The rejection of the petitioner's tender as per
Ext.P9 is because he failed to produce document to establish
eligibility under Class A. As there were 8 Class A Contractors,
who submitted bids, the petitioner's bid could not have been
entertained. The writ court is not a court of appeal and it
cannot review the decision of the tendering authority, but only
the decision making process. This Court cannot declare the 2025:KER:39435
petitioner as a person qualified, when the tendering authority
found him ineligible.
The writ petition is therefore without any merit and it is
hence dismissed.
Sd/-
N. NAGARESH, JUDGE aks/03.06.2025 2025:KER:39435
APPENDIX OF WP(C) 23477/2024
PETITIONER'S EXHIBITS:
Exhibit-P1 TRUE COPY OF THE NOTICE OF RE-TENDER DATED 24.07.2023 ISSUED BY THE 1ST RESPONDENT
Exhibit-P2 TRUE COPY OF APPLICATION DATED 25-09- 2023 SUBMITTED BY THE PETITIONER BEFORE THE 1ST RESPONDENT
Exhibit-P3 TRUE COPY OF THE TECHNICAL BID OPENING SUMMARY PREPARED ON OPENING TECHNICAL BID ON 12-10-2023 Exhibit-P4 TRUE COPY OF REQUEST DATED 24-11-2023 ISSUED BY THE 1ST RESPONDENT TO THE PETITIONER Exhibit-P5 TRUE COPY OF CONCURRENCE DATED 07-12- 2023 SUBMITTED BY THE PETITIONER BEFORE THE 1ST RESPONDENT Exhibit-P6 TRUE COPY OF RETENDER ISSUED ON 05-02-
Exhibit-P7 TRUE COPY OF APPLICATION DATED 21-02- 2024 SUBMITTED BY THE PETITIONER BEFORE THE 1ST RESPONDENT Exhibit-P8 TRUE COPY OF WRITTEN COMPLAINT DATED 29.02.2024 SUBMITTED BY THE PETITIONER BEFORE THE 1ST RESPONDENT Exhibit -P9 TRUE COPY OF LETTER DATED 27.03.2024 REJECTING THE PETITIONER'S BID ISSUED BY THE 1ST RESPONDENT TO THE PETITIONER Exhibit-P10 TRUE COPY OF THE APPEAL AS PER APPEAL LETTER NO. MT/CENWKCH/101/03 DATED 02.04.2024 PREFERRED BY THE PETITIONER BEFORE THE 2ND RESPONDENT Exhibit-P11 TRUE COPY OF ORDER BEARING NO.
800001/GEN KOCHI/550/E8 DATED 27.06.2024 ISSUED BY THE 2ND RESPONDENT IN EXHIBIT P10 2025:KER:39435
Exhibit-P12 TRUE COPY OF THE UDYAM REGISTERING CERTIFICATE BEARING NO.UDYAM-KL-04-
0006560 DATED 20-08-2021
RESPONDENTS' EXHIBITS:
EXHIBIT R1(A) True copy of the relevant pages of the Military Engineer Services Notice of Tender dated 24-07-2023 Exhibit R1(B) True copy of the Tender Summary Report dated 27-03-2024 Annexure R3-A TRUE COPY OF THE FINANCIAL BID OPENING SUMMERY WITH RESPECT OF THE TENDER FOR THE COMPLETION OF INCOMPLETE WORKS FOR SETTING UP SINGLE OFFICERS' ACCOMMODATION AS A PART OF AUGMENTATION OF INFRASTRUCTURE AND FACILITIES IN INA EZHIMALA (PHASE II) UPLOADED IN THE WEBSITE ON 28/03/2025 Annexure R3-B TRUE COPY OF THE LETTER OF THE 1ST RESPONDENT DATED 28/03/2025
PETITIONER'S EXHIBITS:
Exhibit-P13 TRUE COPY OF THE COMMUNICATION OF THE 1ST RESPONDENT DATED 28/03/2025. Exhibit P14 TRUE COPY OF THE TECHNICAL EVALUATION SUMMERY DATED 28/03/2025.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!