Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Tech Sharp Engineers Pvt Ltd vs Bharat Petroleum Corporation Ltd
2025 Latest Caselaw 2851 Ker

Citation : 2025 Latest Caselaw 2851 Ker
Judgement Date : 24 January, 2025

Kerala High Court

Tech Sharp Engineers Pvt Ltd vs Bharat Petroleum Corporation Ltd on 24 January, 2025

OP(ATE) NO.2 OF 2025            1



                                                 2025:KER:6014


          IN THE HIGH COURT OF KERALA AT ERNAKULAM

                             PRESENT

         THE HONOURABLE MR.JUSTICE SYAM KUMAR V.M.

   FRIDAY, THE 24TH DAY OF JANUARY 2025 / 4TH MAGHA, 1946

                       OP(ATE) NO.2 OF 2025

PETITIONER:

         TECH SHARP ENGINEERS PVT LTD
         10/17, 1514, J BLOCK, ANNA NAGAR, CHENNAI
         (REPRESENTED BY DANNIE MATHEW, PROJECT DIRECTOR),
         AGED 50, PIN - 600040

         BY ADVS.
         ABRAHAM JOSEPH MARKOS
         ISAAC THOMAS
         P.G.CHANDAPILLAI ABRAHAM
         ALEXANDER JOSEPH MARKOS
         JOHN VITHAYATHIL


RESPONDENT:

         BHARAT PETROLEUM CORPORATION LTD.
         POST BAG NO.2, AMBALAMUGAL,
         ERNAKULAM, KERALA, PIN - 682302

         BY ADV.SRI.M.GOPIKRISHNAN NAMBIAR, SC


     THIS OP(ARBITRATION TIME EXTENSION) HAVING COME UP FOR
ADMISSION ON 24.01.2025, THE COURT ON THE SAME DAY DELIVERED
THE FOLLOWING:
 OP(ATE) NO.2 OF 2025               2



                                                           2025:KER:6014




                             JUDGMENT

Dated this the 24th day of January, 2025

This O.P.(ATE) is filed invoking Section 29A of the Arbitration

and Conciliation Act, 1996 (hereinafter referred to as "the Act"),

seeking to extend the Arbitrator's mandate.

2. This Court had vide order dated 14.10.2022 in

A.R.No.98 of 2022 appointed an Arbitrator to adjudicate and

resolve the disputes and differences between the petitioner and

the respondent. It is submitted that arbitration had commenced

before the learned Arbitrator thus appointed and the pleadings in

terms of Section 23 (4) of the Act were completed on 28.07.2023.

The arbitral award was to be rendered by 28.07.2024 as

stipulated in Section 29A(1) of the Act. However, due to the

complex nature of arbitration proceedings and the voluminous

pleadings and evidence involved, the proceedings could not be

completed within the stipulated time. Hence the parties by mutual

consent extended the time for 6 more months that is till

28.01.2025. It is stated that now the evidence is complete and

2025:KER:6014

all that remains is the final arguments of both sides and rendering

of the award. Since it is certain that it will not be possible to

conclude the arbitration proceedings and render the award within

the stipulated time, O.P.(ATE) is filed seeking an extension of time

from 28.01.2025 to 28.07.2025.

3. Heard Sri.Abraham Joseph Markos, Advocate for the

petitioner and Smt.Pooja Menon, Advocate for the respondent.

4. The counsel are ad idem regarding the extension

sought and concurs that the time period can be extended as

requested.

5. In the course of hearing, however, it is pointed out

that the Hon'ble Supreme Court in Chief Engineer (NH) PWD

(Roads) v. BSC&C and C JV (2024 SCC Online SC 1801) has,

while disposing an SLP filed challenging the Judgment and order

of the High Court of Meghalaya dismissing a Section 29 A petition

inter alia pointing out that it did not possess Original Civil

Jurisdiction, held as follows:

"In this case, the High Court does not have the ordinary original civil jurisdiction. The power under Sub-Section (6) of Section 29A is only a consequential power vesting in the Court which is

2025:KER:6014

empowered to extend the time. If the Court finds that the cause of delay is one or all of the arbitrators, while extending the time, the Court has power to replace and substitute the Arbitrator(s). The said power has to be exercised by the Court which is empowered to extend the time as provided in sub-Section (4) of Section 29A of the Arbitration Act."

6. In the light of the above dictum laid down by the

Hon'ble Supreme Court, doubt is raised regarding the

maintainability of application filed under Section 29 A of the Act

before this Court, especially since this Court, like the High Court

of Meghalaya, does not possess Original Civil Jurisdiction. The

term 'Court' as used in Section 29A(4) in contradistinction to the

term 'High Court' as used in Section 11 (3A) is highlighted by the

counsel for the respondent as a pointer to the legislative intent

that the power to extend the time period has been conferred on

the 'Court' as defined in Section 2 (1) (e) (i) of the Act ie., the

Principal Civil Court having original jurisdiction in the District

having competence to decide questions forming the subject

matter of the arbitration and not on this Court.

7. I note that the very same question regarding

maintainability was considered in extenso by this Court in Kauser

2025:KER:6014

Fathima v. Asset Homes Pvt. Ltd. [Arb.P.No.2 of 2024 dated

12.09.2024]. Taking note of the above-quoted observation of the

Hon'ble Supreme Court in Chief Engineer (NH) (supra), this

Court had in Kauser Fathima (supra) concluded as follows:

3. The counsel for the petitioner submitted that the power to extend the mandate contained in Section 29A (4) available to this Court has not been taken away by the judgment of the Hon'ble Supreme Court. It is pointed out that the Supreme Court was considering a Special Leave to Appeal filed against the judgment of the High Court of Court of Meghalaya has been placed before me, from which it is seen that the Court was considering the extension of the mandate in a case where the Arbitrator was not appointed under Section 11(6) of the Act. After detailed consideration of the mode of appointment of the Arbitrator, the High Court of Meghalaya held that since it was a case where the Arbitrator was not appointed by invoking the power under Section 11(6) of the Act, the Principal Civil Court of original jurisdiction alone can exercise the power under Section 29A(4). The court specifically considered the anomalous situation which would arise if a substitution has to be made by the Principal Civil Court in a case where the Arbitrator was appointed by the High Court under Section 11(6). The Supreme Court affirmed the judgment of the Meghalaya High Court and in doing so, made the observation above referred.

XXX The counsel for the petitioner also placed before me an order on reference made by a Division Bench of the High Court of Bombay in Sheela Chowgule vs. Vijay V. Chowgule and Ors (Writ Petition No.88 of 2024 MANU/MH/5153/2024) when a similar situation was faced by the court. After considering the judgments on the issue, the Court held that a contextual interpretation is required since the word "Court" defined under Section 2(1)

(e) specifically says that the definition as "unless

2025:KER:6014

the context otherwise requires" the court held that in a case where the Arbitrator is appointed by the High Court under Section 11(6) there is a different context which requires a different meaning to be attributed to the meaning of the word "Court". It was hence held that in the event an Arbitral Tribunal constituted by the High Court under Section 11(6) fails to complete the proceedings within the stipulated period/extended period, then an application under Section 29A(4) would lie to the High Court in case of a domestic arbitration. I am in respectful agreement with the above view.

8. I respectfully concur with the view expressed in

Kauser Fathima's case (supra). Further, the question of whether

the term "court" contained in Section 29A(4) requires a contextual

interpretation apart from the meaning contained in Section 2(1)(e)

(i) of the Act. has been answered by a Division Bench of this Court

in Lots Shipping Company Ltd. v. Cochin Port Trust [2020

(2) KLT 907] holding that a contextual interpretation is clearly

permissible in view of the rider contained in sub-section (1) of

Section (2), which reads, "unless the context otherwise requires".

Moreover, the Judgment of the Hon'ble Supreme Court in Chief

Engineer (NH) (supra) does not restrict or take away power

vested in this court by Section 29A (4) since unlike in Chief

Engineer (NH) (supra) the Arbitrator whose mandate is sought

2025:KER:6014

to be extended in the above O.P.(ATE) was in fact appointed by

this Court and hence this Court retains the power to extend time

of the arbitral Tribunal that it had appointed. The above O.P.(ATE)

is thus maintainable and can be entertained by this Court.

9. In view of the above, this Original Petition is

allowed and the mandate of the learned Arbitrator is as

requested, extended from 28.01.2025 to 28.07.2025.

O.P.(ATE) is disposed of accordingly.

Sd/-

SYAM KUMAR V.M. JUDGE csl

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter