Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Power Grid Corporation Of India Ltd vs Ahammedkutty
2024 Latest Caselaw 15991 Ker

Citation : 2024 Latest Caselaw 15991 Ker
Judgement Date : 7 June, 2024

Kerala High Court

Power Grid Corporation Of India Ltd vs Ahammedkutty on 7 June, 2024

Author: V.G.Arun

Bench: V.G.Arun

              IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                    PRESENT
                  THE HONOURABLE MR.JUSTICE V.G.ARUN
     FRIDAY, THE 7TH DAY OF JUNE 2024 / 17TH JYAISHTA, 1946
                            CRP NO. 604 OF 2018
AGAINST THE ORDER/JUDGMENT DATED IN OPELE NO.123 OF 2011
OF ADDITIONAL DISTRICT COURT, KOZHIKODE
REVISION PETITIONER/S:

               POWER GRID CORPORATION OF INDIA LTD
               REPRESENTED BY ITS ADDITIONAL GENERAL MANAGER,
               UGRAPURAM, AREACODE, MALAPPURAM DISTRICT.
               BY ADV SRI.E.M.MURUGAN


RESPONDENT/S:

       1       AHAMMEDKUTTY
               S/O.MOIDEEN, KOLATHUMKANDI HOUSE, KAMBALATHGODI,
               VALILLAPUZHA P.O.,KODIYATHUR-673 001.
       2       NAFEESA WO.AHAMMED KUTTY KOLATHUMKANDI HOUSE
               KAMBALATHODI VALILLAPUZHA P.O. KODIYATHUR-673
               001.
               BY ADV SRI.O.D.SIVADAS


           THIS CIVIL REVISION PETITION HAVING COME UP FOR ADMISSION
ON    07.06.2024,     THE   COURT    ON   THE   SAME   DAY   DELIVERED   THE
FOLLOWING:
 CRP No.604 of 2018


                                  -2-



                             ORDER

Dated this the 07th day of June, 2024

The revision petitioner, Power Grid

Corporation of India Ltd ('the Corporation' for

short), is aggrieved by the enhanced compensation

ordered to be paid to the respondents towards

diminution in land value, consequent upon the

drawing of 400 KV electric lines across their

property by the Corporation. The essential facts

are as under;

The respondents are in ownership and

possession of landed property having an extent of

37 cents comprised in Sy.No.186 of Kodiyathur

Village. The land was cultivated with various

yielding and non-yielding trees. In order to

facilitate drawing of 400 KV electric lines for

the smooth transmission of power in the Mysore-

Kozhikode sector, large number of trees were cut

from the respondents' property. According to the

respondents, the drawing of high tension lines

had rendered the land underneath and adjacent

useless, resulting in diminution of the land

value. In spite of the huge loss suffered by the

respondents, only small amount was granted as

compensation. Hence, the original petition was

filed, seeking enhanced compensation towards the

value of trees cut and diminution in land value.

Being dissatisfied with the enhanced compensation

ordered by the court, the respondents preferred

civil revision petition and the same was allowed

by this Court and the case remanded back with a

direction to determine yield from each tree and

to consider all components of diminution in land

value including prevailing market price of the

land and any new factor which may be brought to

the notice of the court by the respondents.

2. After remand, the respondents filed a

statement before the court below clarifying that

they are not claiming additional compensation for

loss in value of improvements. Accordingly, the

court below considered the claim for enhanced

compensation towards diminution in land value

alone and passed the impugned order.

3. Heard learned Counsel appearing on

either side.

4. Learned Counsel for the revision

petitioner Corporation contended that the land

value fixed is not based on legal evidence.

Further, the additional compensation awarded is

unreasonable and the diminution in land value,

far in excess of the percentage fixed by the

Government. Per contra, learned Counsel for the

respondents argued that the enhancement is

reasonable and has been granted after considering

all relevant factors.

5. A perusal of the impugned order shows

that, although respondents had relied on Ext.A9

document for the purpose of fixing land value,

considering the lie of the land and nature of

transaction, the court below found that the

property involved in Ext.A9 and the petition

schedule property are not similar or similarly

situated. The court below took note of the fact

that an extent of 33.46 cents is affected due to

the drawing of electric lines and going by the

manner in which the lines were drawn, major

portion of the petition schedule property was

affected. Relying on the commission report and

plan, the court below found that the respondents'

property has no direct vehicular access and the

petition schedule property is connected to the

Panchayat road by a footpath. Based on the said

factors, the court below fixed the land value and

also the affected area and directed to pay 30% of

the land value as compensation. A table

containing the compensation thus awarded is

appended below;

 Case    Affected     Land value    Percentage   Compensation Compensation      Balance
  No.    area (in      per cent         of          payable       paid       Compensation
          cents)                   diminution                                     due
OP           33.46    25,000       30%               2,50,950       80,304       1,70,646
123/



        6.      On     careful            scrutiny          of     the       impugned






order, it is seen that the compensation payable

towards diminution in land value was fixed based

on factors like situs of the land, the extent to

which the land is adversely affected and

consequent diminution in the value of the land,

as laid down by the Apex Court in KSEB v. Livisha

[(2007) 6 SCC 792].

7. The contention of the Corporation that

the Government having fixed the fair value of the

land and also issued guidelines for the fixation

of the percentage of diminution, the court below

ought to have fixed the land value and percentage

of diminution in accordance with the same is

liable to be rejected since the court is not

bound by the guidelines/orders issued by the

Government while fixing the compensation. The

contention that the court below committed an

illegality by awarding 12% interest cannot also

be sustained in the light of the decision of this

Court in P.Raghavan v. KSEB [CRP No.3256 of

2001]. In view of the decision of this Court in

KSEB v Maranchi Matha [2008 (1) KLT 1038], the

contention that the court below has transgressed

its jurisdiction, by granting interest from the

date of cutting of trees, is also liable to be

rejected. As such, I find no reason to interfere

with the well considered order of the court

below, rendered after taking all relevant factors

into consideration.

For the aforementioned reasons, the civil

revision petition is dismissed.

Sd/-

V.G.ARUN JUDGE Scl/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter