Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Royal Engineering Contractors vs Bharat Petroleum Corporation Ltd
2024 Latest Caselaw 8769 Ker

Citation : 2024 Latest Caselaw 8769 Ker
Judgement Date : 27 March, 2024

Kerala High Court

M/S. Royal Engineering Contractors vs Bharat Petroleum Corporation Ltd on 27 March, 2024

Author: T.R.Ravi

Bench: T.R.Ravi

               IN THE HIGH COURT OF KERALA AT ERNAKULAM
                               PRESENT
                 THE HONOURABLE MR. JUSTICE T.R.RAVI
    WEDNESDAY, THE 27TH DAY OF MARCH 2024 / 7TH CHAITHRA, 1946
                       WP(C) NO. 12991 OF 2024


PETITIONER:

          M/S. ROYAL ENGINEERING CONTRACTORS,
          REPRESENTED BY ITS MANAGING PARTNER SHAFEER.V.M.,
          XIV/488, MALOTH BUILDING,
          PUTHENCRUZ, ERNAKULAM, PIN - 682303

          BY ADVS.
          K.R.GANESH
          ELVIN PETER P.J. (SR.)
          GOURI BALAGOPAL
          SREELEKSHMI A.S.



RESPONDENTS:

    1     BHARAT PETROLEUM CORPORATION LTD.
          BHARAT BHAVAN 4 AND 6,
          REPRESENTED BY THE CHAIRMAN/ MANAGING DIRECTOR.
          CURRIMBHOY ROAD, BALLARD ESTATE,
          P.B. NO. 688 MUMBAI, MAHARASHTRA, PIN - 400001

    2     THE EXECUTIVE DIRECTOR I/C
          BHARAT PETROLEUM CORPORATION LTD.,
          KOCHI REFINERY, AMBALAMUGAL,
          ERNAKULAM, PIN - 682302

    3     THE GENERAL MANAGER IN CHARGE (MAINTENANCE)
          BHARATH PETROLEUM CORPORATION LIMITED,
          KOCHI REFINERY, ERNAKULAM, PIN - 682302

          SRI. M. GOPIKRISHNAN NAMBIAR, SC.




     THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
27.03.2024, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 WP(C) NO. 12991 OF 2024
                                    2



                              T.R. RAVI, J.
               --------------------------------------------
                      W. P. (C). No.12991 of 2024
                --------------------------------------------
                 Dated this the 27th day of March, 2024

                               JUDGMENT

The writ petition has been filed challenging the termination of a

contract as per Ext.P3. Ext.P3 is a notice of termination stating that

the notice is issued under Clause 42 of the General Conditions of

Contract, which is binding on both the parties. As per the Clause, the

respondent shall, in addition to any other right enabling it to

terminate the contract, have the right to terminate the contract at

any time by giving prior written notice of at least 14 days to the

contractor. The respondent has complied with the said condition of

notice. The Clause further says that the termination shall be without

prejudice to the rights of the parties that have accrued on or before

the date of termination of the contract. Thus the right of the

petitioner on termination is also safeguarded and the Clause further

says about the compensation to which the contractor will be entitled

in case of such termination.

2. The counsel for the petitioner relied on the decision in ABL

International Ltd. and Another V. Export Credit Guarantee WP(C) NO. 12991 OF 2024

Corporation of India Ltd. and Others [(2004) 3 SCC 553], with

particular reference to paragraph 10, wherein the Court had held that

if a State acts in an arbitrary manner even in a matter of contract, an

aggrieved party can approach the Court by way of writ. The Court

had relied on the earlier decisions in K.N. Guruswamy V. State of

Mysore (AIR 1954 SC 592) and other cases. Reference is also

made to the judgment in Reliance Energy Ltd. and Another V.

Maharashtra State Road Development Corpn. Ltd. and Others

[(2007) 8 SCC 1]. In paragraph 36 of the said judgment, the Court

held that standards applied by Courts must be justified by

constitutional principles which govern the proper exercise of public

power in a democracy. After referring to the judgment in I.R.Coelho

V. State of Tamil Nadu [(2007) 2 SCC 1], the Court dealt with the

aspect of level playing field in the matter of contracts and held that

failure to satisfy the test of reasonableness even in contractual

matters can invite judicial review. I do not think that the principles

laid down in the said judgments will apply to the case of this nature.

This is a case where the contract provides for termination of the

contract and also speaks about the consequences of such termination.

The parties have agreed on the basis of the said condition in the WP(C) NO. 12991 OF 2024

contract. As such, this is not a matter in which this Court should be

exercising its jurisdiction under Article 226. The contractual rights of

the parties are very much kept intact even by the termination. I do

not find any reason to entertain this writ petition.

The writ petition is dismissed.

Sd/-/--/-

T.R. RAVI JUDGE

Pn WP(C) NO. 12991 OF 2024

APPENDIX OF WP(C) 12991/2024

PETITIONER EXHIBITS

EXHIBIT P1 TRUE COPY OF THE ORDER DATED 03.08.2022 AWARDING THE CONTRACT TO THE PETITIONER BY THE 1ST RESPONDENT.

EXHIBIT P2 RELEVANT EXTRACT OF THE GENERAL CONDITIONS OF THE CONTRACT OF THE BPCL.

EXHIBIT P3 TRUE COPY OF THE NOTICE DATED 18.03.2024 ISSUED TO THE PETITIONER TERMINATING THE CONTRACT AWARDED TO THE PETITIONER UNDER EXT.P1.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter