Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

State Of Kerala vs The Cochin Malabar Estate And ...
2024 Latest Caselaw 32814 Ker

Citation : 2024 Latest Caselaw 32814 Ker
Judgement Date : 13 November, 2024

Kerala High Court

State Of Kerala vs The Cochin Malabar Estate And ... on 13 November, 2024

                                                      2024:KER:84046
L.A.A.No.469/2012                      1


             IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                 PRESENT

                    THE HONOURABLE MR. JUSTICE G.GIRISH

WEDNESDAY, THE 13TH DAY OF NOVEMBER 2024/22ND KARTHIKA, 1946

                          LA.APP. NO.469 OF 2012

          AGAINST THE       JUDGMENT & DECREE DATED 30.06.2011 IN

 LAR NO.60 OF 1985 OF ASSISTANT SESSIONS COURT/ADDITIONAL

                         SUB COURT, IRINJALAKUDA

APPELLANT/RESPONDENT:

               GOVERNMENT OF KERALA
               REPRESENTED BY DISTRICT COLLECTOR, AYYANTHOLE, THRISSUR


               BY ADV GOVERNMENT PLEADER

RESPONDENT/CLAIMANT:

               THE COCHIN MALABAR ESTATE AND INDUSTRIES LTD.
               VARANDARAPPILLY VILLAGE AND DESOM, MUKUNDAPURAM TALUK,
               REP. BY SENIOR GENERAL MANAGER PUSHKARAKSHAN. 680303.


               BY ADVS.
               SRI.P.BENNY THOMAS
               SRI.D.PREM KAMATH


     THIS LAND ACQUISITION APPEAL HAVING BEEN FINALLY
HEARD ON 06.11.2024, THE COURT ON 13.11.2024 DELIVERED THE
FOLLOWING:
                                                              2024:KER:84046
L.A.A.No.469/2012                           2


                                JUDGMENT

The Government of Kerala represented by the District

Collector, Thrissur has filed this appeal against the judgment dated

30.06.2011 of the Additional Sub Court, Irinjalakkuda in

L.A.R.No.60/1985.

2. The acquisition involved in the case was made under

the erstwhile Kerala Land Acquisition Act, 1961 for the purpose of

the Chimney Dam Project and staff colony. The land acquired was

in fact the land of the erstwhile Cochin Government leased out to

the Cochin Malabar Estate and Industries Limited. On the basis of

the notification issued under section 3(1) of the repealed Kerala

Land Acquisition Act, 1961, on 19.04.1977, the Land Acquisition

Officer passed an award dated 28.02.1981 granting compensation

for the yielding rubber trees cultivated in that property by the

claimant. The Acquisition Officer found that the claimant was

entitled for a total amount of compensation of Rs.70,951/- by

calculating the average yield from the rubber trees as 2.9 Kg and

the price at Rs.7.44/- per Kg. Though the claimant challenged the

above calculation of compensation, the only document relied on 2024:KER:84046

before the court below was the copy of the judgment of a Division

Bench of this Court in L.A.A.No.113/1987 in relation to similar

acquisition wherein it was found that the claimant in that case,

which is the very same claimant in the present case, was entitled to

compensation by reckoning the value of yields from the rubber

trees at the rate of Rs.9.82/- per Kg. Relying on the aforesaid

judgment, the learned Additional Sub Judge passed the impugned

award with the finding that the compensation has to be reckoned

for the 996 rubber trees planted in the year 1964 by applying the

multiplier of 20 as the expected future life period, and the

remaining 16 rubber trees planted in the year 1946 by applying the

multiplier of 2 as the future expected life period. In addition to the

above compensation, the learned Additional Sub Judge found that

the claimant was entitled to get 12% interest per annum from the

date of publication of the notification under section 3(1) to the date

of award of the District Collector, and also solatium @ 30% of land

value. Damages worth Rs.30/- per tree from each day from the

date of advance possession till the notice under section 3(1) was

also granted by the Reference Court.

2024:KER:84046

3. The main challenge raised by the appellant is that the

claimant is not entitled for the interest, solatium and other benefits

granted by the Reference Court. According to the appellant, the

claimants are disentitled for the benefits under the amended Land

Acquisition Act, 1894, since the award was passed prior to

30.04.1982. It is also contended that the period from 08.08.1991

to 28.06.2001 while a stay obtained by the claimant from this Court

was pending shall not be reckoned while calculating interest on the

compensation amount.

4. Heard the learned Government Pleader representing the

appellant and the learned counsel for the respondent.

5. The learned Government Pleader advanced an argument

that the benefits granted by the Reference Court are prima facie

unsustainable since no land belonging to the claimant was acquired

in this case and hence there cannot be any award of interest or

solatium on the land value. The argument in the above regard is

prima facie untenable in view of the definition of land under section

3(a) of the Land Acquisition Act, 1894 wherein it is provided that

the expression 'land' includes benefits to arise out of land, and 2024:KER:84046

things attached to earth or permanently fastened to anything

attached to the earth. The further contention of the learned

Government Pleader challenging the impugned award of the

Reference Court granting solatium as provided under Section 23(2)

and interest as provided under section 28 of the Land Acquisition

Act, 1894, is also prima facie unsustainable since the Land

Acquisition Amendment Act, 1984 makes it clear that the aforesaid

reliefs are to be granted to those acquisitions where the award of

the Land Acquisition Officer was passed even prior to 30.04.1982.

However, the challenge against the benefit of interest granted by

the Reference Court under section 23(1A) of the Land Acquisition

Act, 1894 is found sustainable in view of the specific exclusion,

under Act 68 of 1984, of the aforesaid benefit to those acquisition

proceedings where the award of the Land Acquisition Officer had

been passed prior to 30.04.1982.

6. The disentitlement of the benefits under section 23(1A)

of the Land Acquisition Act, 1894 in respect of those acquisitions

where the award was passed prior to 30.04.1982 has been upheld

by the Division Bench decisions of this Court in State of Kerala v.

2024:KER:84046

Mytheen Pillai [1996 (1) KLT 587] and Jayakumar and

Others v. State of Kerala [2016 (5) KHC 842]. However, in

both the decisions, the entitlement of the claimant for the benefits

under Section 23(2) and Section 28 of the Land Acquisition Act,

1894 are upheld.

7. The argument of the learned Government Pleader that

the period from 08.08.1991 to 28.06.2001 when there existed a

stay of proceedings as per the order of this Court, has to be

excluded while reckoning the interest on the compensation, cannot

be accepted since no such exclusions are provided for the reliefs to

which the claimant is entitled under Section 28 of the Land

Acquisition Act, 1894. In Ratti Ram v. Union of India and

Another [(2016) 11 SCC 110], the Apex Court has held that

there is no exclusion of any period contemplated on whatever

account under section 28 of the Act. It is further made clear in the

aforesaid decision that the only reference in that Section is to the

date of dispossession, and that the liability to pay interest starts to

run from that date onwards. Therefore, the contention of the

appellant for exclusion of the period of stay while charging the 2024:KER:84046

interest as provided under Section 28 of the Land Acquisition Act,

1894, has no legal basis.

8. In the light of the above discussions, it follows that the

award passed by the Additional Sub Court, Irinjalakkuda as per

judgment dated 30.06.2011 in L.A.R.No.60/1985 is liable to be

modified only to the extent of excluding the benefit of interest @

12% per annum granted on the compensation amount from the

date of notification to the date of award under section 23(1A) of the

Land Acquisition Act, 1894.

9. In the result, the appeal stands allowed in part

excluding the benefit of interest @ 12% per annum granted by the

learned Additional Sub Judge under section 23(1A) of the Land

Acquisition Act, 1894 to the compensation amount from the date of

notification till the date of award of the District Collector. In all

other respects, the award passed by the Reference Court by virtue

of its judgment dated 30.06.2011 stands upheld.

(Sd/-) G.GIRISH, JUDGE

jsr/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter