Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Power Grid Corporation Of India Ltd vs Antony E.O
2024 Latest Caselaw 15992 Ker

Citation : 2024 Latest Caselaw 15992 Ker
Judgement Date : 7 June, 2024

Kerala High Court

Power Grid Corporation Of India Ltd vs Antony E.O on 7 June, 2024

Author: V.G.Arun

Bench: V.G.Arun

             IN THE HIGH COURT OF KERALA AT ERNAKULAM
                             PRESENT
              THE HONOURABLE MR.JUSTICE V.G.ARUN
  FRIDAY, THE 7TH DAY OF JUNE 2024 / 17TH JYAISHTA, 1946
                       CRP NO. 605 OF 2018
AGAINST   THE     ORDER/JUDGMENT   DATED    08.03.2018     IN    OPELE
NO.156 OF 2011 OF ADDITIONAL DISTRICT COURT, KOZHIKODE
REVISION PETITIONER/S:

            POWER GRID CORPORATION OF INDIA LTD.
            REP BY ITS ADDITIONAL GENERAL MANAGER,UGRAPURAM,
            AREACODE, MALAPPURAM DT.
            BY ADV SRI.E.M.MURUGAN


RESPONDENT/S:

            ANTONY E.O
            S/O. AUSEPH, CHIRAYATH (H),VELAMKODE AMSOM
            DESOM, KODENCHERY.
            BY ADV SRI.O.D.SIVADAS


     THIS    CIVIL   REVISION    PETITION   HAVING    COME      UP   FOR
ADMISSION    ON    07.06.2024,   THE   COURT   ON    THE   SAME      DAY
DELIVERED THE FOLLOWING:
 CRP No.605 of 2018


                                   -2-



                                 ORDER

Dated this the 07th day of June, 2024

The revision petitioner, Power Grid

Corporation of India Ltd ('the Corporation' for

short), is aggrieved by the enhanced compensation

ordered to be paid to the respondent towards

diminution in land value, consequent upon the

drawing of 400 KV electric lines across his

property by the Corporation. The essential facts

are as under;

In order to facilitate drawing of 400 KV

electric lines for the smooth transmission of

power in the Mysore-Kozhikode sector, large

number of trees were cut from the respondent's

property. According to the respondent, the

drawing of high tension lines had rendered the

land underneath and adjacent useless, resulting

in diminution of the land value. In spite of the

huge loss suffered by the respondent, only small

amount was granted as compensation. Hence, the

original petition was filed, seeking enhanced

compensation towards the value of trees cut and

diminution in land value. Being dissatisfied with

the enhanced compensation ordered by the court,

the respondent preferred civil revision petition

and the same was allowed by this Court and the

case remanded back with a direction to determine

yield from each tree and to consider all

components of diminution in land value including

prevailing market price of the land and any new

factor which may be brought to the notice of the

court by the respondent.

2. After remand, the respondent filed a

statement before the court below clarifying that

he is not claiming additional compensation for

loss in value of improvements. Accordingly, the

court below considered the claim for enhanced

compensation towards diminution in land value

alone and passed the impugned order.

3. Heard learned Counsel appearing on

either side.

4. Learned Counsel for the revision

petitioner Corporation contended that the land

value fixed is not based on legal evidence.

Further, the additional compensation awarded is

unreasonable and the diminution in land value,

far in excess of the percentage fixed by the

Government. Per contra, learned Counsel for the

respondent argued that the enhancement is

reasonable and has been granted after considering

all relevant factors.

5. A perusal of the impugned order shows

that, although respondent had relied on Exts.A8

and A9 documents for the purpose of fixing land

value, considering the lie of the lands and

nature of transactions, the court below found

that the properties involved in Exts.A8 and A9

and the petition schedule property are not

similar or similarly situated. The court below

took note of the fact that an extent of 22.25

cents is affected due to the drawing of electric

lines and going by the manner in which the lines

were drawn, major portion of the property was

affected. Relying on the commission report and

sketch, the court below found that the petition

schedule property, which is an agricultural land,

has no direct road access and the property is

connected to the nearby road by a mud road. The

court below also took note of the fact that the

petition schedule property is situated at a

distance of 150 metres from the nearby town

centres. Based on the said factors, the land

value and also the affected area were fixed and

the Corporation was directed to pay 30% of the

land value as compensation. A table containing

the compensation thus awarded is appended below;

 Sl    Case   Affected     Land    Percentage Compensation Compensation   Balance
 No     No.   area (in   value per     of        payable       paid     Compensation
               cents)      cent    diminution                               due
 1    OP      22.25      25,000    30%            1,66,875       26,700     1,40,175
      156/



       6.      On        careful         scrutiny       of      the       impugned






order, it is seen that the compensation payable

towards diminution in land value was fixed based

on factors like situs of the land, the extent to

which the land is adversely affected and

consequent diminution in the value of the land,

as laid down by the Apex Court in KSEB v. Livisha

[(2007) 6 SCC 792].

7. The contention of the Corporation that

the Government having fixed the fair value of the

land and also issued guidelines for the fixation

of the percentage of diminution, the court below

ought to have fixed the land value and percentage

of diminution in accordance with the same is

liable to be rejected since the court is not

bound by the guidelines/orders issued by the

Government while fixing the compensation. The

contention that the court below committed an

illegality by awarding 12% interest cannot also

be sustained in the light of the decision of this

Court in P.Raghavan v. KSEB [CRP No.3256 of

2001]. In view of the decision of this Court in

KSEB v Maranchi Matha [2008 (1) KLT 1038], the

contention that the court below has transgressed

its jurisdiction, by granting interest from the

date of cutting of trees, is also liable to be

rejected. As such, I find no reason to interfere

with the well considered order of the court

below, rendered after taking all relevant factors

into consideration.

For the aforementioned reasons, the civil

revision petition is dismissed.

Sd/-

V.G.ARUN JUDGE Scl/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter