Citation : 2025 Latest Caselaw 4625 Ker
Judgement Date : 28 February, 2025
1
W.P(C) Nos.39941 of 2018
and 7129 of 2018 2025:KER:16595
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE HARISANKAR V. MENON
FRIDAY, THE 28TH DAY OF FEBRUARY 2025 / 9TH PHALGUNA, 1946
WP(C) NO.39941 OF 2018
PETITIONER:
M/S.ROHINI FACILITY MANAGEMENT SERVICES,
REVENUE TOWER, B18, NEAR BOAT JETTY, ERNAKULAM,
COCHIN-682011, REPRESENTED BY PROPRIETOR, A.D. GIREESH,
AGED 44, S/O. DHARMAN, ALLAPARAMBIL, CHERAI,
PALLIPPURAM VILLAGE, KOCHI TALUK, ERNAKULAM DISTRICT.
BY ADV.VARGHESE C.KURIAKOSE
RESPONDENTS:
1 STATE OF KERALA,
REPRESENTED BY CHIEF SECRETARY, SECRETARIAT,
MAHATHMA GANDHI ROAD JUNCTION, STATUE ROAD,
PALAYAM, THIRUVANANTHAPURAM, KERALA-695001.
2 THE SECRETARY, DEPARTMENT OF PUBLIC WORKS,
SECRETARIAT, MAHATHMA GANDHI ROAD JUNCTION,
STATUE ROAD, PALAYAM, THIRUVANANTHAPURAM,
KERALA-695001.
3 THE LAND REVENUE COMMISSIONER,
STATE OF KERALA, PUBLIC OFFICE BUILDING,
MUSEUM ROAD, OPPOSITE ZOO, VIKHAS BHAVAN P.O.,
THIRUVANANTHAPURAM, KERALA-695033.
4 THE DISTRICT COLLECTOR, ERNAKULAM DISTRICT,
CIVIL STATION, KAKKANAD, KOCHI-682030.
5 THE DEPUTY TAHASILDAR (RR).
KOCHI TALUK, FORT KOCHI-682001.
2
W.P(C) Nos.39941 of 2018
and 7129 of 2018 2025:KER:16595
6 THE ROADS AND BRIDGES DEVELOPMENT CORPORATION OF
KERALA LTD., 2ND FLOOR, PREETHI BUILDING, M.V. ROAD,
PALARIVATTOM, KOCHI-682025, REPRESENTED BY ITS MANAGING
DIRECTOR.
BY SENIOR GOVERNMENT PLEADER, SRI.E.G.GORDEN
SRI.VIPIN P.VARGHESE
SRI.ADARSH MATHEW
SRI.DILJITH K.MANOHAR
SMT. DHANYA T MALLAR
RESMITHA.R.CHANDRAN, STANDING COUNSEL
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 20.02.2025,
ALONG WITH WP(C).7129/2018, THE COURT ON 28.02.2025 DELIVERED THE
FOLLOWING:
3
W.P(C) Nos.39941 of 2018
and 7129 of 2018 2025:KER:16595
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE HARISANKAR V. MENON
FRIDAY, THE 28TH DAY OF FEBRUARY 2025 / 9TH PHALGUNA, 1946
WP(C) NO. 7129 OF 2018
PETITIONER:
A.D. GIREESH, AGED 42 YEARS,
S/O.DHARMAN A.R., ALLAPARAMBIL HOUSE, CHERAI P.O.,
PIN-683514, PROPRIETOR, ROHINI FACILITY MANAGEMENT
SERVICES, ROHINI TOWER, B-18, NEAR BOAT JETTY,
ERNAKULAM, KOCHI-682011.
BY ADVS.
SRI.VARGHESE C.KURIAKOSE
SRI.P.J.JOSE
SMT.SEENU SADIQUE
RESPONDENTS:
1 STATE OF KERALA, REP. BY SECRETARY, PUBLIC WORKS
DEPARTMENT, SECRETARIAT, THIRUVANANTHAPURAM-695001.
2 THE PRINCIPAL SECRETARY, PUBLIC WORKS DEPARTMENT,
THIRUVANANTHAPURAM-695001.
3 THE ROADS AND BRIDGES DEVELOPMENT,
CORPORATION OF KERALA, PALARIVATTOM,
REP. BY ITS MANAGING DIRECTOR-682024.
BY SMT.RESMITHA.R.CHANDRAN, STANDING COUNSEL
BY SRI.E.G.GORDEN, SENIOR GOVERNMENT PLEADER
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 20.02.2025,
ALONG WITH WP(C).39941/2018, THE COURT ON 28.02.2025 DELIVERED THE
FOLLOWING:
4
W.P(C) Nos.39941 of 2018
and 7129 of 2018 2025:KER:16595
JUDGMENT
[W.P(C) Nos.39941/2018 and 7129/2018]
These two writ petitions are filed challenging the steps
taken by the 6th respondent Corporation in W.P(C)No.39941
of 2018 (3rd respondent in W.P(C)No.7129 of 2018) with
respect to the dispute over the user fee collection at the
overbridges at S.N junction, Tripunithura-Irumpanam in the
Seaport-Airport road and Ponnurunni overbridge
respectively.
2. The petitioner in W.P(C)No.39941 of 2018 states
that he was the successful bidder for the collection of user
fee on contract basis on the overbridges noticed above,
awarded by the 6th respondent - a Government of Kerala
undertaking. The total amount payable by the petitioner was
to the extent of Rs.3,67,20,000/-, in 24 installments
commencing from 01.06.2014 and ending by 16.05.2015.
The contract was for a period of one year from 01.06.2014
and 7129 of 2018 2025:KER:16595
to 01.06.2015. A bank guarantee for Rs.93,63,600/- is
stated to have been furnished towards the security deposit.
The petitioner contends that they were not in a position to
collect the user fee on account of agitation by the regional
residents associations and the local politicians, according to
whom, more than sufficient collection compared to the cost
of construction has already been made. On account of the
afore, the petitioner states that he could not effect the
installments as stipulated. The petitioner states that though
he filed a writ petition seeking police protection, during the
pendency of the same, the 6th respondent Corporation, as
per Ext.P1 dated 16.08.2014, terminated the contract. The
petitioner states that they submitted a detailed
representation to the 6th respondent pointing out the
difficulties faced by them. However, the respondent
Corporation invoked the bank guarantee submitted by the
petitioner. The petitioner also approached the Government
and 7129 of 2018 2025:KER:16595
voicing his grievance and the same was rejected by the
Government. The said rejection was the subject matter for
challenge in W.P(C)No.3022 of 2015 filed by the petitioner,
which stood disposed of by judgment dated 26.10.2016,
noticing that the impugned order was issued by the
Managing Director of the respondent Corporation at that
point of time, who was also holding the charge of the
Secretary to the Government. This Court noticing that the
encashment of the bank guarantee was made without a
proper adjudication and consequential quantification of
liability, permitted the petitioner to make a motion to that
effect to the Government, further directing the Government
to take a decision on the matter after obtaining legal advice
from the Law Department, if found necessary.
3. The Government thereafter issued Ext.P9 dated
28.08.2017 and found that the amount realized by invoking
the bank guarantee was required to be refunded to the
and 7129 of 2018 2025:KER:16595
petitioner on "humanitarian reasons". It may straight away
be noticed that the order recorded that the petitioner was
not able to collect the user fee on account of the public
outcry.
4. The afore order of the Government was
challenged by the respondent Corporation by filing
W.P(C)No.29860 of 2017, essentially on the ground that out
of the security deposit encashed-Rs.93,63,600/-, an amount
of Rs.47,42,400/- has been adjusted to the installments
defaulted by the petitioner prior to termination of the
contract and it is the balance of Rs.45,79,420/-, that need to
be refunded to the petitioner. However, by Ext.P11 judgment
dated 10.10.2017, that writ petition was withdrawn by the
respondent Corporation unconditionally. Later, notice dated
29.06.2018 was issued seeking to recover the installments
defaulted till the termination of the contract to which the
petitioner submitted Ext.P13 reply, that nothing remains to
and 7129 of 2018 2025:KER:16595
be recovered from the petitioner in the light of Ext.P9
Government Order dated 28.08.2017. The respondent
Corporation has thereafter sought to realize the afore arrears
through revenue recovery proceedings by Exts.P16 and P17.
It is in the afore circumstance that W.P(C)No.39941 of 2018
is filed.
5. W.P(C)No.7129 of 2018 is filed by the petitioner
contending that he was the successful bidder for the
collection of user fee on a contract basis from the Ponnurunni
overbridge, that no collection could be effected on account
of the public uproar as in the other case. When it was
pointed out, the respondent Corporation sought to cancel the
agreement upon the petitioner consenting to the same by
Ext.P6 dated 14.11.2014, without endorsing the risk and cost
liability allowing an amount of Rs.4,60,571/- to the
petitioner, however, adjusting the afore amount to the
alleged dues payable with respect to the overbridges which
and 7129 of 2018 2025:KER:16595
are the subject matter of the dispute in the connected case.
The petitioner has sought a refund of the afore amounts
through this writ petition.
6. I have heard Sri. Varghese C. Kuriakose, the learned
counsel for the petitioners, Smt. Resmitha R. Chandran, the
learned Standing Counsel for the respondent Corporation
and Sri. E.G. Gorden, the learned Senior Government
Pleader for the State.
7. The following issues arise for consideration in these
writ petitions: -
i. Whether the petitioner can maintain a challenge
against the recovery proceedings through a writ
petition filed under Article 226 of the Constitution
of India in the facts and circumstances of the case?
ii. Whether the respondent Corporation is entitled to
take steps to realize the alleged defaulted arrears
of installments in the light of the findings in Ext.P9
and 7129 of 2018 2025:KER:16595
Government Order?
8. The first issue arising for consideration in these writ
petitions is with reference to the maintainability of the writ
petitions. Smt. Resmitha, the learned counsel for the
respondent Corporation relied on the judgment of the Apex
Court in Joshi Technologies International Inc. v. Union
of India and Others [(2015) 7 SCC 728]. True, the afore
judgment of the Apex Court held that writ jurisdiction of High
Court was not intended to facilitate avoidance of contractual
obligation. However, in the case at hand, the contention
raised by the petitioner is to the effect that the liability, if any
of the petitioner stood governed by the orders issued by the
Government at Ext.P9 dated 28.08.2017 and on the face of
the afore, the respondent Corporation cannot proceed to
invoke the power under the Kerala Revenue Recovery Act,
1968, for realization of the alleged defaulted installments. In
other words, the case of the petitioner is centered around
and 7129 of 2018 2025:KER:16595
the scope of Ext.P9 Government Order. The prayer in the
writ petition is also with reference to the proposal to realize
the defaulted installments on the face of Ext.P9, and when
that be so, I am of the opinion that the petitioner can
maintain a writ petition challenging the coercive
proceedings. Therefore, the first objection raised by Smt.
Resmitha is only to be recorded and rejected.
9. The second issue arising for consideration is with
reference to the steps taken to realize the alleged defaulted
installments by the respondent Corporation under the Kerala
Revenue Recovery Act, 1968. The amount sought to be
realized is the arrears of installments till termination of the
contract, is clear from a perusal of Ext.P12.
10. The learned counsel Smt.Resmitha relied on clauses
3.18 and 3.19 of Ext.R6(1) agreement executed between the
parties to contend that once there is a default, the
respondent Corporation is at liberty to recover the loss. She
and 7129 of 2018 2025:KER:16595
would also rely on clause 3.12 to contend that the petitioner
cannot plead ignorance of the ground realities, with
reference to the public protest pointed out by the petitioner.
11. I have considered the afore contention. True, clause
3.12 of Ext.R6(1) agreement reads as under:-
"3.12 Contractor has to make all arrangements other than what are existing at the tollbooths for the smooth running of user fee collection at his own expense. RDBCK has no liability in this regard."
Therefore, it is for the petitioner to make arrangements for
the smooth running of the toll booth. The petitioner has
contended that when obstruction was created, they had
approached this Court seeking police protection and it was at
that point, the agreement was terminated. In this
connection, I notice the dictum laid down by the Apex court
in ABL International Ltd. and Another v. Export Credit
Guarantee Corporation of India Ltd. and Others
[(2004) 3 SCC 553] wherein it is held that when the State
and 7129 of 2018 2025:KER:16595
or its instrumentality is a party to a contract, it has an
obligation to act fairly, justly and reasonably with reference
to the requirement under Article 14 of the Constitution. It is
in the light of the afore principles that in the proceedings at
Ext.P9 the existence of the public outcry, as pointed out by
the petitioner, which prevented him from making the toll
collection, is found correct. In the light of the afore, the case
built up by the respondent Corporation with reference to
clauses 3.12 and 3.19, does not appear to be convincing.
12. It is also to be noticed that under clause 3.19, once
there is a default in payment of the installments as stipulated
in clause 3.17, the work can be rearranged at the risk and
cost for the petitioner and the loss if any sustained by the
respondent Corporation can be recovered from either the
security deposit or by revenue recovery action. In the case
at hand, along with termination of the contract, the entire
amount of security deposit is seen realized from out the bank
and 7129 of 2018 2025:KER:16595
guarantee furnished by the petitioner. Therefore, the
respondent Corporation has invoked the provisions of clause
3.19 against the petitioner. But the Government intervened,
taking note of the special circumstance, which, according to
the Government, requires the application of "humanitarian
reasons", ordering the entire security deposit of
Rs.92,63,600/- to be returned to the petitioner. In the light
of the afore, I am of the opinion that the Government has
thought it as a fit case not to invoke clause 3.19 of the
agreement. When the Government directs a fixed deposit to
be returned back to the petitioner even after the same being
invoked, there cannot be a separate recourse to the revenue
recovery proceedings under clause 3.19.
13. From the afore, I notice that the respondent
Corporation was also aware that there cannot be any further
proceedings against the petitioner in the light of Ext.P9 order
and that is why W.P(C)No.29860 of 2017 was filed by them
and 7129 of 2018 2025:KER:16595
challenging the Government Order at Ext.P9. However, the
afore writ petition was withdrawn by the respondent
Corporation themselves and in the light of the afore, there
cannot be any further proceedings against the petitioner. In
this connection, I take note of the contention raised by the
learned counsel Smt. Resmitha, with reference to Ext.R6(a)
communication of the Government dated 16.05.2018,
whereby the Government informed the respondent
Corporation that the default amount may be dealt with as
per the Rules of the company. However, I notice that the
afore communication has not been issued with specific
reference to the Government Order at Ext.P9 dated
28.08.2017 and that the petitioner was also not heard while
issuing the same. Therefore, I am of the opinion that much
reliance can't be placed on the said communication as
contended by the respondent Corporation.
and 7129 of 2018 2025:KER:16595
14. I also notice that the Government issued Ext.P9
with specific reference to the directions contained in
W.P(C)No.3022/2015. A reading of the afore judgment would
make it clear that this Court directed the Government to
consider the rival contentions/entitlements/liability in their
entirety taking note of the factual and legal issues.
Considering the aforementioned, the findings in Ext.P9 can
only be one rendered by the Government with respect to the
liability of the petitioner for the default in installments as well
as the entitlement to get back the security deposit.
15. Furthermore, if the contention raised by the
respondent Corporation is to be accepted, then it has to be
held that the extension of the humanitarian grounds can only
be for the claim of realization of security deposit and not for
realization of the defaulted installments. As already noticed,
the security deposit is furnished for safeguarding the
defaulted installments also.
and 7129 of 2018 2025:KER:16595
16. Therefore, I hold that the respondent Corporation is
not entitled to initiate revenue recovery proceedings for
realization of the defaulted installments, in the light of the
findings contained in Ext.P9. I also notice that as regards
the Ponnurunni overbridge, the subject matter of
W.P(C)No.7129 of 2018, admittedly, no amount towards
risk/cost is sought to be demanded from the petitioner.
When that be so, it is only just and proper that the same
yardstick is applied as regards the dispute involved in the
other case also.
17. In the light of the afore, the attempt of the
respondent Corporation to adjust the amount of
Rs.4,60,571/- as per the impugned order at Ext.P9 in
W.P(C)No.7129 of 2018 is also to be declared illegal and
arbitrary.
In the result, these writ petitions are disposed of as
under:
and 7129 of 2018 2025:KER:16595
i. W.P(C)No.39941 of 2018 is allowed by setting aside
Exts.P16 and P17 issued by the 5th respondent.
ii. W.P(C)No.7129 of 2018 is allowed by setting aside
Ext.P9 order issued by the 3rd respondent, to the
extent an amount of Rs.4,60,571/- is sought to be
adjusted towards the alleged liability payable by the
petitioner.
Sd/-
HARISANKAR V. MENON, JUDGE
ln
and 7129 of 2018 2025:KER:16595
APPENDIX OF WP(C) 7129/2018
PETITIONER'S EXHIBITS:
EXHIBIT P1 TRUE PHOTOCOPY OF THE WORK ORDER DATED 30-01-2014.
EXHIBIT P2 TRUE PHOTOCOPY OF THE AGREEMENT DATED 31-01-2014.
EXHIBIT P3 TRUE PHOTOCOPY OF THE RECEIPT DATED 31-01-2014
ISSUED BY THE 3RD RESPONDENT.
EXHIBIT P4 TRUE PHOTOCOPY OF THE RECEIPT ISSUED BY THE 3RD
RESPONDENT.
EXHIBIT P5 TRUE PHOTOCOPY OF THE REPLY DATED 25-10-2014.
EXHIBIT P6 TRUE PHOTOCOPY OF THE LETTER DATED 14-11-2014.
EXHIBIT P7 TRUE PHOTOCOPY OF THE JUDGMENT DATED 26-10-2016 IN
WP(C)NO.3022/2015 PASSED BY THIS HONOURABLE COURT.
EXHIBIT P8 TRUE PHOTOCOPY OF THE ORDER PASSED BY THE GOVT. ON 28-08-2017.
EXHIBIT P9 TRUE PHOTOCOPY OF THE REPLY NOTICE DATED 22-12- 2017.
EXHIBIT P10 TRUE PHOTOCOPY OF THE REPLY NOTICE DATED 30-01- 2018.
EXHIBIT P11 TRUE PHOTOCOPY OF THE PETITION TO THE 1ST RESPONDENT ON 18-12-2017.
RESPONDENTS' EXHIBITS:
EXHIBIT R3(A) PHOTOSTAT COPY OF AGREEMENT EXECUTED BETWEEN THE WRIT PETITIONER AND MANAGING DIRECTOR, ROADS & BRIDGES DEVELOPMENT CORPORATION OF KERALA LTD.
DATED 31.1.2014
and 7129 of 2018 2025:KER:16595
APPENDIX OF WP(C) NO.39941/2018
PETITIONER'S EXHIBITS:
EXHIBIT P1 TRUE PHOTOSTAT COPY OF THE NOTICE OF
TERMINATION DATED 16/08/2014 SERVED ON 20/08/2014.
EXHIBIT P2 TRUE PHOTOSTAT COPY OF THE OBJECTION FILED BY THE PETITIONER.
EXHIBIT P3 TRUE PHOTOSTAT COPY OF THE REPRESENTATION DATED 23/10/2014.
EXHIBIT P4 TRUE PHOTOSTAT COPY OF THE INFORMATION COLLECTED ON 03/07/2014.
EXHIBIT P5 TRUE PHOTOSTAT COPY OF THE INFORMATION COLLECTED ON 19/09/2013.
EXHIBIT P6 TUE PHOTOSTAT COPY OF THE REPRESENTATION DATED 24/10/2014 SUBMITTED BY THE PETITIONER BEFORE 2ND RESPONDENT.
EXHIBIT P7 TRUE PHOTOSTAT COPY OF THE JUDGMENT DATED 05/11/2017 IN WPC NO.29025/2014 IF THIS HON'BLE COURT.
EXHIBIT P8 TRUE PHOTOSTAT COPY OF THE JUDGMENT DATED 26/10/2016 IN WPC NO.3022/2015.
EXHIBIT P9 TRUE PHOTOSTAT COPY OF THE ORDER DATED 28/08/2017 PASSED BY THE 2ND RESPONDENT.
EXHIBIT P10 TRUE PHOTOSTAT COPY OF THE WRIT PETITION FILED AS WPC NO.29860/2017 WITHOUT EXHIBITS.
EXHIBIT P11 TRUE PHOTOSTAT COPY OF THE JUDGMENT DATED 10/10/2017 IN WPC NO.29860/2017.
EXHIBIT P12 TRUE PHOTOSTAT COPY OF THE LETTER DATED and 7129 of 2018 2025:KER:16595
29/06/2018 WAS ISSUED TO THE PETITIONER.
EXHIBIT P13 TRUE PHOTOSTAT COPY OF THE OBJECTION DATED 02/07/2018 GIVEN BY THE PETITIONER.
EXHIBIT P14 TRUE PHOTOSTAT COPY OF THE REPLY DATED 14/08/2018 ISSUED BY THE 6TH RESPONDENT.
EXHIBIT P15 TRUE PHOTOSTAT COPY OF THE REPLY DATED 21/08/2018 GIVEN BY THE PETITIONER.
EXHIBIT P16 TRUE PHOTOSTAT COPY OF THE DEMAND NOTICE ISSUED UNDER SECTION 7 OF THE KERALA REVENUE RECOVERY ACT.
EXHIBIT P17 TRUE PHOTOSTAT COPY OF THE DEMAND NOTICE DATED 17/09/2018 ISSUED UNDER SECTION 34 OF THE KERALA REVENUE RECOVERY ACT.
EXHIBIT P18 TRUE PHOTOSTAT COPY OF THE APPEAL PETITION DATED 24/11/2018 FILED BY THE PETITIONER BEFORE THE 3RD RESPONDENT.
RESPONDENTS' EXHIBITS:
EXHIBIT R6(3) TRUE COPY OF THE PARTITION DEED NO. 127/2022 OF SUB REGISTRAR OFFICE, KUZHUPPULLY.
EXHIBIT R6(4) TRUE COPY OF THE LETTER SENT BY THE ANSWERING RESPONDENT TO THE 4TH RESPONDENT HEREIN ON 14/02/2023.
EXHIBIT R6(5) TRUE COPY OF THE WRIT PETITION IN WPC NO.
29768 OF 2021.
EXHIBIT R6(6) TRUE COPY OF THE JUDGMENT DATED 05/01/2022 IN WPC NO. 29768 OF 2021 .
EXHIBIT R6(7) TRUE COPY OF RECEIPT NO. 3404 DATED 05.05.2014 EVIDENCING THE PAYMENT OF RS.5,00,000/.
and 7129 of 2018 2025:KER:16595 EXHIBIT R6(8) TRUE COPY OF RECEIPT NO. 3423 DATED 20.05.2014EVIDENCING THE PAYMENT OF RS. 6,95,669/-.
EXHIBIT R6(9) TRUE COPY OF RECEIPT NO. 3434 DATED 30.05.2014 EVIDENCING THE PAYMENT OF RS.3,64,931/-.
EXHIBIT R6(10) TRUE COPY OF RECEIPT NO. 3470 DATED 17.07.2014 EVIDENCING THE PAYMENT OF RS. 10,00,000/-.
EXHIBIT R6(11) TRUE COPY OF RECEIPT NO.3493 DATED 05.08.2014 EVIDENCING THE PAYMENT OF RS. 5,00,000/-.
EXHIBIT R6(12) TRUE COPY OF THE EXTRACT OF THE RELEVANT PAGE OF THE CHEQUE REGISTER EVIDENCING THE RETURN OF AN AMOUNT OF RS. 92,79,627/- VIDE CHEQUE NO. 993659 DRAWN ON THE STATE BANK OF INDIA.
EXHIBIT R6(1)- TRUE COPY OF THE AGREEMENT DATED 30/05/2014 R6(1) 25 EXECUTED BY THE PETITIONER.
EXHIBIT R1(A) TRUE COPY OF THE LETTER NO.H2/192/2017/PWD DATED 16.05.2018.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!