Citation : 2024 Latest Caselaw 37 Ker
Judgement Date : 3 January, 2024
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE DEVAN RAMACHANDRAN
WEDNESDAY, THE 3RD DAY OF JANUARY 2024 / 13TH POUSHA, 1945
WP(C) NO. 4703 OF 2023
PETITIONER:
ANEESH APPU, AGED 35 YEARS, PWD CONTRACTOR, S/O.APPU,
VELLAYIKUDATH HOUSE, VASUPURAM, MATTATHUR VILLAGE,
CHALAKUDY TALUK, THRISSUR DISTRICT, PIN - 680684
LINDONS C.DAVIS
E.U.DHANYA
SWATHY A.P.
RESPONDENTS:
1 STATE OF KERALA, REPRESENTED BY THE SECRETARY,
REPUBLIC WORKS DEPARTMENT, SECRETARIAT,
THIRUVANANTHAPURAM, PIN - 680684
2 SUPERINTENDING ENGINEER
PWD ROADS - CENTRE CIRCLE, OFFICE OF THE SUPERINTENDING
ENGINEER PWD ROADS, SUB JAIL ROAD, PERIYAR NAGAR,
ALUVA, ERNAKULAM DISTRICT, PIN - 683101
3 EXECUTIVE ENGINEER, PWD ROADS DIVISION, NEAR
RAMANILAYAM, THRISSUR, PIN - 680020
4 ASSISTANT EXECUTIVE ENGINEER, PWD ROADS SUB DIVISION,
THRISSUR THRISSUR DISTRICT, PIN - 680020
5 ASSISTANT ENGINEER, PWD ROADS, TOWN SECTION, THRISSUR
THRISSUR DISTRICT, PIN - 680020
SRI.P.S.APPU - GP
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
03.01.2024, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C) NO. 4703 OF 2023
2
JUDGMENT
The petitioner undertook certain works for the Public
Works Department (PWD), but was unable to complete the
same on account of various reasons which, he says, are not
attributable to him. He alleges that, however, in spite of this,
the third respondent - Executive Engineer, has issued Exts.P3
to P6 orders cancelling the contract at his "risk and cost",
followed by Ext.P7 order issued by the 2 nd respondent -
Superintending Engineer, directing him to appear before him
on 03.02.2023, for a hearing to fix the "risk and cost" liability
against him. He thus impugns Exts.P3 to P7 as being illegal
and unlawful.
2. Sri.Lindons C.Davis - learned counsel for the
petitioner, vehemently argued that, as is evident from Exts.P1
and P2 earlier representations made by his client before
respondents 2 and 3 respectively, among the various reasons
that have led to the running contract being unable to be
performed by his client effectively, is the withholding of the
bills and security deposits with respect to the said works and
that of other collateral and earlier works, without any tangible WP(C) NO. 4703 OF 2023
reasons. He submitted that this is a clear case where his client
is financially choked; thus being incapacitated from continuing
with the contract effectively, even though his intention was and
is to honour it fully. He submitted that, therefore, his client
does not stand in the way of the contracts being terminated,
but that the action now proposed in Ext.P7, namely to fix risk
and cost, is illegal and unlawful.
3. Sri.P.S.Appu - learned Government Pleader, in
response, submitted that, as is evident from Exts.P3 to P6, the
Executive Engineer has no other option, but to cancel the
contract awarded to the petitioner and to fix risk and cost
responsibility against him, because he did not respond to any
of the letters issued to him, as have been referred to in the said
orders. He submitted that Exts.P1 and P2 are self-serving
documents now placed on record by the petitioner, in which,
untenable objections have been impelled; and therefore, that
this writ petition is not maintainable. He then argued that,
there was no reason for the petitioner to have approached this
Court at all because, Ext.P7 is only a notice asking him to show
cause why risk and cost is not fixed against him; and that he
can always reply to the same, as also explain why his licences WP(C) NO. 4703 OF 2023
be not cancelled in future. He concluded saying that the
Superintending Engineer will take any further action against
the petitioner only if it is warranted; and that too, after
following due procedure and in terms of law, without any
breach.
4. When I assess and evaluate the afore rival assertions,
it is limpid that there are disputations of facts between the
parties, which cannot be resolved by this Court, while acting
under Article 226 of the Constitution of India. On one hand,
the petitioner says that he has endeavored to complete the
work as per the contract, but was unable to do so on account of
the severe financial crunch brought upon him by the conduct of
the respondents in not releasing the payments in time; while,
on the other, the officials take the stand that the petitioner did
not respond to any of the earlier notices issued to him, thus
constraining the Executive Engineer to issue Exts.P3 to P6
letters, cancelling the contracts and terminating the same
under the risk and cost of the petitioner. As a corollary, the
official respondents maintain that the cancellation of the
licence is a necessary consequence and nothing else.
5. However, it must be borne in mind that it is the WP(C) NO. 4703 OF 2023
specific case of the petitioner that, he was willing and ready to
continue with the work but could not do so on account of the
financial crisis, which was allegedly brought upon him since
the bills entitled to him were not released by the official
respondents. 6. Obviously, these are matters which will
have to be considered comprehensively by the Superintending
Engineer before any further action, to either terminate the
licence of the petitioner, or to cancel the contract at risk and
cost is taken and completed.
7. In the afore circumstances, acceding to the request of
the learned Government Pleader, I allow this writ petition to
the limited extent of granting liberty to the petitioner to make
a detailed objection against Ext.P7 before the Superintending
Engineer; and if this is done within a period of one month from
the date of receipt of a copy of this judgment, the said
Authority will hear him and advert to the said objections; thus
culminating in an appropriate order, detailing the reasons, if
any, for either imposing risk and cost on him, and/or
cancelling his licence - as the case may be.
Needless to say, until such time as the afore exercise is
completed and resultant order communicated to the petitioner, WP(C) NO. 4703 OF 2023
the detriment of either the risk and cost, or the cancellation of
his contract - even if it is to be so ordered by the
Superintending Engineer - shall not be given effect to.
Sd/- DEVAN RAMACHANDRAN JUDGE stu WP(C) NO. 4703 OF 2023
APPENDIX OF WP(C) 4703/2023
PETITIONER EXHIBITS
Exhibit P1 A TRUE COPY OF THE REPRESENTATION E-MAILED ON 18.01.2023 TO THE 2ND RESPONDENT
Exhibit P2 A TRUE COPY OF THE REPRESENTATION E-MAILED ON 18.01.2023 TO THE 3RD RESPONDENT
Exhibit P3 A TRUE COPY OF THE ORDER NO.D1/PWD/RW/EST/104210/2021 DATED 20.01.2023 ISSUED BY THE 3RD RESPONDENT
Exhibit P4 A COPY OF THE ORDER NO.D1/PWD/RW/EST/104352/2021 DATED 20.01.2023 ISSUED BY THE 3RD RESPONDENT
Exhibit P5 A COPY OF THE ORDER NO.D1/PWD/RW/EST/104313/2021 DATED 20.01.2023 ISSUED BY THE 3RD RESPONDENT
Exhibit P6 A COPY OF THE ORDER NO.D1/PWD/RW/EST/104888/2021 DATED 20.01.2023 ISSUED BY THE 3RD RESPONDENT
Exhibit P7 . A COPY OF THE LETTER NO.FCR-485/2013 DATED 27.01.2023 ISSUED BY THE 2ND RESPONDENT
Exhibit P8 A COPY OF THE WRITTEN SUBMISSION TOWARDS HEARING DATED 03.02.2023 BEFORE THE 2ND RESPONDENT
Exhibit P9 A COPY OF THE INTERIM ORDERS DATED 01.11.2022 IN WP(C) NO.33871/2022
Exhibit P10 . A COPY OF THE REQUEST OF THE PETITIONER DATED 29.10.2022 BEFORE THE 2ND RESPONDENT
Exhibit P11 A TRUE COPY OF THE RELEVANT PAGES OF PWD MANUAL 2012 WP(C) NO. 4703 OF 2023
RESPONDENT EXHIBITS
Exhibit R2(a) A true copy of GO(Rt) No.147/2022/PWD dated 09.02.2022
exhibit R3a GORT 147/2022/PWD dt.9.2.2022
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!