Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

P & C Projects Pvt Ltd vs M/S. Inkel Limited
2024 Latest Caselaw 32655 Ker

Citation : 2024 Latest Caselaw 32655 Ker
Judgement Date : 12 November, 2024

Kerala High Court

P & C Projects Pvt Ltd vs M/S. Inkel Limited on 12 November, 2024

                                                2024:KER:83950
A.R.No.114/2024                     1


           IN THE HIGH COURT OF KERALA AT ERNAKULAM

                           PRESENT

              THE HONOURABLE MR. JUSTICE G.GIRISH

  TUESDAY, THE 12TH DAY OF NOVEMBER 2024 / 21ST KARTHIKA,

                             1946

                      AR NO. 114 OF 2024

PETITIONER:

            P & C PROJECTS PVT LTD.
            P & C TOWERS, 2ND FLOOR 140, PERUNDURAI ROAD, ERODE,
            REPRESENTED BY ITS GENERAL MANAGER CONTRACTS AND
            AUTHORIZED SIGNATORY MR. M.A SYED SIRAJUDEEN, PIN -
            638011


            BY ADVS.
            NISHA GEORGE
            GEORGE POONTHOTTAM (SR.)


RESPONDENT:

            M/S. INKEL LIMITED
            DOOR NO.7/473 ZA-5 AND 6 AJIYAL COMPLEX, POST OFFICE
            ROAD KAKKANAD, COCHIN, REPRESENTED BY ITS MANAGING
            PLEADER SHRI. A.MOHAN LAL, PIN - 682030


            BY ADV P.U.SHAILAJAN

     THIS ARBITRATION REQUEST HAVING COME UP FOR ADMISSION
ON 05.11.2024, THE COURT ON 12.11.2024 DELIVERED THE
FOLLOWING:
                                                        2024:KER:83950
A.R.No.114/2024                       2




                         G.GIRISH, J.
                         ---------------
                     A.R.No.114 of 2024
                 ------------------------------
       Dated this the 12th day of November, 2024
        -----------------------------------------------

                            ORDER

The applicant, a company registered under the Companies

Act, 1956, has filed this application under Section 11(6) of the

Arbitration and Conciliation Act, 1996 (for short 'the Act') for

the appointment of a sole Arbitrator to adjudicate the disputes

between the applicant and the respondent in terms of Clause 25

of Annexure-A3 agreement executed in between them on

06.08.2018.

2. As per Annexure-A3 agreement, the applicant

undertook the work for developing and constructing the flagship

project of Cochin Cancer Research Centre, Ernakulam funded by

the Kerala State Infrastructural Investment Fund Board (KIIFB).

The period initially fixed for the completion of the project was

730 days from the date of handing over of the project site.

However, the applicant was not able to complete the project

within the above stipulated time due to the reasons which, 2024:KER:83950

according to the applicant, amounted to force majeure. At the

request of the applicant, the period for completion of the

project was said to have been extended to 949 days. Even

after the expiry of the extended period, the applicant was not

able to complete the project as undertaken in the agreement

executed between the parties. Thereafter, the respondent,

pursuant to show cause notices issued to the applicant,

terminated the contract stating the reason that the explanations

offered by the applicant were unsatisfactory. The applicant

challenged the aforesaid termination unsuccessfully by filing

W.P.(C) No.2200/2021 and W.A.No.905/2021 before this Court.

Pursuant to the dismissal of S.L.P (C) No.5672/2022 which the

applicant filed before the Supreme Court against the judgment

in W.A.No.905/2021, Arbitration Request No.115/2022 was filed

before this Court under Section 11(6) of the Act. This Court, as

per Annexure-A28 order dated 10.08.2022 observed that the

final bill submitted by the applicant has to be considered by the

Dispute Redressal Committee as provided under Clause 25 of

Annexure-A3 agreement, and accordingly disposed of the

Arbitration Request without prejudice to the rights of the

applicant to seek the appointment of an Arbitrator at a later 2024:KER:83950

stage, if so warranted. It is the grievance of the applicant that

even the Dispute Redressal Committee constituted by the

respondent, after much persuasion, did not take any effective

steps to redress his grievance. Accordingly, the applicant

issued Annexure-A49 letter to the respondent invoking the

Arbitration Clause contained in Annexure-A3 agreement

suggesting the respondent to choose one among the three

Arbitrators mentioned in that letter for the resolution of the

disputes which arose in connection with the agreement between

the parties. Alleging non co-operation on the part of the

respondent to have the dispute resolved through the mode of

arbitration provided under Annexure-A3 agreement, the

applicant has filed the present Arbitration Request.

3. The respondent appeared through their counsel and

filed a counter affidavit strongly disputing the entitlement of the

applicant to seek the appointment of an Arbitrator. According to

the respondent, the applicant was delaying the work from the

very beginning itself, and it could not be completed even after

the respondent granted extension of period to 949 days from

the initial period of 730 days originally fixed. It is also alleged 2024:KER:83950

that the work carried out by the applicant was of poor quality.

According to the respondent, the contract was terminated due

to the failure of the respondent to complete even a substantial

portion of the work within the extended period. The respondent

also stated in the counter affidavit that all the issues raised by

the applicant in connection with the claim for arbitration had

already been considered and rejected by this Court in the writ

petition and the writ appeal filed by the applicant. It is further

contended that the petitions filed by the applicant before the

Commercial Court, Ernakulam in C.M.A (Arb) No.546/2021 were

dismissed by the said court accepting the contentions of the

respondent in the counter affidavit filed by them. As regards

the proceedings of the Dispute Redressal Committee, the

respondent stated that the said Committee had conducted five

meetings with a view to redress the grievance of the applicant.

It is thus stated that in the last sitting of the DRC held on

02.12.2023, it was resolved that all the claims placed by the

applicant in the final bill, as well as the statutory deductions

and compensation payable to the respondent for the delay in

the completion of the project etc., are to be determined at the

time of final settlement, and that there shall be no further 2024:KER:83950

claims from the applicant in connection with the

materials/plant/equipments lying in the project site since the

applicant has been allowed to take such

materials/plant/equipments etc. at its own risk and cost. By

adverting to Clause 25 of Annexure-A3, the respondent would

contend that there is no scope for appointment of Arbitrator

since the Dispute Redressal Committee had already dealt with

the issue and resolved that the claims of the applicant are to be

considered at the time of final settlement. Thus, it is stated

that the Arbitration Request is premature since it could be

resorted to only after the DRC takes a final decision.

4. Heard the learned Senior Counsel Adv.Mr.George

Poonthottam appearing for the applicant under instructions

from Adv.Mrs.Nisha George, and Adv.Mr.P.U.Shailajan, the

learned counsel for the respondent.

5. The fact that the applicant and the respondents had

entered into Annexure-A3 agreement which provides for the

resolution of the disputes arising between the parties in

connection with the said agreement by resorting to arbitration

as provided under Clause 25 of the said agreement, is not in 2024:KER:83950

dispute. The contention of the respondent is that the provisions

contained in Clause 25 regarding the appointment of Arbitrator

could be resorted to only when the DRC fails to give its decision

within the period prescribed thereunder or when any of the

parties are dissatisfied with the decision of the DRC. Thus, it is

stated that the DRC constituted in this case had rendered

Annexure-R1(ad) decision to have the claims raised by the

applicant determined at the time of final settlement after the

completion of the project. Accordingly, it is contended that the

applicant is entitled to seek the appointment of an Arbitrator

only after the completion of the project by the new company

entrusted with the task by the respondent. It is the further

contention of the respondent that Annexure-A49 letter cannot

be considered as a valid notice since even after the said letter

of the applicant, two sittings were conducted by the DRC, which

the applicant had suppressed in this proceedings.

6. The first contention of the respondent that the

applicant has to wait till the completion of the project by the

new entity entrusted by the respondent, to have its claim

resolved at the instance of the DRC, prima facie defeats the 2024:KER:83950

purpose of the Arbitration and Conciliation Act, 1996 enacted

for speedy and efficacious remedy to be rendered to the parties

to commercial disputes. It is to be noted that the DRC is only

an in-house mechanism provided by the respondent itself, with

its members chosen at the discretion of the respondent. There

is no point in arguing that the applicant has to wait till the

Project Work of the respondent is completed by the present

company entrusted with the task, and the DRC again convened

to delve upon the final settlement of the bills, for getting the

payment of amounts lawfully entitled to them. Therefore the

objection raised by the respondent in the above regard is bereft

of merit. The contention of the respondent about the

suppression of facts by the applicant on the decisions taken by

the DRC in the two sittings conducted after Annexure-A49

notice, is also totally untenable since it could be seen from

Paragraph 31 of the Arbitration Request that the applicant has

disclosed the details pertaining to the efforts made by them to

remove their materials lying at the site, and Annexures-A50 and

A52 letters issued by the respondent consequent to the decision

of DRC to permit the applicant to remove the materials, plant,

equipments etc., from the Project site. The mere fact that the 2024:KER:83950

applicant co-operated with the respondent in the two DRC

meetings held after Annexure-A49 notice, cannot be termed as

a circumstance which would vitiate or nullify the sanctity of

Annexure-A49 notice. A reading of the said letter issued by the

applicant would reveal that it contains the essential

requirements envisaged under law as prerequisites for invoking

the Arbitration Clause in an agreement between the parties.

7. Another argument advanced by the respondent is that

the present application filed, without KIFB in the party array, is

prima facie not maintainable due to non joinder of necessary

parties. I find no merit in the above argument since there is

absolutely no requirement to arraign persons outside Annexure

A3 agreement as parties to this Arbitration Request, which is to

be decided on the basis of the contract inter-se between the

parties to that agreement.

8. As a conclusion to the aforesaid discussion, I find

that the applicant is entitled to invoke Section 11(6) of the Act,

and seek the appointment of an Arbitrator at the instance of

this Court.

2024:KER:83950

In the result, the application stands allowed, and an order

is passed as follows:

i) Mr. Justice M. Sasidharan Nambiar, 'Swapnam', Amritha Lane, Near Puthenkulangara Temple, Eroor North P.O., Kochi- 682 306 is nominated as the sole Arbitrator to arbitrate upon the disputes that have arisen between the petitioner and the respondent within the purview of Annexure-A3 agreement.

ii) The learned Arbitrator is at liberty to rule on all issues between the parties in connection with the said agreement, including his own jurisdiction if the parties raise such a dispute.

iii) The Registry is directed to communicate a copy of this order to the learned Arbitrator within a period of ten days from today and to obtain a Statement of Disclosure from the learned Arbitrator as provided under Section 11(8) read with Section12(1) of the Act.

iv) Once the Disclosure Statement is obtained from the learned Arbitrator, the Registry shall issue the certified copy of this order to the learned Arbitrator, with a copy of the said statement appended to it, retaining the original of the same by this Court.

2024:KER:83950

v) The fees of the learned Arbitrator shall be governed by the Fourth Schedule of the Act.

vi) The learned Arbitrator shall decide the manner in which the fees and expenses of the arbitration proceeding has to be paid by the parties.

vii) The parties will appear before the learned Arbitrator on such date and place as decided by the learned Arbitrator.

(sd/-)

G.GIRISH, JUDGE

jsr 2024:KER:83950

PETITIONER ANNEXURES

Annexure A1 A COPY OF THE NOTICE INVITING TENDER DOCUMENT NO. NIT/INKEL/ KIIFB/2018-19/010 DATED 05.04.2018 ISSUED BY THE RESPONDENT

Annexure A2 A COPY OF THE LETTER ACCEPTANCE NO. INKEL/ CE/LOA/HEALTH/ 2018/037 DATED 13.06.2018 ISSUED BY THE RESPONDENT

Annexure A3 A COPY OF THE AGREEMENT NO.

04/KIIFB/INKEL/2018-19 DATED 06.08.2018 ENTERED BETWEEN THE RESPONDENT AND THE APPLICANT

Annexure A4 TRUE COPY OF THE LETTER RELATED TO BILL DATED 03.06.2019

Annexure A4(a) COPY OF THE LETTER RELATED TO BILL DATED 17.06.2019

Annexure-A5 TRUE COPY OF THE LETTER RELATED TO LABOUR UNION ISSUES DATED 10.09.2018

Annexure-A5(a) TRUE COPY OF THE LETTER DATED 11.09.2018

Annexure A5(b) TRUE COPY OF THE LETTER DATED 17.03.2020.

Annexure-A6 TRUE COPY OF THE LETTER RELATED TO DRAWINGS DATED 01.09.2018.

Annexure-A6(a) TRUE COPY OF THE LETTER DATED 06.07.2019.

Annexure-A6(b) TRUE COPY OF THE LETTER DATED 16.08.2019

Annexure -A7 TRUE COPY OF THE CO-ORDINATION LETTERS DATED 24.09.2018.

Annexure-A8 TRUE COPY OF THE LETTER WITH RESPECT TO OVERALL DELAY EVENTS DATED 28.03.2019.

Annexure-A8(a) TRUE COPY OF THE LETTER DATED 30.05.2019 2024:KER:83950

Annexure-A8(b) TRUE COPY OF THE LETTER DATED 04.07.2019.

Annexure-A8(c) TRUE COPY OF THE LETTER DATED 10.07.2019

Annexure-A8(d) TRUE COPY OF THE LETTER DATED 18.11.2019

Annexure-A8(e) TRUE COPY OF THE LETTER DATED 25.06.2020

Annexure-A8(f) TRUE COPY OF THE LETTER DATED 08.01.2021

Annexure-A9 TRUE COPY OF THE LETTER RELATED TO FLOODS DATED 11.10.2018.

Annexure-A9(a) TRUE COPY OF THE LETTER DATED 16.10.2018

Annexure-A10 TRUE COPY OF THE LETTER RELATED TO E-PASS DATED 13.07.2020

Annexure-A10(a) TRUE COPY OF THE LETTER DATED 27.07.2020

Annexure-A10(b) TRUE COPY OF THE LETTER DATED 18.07.2020.

Annexure -A11 TRUE COPY OF THE LETTER RELATED TO COVID – 19 DATED 10.08.2020

Annexure-A11(a) TRUE COPY OF THE LETTER DATED 18.08.2020

Annexure-A11(b) TRUE COPY OF THE LETTER DATED 20.08.2020

Annexure-A11(c) TRUE COPY OF THE LETTER DATED 25.07.2020

Annexure-A11(d) TRUE COPY OF THE LETTER DATED 29.07.2020.

Annexure-A12 TRUE COPY OF THE LETTER RELATED TO EOT DATED 23.11.2018.

Annexure-A12(a) TRUE COPY OF THE LETTER DATED 09.03.2019.

Annexure -A12(b) TRUE COPY OF THE LETTER DATED 23.07.2019

Annexure-A12(c) TRUE COPY OF THE LETTER DATED 24.07.2019 2024:KER:83950

Annexure-A12(d) TRUE COPY OF THE LETTER DATED 10.07.2019.

Annexure-A12(e) TRUE COPY OF THE LETTER DATED 20.07.2020.

Annexure-A12(f) TRUE COPY OF THE LETTER DATED 23.11.2018.

Annexure-A12(g) TRUE COPY OF THE LETTER DATED 25.06.2020.

Annexure-A13 TRUE COPY OF THE LETTER DATED 11.06.2020

Annexure -A14 TRUE COPY OF THE LETTER DATED 23.07.2020

Annexure-A15 TRUE COPY OF THE LETTER DATED 15.09.2020 SUBMITTED BY THE APPLICANT.

Annexure-A16 TRUE COPY OF THE SUPPLEMENTARY AGREEMENT DATED 24.09.2020 EXECUTED BETWEEN THE APPLICANT AND THE RESPONDENT.

Annexure-A17 TRUE COPY OF THE SHOW CAUSE NOTICE DATED 26.12.2020 ISSUED BY THE RESPONDENT.

Annexure-A18 TRUE COPY OF THE LETTER DATED 04.01.2021 ISSUED BY THE APPLICANT.

Annexure-A19 TRUE COPY OF THE LETTER DATED 06.01.2021 ISSUED BY THE APPLICANT

Annexure-A20 TRUE COPY OF THE LETTER DATED 08.01.2021 ADDRESSED TO THE HEALTH AND FAMILY WELFARE DEPARTMENT BY THE APPLICANT.

Annexure -A21 TRUE COPY OF THE LETTER DATED 18.01.2021 ISSUED BY THE RESPONDENT TO THE APPLICANT

Annexure -A22 TRUE COPY OF THE JUDGMENT DATED 26.04.2021 IN W.P(C) NO.2200 OF 2021 PASSED BY THIS HON'BLE COURT.

Annexure-A23 . TRUE COPY OF THE JUDGMENT DATED 13.10.2021 IN W.A. NO. 905 OF 2021 PASSED BY THIS HON'BLE COURT.

Annexure-A24 TRUE COPY OF THE ORDER OF THE HON'BLE SUPREME 2024:KER:83950

COURT OF INDIA DATED 13.4.2022 IN SLP (C) NO.5672 OF 2022.

Annexure-A25 TRUE COPY OF THE LETTER DATED 11.02.2022 ISSUED BY THE APPLICANT

Annexure-A26 TRUE COY OF THE LETTER DATED 15.03.2022 ISSUED ON BEHALF OF THE RESPONDENT.

Annexure-A27 TRUE COPY OF THE ARBITRATION REQUEST NO. 115 OF 2022 FILED BEFORE THIS HON'BLE COURT ON 07.05.2022, WITHOUT ITS ANNEXURES.

Annexure-A28 TRUE COPY OF THE ORDER OF THIS HON'BLE COURT IN ARBITRATION REQUEST NO. 115 OF 2022 DATED 10.08.2022.

Annexure-A29 TRUE COPY OF THE LETTER NO. INKEL/LEGAL/ LETTER/7475 DATED 19.08.2022 ISSUED BY THE RESPONDENT.

Annexure-A30 TRUE COPY OF THE LETTER DATED 02.09.2022 ISSUED BY THE RESPONDENT.

Annexure-A31 TRUE COPY OF THE LETTER DATED 27.09.2022 ISSUED BY THE RESPONDENT

Annexure -A32 TRUE COPY OF THE LETTER DATED 18TH OCTOBER 2022 ISSUED BY THE RESPONDENT.

Annexure-A33 TRUE COPY OF THE LETTER DATED 12.12.2022 ISSUED BY THE APPLICANT.

Annexure-A34 TRUE COPY OF THE LETTER DATED 22.10.2022 ISSUED BY THE APPLICANT

Annexure-A35 TRUE COPY OF THE LETTER DATED 16.11.2022 ISSUED BY THE RESPONDENT.

Annexure-A36 TRUE COPY OF THE LETTER DATED 22.12.2022 ISSUED BY THE RESPONDENT.

Annexure -A37 TRUE COPY OF THE LETTER DATED 19.04.2023 ISSUED BY THE APPLICANT .

2024:KER:83950

Annexure-A38 TRUE COPY OF THE LETTER DATED 17.06.2023 ISSUED BY THE APPLICANT

Annexure-A39 TRUE COPY OF THE LETTER DATED 10.07.2023 ISSUED BY THE RESPONDENT, ALONG WITH ENCLOSURE

Annexure-A40 TRUE COPY OF THE LETTER DATED 20.07.2023 ISSUED BY THE RESPONDENT

Annexure -A41 TRUE COPY OF THE MINUTES OF THE MEETING DATED 04.08.2023

Annexure-A42 TRUE COPY OF THE MINUTES OF THE MEETING DATED 07.09.2023

Annexure-A43 TRUE COPY OF THE MINUTES OF THE MEETING DATED 20.09.2023

Annexure A44 TRUE COPY OF THE MINUTES OF THE MEETING DATED 06.10.2023

Annexure-A45 TRUE COPY OF THE LETTER DATED 06.09.2023 ISSUED BY THE APPLICANT

Annexure -A46 TRUE COPY OF THE LETTER DATED 19.09.2023 ISSUED BY THE APPLICANT WITH ENCLOSURES

Annexure-A47 TRUE COPY OF THE LETTER DATED 21.10.2023 ISSUED BY THE RESPONDENT.

Annexure -A48 TRUE COPY OF THE LETTER DATED 27.10.2023 ISSUED BY THE APPLICANT

Annexure-A49 . TRUE COPY OF THE LETTER DATED 27.10.2023 ISSUED BY THE APPLICANT

Annexure-A50 TRUE COPY OF THE LETTER DATED 05.12.2023 ISSUED BY THE RESPONDENT

Annexure-A51 TRUE COPY OF THE LETTER DATED 17.02.2024 ISSUED BY THE APPLICANT TO THE RESPONDENT

Annexure-A52 TRUE COPY OF THE LETTER DATED 17.02.2024 2024:KER:83950

ISSUED BY THE RESPONDENT

RESPONDENT ANNEXURES

Annexure R1(a) True copy of the Government order No.GO(Rt)No.6/2017/Hand FWD dated 4.1.2017

Annexure R1(b) True copy of the tripartite agreement between M/s.INKEL Ltd, Health and Family Welfare Department and Kerala Infrastructure Investment Fund Board (KIIFB) dated 29.7.2017

Annexure R1(c) true copy of the Hindrance Register maintained at the site

Annexure R1(d) True copy of the letter dated 10.3.2020 submitted by the applicant

Annexure R1(e) True copy of the report submitted by Green Lab Industrial and Environmental Solutions (Pvt.) Ltd on 21-22 November 2019

Annexure R1(f) True copy of the report of the semi destructive core test on RC columns conducted by Bureau Veritas, an NABL Accredited Lab

Annexure R1(g) True copy of the letter dated 25.6.2020 issued by the applicant along with the test lists

Annexure R1(h) True copy of the letter dated 29.11.2018 issued by the respondent to the applicant

Annexure R1(i) True copy of the letter dated 6.12.2018 issued by the respondent to the applicant

Annexure R1(j) True copy of the letter dated 6.3.2019 issued by the respondent to the applicant

Annexure R1(k) True copy of the letter dated 8.4.2019 issued by the respondent to the applicant

Annexure R1(l) The true copy of the letter dated 3.5.2019 issued by the respondent to the applicant 2024:KER:83950

Annexure R1(m) True copy of the letter dated 20.6.2019 issued by the respondent to the applicant

Annexure R1(n) True copy of the letter dated 2.7.2019 issued by the respondent to the applicant

Annexure R1(o) true copy of the letter dated 22.7.2019 issued by the respondent to the applicant

Annexure R1(p) True copy of the letter dated 5.8.2019 issued by the respondent to the applicant

Annexure R1(q) True copy of the letter dated 22.11.2019 issued by the respondent to the applicant

Annexure R1(r) True copy of the letter dated 23.7.2020 issued by the respondent to the applicant

Annexure R1(s) True copy of the W.P(C)No.2200/2021 dated 27.1.2021 filed by the applicant (without documents) before this Honourable Court

Annexure R1(t) True copy of the counter affidavit dated 4.2.2021 in W.P(C)No.2200/2021 (without documents) filed by the respondent before this Honourable Court.

Annexure R1(u) True copy of the additional counter affidavit dated 22.3.2021 in W.P(C)No.2200/2021 (without documents) filed by the respondent before this Honourable Court

Annexure R1(v) true copy of the appeal memorandum dated 11.6.2021 in W.A.No.905/2021 filed by the applicant before this Honourable Court

Annexure R1(w) True copy of the petition filed by the applicant in CMA(Arb.)No.546/2021 before the Commercial Court, Ernakulam dated 18.10.2021

Annexure R1(x) True copy of the counter affidavit filed by this respondent in CMA(Arb)No.546/2021 dated 27.10.2021 before the Commercial Court, Ernakulam 2024:KER:83950

Annexure R1(x)(1) True copy of the additional counter affidavit filed by this respondent in CMA(Arb)No.546/2021 dated 1.11.2021 before the Commercial Court, Ernakulam

Annexure R1(y) True copy of the memo submitted by the applicant in CMA(Arb.)No.546/2021 before the Commercial Court, Ernakulam dated 29.10.2021

Annexure R1(z) True copy of the order dated 20.11.2021 in I.A. Nos.2 and 3 of 2021 in CMA(Arb.) No.546 of 2021 of the Commercial Court, Ernakulam

Annexure R1(aa) True copy of the counter affidavit (without documents) filed by the respondent in A.R.No.115/2022 before this Honourable Court dated 14.7.2022

Annexure R1(ab) True copy of the letter dated 24.11.2023 issued by the respondent to the applicant

Annexure R1(ac) ): True copy of the proceedings of Dispute Redressal Committee of the respondent dated 28.11.2023

Annexure R1(ad) True copy of the proceedings of Dispute Redressal Committee of the respondent dated 2.12.2023

Annexure R1(ae) True copy of the gate passes issued by the respondent to the applicant to take away the materials from the site

Annexure R1(af) True copy of I.A.No.26 of 2023 to withdraw I.A.No.16 of 2021 in CMA(Arb.)No.546 of 2021 filed by the applicant before the Commercial Court, Ernakulam dated 11.12 2023

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter