Citation : 2024 Latest Caselaw 31234 Ker
Judgement Date : 1 November, 2024
2024:KER:83227
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE V.G.ARUN
FRIDAY, THE 1ST DAY OF NOVEMBER 2024 / 10TH KARTHIKA, 1946
WP(C) NO. 25221 OF 2024
PETITIONER:
M/S. KAVUMKAL ROAD BUILDERS
CHEMPANOLI, VECHOOCHIRA P.O, PATHANAMTHITTA DISTRICT
REPRESENTED BY ITS MANAGING PARTNER KURIAKOSE SABU AGED
60 S/O. LATE.UTHUPPAN KURIAKOSE, KAVUMKAL HOUSE ANGADI
P.O, RANNY, PATHANAMTHITTA DISTRICT, PIN - 689674
BY ADVS.
V.PHILIP MATHEWS
ABIYA MARIYAM MATHEW
RESPONDENTS:
1 STATE OF KERALA
REPRESENTED BY ITS SECRETARY DEPARTMENT OF PUBLIC
WORKS, KERALA GOVERNMENT SECRETARIAT
THIRUVANANTHAPURAM, PIN - 695001
2 THE CHIEF ENGINEER PWD (ROADS )
OFFICE OF THE CHIEF ENGINEER LMS VELLAYAMBALAM RD,
UNIVERSITY OF KERALA SENATE HOUSE CAMPUS, PALAYAM,
THIRUVANANTHAPURAM, PIN - 695033
3 THE SUPERINTENDING ENGINEER
OFFICE OF SUPERINTENDING ENGINEER, PWD ROADS AND
BRIDGES, SOUTH CIRCLE, THIRUVANANTHAPURAM, PIN - 695033
4 THE EXECUTIVE ENGINEER
OFFICE OF THE EXECUTIVE ENGINEER, PWD ROADS DIVISION,
NEAR COLLECTORATE, CHITTOOR, PATHANAMTHITTA, PIN -
689645
SMT. DEEPA NARAYANAN, SR. GP.
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
01.11.2024, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C)No.25221 of 2024 2024:KER:83227
2
JUDGMENT
Dated this the 1st day of November, 2024
Petitioner was awarded the work-"FDR
2018-19 Improvements of Maramon Arattupuzha
Road ch.0/000/05/490 and Parappuzha CRS Ch.
1/900/02/724". The work was completed on
30.06.2022, evidenced by Exhibit P1 Completion
Certificate. This writ petition is filed seeking a
direction to the respondents to disburse the amounts
due to the petitioner for Exhibit P1 work.
2. On behalf of the 4th respondent, a
statement has been filed, the relevant portion of
which reads as follows:
"During the 2018 floods, both sides of the road suffered erosion. forming deep cutting edges. Local residents requested Irish concrete or interlocking concrete for these sections, prioritizing essential areas. Additionally, berm concrete was necessary to drain water flowing from elevated side roads onto the main road due to the level difference. A revised estimate was submitted for these unforeseen works, which were WP(C)No.25221 of 2024 2024:KER:83227
not included in the initial estimate and required supplementary approval for project completion. Payment to the contractor can only be made upon obtaining approval for the revised estimate from higher authorities. It has been learned that the proceedings are in the final stage. Upon approval, the contractor's payment will be processed immediately."
3. It is evident from the above statement that
the amount due to the petitioner will be paid on the
revised estimate being approved. Insofar as the
petitioner had completed the work on 30.06.2022,
the payment cannot be delayed further.
4. The writ petition is hence disposed of,
directing the competent among the respondents to
disburse the amount due to the petitioner towards
the work covered by Exhibit P1 within two months of
receipt of a copy of this judgment.
Sd/-
V.G.ARUN JUDGE SSK/01/11 WP(C)No.25221 of 2024 2024:KER:83227
APPENDIX OF WP(C) 25221/2024
PETITIONER EXHIBITS
Exhibit P1 TRUE COPY OF THE CERTIFICATE OF COMPLETION OF WORK FDR -2018-19-IMPROVEMENTS TO
Exhibit P 2 TRUE COPY OF REPRESENTATION DATED 01-07- 2024 SUBMITTED TO RESPONDENTS 2 TO 4
TRUE COPY P.A. TO JUDGE
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!